CN204349507U - Box-like the filling of green flexible stereo smart group changes electric the complete sets of equipment - Google Patents

Box-like the filling of green flexible stereo smart group changes electric the complete sets of equipment Download PDF

Info

Publication number
CN204349507U
CN204349507U CN201420865020.0U CN201420865020U CN204349507U CN 204349507 U CN204349507 U CN 204349507U CN 201420865020 U CN201420865020 U CN 201420865020U CN 204349507 U CN204349507 U CN 204349507U
Authority
CN
China
Prior art keywords
electric
equipment
room
change
level
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420865020.0U
Other languages
Chinese (zh)
Inventor
单台阶
Original Assignee
单台阶
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 单台阶 filed Critical 单台阶
Priority to CN201420865020.0U priority Critical patent/CN204349507U/en
Application granted granted Critical
Publication of CN204349507U publication Critical patent/CN204349507U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

Box-like the filling of green flexible stereo smart group changes electric the complete sets of equipment, belongs to electric automobile and fills and change electro-technical field.Fill the wind power equipment (1) and photovoltaic solar equipment (2) that change and to be provided with directly over electric room for generating electricity; Fill and change electric room by being used as high level that charging and electric energy change, forming as the middle level of Measuring error, the low layer that changes electricity as electric automobile, high-rise, between middle level and low layer, pass through lowering or hoisting gear (7) UNICOM.This electric the complete sets of equipment easy to disassemble and assemble; be produced on a large scale, promote; change electric the complete sets of equipment by intelligence dress and change electricity easily and efficiently; no longer scene charging is carried out to electric automobile; fill and change electric room wind energy, solar energy, electric energy and electric power storage can be combined effectively; and only utilize trough-electricity to charge to energy storage battery, substantially increase trough-electricity utilance.

Description

Box-like the filling of green flexible stereo smart group changes electric the complete sets of equipment
Technical field
Box-like the filling of green flexible stereo smart group changes electric the complete sets of equipment, belongs to electric automobile and fills and change electro-technical field.
Background technology
Electric automobile is as clean, environment-friendly vehicle, electric automobile becomes the emphasis of auto industry and energy industry development gradually, China has become the fastest-rising country of automobile pollution in the world, the charging of domestic electric automobile is main to build charging station and charging pile at present, the major function of charging station realizes filling soon, the function of trickle charge is realized by charging pile, and this mode also exists following problem: the charging station land utilization ratio of construction is also not high, and greening degree not enough.Trickle charge needs 5 to 8 hours, fills soon in the time of 20 minutes to 30 minutes, and be only battery charging 50% to 80%, this consumes the quality time that electric automobile runs all in various degree, reduces operational efficiency.Electric automobile energy storage battery runs in units of individuality is privately owned, cannot realize the unified box-like management of flexible stereo smart group.Charging station or charging pile power supply, from the common electricity consumption of national grid, are unfavorable for comprehensive utilization of energy and energy-conserving and environment-protective.Electric automobile is to charging station or charging pile charging, and be fill at any time according to individual demand, cannot utilize the peak-valley difference of common electricity consumption, trough-electricity utilance is low.Charging station only charges too single, and computer room construction does not have modularization construction, is unfavorable for Rapid Popularization.Automaticity is not high, efficiency is low.
Utility model content
The technical problems to be solved in the utility model is: overcome the deficiencies in the prior art; box-like the filling of green flexible stereo smart group is provided to change electric the complete sets of equipment; this electric the complete sets of equipment easy to disassemble and assemble; be produced on a large scale, promote; change electric the complete sets of equipment by intelligence dress and change electricity easily and efficiently; no longer scene charging is carried out to electric automobile; fill and change electric room wind energy, solar energy, electric energy and electric power storage can be combined effectively; and only utilize trough-electricity to charge to energy storage battery, substantially increase trough-electricity utilance.
