CN204417983U - A kind of prefabricated units on-site consolidation compound beam for rushing to repair concrete box girder - Google Patents
A kind of prefabricated units on-site consolidation compound beam for rushing to repair concrete box girder Download PDFInfo
- Publication number
- CN204417983U CN204417983U CN201420847247.2U CN201420847247U CN204417983U CN 204417983 U CN204417983 U CN 204417983U CN 201420847247 U CN201420847247 U CN 201420847247U CN 204417983 U CN204417983 U CN 204417983U
- Authority
- CN
- China
- Prior art keywords
- concrete
- corrugated steel
- bottom plate
- steel web
- roof
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 195
- 230000008439 repair process Effects 0.000 title claims abstract description 70
- 150000001875 compounds Chemical class 0.000 title 1
- 238000007596 consolidation process Methods 0.000 title 1
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 89
- 239000010959 steel Substances 0.000 claims abstract description 89
- 239000002131 composite material Substances 0.000 claims abstract description 23
- 210000002435 tendon Anatomy 0.000 claims description 38
- 239000003822 epoxy resin Substances 0.000 claims description 14
- 229920000647 polyepoxide Polymers 0.000 claims description 14
- 239000003292 glue Substances 0.000 claims description 7
- 238000000034 method Methods 0.000 abstract description 15
- 238000010586 diagram Methods 0.000 description 17
- 239000011083 cement mortar Substances 0.000 description 7
- 238000010276 construction Methods 0.000 description 4
- 239000011513 prestressed concrete Substances 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 2
- 230000000712 assembly Effects 0.000 description 1
- 238000000429 assembly Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
一种用于抢修混凝土箱梁的预制构件现场拼装组合梁,通过组拼预制混凝土顶板、混凝土底板、波形钢腹板和两端堵头,从而实现对铁路、公路和城市交通等的混凝土箱梁的应急抢修和快速恢复运营。这种抢修方法能够有效地减少抢修过程中对大型运输和起吊设备的依赖,加快桥梁的抢修速度,减少应急梁储存场地的面积和规模,降低抢修成本,实现快速恢复交通线路运营的目标。
A prefabricated component field assembled composite beam used for emergency repair of concrete box girders. By assembling prefabricated concrete top slabs, concrete bottom slabs, corrugated steel webs and plugs at both ends, concrete box girders for railways, highways and urban traffic, etc. are realized. Emergency repairs and rapid restoration of operations. This emergency repair method can effectively reduce the reliance on large-scale transportation and lifting equipment in the emergency repair process, speed up bridge repairs, reduce the area and scale of emergency beam storage sites, reduce repair costs, and achieve the goal of quickly restoring traffic line operations.
Description
技术领域 technical field
本实用新型属于土木工程临时性抢修桥梁的技术领域,涉及一种用于抢修混凝土箱梁的预制构件现场拼装组合梁,应用于铁路、公路和城市交通等的混凝土箱梁应急抢修和快速恢复。 The utility model belongs to the technical field of temporary emergency repair bridges in civil engineering, and relates to a prefabricated component field assembled composite beam used for emergency repair of concrete box girders, which is applied to emergency emergency repair and rapid recovery of concrete box girders in railways, highways and urban traffic.
背景技术 Background technique
目前,由于混凝土箱梁具有纵、横向刚度大、整体性好、动力性能好等优点,被广泛地应用在桥梁工程中。然而,当混凝土箱梁遭遇自然灾害、战争、撞击等破坏后,由于混凝土箱梁体积大、重量大导致抢修难度的加大。现行的混凝土箱梁抢修主要是采用六四式铁路军用钢梁、拆装式钢桁梁、分节段预制拼装等方法。实用新型专利“CD型装配式公路钢桥”(申请号:CN201320317588)提供了一种CD型装配式公路钢桥的应急抢修梁结构,该结构构造简单、受力明确、构件数量少、架设速度快、连接可靠适用面广,但其刚度较低,导致抢修后梁体在行车时变形大、振动大、噪音高、车辆运行速度低,不适合抢修高速铁路或重载铁路上的混凝土箱梁;发明专利“一种混凝土箱梁的应急抢修方法”(申请号:CN201410324659)介绍了一种适用于高速铁路和重载铁路的混凝土箱梁抢修方法,该方法实现了满足抢修后梁体刚度大、变形小、振动小、噪音低的要求,其混凝土顶板、底板整体的预制拼装件也在一定程度上减小了整梁的吊装重量,但混凝土顶板、底板整体的重量和体积依旧很大;实用新型专利“一种波型钢腹板预应力混凝土组合箱梁节段”(专利号:ZL 200820036647.X)和“铁路预制节段拼装胶结箱梁”(申请号:CN201020259427)分别提及了一种预制节段拼装的波形钢腹板箱梁和预制节段拼装的混凝土箱梁,在上述两实用新型专利中,波形钢腹板混凝土箱梁节段和混凝土箱梁节段在工厂预制后,运 输至桥梁现场进行拼装,由于波形钢腹板混凝土箱梁节段和混凝土箱梁节段的重量和体积依旧很大,给波形钢腹板组合箱梁节段和混凝土箱梁节段的储存和运输带来诸多不便,致使抢修施工时必须依赖于大型的运输设备和吊装设备,这在一定程度上制约了上述技术在实际工程中的应用;发明专利“预制部件装配节段拼装波形钢腹板RPC组合箱梁及方法”(申请号:CN 102704386A)介绍了一种分构件预制拼装的波形钢腹板组合梁,该方法大大减轻了结构自重和吊装重量,但其混凝土底板和顶板均采用现场浇筑的方法,增加了混凝土的现场浇筑及养护周期,减缓了桥梁抢修的速度,且相邻节段的顶板、底板组合件之间仅采用胶结方法进行连接,并未设置抗剪连接件,其抗剪能力较弱。 At present, concrete box girders are widely used in bridge engineering due to their advantages such as large longitudinal and transverse stiffness, good integrity, and good dynamic performance. However, when the concrete box girder is damaged by natural disasters, wars, impacts, etc., it is more difficult to repair it due to the large volume and weight of the concrete box girder. The current emergency repair of concrete box girder mainly adopts methods such as 64-type railway military steel girder, disassembled steel truss girder, and segmental prefabricated assembly. The utility model patent "CD-type prefabricated highway steel bridge" (application number: CN201320317588) provides an emergency repair beam structure for a CD-type prefabricated highway steel bridge. Fast, reliable connection and wide application, but its low rigidity will lead to large deformation of the beam body after emergency repair, large vibration, high noise, and low vehicle speed, so it is not suitable for emergency repair of concrete box girders on high-speed railways or heavy-duty railways; The invention patent "A Method for Emergency Repair of Concrete Box Girder" (application number: CN201410324659) introduces a method for emergency repair of concrete box girders