CN204385761U - A kind of main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional - Google Patents

A kind of main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional Download PDF

Info

Publication number
CN204385761U
CN204385761U CN201420869300.9U CN201420869300U CN204385761U CN 204385761 U CN204385761 U CN 204385761U CN 201420869300 U CN201420869300 U CN 201420869300U CN 204385761 U CN204385761 U CN 204385761U
Authority
CN
China
Prior art keywords
built
earthquake isolating
isolating equipment
fitting
main transformer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201420869300.9U
Other languages
Chinese (zh)
Inventor
卢懿
钟山
余波
张映桢
徐小丽
杨关
冯仁德
何勇
毛宇
周华强
刘承
刘月署
张勤
魏勇
冯兵
伍鑫元
羊鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Electric Power Design Institute Co Ltd of China Power Engineering Consulting Group
Original Assignee
Southwest Electric Power Design Institute Co Ltd of China Power Engineering Consulting Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Electric Power Design Institute Co Ltd of China Power Engineering Consulting Group filed Critical Southwest Electric Power Design Institute Co Ltd of China Power Engineering Consulting Group
Priority to CN201420869300.9U priority Critical patent/CN204385761U/en
Application granted granted Critical
Publication of CN204385761U publication Critical patent/CN204385761U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Landscapes

  • Housings And Mounting Of Transformers (AREA)

Abstract

The utility model provides a kind of main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional, comprise basic pedestal, basis installation portion and the jack built-in fitting be made up of the first embedded board and the earthquake isolating equipment built-in fitting be formed by fixedly connecting by the second embedded board and built-in bolt sleeve, installation portion bottom, basis is fixedly connected with basic pedestal, and between adjacent two basic installation portions, a determining deviation is set, basis installation portion top respectively with jack built-in fitting, earthquake isolating equipment built-in fitting is fixedly connected with, second embedded board is offered the locating hole communicated with built-in bolt sleeve, it is inner that built-in bolt sleeve is cemented in basic installation portion.Utilize the utility model that earthquake isolating equipment can be made easily to be connected and fixed with earthquake isolating equipment built-in fitting by high-strength bolt, improve the stability against earthquake performance of main transformer equipment, and convenient operation personnel comprise earthquake isolating equipment to main transformer equipment and install, overhaul and replacement operation, there is the outstanding advantages such as structure is simple, cost-saving.