The technical solution of the utility model is, box-like the filling of green flexible stereo smart group of the present utility model changes electric the complete sets of equipment, comprises filling and changes electric room, it is characterized in that: fill the wind power equipment and photovoltaic solar equipment that change and to be provided with directly over electric room for generating electricity; Fill and change electric room by being used as high level that charging and electric energy change, forming as the middle level of Measuring error, the low layer that changes electricity as electric automobile, high-rise, between middle level and low layer, pass through lowering or hoisting gear UNICOM; High-rise inside is provided with charging device, energy storage battery, electric energy converting equipment, and inside, middle level is provided with checkout equipment, and electric energy converting equipment is electrically connected with wind power equipment, photovoltaic solar equipment respectively.
Described high-rise interior separation have the energy storage battery room for installing energy storage battery, for install charging device charging device room, for installing the electric energy switch room of electric energy converting equipment, the high-rise inner charging energy-storing accumulator stand be also provided with for placing energy storage battery.
Inside, described middle level is provided with safety supervision room, Maintenance Room and the sensing chamber for installation and measuring equipment, and inside, middle level is also provided with the energy storage battery frame to be detected for putting energy storage battery to be detected.
Described low layer interior separation has electric automobile designated lane, transformer room, night shift room and center monitoring room, and center monitoring indoor location has Intelligent infrared inductive probe and RFID detector.
Described fill to change in electric room connect as a whole as the steel construction of skeleton with bolt by flange, outer wall template is by grafting or be bolted between steel construction as body of wall; Fill and change electric room by lower margin flange be embedded in being bolted on ground of ground.
The roof of described high level is provided with greenbelt, and high level, middle level and low layer are provided with the greening fence of green plants of can planting respectively on the exterior wall at its roof place.
Described high level, middle level and low layer are equipped with the hatchway for being connected lowering or hoisting gear, the inside of high-rise, middle level and low layer is equipped with the moving track for transporting energy storage battery, and the initiating terminal of moving track is connected with hatchway.
Described wind power equipment and photovoltaic solar equipment are fixed on to fill by bracing frame and change directly over electric room, wind power equipment and photovoltaic solar equipment and fill change electric room roof between leave space.
Described filling is changed electric room flank wall external body and is provided with wind power equipment and photovoltaic solar equipment.
Described energy storage battery is provided with RFID label tag, GPS chip and scanning Quick Response Code.
The utility model is described as follows:
Described moving track is provided with intelligence and changes electromechanical people.Lowering or hoisting gear, hatchway, moving track, on moving track, intelligence changes the energy storage battery frame to be detected in electromechanical people and middle level, high-rise charging energy-storing accumulator stand with the use of, can realize carrying out convenience, change efficiently electric intelligence change electromechanical people be can only work in fixing post industrial general humanoid robot (as Beijing Electric Power Corp.'s independent research for passenger car change electricity arm robot), be fixed on a universal intelligent small rail car, can start along trapped orbit or travel, realize whole energy storage battery to get, let slip process automation.Lowering or hoisting gear is general elevator, and moving track is that ordinary carbon steel parallel track is laid on intelligence and changes on the pre-designed running route of electromechanical people.
Described center monitoring room is the computer supervisory control system of a set of advanced technology and perfect in shape and function, IT technology of new generation is applied to charging electric vehicle facility, by at electric automobile, energy storage battery, transducer and rfid system are set in charging device, can real-time perception electric automobile running status, energy storage battery using state, charging device working condition, electrically-charging equipment auxiliary equipment ruuning situation etc., utilize rfid system, infrared scan and fast Ethernet characteristic, information exchange each other and supervision interval connection blocking function is realized by GOOSE, whole system unified Modeling, unified networking, share unified information.