suitable for high-speed railways and heavy-duty railways. Small size, low vibration and low noise requirements, the prefabricated assembly of the concrete roof and bottom plate also reduces the hoisting weight of the whole beam to a certain extent, but the overall weight and volume of the concrete roof and bottom plate are still large; utility model The patents "a corrugated steel web prestressed concrete composite box girder segment" (patent number: ZL 200820036647.X) and "assembled and cemented box girder for railway prefabricated segments" (application number: CN201020259427) respectively mention a prefabricated Corrugated steel web box girder assembled by segment and concrete box girder assembled by prefabricated segment. In the above two utility model patents, the concrete box girder segment with corrugated steel web and the concrete box girder segment are prefabricated in the factory and then transported Assembled at the bridge site, due to the weight and volume of the corrugated steel web concrete box girder section and the concrete box girder section are still very large, the storage and transportation of the corrugated steel web composite box girder section and the concrete box girder section It brings a lot of inconvenience, which makes it necessary to rely on large-scale transportation equipment and hoisting equipment during emergency repair construction, which restricts the application of the above-mentioned technology in actual engineering to a certain extent; Composite box girder and method” (application number: CN 102704386A) introduced a corrugated steel web composite girder prefabricated and assembled by sub-components. This method greatly reduces the structure’s self-weight and hoisting weight, but its concrete bottom and roof are poured on site. The method increases the on-site pouring and maintenance period of concrete, slows down the speed of bridge repairs, and the roof and floor assemblies of adjacent sections are only connected by cementation, and no shear connectors are set. Shearing ability is weak.
从目前已有专利、公开文献和实际工程应用来看,还未有一种用于抢修混凝土箱梁的预制构件现场拼装组合梁。这种组合梁能节约储存场地,有效地减少抢修过程中对大型运输和起吊设备的依赖,加快损坏桥梁的抢修速度,实现快速恢复线路运营的目标。 From present existing patent, open document and practical engineering application, also do not have a kind of prefabricated component field assembled composite beam that is used for repairing concrete box girder. This kind of composite beam can save storage space, effectively reduce the dependence on large-scale transportation and lifting equipment in the repair process, speed up the repair speed of damaged bridges, and achieve the goal of quickly restoring line operation.
实用新型内容 Utility model content
本实用新型所要解决的技术问题是:提供一种用于抢修混凝土箱梁的预制构件现场拼装组合梁,解决铁路、公路和城市交通等的混凝土箱梁的应急抢修和快速恢复线路运营的问题。 The technical problem to be solved by the utility model is: to provide a prefabricated component field assembled composite beam for emergency repair of concrete box girders, so as to solve the problems of emergency repair and quick restoration of line operation of concrete box girders of railways, highways and urban traffic.
本实用新型解决其技术问题所采用的技术方案是: The technical scheme that the utility model solves its technical problem adopts is:
一种用于抢修混凝土箱梁的预制构件现场拼装组合梁,包括混凝土顶板1、混凝土底板2、波形钢腹板3、桥墩4、支架5、堵头6、顶板榫头7-1、底板榫头7-2、顶板榫孔8-1、底板榫孔8-2、顶板体内预应力筋9-1、底板体内预应力筋9-2、顶板预应力孔道10-1、底板预应力孔道10-2、体外预应力筋11、转向块12、顶板与波形钢腹板连接螺栓13-1、底板与波形钢腹板连接螺栓13-2、波 形钢腹板与波形钢腹板连接螺栓13-3;其特征在于,混凝土顶板1通过两端设有的顶板榫头7-1和顶板榫孔8-1进行连接;混凝土底板2通过两端设有的底板榫头7-2和底板榫孔8-2进行连接;波形钢腹板3与混凝土顶板1通过预埋在混凝土顶板1内的顶板与波形钢腹板连接螺栓13-1进行连接;波形钢腹板3与混凝土底板2通过预埋在混凝土底板2内的底板与波形钢腹板连接螺栓13-2进行连接;波形钢腹板3节段间采用波形钢腹板与波形钢腹板连接螺栓13-3进行连接;上述各构件拼装完成后,需在转向块12内穿入体外预应力筋11,并张拉体外预应力筋11。 A prefabricated component field-assembled composite beam for emergency repair of concrete box girders, including concrete roof 1, concrete floor 2, corrugated steel web 3, pier 4, bracket 5, plug 6, top plate tenon 7-1, bottom plate tenon 7 -2. Top plate tenon hole 8-1, bottom plate tenon hole 8-2, prestressed ribs inside the top plate 9-1, prestressed ribs inside the bottom plate 9-2, top plate prestressed channel 10-1, bottom plate prestressed channel 10-2 , External prestressed tendons 11, steering block 12, connecting bolts between top plate and corrugated steel web 13-1, connecting bolts between bottom plate and corrugated steel web 13-2, connecting bolts between corrugated steel web and corrugated steel web 13-3 It is characterized in that the concrete top plate 1 is connected by the top plate tenon 7-1 and the top plate tenon hole 8-1 provided at both ends; the concrete bottom plate 2 is connected by the bottom plate tenon 7-2 and the bottom plate tenon hole 8-2 provided at both ends The corrugated steel web 3 and the concrete roof 1 are connected by the top plate embedded in the concrete roof 1 and the corrugated steel web connecting bolt 13-1; the corrugated steel web 3 and the concrete bottom plate 2 are connected by pre-embedded The bottom plate in 2 is connected with the corrugated steel web connecting bolt 13-2; the corrugated steel web 3 sections are connected with the corrugated steel web and the corrugated steel web connecting bolt 13-3; after the assembly of the above components is completed, It is necessary to penetrate the external prestressed tendons 11 in the steering block 12 and stretch the external prestressed tendons 11 .