Description

A kind of main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional
Technical field
The utility model relates to extra-high voltage electric power transmission infrastructure field, especially relates to a kind of main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional.
Background technology
(g is wherein acceleration of gravity to be arranged in the electric equipments equal demand fulfillment horizontal earthquake acceleration 0.4g of the 500kV transformer station in 8 degree of high earthquake intensity areas, shock resistance down together), for the main transformer (abbreviation of " main transformer " in 500kV transformer station, lower same), because its physical dimension is large, center of gravity is low, quality is large, based on shear strain under geological process, belong to heavy dwarf forms equipment.When an earthquake occurs, the porcelain bushing of main transformer body device body to its top has obvious earthquake enlarge-effect, therefore, even if also may bear through the sleeve pipe of seismic design the geological process exceeding its limiting design value.
In order to alleviate the damaging influence of earthquake to main transformer, need (to be called for short " main transformer foundation " at the installation foundation of main transformer equipment and main transformer, earthquake isolating equipment is rationally installed additional down together), connecting portion normally between main transformer equipment and main transformer foundation installs laminated rubber isolation cushion additional, and the model of isolation cushion, quantity, layout location are determined by Cable Power Computation.By the seismic response adopting earthquake isolating equipment farthest to reduce main transformer equipment under geological process, while alleviating main transformer apparatus body geological process, protective casing is not destroyed.Therefore, the shock resistance of main transformer foundation is most important for the safety of protection main transformer equipment under geological process.If main transformer foundation suffers seismic damage, it will be catastrophic to the destruction that main transformer equipment causes, and not only directly cause blackout, and the likely secondary disaster such as initiation fire.
Utility model content
The technical problems to be solved in the utility model is: for prior art Problems existing, a kind of main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional is provided, improve the stability against earthquake performance of main transformer equipment, and conveniently earthquake isolating equipment is comprised to main transformer equipment install, overhaul and replacement operation.
The technical problems to be solved in the utility model realizes by the following technical solutions: a kind of main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional, comprise basic pedestal, basis installation portion and the jack built-in fitting be made up of the first embedded board and the earthquake isolating equipment built-in fitting be formed by fixedly connecting by the second embedded board and built-in bolt sleeve, described basic installation portion bottom is fixedly connected with basic pedestal, and between adjacent two basic installation portions, a determining deviation is set, described basic installation portion top respectively with jack built-in fitting, earthquake isolating equipment built-in fitting is fixedly connected with, second embedded board is offered the locating hole communicated with built-in bolt sleeve, it is inner that described built-in bolt sleeve is cemented in basic installation portion.
Preferably, described jack built-in fitting also comprises the first connection dowel, and described first connects dowel is fixedly connected with the first embedded board, and the first connection dowel is cemented in basic installation portion inside.
Preferably, be welded and fixed between described first connection dowel and the first embedded board.
Preferably, between the first embedded board side of described jack built-in fitting and basic installation portion, the first buffer fillings layer be made up of elastomeric material is set.
Preferably, the first described buffer fillings layer is silicone weather resistant glue.
Preferably, the second described embedded board offers through hole.
Preferably, the second buffer fillings layer be made up of elastomeric material is set between described second embedded board side and basic installation portion.
Preferably, the second described buffer fillings layer is silicone weather resistant glue.
Preferably, described earthquake isolating equipment built-in fitting also comprises the second connection dowel, and described second connects dowel is fixedly connected with the second embedded board, and the second connection dowel is cemented in basic installation portion inside.
Preferably, described earthquake isolating equipment built-in fitting also comprises the second connection dowel, and described second connection dowel forms screw thread with built-in bolt sleeve and is flexibly connected, and the second connection dowel is cemented in basic installation portion inside.
Compared with prior art, the beneficial effects of the utility model are: owing to being provided with jack built-in fitting and earthquake isolating equipment built-in fitting on main transformer foundation, and a reserved determining deviation forms constructing operation passage and access path between basic installation portion on main transformer foundation, earthquake isolating equipment easily can be connected and fixed with earthquake isolating equipment built-in fitting by high-strength bolt, improve main transformer equipment and be installed to stability against earthquake performance on main transformer foundation, and save the constructional materials consumption of main transformer foundation, be conducive to reducing the construction volume of main transformer foundation and saving the overall construction cost of main transformer foundation, jack jacking main transformer equipment can be facilitated by jack built-in fitting, install so that operating personnel comprise earthquake isolating equipment to main transformer equipment, overhaul and replacement operation, and ensure the safety of operation.
Accompanying drawing explanation
Fig. 1 is a kind of top view installing the main transformer foundation of earthquake isolating equipment for 500kV transformer station additional of the utility model.
Fig. 2 be in Fig. 1 A-A to sectional view.
Fig. 3 is the partial enlarged drawing at B place in Fig. 1.
Fig. 4 is the top view of jack built-in fitting in Fig. 1.
Fig. 5 be in Fig. 4 C-C to sectional view.
Fig. 6 is the top view of earthquake isolating equipment built-in fitting in Fig. 1.
Fig. 7 be in Fig. 6 E-E to sectional view (second connects dowel and the second embedded board directly fixes).
Fig. 8 be in Fig. 6 E-E to sectional view (second connects dowel and built-in bolt sleeve is interconnected).
Mark in figure: 1-basis pedestal, 2-basis installation portion, 3-jack built-in fitting, 4-earthquake isolating equipment built-in fitting, 5-first buffer fillings layer, 6-second buffer fillings layer, 31-first embedded board, 32-first connects dowel, 41-second embedded board, 42-through hole, 43-locating hole, 44-built-in bolt sleeve, 45-second connects dowel.
Detailed description of the invention
In order to make the purpose of this utility model, technical scheme and advantage clearly understand, below in conjunction with the drawings and specific embodiments, the utility model is described in detail.Should be appreciated that specific embodiment described herein only in order to explain the utility model, and be not used in restriction the utility model.