Compared with prior art, box-like the filling of green flexible stereo smart group of the present utility model is changed the beneficial effect that electric the complete sets of equipment have and is:
1, this fills that to change electric the complete sets of equipment easy for installation.Fill and change electric room easy to disassemble and assemble; be produced on a large scale, promote; fill that to change electric room be steel construction master die board house; divide large, medium and small three kinds of specifications; high, in, end high-level structure arranges, Assembling completes, and steel construction connects as a whole by flange with bolt; be connected with the bolt being embedded in ground by lower margin flange, wall form is by grafting or be bolted between steel construction.
2, this fills that to change electric the complete sets of equipment easy to use.Change electric the complete sets of equipment by intelligence dress and carry out convenience, change electricity efficiently, no longer scene charging is carried out to electric automobile, effectively improve the conevying efficiency of electric automobile, it is unit operation that the setting of intelligence energy storage battery solves energy storage battery privately owned, the problem of the unified box-like management of flexible stereo smart group cannot be realized, run convenient and swift, fill and change electric room by green, wind energy, solar energy, the intellectualities such as electric energy and electric power storage energy, informationalizedly effectively to combine, and only utilize trough-electricity to charge to energy storage battery, substantially increasing trough-electricity utilance is comprehensive utilization of energy truly, fill and change electric room by wind energy, solar energy, electric energy and electric power storage can combine effectively, and only utilize trough-electricity to charge to energy storage battery.
3, this fills and changes electric the complete sets of equipment environmental protection.Above bracing frame, wind, light device of solar generating are installed, between leave into bottom surface, middle level ventilate space, bottom surface, middle level is that greenbelt both can also can be planted green plants by planting vegetable, low layer is electric automobile passage, whole fill change electric room can green coverage much larger than the land area taken, achieve soil zero takies, and allows the utility model energy-saving and environmental protection more, is highly suitable for fast quick change electricity and the ideal charging of electric powered motor energy storage battery group.
Accompanying drawing explanation
Fig. 1 be green flexible stereo smart group box-like fill to change in electric the complete sets of equipment to fill change electric room structural representation.
Fig. 2 is that Fig. 1 fills and changes electric room low layer floor map.
Fig. 3 is that Fig. 1 fills and changes middle level, electric room floor map.
Fig. 4 is that Fig. 1 fills and changes the high-rise floor map in electric room.
Fig. 5 fills the access way structural representation changing electric room.
Fig. 6 is that Fig. 5 fills the access way two layer plane schematic diagram changing electric room.
Fig. 7 is that Fig. 5 fills access way one deck floor map of changing electric room.
Fig. 8 is charge technology schematic flow sheet of the present utility model.
Wherein: wherein: 1, wind power equipment; 2, photovoltaic solar equipment; 3, fence is afforested; 4, outer wall template; 5, energy storage battery; 6, charging energy-storing accumulator stand; 7, lowering or hoisting gear; 8, checkout equipment; 9, energy storage battery frame to be detected; 10, steel construction; 11, bolt; 12, electric automobile; 13, electric automobile designated lane; 14, transformer room; 15, night shift room; 16, center monitoring room; 17, safety supervision room; 18, Maintenance Room; 19, sensing chamber; 20, moving track; 21, hatchway; 22, energy storage battery room; 23, charging device room; 24, charging device; 25, electric energy switch room; 26, electric energy converting equipment; 27, ground; 28, greenbelt.
Embodiment
Fig. 1 ~ 4 are most preferred embodiments of the present utility model, are described further below in conjunction with accompanying drawing 1 ~ 8 pair of the utility model.
With reference to Fig. 1 ~ 7, box-like the filling of green flexible stereo smart group changes electric the complete sets of equipment, comprises filling and changes electric room, fills the wind power equipment 1 and photovoltaic solar equipment 2 that change and to be provided with directly over electric room for generating electricity; Wind power equipment 1 and photovoltaic solar equipment 2 are fixed on to fill by bracing frame and change directly over electric room, wind power equipment 1 and photovoltaic solar equipment 2 and fill change electric room roof between leave space, space can be used for ventilating.Bracing frame comprises end face and the supporting leg for supporting, and end face is fixed with wind power equipment 1 and photovoltaic solar equipment 2, top surface inclination, and from the horizontal by 15 ~ 70 ° of angles.Fill and change electric room flank wall external body and be provided with wind power equipment 1 and photovoltaic solar equipment 2, the photovoltaic solar equipment 2 on the body of wall of side should be arranged on outside the side body of wall that fills and change Chaoyang, electric room.