上述的一种用于抢修混凝土箱梁的预制构件现场拼装组合梁,其特征在于,现场拼装时先将环氧树脂胶涂抹在混凝土底板2两端侧面和底板榫头7-2、底板榫孔8-2上,将底板榫头7-2插入底板榫孔8-2内,待各节段混凝土底板2间环氧树脂胶达到设计强度后,在底板预应力孔道10-2内穿入底板体内预应力筋(9-2)并张拉底板体内预应力筋9-2。 The above-mentioned prefabricated component field assembled composite beam for emergency repair of concrete box girder is characterized in that, when assembling on site, epoxy resin glue is first applied to the sides of the two ends of the concrete bottom plate 2, the bottom plate tenon 7-2, and the bottom plate tenon hole 8 -2, insert the tenon 7-2 of the bottom plate into the tenon hole 8-2 of the bottom plate, and after the epoxy resin glue between the two concrete bottom plates of each segment reaches the design strength, penetrate the prestressed hole 10-2 of the bottom plate into the prestressing hole 8-2 of the bottom plate Stress tendons (9-2) and tension the prestressed tendons 9-2 in the base plate.
上述的一种用于抢修混凝土箱梁的预制构件现场拼装组合梁,其特征在于,混凝土底板2拼接完成后,将波形钢腹板3与混凝土底板2用底板与波形钢腹板连接螺栓13-2连接,各波形钢腹板3节段间也采用波形钢腹板与波形钢腹板连接螺栓13-3连接。 The above-mentioned prefabricated component field assembled composite beam for emergency repair of concrete box girders is characterized in that after the concrete floor 2 is spliced, the corrugated steel web 3 and the concrete floor 2 are connected by the bottom plate and the corrugated steel web with bolts 13- 2 connection, each corrugated steel web 3 segments are also connected by corrugated steel web and corrugated steel web connecting bolt 13-3.
上述的一种用于抢修混凝土箱梁的预制构件现场拼装组合梁,其特征在于,现场拼装时先将环氧树脂胶涂抹在混凝土顶板1两端侧面和顶板榫头7-1、顶板榫孔8-1上,将顶板榫头7-1插入顶板榫孔8-1内,待各节段混凝土顶板1间环氧树脂胶达到设计强度后,在顶板预应力孔道10-1内穿入顶板体内预应力筋9-1并张拉顶板体内预应力筋9-1;混凝土顶板1和波形钢腹板3间采用顶板与波形钢腹板连接螺栓13-1连接。 The above-mentioned prefabricated component on-site assembled composite beam for emergency repair of concrete box girder is characterized in that, during on-site assembly, epoxy resin glue is first applied to the sides of the two ends of the concrete roof 1, the roof tenon 7-1, and the roof tenon hole 8 -1, insert the tenon head 7-1 of the top plate into the tenon hole 8-1 of the top plate. Stress tendons 9-1 and tension the prestressed tendons 9-1 in the roof; the concrete roof 1 and the corrugated steel web 3 are connected by connecting bolts 13-1 between the roof and the corrugated steel web.
上述的一种用于抢修混凝土箱梁的预制构件现场拼装组合梁,其特征在于,混凝土顶板1、混凝土底板2、波形钢腹板3拼装完成后,需在转向块12内穿入体外预应力筋11,并张拉体外预应力筋11,吊装两端堵头6,并将体外预应力筋11锚固在堵头6上。 The above-mentioned prefabricated component field assembled composite beam for emergency repair of concrete box girder is characterized in that, after the assembly of the concrete roof 1, the concrete floor 2, and the corrugated steel web 3 is completed, it is necessary to penetrate the external prestressing force in the steering block 12 Tendons 11, and stretch the external prestressed tendons 11, hoist the plugs 6 at both ends, and anchor the external prestressed tendons 11 on the plugs 6.
本实用新型的有益效果是: The beneficial effects of the utility model are:
一种用于抢修混凝土箱梁的预制构件现场拼装组合梁,通过组拼预制混凝土顶板、混凝土底板、波形钢腹板和两端堵头,从而实现对铁路、公路和城市交通等的混凝土箱梁的应急抢修和快速恢复运营。这种抢修方法能够有效地减少抢修过程中对大型运输和起吊设备的依赖,加快桥梁的抢修速度,减少应急梁储存场地的面积和规模,降低抢修成本,实现快速恢复交通线路运营的目标。 A prefabricated component field assembled composite beam used for emergency repair of concrete box girders. By assembling prefabricated concrete top slabs, concrete bottom slabs, corrugated steel webs and plugs at both ends, concrete box girders for railways, highways and urban traffic, etc. are realized. Emergency repairs and rapid restoration of operations. This emergency repair method can effectively reduce the reliance on large-scale transportation and lifting equipment in the emergency repair process, speed up bridge repairs, reduce the area and scale of emergency beam storage sites, reduce repair costs, and achieve the goal of quickly restoring traffic line operations.
附图说明 Description of drawings
图1应急抢修混凝土箱梁分构件示意图。 Fig. 1 Schematic diagram of sub-components of concrete box girder for emergency repair.
图2应急抢修混凝土箱梁横截面示意图。 Figure 2 Schematic diagram of the cross-section of the emergency repair concrete box girder.
图3应急抢修混凝土箱梁顶板节段示意图。 Fig. 3 Schematic diagram of emergency repair concrete box girder roof segment.