A kind of main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional as shown in Figure 1 and Figure 2, it is vertically being divided into upper and lower two large divisions in appearance: the part being positioned at below oil sump base plate is the basic pedestal 1 of complete board type, to strengthen the integral rigidity of main transformer foundation, alleviating bottom main transformer foundation while subsidiary stress, its seismic stability can strengthened, the part being positioned at more than oil sump base plate is the strip foundation installation portion 2 of sectional type, between adjacent two basic installation portions 2, a determining deviation is set, all basic installation portions 2 all adopt reinforced concrete whole-casting to form integral structure with basic pedestal 1, adopt such structure can while the integral rigidity ensureing main transformer foundation and the intensity that is rigidly connected between basic installation portion 2 and basic pedestal 1, the headspace between two adjacent basic installation portions 2 is made to form constructing operation passage and access path, earthquake isolating equipment is comprised to main transformer equipment install to facilitate, maintenance and replacement operation, and structure is simple, compact, save the constructional materials consumption of main transformer foundation, reduce the construction volume of main transformer foundation, save the overall construction cost of main transformer foundation.
The jack built-in fitting 3 and earthquake isolating equipment built-in fitting 4 of being convenient to jack jacking main transformer equipment is fixedly connected with respectively on basic installation portion 2 top, described jack built-in fitting 3 as shown in Figure 4, Figure 5, form primarily of the first embedded board 31, described first embedded board 31 is square plate, and is cemented in basic installation portion 2 top with embedded mode.Described earthquake isolating equipment built-in fitting 4 is as shown in Fig. 6, Fig. 7, Fig. 8, be welded and fixed primarily of the second embedded board 41 and built-in bolt sleeve 44 and form, described second embedded board 41 is square plate, and be cemented in basic installation portion 2 top with embedded mode, it is inner that described built-in bolt sleeve 44 is cemented in basic installation portion 2, and the second embedded board 41 is offered the locating hole 43 communicated with built-in bolt sleeve 44.Build in consolidation process at the second embedded board 41 with basic installation portion 2, hollow is there is in order to prevent the joint portion between the second embedded board 41 and basic installation portion 2 top, through hole 42 can be offered at the central part of the second embedded board 41, as shown in Figure 6, fully to ensure that the second embedded board 41 is sturdy with basic installation portion 2 top end face, paste jail, thus ensure that the bonding strength between earthquake isolating equipment built-in fitting 4 and main transformer foundation.
Main transformer foundation of the present utility model and earthquake isolating equipment pass through high strength exploitation, earthquake isolating equipment is placed on the second embedded board 41, the bolt hole adjusted on its junction plate aligns with the locating hole 43 on the second embedded board 41, high-strength bolt is flexibly connected through forming screw thread with built-in bolt sleeve 44 after the bolt hole on earthquake isolating equipment junction plate, locating hole 43, to facilitate maintenance and the replacing of earthquake isolating equipment successively.When earthquake isolating equipment needs maintenance or changes, by jack jacking main transformer equipment, after disassembling the high-strength bolt be connected with earthquake isolating equipment built-in fitting 4, the quick fetching of earthquake isolating equipment just can be realized.
When by jack jacking main transformer equipment, in order to improve the connection reliability between jack built-in fitting 3 and main transformer foundation, some first can be welded and fixed connect dowel 32 on the first embedded board 31, as shown in Figure 4, Figure 5, described first connection dowel 32 is all cemented in basic installation portion 2 inside.The contact area between jack built-in fitting 3 and basic installation portion 2 can be increased by the first connection dowel 32, thus the bonding strength strengthened between itself and main transformer foundation, improve the connection reliability of jack built-in fitting 3, be conducive to safety when ensureing jack jacking main transformer equipment.Similarly, in order to improve the connection reliability between earthquake isolating equipment built-in fitting 4 and main transformer foundation, some second can be welded and fixed connect dowel 45 on the second embedded board 41, as shown in Figure 7, also can connect dowel 45 one end second and the end of thread is set, make the second connection dowel 45 can form screw thread with built-in bolt sleeve 44 to be flexibly connected, as shown in Figure 8, described second connects dowel 45 is all cemented in basic installation portion 2 inside.The contact area between earthquake isolating equipment built-in fitting 4 and basic installation portion 2 can be increased by the second connection dowel 45, enhance the bonding strength between itself and main transformer foundation, improve the connection reliability between earthquake isolating equipment built-in fitting 4 and main transformer foundation, be conducive to the safety ensureing main transformer equipment, damping device.
Consider and main transformer foundation may increase other equipment by welding manner, when the first embedded board 31 of jack built-in fitting 3, the second embedded board 41 of earthquake isolating equipment built-in fitting 4 carry out welding operation with other equipment, the high temperature produced in welding process will cause the first embedded board 31, second embedded board 41 expanded by heating, thus very large expansion power is produced to basic installation portion 2, be unfavorable for the safety of main transformer foundation.For this reason, can the first buffer fillings layer 5 be made up of elastomeric material be set between the first embedded board 31 side and basic installation portion 2, similarly, the the second buffer fillings layer 6 be made up of elastomeric material is set between the second embedded board 41 side and basic installation portion 2, as shown in Figure 1, Figure 3, preferably, the first buffer fillings layer 5, second buffer fillings layer 6 wherein all adopts silicone weather resistant glue.Like this, just can be cushioned the expanded by heating of the first embedded board 31, second embedded board 41 respectively by the first buffer fillings layer 5, second buffer fillings layer 6, thus alleviate the first embedded board 31, second embedded board 41 expanded by heating to the direct impact of basic installation portion 2, improve the stability against earthquake performance of main transformer equipment, be conducive to the general safety ensureing main transformer foundation.
The foregoing is only preferred embodiment of the present utility model; not in order to limit the utility model; it should be pointed out that all do within spirit of the present utility model and principle any amendment, equivalent to replace and improvement etc., all should be included within protection domain of the present utility model.