Fill and change electric room by being used as high level that charging and electric energy change, forming as the middle level of Measuring error, the low layer that changes electricity as electric automobile, high-rise, between middle level and low layer, pass through lowering or hoisting gear 7 UNICOM; High-rise, middle level and the hatchway 21 low layer is equipped with for being connected lowering or hoisting gear 7, the inside of high-rise, middle level and low layer is equipped with the moving track 20 for transporting energy storage battery, and the initiating terminal of moving track 20 is connected with hatchway 21.The shape of moving track 20 is U-shaped, I type or L-type.High-rise inside is provided with charging device 24, energy storage battery 5, electric energy converting equipment 26, and inside, middle level is provided with checkout equipment 8, and electric energy converting equipment 26 is electrically connected with wind power equipment 1, photovoltaic solar equipment 2 respectively.High-rise roof is provided with greenbelt 28, the soil horizon being provided with 40cm in greenbelt 28 can planting vegetable or greening, can arbitrarily plant the four seasons evergreen green plants, high-rise, middle level and low layer are provided with the greening fence 3 of green plants of can planting respectively on the exterior wall at its roof place.
Filling to change in electric room adopts the steel construction 10 as skeleton to connect as a whole with bolt by flange, and outer wall template 4 is by grafting or be bolted between steel construction 10 as body of wall; Fill and change electric room and be fixed on ground 27 by lower margin flange and the bolt 11 that is embedded in ground.
High-rise interior separation have the energy storage battery room 22 for installing energy storage battery 5, for install charging device 24 charging device room 23, for installing the electric energy switch room 25 of electric energy converting equipment 26, the high-rise inner charging energy-storing accumulator stand 6 be also provided with for placing energy storage battery 5.High-rise moving track 20 is U-shaped, and charging energy-storing accumulator stand 6 is adjacent with high-rise moving track 20.Charging energy-storing accumulator stand 6 is positioned at the outside of energy storage battery room 22, charging device room 23, electric energy switch room 25 with high-rise moving track 20.
Inside, middle level is provided with safety supervision room 17, Maintenance Room 18 and the sensing chamber 19 for installation and measuring equipment 8, and inside, middle level is also provided with the energy storage battery frame 9 to be detected for putting energy storage battery 5 to be detected.The moving track 20 in middle level is U-shaped, and energy storage battery frame 9 to be detected is adjacent with the moving track 20 in middle level.Energy storage battery frame to be detected 9 and the moving track 20 in middle level are positioned at the outside of safety supervision room 17, Maintenance Room 18 and sensing chamber 19.
Low layer interior separation has electric automobile designated lane 13, transformer room 14, night shift room 15 and center monitoring room 16, is provided with Intelligent infrared inductive probe and RFID detector in center monitoring room 16.Energy storage battery 5 is provided with RFID label tag, GPS chip and scanning Quick Response Code.The moving track 20 of low layer is in I type, and the moving track 20 of low layer is arranged on the side of the inside of electric automobile designated lane 13.
With reference to Fig. 5 ~ 7, fill and change electric room outer setting and have access way, access way with fill that to change electric room adjacent.Access way comprises one deck and two layers, and with reference to Fig. 7, one deck inside of access way is provided with the passageway travelled for electric automobile 12, this passageway with fill the electric automobile designated lane 13 changing electric room low layer and communicate.Access way two layers is provided with greenbelt 28, and greenbelt 28 covers whole two layers of bottom surface.The body of wall that access way two layers is outside is provided with the greening fence 3 of green plants of can planting.By bracing frame, wind power equipment 1 for generating electricity and photovoltaic solar equipment 2 are installed directly over access way.