图4应急抢修混凝土箱梁跨中底板节段示意图。 Fig. 4 Schematic diagram of emergency repair concrete box girder mid-span mid-floor segment.
图5应急抢修混凝土箱梁支座附近底板节段示意图。 Fig. 5 Schematic diagram of the floor section near the concrete box girder support for emergency repair.
图6应急抢修混凝土箱梁波形钢腹板节段示意图。 Fig. 6 Schematic diagram of corrugated steel web section of concrete box girder for emergency repair.
图7应急抢修混凝土箱梁整体布置图。 Fig. 7 Overall layout of concrete box girder for emergency repair.
图8应急抢修混凝土箱梁体外预应力布置示意图。 Fig. 8 Schematic diagram of external prestressed layout of concrete box girder for emergency repair.
图9混凝土箱梁现场抢修时在现场桥墩之间搭设支架立面示意图。 Figure 9 is a schematic diagram of the elevation of supports erected between on-site bridge piers during on-site emergency repair of concrete box girders.
图10混凝土箱梁现场抢修时在现场桥墩之间搭设支架Ⅰ―Ⅰ断面示意图。 Fig. 10 Schematic diagram of the cross-section of brackets Ⅰ-Ⅰ erected between on-site bridge piers during on-site emergency repair of concrete box girders.
图11混凝土箱梁现场抢修时吊装混凝土底板构件到搭设好支架上立面示意图。 Fig. 11 Schematic diagram of the elevation of the concrete bottom plate member hoisted to the erected support during the on-site emergency repair of the concrete box girder.
图12混凝土箱梁现场抢修时吊装混凝土底板构件到搭设好支架上Ⅱ—Ⅱ断面示意图。 Fig. 12 Schematic diagram of section Ⅱ-Ⅱ of hoisting the concrete bottom plate member to the erected bracket during the on-site emergency repair of the concrete box girder.
图13混凝土箱梁现场抢修时吊装波形钢腹板并与混凝土底板构件进行拼装连接立面示意图。 Fig. 13 Elevation schematic diagram of hoisting corrugated steel web and assembling connection with concrete floor members during on-site emergency repair of concrete box girder.
图14混凝土箱梁现场抢修时吊装波形钢腹板并与混凝土底板构件进行拼装连接Ⅲ―Ⅲ断面示意图。 Fig. 14 Schematic diagram of cross section III-III of hoisting corrugated steel web and assembling connection with concrete floor members during on-site emergency repair of concrete box girder.
图15混凝土箱梁现场抢修时吊装混凝土顶板构件与波形钢腹板进行拼装连接立面示意图。 Figure 15. Elevation schematic diagram of the assembled connection between the hoisting concrete roof member and the corrugated steel web during the on-site emergency repair of the concrete box girder.
图16混凝土箱梁现场抢修时吊装混凝土顶板构件与波形钢腹板进行拼装连接Ⅳ—Ⅳ断面示意图。 Figure 16 Schematic diagram of the Ⅳ-Ⅳ section of the assembled connection between the hoisting concrete roof member and the corrugated steel web during the on-site emergency repair of the concrete box girder.
图17混凝土箱梁现场抢修时吊装完成后混凝土箱梁整体布置立面示意图。 Figure 17 Schematic diagram of the elevation of the overall layout of the concrete box girder after the hoisting is completed during the on-site emergency repair of the concrete box girder.
图18混凝土箱梁现场抢修时吊装完成后混凝土箱梁整体布置Ⅴ―Ⅴ断面示意图。 Figure 18 Schematic diagram of the V-V section of the overall layout of the concrete box girder after the hoisting is completed during the on-site emergency repair of the concrete box girder.
图中:1—混凝土顶板;2—混凝土底板;3—波形钢腹板;4—桥墩;5—支架;6—堵头;7-1—顶板榫头;7-2—底板榫头;8-1—顶板榫孔;8-2—底板榫孔;9-1—顶板体内预应力筋;9-2—底板体内预应力筋;10-1—顶板预应力孔道;10-2—底板预应力孔道;11—体外预应力筋;12—转向块;13-1—顶板与波形钢腹板连接螺栓;13-2—底板与波形钢腹板连接螺栓;13-3—波形钢腹板与波形钢腹板连接螺栓。 In the figure: 1—concrete top slab; 2—concrete bottom slab; 3—corrugated steel web; 4—bridge pier; 5—bracket; 6—plug; —top mortise hole; 8-2—bottom mortise hole; 9-1—prestressed tendon in top plate; 9-2—prestressed tendon in bottom plate; 10-1—top prestressed channel; 10-2—bottom plate prestressed channel ; 11—external prestressed tendons; 12—steering block; 13-1—connecting bolts between top plate and corrugated steel web; 13-2—connecting bolts between bottom plate and corrugated steel web; 13-3—corrugated steel web and corrugated steel Web connection bolts.
具体实施方式 Detailed ways
结合附图对本实用新型做进一步说明: The utility model is further described in conjunction with the accompanying drawings:
一种用于抢修混凝土箱梁的预制构件现场拼装组合梁,其特征在于包括以下步骤: A prefabricated on-site assembled composite beam for repairing concrete box girders is characterized in that it comprises the following steps:
步骤1:按一定尺寸和规格预制混凝土顶板1、混凝土底板2、波形钢腹板3、堵头6等构件并存放在存梁场内。 Step 1: Prefabricate concrete roof 1, concrete bottom 2, corrugated steel web 3, plug 6 and other components according to a certain size and specification and store them in the beam storage yard.
步骤2:拆除已损坏的混凝土箱梁,在其现场两桥墩之间搭设支架5。 Step 2: Remove the damaged concrete box girder, and erect support 5 between two bridge piers on site.
步骤3:去存梁场内把对应尺寸和规格的已预制好的混凝土顶板1、混凝土底板2、波形钢腹板3、堵头6等构件运到抢修现场。 Step 3: Go to the beam storage yard and transport the prefabricated concrete roof 1, concrete floor 2, corrugated steel web 3, plug 6 and other components of corresponding sizes and specifications to the emergency repair site.