Claims (10)

1. one kind installs the main transformer foundation of earthquake isolating equipment additional for 500kV transformer station, it is characterized in that: comprise basic pedestal (1), basis installation portion (2) and the jack built-in fitting (3) be made up of the first embedded board (31) and the earthquake isolating equipment built-in fitting (4) be formed by fixedly connecting by the second embedded board (41) and built-in bolt sleeve (44), described basic installation portion (2) bottom is fixedly connected with basic pedestal (1), and between adjacent two basic installation portions (2), a determining deviation is set, described basic installation portion (2) top respectively with jack built-in fitting (3), earthquake isolating equipment built-in fitting (4) is fixedly connected with, earthquake isolating equipment built-in fitting (4) is offered the locating hole (43) communicated with built-in bolt sleeve (44), it is inner that described built-in bolt sleeve (44) is cemented in basic installation portion (2).
2. the main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional according to claim 1, it is characterized in that: described jack built-in fitting (3) also comprises the first connection dowel (32), described first connects dowel (32) is fixedly connected with the first embedded board (31), and the first connection dowel (32) is cemented in basic installation portion (2) inside.
3. the main transformer foundation installing earthquake isolating equipment additional for 500kV transformer station according to claim 2, is characterized in that: be welded and fixed between described first connection dowel (32) and the first embedded board (31).
4. the main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional according to any one of claim 1-3, is characterized in that: arrange the first buffer fillings layer (5) be made up of elastomeric material between the first embedded board (31) side of described jack built-in fitting (3) and basic installation portion (2).
5. the main transformer foundation installing earthquake isolating equipment additional for 500kV transformer station according to claim 4, is characterized in that: the first described buffer fillings layer (5) is silicone weather resistant glue.
6. the main transformer foundation installing earthquake isolating equipment additional for 500kV transformer station according to claim 1, is characterized in that: described the second embedded board (41) offers through hole (42).
7. the main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional according to claim 1 or 6, is characterized in that: arrange the second buffer fillings layer (6) be made up of elastomeric material between described the second embedded board (41) side and basic installation portion (2).
8. the main transformer foundation installing earthquake isolating equipment additional for 500kV transformer station according to claim 7, is characterized in that: the second described buffer fillings layer (6) is silicone weather resistant glue.
9. the main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional according to claim 1, it is characterized in that: described earthquake isolating equipment built-in fitting (4) also comprises the second connection dowel (45), described second connects dowel (45) is fixedly connected with the second embedded board (41), and the second connection dowel (45) is cemented in basic installation portion (2) inside.
10. the main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional according to claim 1, it is characterized in that: described earthquake isolating equipment built-in fitting (4) also comprises the second connection dowel (45), described second connection dowel (45) forms screw thread with built-in bolt sleeve (44) and is flexibly connected, and the second connection dowel (45) is cemented in basic installation portion (2) inside.
CN201420869300.9U 2014-12-31 2014-12-31 A kind of main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional Withdrawn - After Issue CN204385761U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420869300.9U CN204385761U (en) 2014-12-31 2014-12-31 A kind of main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420869300.9U CN204385761U (en) 2014-12-31 2014-12-31 A kind of main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional

Publications (1)

Publication Number Publication Date
CN204385761U true CN204385761U (en) 2015-06-10

Family

ID=53358494

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420869300.9U Withdrawn - After Issue CN204385761U (en) 2014-12-31 2014-12-31 A kind of main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional

Country Status (1)

Country Link
CN (1) CN204385761U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104563154A (en) * 2014-12-31 2015-04-29 中国电力工程顾问集团西南电力设计院有限公司 Main transformer base for installing isolation device for 500kV transformer substation
CN105525626A (en) * 2016-01-07 2016-04-27 浙江省送变电工程公司 Adjustable mechanical connection embedded part and use method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104563154A (en) * 2014-12-31 2015-04-29 中国电力工程顾问集团西南电力设计院有限公司 Main transformer base for installing isolation device for 500kV transformer substation
CN105525626A (en) * 2016-01-07 2016-04-27 浙江省送变电工程公司 Adjustable mechanical connection embedded part and use method thereof

Similar Documents

Publication Publication Date Title
CN103225259B (en) Tension-compression elastic support
CN201851582U (en) A High Damping Anti-Overturning Composite Seismic Isolation Bearing
CN102900153B (en) Three-dimensional lead extrusion bearing capable of insulating shock and dissipating energy
CN202767242U (en) Three-direction shock insulation support
CN204257330U (en) A kind of 500kV transformer isolation structure
CN203594130U (en) Horizontal shearing shutting vibration isolation device
CN107327535A (en) A kind of laminated type metal-rubber shock isolating pedestal for Substation Electric Equipment
CN204385761U (en) A kind of main transformer foundation installing earthquake isolating equipment for 500kV transformer station additional
CN103122662A (en) Buckling restrained brace with viscoelastic materials
CN203145229U (en) Buckling restrained brace containing viscous-elastic materials
CN104563154B (en) A kind of main transformer foundation installing earthquake isolating equipment for 500kV substation additional
CN207761093U (en) A kind of isolation cushion suitable for data center's foundation shock absorption
CN110144964A (en) Underground pipe gallery structure with multi-directional shock-absorbing protection function
CN103645366B (en) A kind of individual struts built-up type optical transformer
CN103046571A (en) Annular rubber gasket and sand cushion parallel isolation base of storage tank
CN103470590A (en) Flange for composite sleeve of electrical equipment, and connecting method thereof
CN203654464U (en) Anti-aging vibration isolation rubber support
CN206928454U (en) A kind of Multi-function earthquake-resistant building structure
CN102041775B (en) Steel-lead combined core vibration-isolating rubber support
CN105484153A (en) Seismic mitigation and isolation bearing adopting tension-compression energy dissipation characteristic of high-damping rubber and easy to repair and preparation method of seismic mitigation and isolation bearing
CN203257962U (en) Extra-high voltage converter transformer shock insulating and limiting device
CN201686928U (en) Bridge shockproof isolating device
CN204690990U (en) Rubber vibration isolation device
CN112554362A (en) Vertical detachable rubber support for building
CN204729021U (en) A kind of gentle support type ocean drill rod threaded nipple

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20150610

Effective date of abandoning: 20160601

C25 Abandonment of patent right or utility model to avoid double patenting