步骤4:吊装混凝土底板2到搭设好的支架5上,通过设置在混凝土底板2两端侧面上的底板榫头7-2和底板榫孔8-2将各混凝土底板2节段连接起来;混凝土底板2节段连接前,先在榫头7-2和混凝土底板2两端侧面上涂抹环氧树脂或水泥砂浆;混凝土底板2节段连接后,在混凝土底板2节段底板预应力孔道10-2内穿入底板体内预应力筋9-2并进行张拉,使混凝土底板2各节段连接成一个整体。 Step 4: Hoist the concrete base plate 2 to the erected support 5, and connect the concrete base plate 2 sections through the base plate tenon 7-2 and the base plate tenon hole 8-2 arranged on the sides of the concrete base plate 2 at both ends; the concrete base plate Before the two sections are connected, first apply epoxy resin or cement mortar on the tenon 7-2 and the sides of the two ends of the concrete floor 2; Penetrate the prestressed tendons 9-2 in the bottom plate and stretch them, so that the sections of the concrete bottom plate 2 are connected into a whole.
步骤5:吊装波形钢腹板3节段并与混凝土底板2节段进行拼装连接,波形钢腹板3与混凝土底板2间采用底板与波形钢腹板连接螺栓13-2进行连接;各波形钢腹板3节段间采用波形钢腹板与波形钢腹板连接螺栓13-3进行连接。 Step 5: Hoist the corrugated steel web section 3 and assemble it with the concrete floor 2 section. The 3 segments of the web are connected by the corrugated steel web and the corrugated steel web connecting bolt 13-3.
步骤6:吊装混凝土顶板1到拼接好的波形钢腹板3节段上,并使混凝土顶板1节段与波形钢腹板3节段之间采用顶板与波形钢腹板连接螺栓13-1进行连接;通过设置在混凝土顶板1两端侧面上的顶板榫头7-1和顶板榫孔8-1将各混凝土顶板1节段连接起来;混凝土顶板1节段连接前,先在顶板榫头7-1和混凝土顶板1两端侧面上涂抹环氧树脂或水泥砂浆;混凝土顶板1节段连接后,在混凝土顶板1节段顶板预应力孔道10-1内穿入顶板体内预应力筋9-1并进行张拉,使混凝土顶板1各节段连接成一个整体。 Step 6: Hoist the concrete roof 1 onto the spliced corrugated steel web 3 segment, and make the connection between the concrete roof 1 segment and the corrugated steel web 3 segment use the top plate and corrugated steel web connecting bolt 13-1 Connection; each concrete roof 1 segment is connected through the roof tenon 7-1 and roof tenon hole 8-1 arranged on the two ends of the concrete roof 1; before the concrete roof 1 segment is connected, the roof tenon 7-1 Epoxy resin or cement mortar is applied on both ends of the concrete roof 1; after the concrete roof 1 section is connected, the prestressed tendons 9-1 in the roof body are penetrated into the roof prestressed channel 10-1 of the concrete roof 1 section and carried out Stretching, so that the sections of the concrete roof 1 are connected into a whole.
亦可采用下述步骤:吊装混凝土顶板1到拼接好的波形钢腹板3节段上, 先通过设置在混凝土顶板1两端侧面上的顶板榫头7-1和顶板榫孔8-1将各混凝土顶板1节段连接起来;混凝土顶板1节段连接前,先在顶板榫头7-1和混凝土顶板1两端侧面上涂抹环氧树脂或水泥砂浆;混凝土顶板1节段连接后,在混凝土顶板1节段顶板预应力孔道10-1内穿入顶板体内预应力筋9-1并进行张拉,使混凝土顶板1各节段连接成一个整体;最后,使已拼接好的混凝土顶板1节段与波形钢腹板3节段之间采用顶板与波形钢腹板连接螺栓13-1进行连接。 The following steps can also be adopted: hoisting the concrete roof 1 to the spliced corrugated steel web 3 segments, and first through the roof tenons 7-1 and the roof tenons 8-1 arranged on the sides of the concrete roof 1. The concrete roof 1 section is connected; before the concrete roof 1 section is connected, epoxy resin or cement mortar is first applied to the roof tenon 7-1 and the two ends of the concrete roof 1; after the concrete roof 1 section is connected, the concrete roof The prestressed channel 10-1 of the 1-section roof penetrates into the prestressed tendon 9-1 in the roof body and is stretched, so that the sections of the concrete roof 1 are connected into a whole; finally, the spliced concrete roof 1 section The top plate and the corrugated steel web connecting bolt 13-1 are used to connect with the corrugated steel web 3 segments.
步骤7:吊装堵头6到预制拼装的混凝土箱梁的两端,在已拼接好的混凝土底板2和堵头6上布置体外预应力筋11,张拉该体外预应力筋11,使分构件预制拼装的混凝土箱梁各构件形成一个完整的混凝土箱梁。 Step 7: Lift the plugs 6 to the two ends of the prefabricated concrete box girder, arrange the external prestressed tendons 11 on the spliced concrete floor 2 and the plugs 6, and stretch the external prestressed tendons 11 to make the sub-components Each component of the prefabricated and assembled concrete box girder forms a complete concrete box girder.
步骤8:在已拼装好的混凝土箱梁顶板1上安装桥面系和附属设施,待施工质量验收通过后,即可实现对损坏混凝土箱梁的应急抢修和线路的恢复运营。 Step 8: Install the bridge deck system and auxiliary facilities on the assembled concrete box girder roof 1. After the construction quality acceptance is passed, the emergency repair of the damaged concrete box girder and the restoration of the line can be realized.
混凝土箱梁的应急抢修方法的应用 Application of Emergency Repair Method for Concrete Box Girder
实例一一榀跨度为24米双线整体预应力混凝土高速铁路箱梁,遭受人为破坏。为此,采用分构件预制拼装的混凝土箱梁应急抢修方法进行抢修。其抢修方法为: Example 1: A double-track integrally prestressed concrete high-speed railway box girder with a span of 24 meters suffered man-made damage. For this reason, the emergency repair method of concrete box girder prefabricated and assembled by sub-components is used for emergency repair. The repair method is:
步骤1:按一定尺寸和规格预制混凝土顶板1、混凝土底板2、波形钢腹板3、堵头6等构件并存放在存梁场内。 Step 1: Prefabricate concrete roof 1, concrete bottom 2, corrugated steel web 3, plug 6 and other components according to a certain size and specification and store them in the beam storage yard.
步骤2:拆除已损坏的混凝土箱梁,在其现场两桥墩之间搭设支架5。 Step 2: Remove the damaged concrete box girder, and erect support 5 between two bridge piers on site.
步骤3:去存梁场内把对应尺寸和规格的已预制好的混凝土顶板1、混凝土底板2、波形钢腹板3、堵头6等构件运到抢修现场。 Step 3: Go to the beam storage yard and transport the prefabricated concrete roof 1, concrete floor 2, corrugated steel web 3, plug 6 and other components of corresponding sizes and specifications to the emergency repair site.
步骤4:吊装混凝土底板2到搭设好的支架5上,通过设置在混凝土底板2两端侧面上的底板榫头7-2和底板榫孔8-2将各混凝土底板2节段连接起来;混 凝土底板2节段连接前,先在榫头7-2和混凝土底板2两端侧面上涂抹环氧树脂或水泥砂浆;混凝土底板2节段连接后,在混凝土底板2节段底板预应力孔道10-2内穿入底板体内预应力筋9-2并进行张拉,使混凝土底板2各节段连接成一个整体。 Step 4: Hoist the concrete bottom slab 2 onto the erected support 5, and connect the concrete bottom slab 2 segments through the bottom slab tenon 7-2 and the bottom slab tenon hole 8-2 arranged on the two ends of the concrete bottom slab 2; Before connecting the 2 sections of the soil floor, apply epoxy resin or cement mortar on the mortise 7-2 and the sides of the two ends of the concrete floor 2; 2 penetrates the prestressed tendons 9-2 inside the bottom plate and stretches them, so that the sections of the concrete bottom plate 2 are connected into a whole.
步骤5:吊装波形钢腹板3节段并与混凝土底板2节段进行拼装连接,波形钢腹板3与混凝土底板2间采用底板与波形钢腹板连接螺栓13-2进行连接;各波形钢腹板3节段间采用波形钢腹板与波形钢腹板连接螺栓13-3进行连接。 Step 5: Hoist the corrugated steel web section 3 and assemble it with the concrete floor 2 section. The 3 segments of the web are connected by the corrugated steel web and the corrugated steel web connecting bolt 13-3.
步骤6:吊装混凝土顶板1到拼接好的波形钢腹板3节段上,并使混凝土顶板1节段与波形钢腹板3节段之间采用顶板与波形钢腹板连接螺栓13-1进行连接;通过设置在混凝土顶板1两端侧面上的顶板榫头7-1和顶板榫孔8-1将各混凝土顶板1节段连接起来;混凝土顶板1节段连接前,先在顶板榫头7-1和混凝土顶板1两端侧面上涂抹环氧树脂或水泥砂浆;混凝土顶板1节段连接后,在混凝土顶板1节段顶板预应力孔道10-1内穿入顶板体内预应力筋9-1并进行张拉,使混凝土顶板1各节段连接成一个整体。 Step 6: Hoist the concrete roof 1 onto the spliced corrugated steel web 3 segment, and make the connection between the concrete roof 1 segment and the corrugated steel web 3 segment use the top plate and corrugated steel web connecting bolt 13-1 Connection; each concrete roof 1 segment is connected through the roof tenon 7-1 and roof tenon hole 8-1 arranged on the two ends of the concrete roof 1; before the concrete roof 1 segment is connected, the roof tenon 7-1 Epoxy resin or cement mortar is applied on both ends of the concrete roof 1; after the concrete roof 1 section is connected, the prestressed tendons 9-1 in the roof body are penetrated into the roof prestressed channel 10-1 of the concrete roof 1 section and carried out Stretching, so that the sections of the concrete roof 1 are connected into a whole.
步骤7:吊装堵头6到预制拼装的混凝土箱梁的两端,在已拼接好的混凝土底板2和堵头6上布置体外预应力筋11,张拉该体外预应力筋11,使分构件预制拼装的混凝土箱梁各构件形成一个完整的混凝土箱梁。 Step 7: Lift the plugs 6 to the two ends of the prefabricated concrete box girder, arrange the external prestressed tendons 11 on the spliced concrete floor 2 and the plugs 6, and stretch the external prestressed tendons 11 to make the sub-components Each component of the prefabricated and assembled concrete box girder forms a complete concrete box girder.
步骤8:在已拼装好的混凝土箱梁顶板1上安装桥面系和附属设施,待施工质量验收通过后,即可实现对损坏混凝土箱梁的应急抢修和线路的恢复运营。 Step 8: Install the bridge deck system and auxiliary facilities on the assembled concrete box girder roof 1. After the construction quality acceptance is passed, the emergency repair of the damaged concrete box girder and the restoration of the line can be realized.
实例二一榀跨度为32米双线整体预应力混凝土重载铁路箱梁,在地震中上部结构遭受严重破坏。为此,采用分构件预制拼装的混凝土箱梁应急抢修方法进行抢修。其抢修方法为: Example 2: A double-track integrally prestressed concrete heavy-duty railway box girder with a span of 32 meters suffered serious damage to the upper structure during the earthquake. For this reason, the emergency repair method of concrete box girder prefabricated and assembled by sub-components is used for emergency repair. The repair method is:
步骤1:按一定尺寸和规格预制混凝土顶板1、混凝土底板2、波形钢腹板3、堵头6等构件并存放在存梁场内。 Step 1: Prefabricate concrete roof 1, concrete bottom 2, corrugated steel web 3, plug 6 and other components according to a certain size and specification and store them in the beam storage yard.
步骤2:拆除已损坏的混凝土箱梁,在其现场两桥墩之间搭设支架5。 Step 2: Remove the damaged concrete box girder, and erect support 5 between two bridge piers on site.
步骤3:去存梁场内把对应尺寸和规格的已预制好的混凝土顶板1、混凝土底板2、波形钢腹板3、堵头6等构件运到抢修现场。 Step 3: Go to the beam storage yard and transport the prefabricated concrete roof 1, concrete floor 2, corrugated steel web 3, plug 6 and other components of corresponding sizes and specifications to the emergency repair site.
步骤4:吊装混凝土底板2到搭设好的支架5上,通过设置在混凝土底板2两端侧面上的底板榫头7-2和底板榫孔8-2将各混凝土底板2节段连接起来;混凝土底板2节段连接前,先在榫头7-2和混凝土底板2两端侧面上涂抹环氧树脂或水泥砂浆;混凝土底板2节段连接后,在混凝土底板2节段底板预应力孔道10-2内穿入底板体内预应力筋9-2并进行张拉,使混凝土底板2各节段连接成一个整体。 Step 4: Hoist the concrete base plate 2 onto the erected support 5, and connect the concrete base plate 2 sections through the base plate tenon 7-2 and the base plate tenon hole 8-2 arranged on the sides of the concrete base plate 2 at both ends; the concrete base plate Before the two sections are connected, first apply epoxy resin or cement mortar on the tenon 7-2 and the sides of the two ends of the concrete floor 2; Penetrate the prestressed tendons 9-2 in the bottom plate and stretch them, so that the sections of the concrete bottom plate 2 are connected into a whole.
步骤5:吊装波形钢腹板3节段并与混凝土底板2节段进行拼装连接,波形钢腹板3与混凝土底板2间采用底板与波形钢腹板连接螺栓13-2进行连接;各波形钢腹板3节段间采用波形钢腹板与波形钢腹板连接螺栓13-3进行连接。 Step 5: Hoist the corrugated steel web section 3 and assemble it with the concrete floor 2 section. The 3 segments of the web are connected by the corrugated steel web and the corrugated steel web connecting bolt 13-3.
步骤6:吊装混凝土顶板1到拼接好的波形钢腹板3节段上,先通过设置在混凝土顶板1两端侧面上的顶板榫头7-1和顶板榫孔8-1将各混凝土顶板1节段连接起来;混凝土顶板1节段连接前,先在顶板榫头7-1和混凝土顶板1两端侧面上涂抹环氧树脂或水泥砂浆;混凝土顶板1节段连接后,在混凝土顶板1节段顶板预应力孔道10-1内穿入顶板体内预应力筋9-1并进行张拉,使混凝土顶板1各节段连接成一个整体;最后,使已拼接好的混凝土顶板1节段与波形钢腹板3节段之间采用顶板与波形钢腹板连接螺栓13-1进行连接。 Step 6: Hoist the concrete roof 1 to the spliced corrugated steel web 3 section, and first connect each concrete roof 1 section through the roof tenon 7-1 and the roof tenon hole 8-1 arranged on the two ends of the concrete roof 1 before the concrete roof 1 section is connected, apply epoxy resin or cement mortar on the roof tenon 7-1 and the two ends of the concrete roof 1; after the concrete roof 1 section is connected, the concrete roof 1 section roof The prestressed channel 10-1 penetrates the prestressed tendon 9-1 in the roof and stretches it, so that the sections of the concrete roof 1 are connected into a whole; finally, the spliced concrete roof 1 section and the corrugated steel web The top plate and corrugated steel web connecting bolts 13-1 are used to connect the plate 3 sections.
步骤7:吊装堵头6到预制拼装的混凝土箱梁的两端,在已拼接好的混凝土 底板2和堵头6上布置体外预应力筋11,张拉该体外预应力筋11,使分构件预制拼装的混凝土箱梁各构件形成一个完整的混凝土箱梁。 Step 7: Lift the plug 6 to the two ends of the prefabricated concrete box girder, arrange the external prestressed tendons 11 on the spliced concrete floor 2 and the plug 6, and stretch the external prestressed tendons 11 to make the sub-components Each component of the prefabricated and assembled concrete box girder forms a complete concrete box girder.
步骤8:在已拼装好的混凝土箱梁顶板1上安装桥面系和附属设施,待施工质量验收通过后,即可实现对损坏混凝土箱梁的应急抢修和线路的恢复运营。 Step 8: Install the bridge deck system and auxiliary facilities on the assembled concrete box girder roof 1. After the construction quality acceptance is passed, the emergency repair of the damaged concrete box girder and the restoration of the line can be realized.
以上所述的具体实施方法,对本实用新型专利的目的、技术方案和有益效果进行了说明。所应强调的是,以上所述仅为本实用新型专利的具体实施例而已,并不能用于限制本实用新型的范围。凡在本实用新型的精神和原则之内,所做的任何修改、等同替换或改进等,均应包含在本实用新型的保护范围之内。 The specific implementation method described above illustrates the purpose, technical solutions and beneficial effects of the utility model patent. It should be emphasized that the above descriptions are only specific embodiments of the utility model patent, and cannot be used to limit the scope of the utility model. Any modification, equivalent replacement or improvement made within the spirit and principles of the present utility model shall be included in the protection scope of the present utility model.
综上所述,本实用新型提供了一种用于抢修混凝土箱梁的预制构件现场拼装组合梁,该组合梁能够有效地减少抢修过程中对大型运输和起吊设备的依赖,加快桥梁的抢修速度,减少应急梁储存场的面积和规模,降低抢修成本,实现快速恢复交通线路运营的目标。本实用新型具有新颖性、实用性,符合实用新型专利各要求,故依法提出实用新型专利申请。 In summary, the utility model provides a prefabricated component field assembled composite beam for emergency repair of concrete box girders. The composite beam can effectively reduce the dependence on large-scale transportation and lifting equipment in the emergency repair process, and speed up the bridge repair speed , reduce the area and scale of the emergency beam storage yard, reduce the repair cost, and achieve the goal of quickly restoring the operation of the traffic line. The utility model has novelty and practicability, and meets the requirements of the utility model patent, so the utility model patent application is filed according to law.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420847247.2U CN204417983U (en) | 2014-12-26 | 2014-12-26 | A kind of prefabricated units on-site consolidation compound beam for rushing to repair concrete box girder |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420847247.2U CN204417983U (en) | 2014-12-26 | 2014-12-26 | A kind of prefabricated units on-site consolidation compound beam for rushing to repair concrete box girder |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204417983U true CN204417983U (en) | 2015-06-24 |
Family
ID=53468367
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420847247.2U Expired - Lifetime CN204417983U (en) | 2014-12-26 | 2014-12-26 | A kind of prefabricated units on-site consolidation compound beam for rushing to repair concrete box girder |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204417983U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105178166A (en) * | 2015-10-15 | 2015-12-23 | 上海市政工程设计研究总院(集团)有限公司 | Combined steel box beam bridge with transverse ribs |
CN109537467A (en) * | 2018-12-18 | 2019-03-29 | 中交天津航道局有限公司 | A kind of box girder pre-stressed construction method |
CN110878513A (en) * | 2019-11-19 | 2020-03-13 | 辽宁省城乡市政工程集团有限责任公司 | A kind of prefabricated prestressed concrete beam and steel-concrete composite beam splicing bridge and construction method |
CN112458868A (en) * | 2020-11-05 | 2021-03-09 | 滁州职业技术学院 | Corrugated steel web beam bridge capable of improving overall crack resistance |
CN112523062A (en) * | 2020-12-16 | 2021-03-19 | 重庆交通大学 | Steel-concrete combined box girder viaduct structure |
CN114016370A (en) * | 2021-12-09 | 2022-02-08 | 安徽省交通规划设计研究总院股份有限公司 | 'hysteresis type' narrow steel box composite beam and construction method thereof |
-
2014
- 2014-12-26 CN CN201420847247.2U patent/CN204417983U/en not_active Expired - Lifetime
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105178166A (en) * | 2015-10-15 | 2015-12-23 | 上海市政工程设计研究总院(集团)有限公司 | Combined steel box beam bridge with transverse ribs |
CN109537467A (en) * | 2018-12-18 | 2019-03-29 | 中交天津航道局有限公司 | A kind of box girder pre-stressed construction method |
CN110878513A (en) * | 2019-11-19 | 2020-03-13 | 辽宁省城乡市政工程集团有限责任公司 | A kind of prefabricated prestressed concrete beam and steel-concrete composite beam splicing bridge and construction method |
CN112458868A (en) * | 2020-11-05 | 2021-03-09 | 滁州职业技术学院 | Corrugated steel web beam bridge capable of improving overall crack resistance |
CN112523062A (en) * | 2020-12-16 | 2021-03-19 | 重庆交通大学 | Steel-concrete combined box girder viaduct structure |
CN112523062B (en) * | 2020-12-16 | 2022-05-10 | 重庆交通大学 | Steel-concrete combined box girder viaduct structure |
CN114016370A (en) * | 2021-12-09 | 2022-02-08 | 安徽省交通规划设计研究总院股份有限公司 | 'hysteresis type' narrow steel box composite beam and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204417983U (en) | A kind of prefabricated units on-site consolidation compound beam for rushing to repair concrete box girder | |
WO2021147256A1 (en) | Single-side integral hoisted large-span overbridge crossing over multiple railway lines, and construction method therefor | |
CN108049498B (en) | Prefabricated column and prefabricated beam connection structure and method of prefabricated building frame structure | |
CN108978434B (en) | Bracket-free industrialized construction method of steel-concrete combined continuous box girder bridge | |
CN205329526U (en) | Pier is assembled to precast concrete | |
CN104652293B (en) | A kind of Cable-Stayed Bridge Structure for reinforcing PSC Continuous Box Girder Bridge and construction method | |
CN105735101B (en) | A kind of high-speed railway repairing beam and its emergency repair method that can be exchanged into permanent bridge structure | |
CN202718022U (en) | Fabricated type prestressed concrete pavement | |
CN108867310A (en) | The short rib T beam bridge of pretensioning prestressed concrete and its construction method | |
CN106013432A (en) | Joint connecting structure in high-ductility assembled integrated frame and construction method | |
CN114592436B (en) | Pier capping beam lower support system and construction method thereof | |
CN111877182A (en) | Novel construction method for upper structure of multi-chamber continuous UHPC box girder bridge | |
CN202000251U (en) | Cylindrical hollow prefabricated prestressed concrete pier structure | |
CN108951399A (en) | A kind of Single-box multi-chamber box beam bridge and its construction method | |
CN104652244B (en) | A kind of Suspension bridge structure for reinforcing PSC Continuous Box Girder Bridge and construction method | |
CN106149569A (en) | The transforming methods of structural system of self-anchored suspension bridge First cable later girder construction | |
CN106087694B (en) | Assembling steel plate-beams of concrete combined bridge structure and construction method | |
CN203559329U (en) | Steel-RPC (reactive powder concrete) combined bridge | |
CN104612063A (en) | Concrete box beam first-aid repair method with prefabricated part on-site assembling combination beam | |
CN209482130U (en) | A combined structure of fully prefabricated bridge piers and caps | |
CN203639841U (en) | Steel plate-concrete combined reinforcement structure of hollow plate beam | |
CN202466338U (en) | Construction device for rapidly recovering metro station road | |
CN205501788U (en) | A high-speed railway repair beam convertible to a permanent bridge structure | |
CN111926690A (en) | Novel pier is assembled in prefabrication | |
CN108487291B (en) | Installation method of contact net stand column foundation on railway steel-concrete composite beam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term | ||
CX01 | Expiry of patent term |
Granted publication date: 20150624 |