The course of work is as follows: first change electric demand according to filling of different cities, set up central network management and dispatching command centre, then according to city unified planning, in different places according to different needs, by large, in, little three kinds of specifications set up box-like the filling of green flexible stereo smart group of different scales size to change electric the complete sets of equipment, after smooth location carries out basis, Assembling and installation realize standardization, the steel construction master die board house that templating is produced and auxiliary facility, steel construction 10 is fixed on ground 27 by connecting bolt 11, outer wall template 4 is by grafting or be bolted between steel construction, synchronously on request all greening fences 3 and greenbelt 28 are afforested, then box-like the filling of all green flexible stereo smart group is changed electric the complete sets of equipment and debugged, network with central network management and dispatching command centre again after having debugged and carry out unifying to test, test and brought into operation after acceptance(check).
Because having inserted RFID label tag and GPS chip in energy storage battery 5, the information that car owner provides according to central network management and dispatching command centre, input destination, car running computer can calculate electricity mileage automatically, if electricity is enough just without the need to worry, if electricity is not enough, when system can be pointed out for car owner, where change battery, box-like the filling of green flexible stereo smart group is nearby found to change electric the complete sets of equipment easily, be provided with night shift room 15 in device to have a rest for driver or worker, electric automobile 12 has to fill and changes entering of electric room, go out passage to enter to fill and change electric room, center monitoring room 16 is also transmitted in time by supervisory control system induction and enters motor vehicle information, and instruction intelligence is changed electromechanical people and is put in place fast by lowering or hoisting gear 7 and moving track 20, intelligence changes electromechanical people by being located at scanning Quick Response Code on energy storage battery and radio frequency discrimination RFID detector, detect the type identifying present battery case, model, the center monitoring room 16 that the data such as electricity also return in time, center monitoring room 16 relies on quick Ethernet characteristic, information exchange each other and supervision interval connection blocking function is realized by GOOSE, synchronously will reach central network management and dispatching command centre in described data, whole system unified Modeling, unified networking, share unified information.Intelligence is changed electromechanical people and is taken off the energy storage battery that need change electricity according to instruction, through lowering or hoisting gear 7 and moving track 20, battery is put on the energy storage battery frame 9 to be detected of middle level, and then after the energy storage battery high-rise charging energy-storing accumulator stand 6 being full of electricity identifies by lowering or hoisting gear 7 and moving track 20, take out (synchronously by information back center monitoring room 16) according to instruction, through lowering or hoisting gear 7 to ground 27, to the energy storage battery set-point of electric automobile 12, slow electric energy storage battery is installed on car through moving track 20 again, finish the work and the information that returned to center monitoring room 16, information is synchronously reached central network management and dispatching command centre by center monitoring room 16, the whole electric process that changes terminated in 3-5 minute, electric automobile 12 starts, entering of electric room is changed again through filling, go out passage to roll away from, enter in normal traveling.
The energy storage battery to be detected be put on middle level energy storage battery to be detected frame 9 changes electromechanical people through intelligence and is delivered to sensing chamber 19 doorway, there is moved by hand to indoor, after equipment 8 detects after testing, detection transfer of data is carried out data processing to center monitoring room 16, problematicly to keep in repair at Maintenance Room 18, out of question have intelligence to change electromechanical people to be placed on charging energy-storing accumulator stand through lowering or hoisting gear 7 and moving track 20 by energy storage battery, enter state to be charged, whole process has safety supervision room 17 to monitor.
With reference to Fig. 8, charge technology flow process of the present utility model is as follows: first the high voltage electric of national grid enters transformer room 14, transformation becomes can use the voltage of 220V or 380V, this voltage has three kinds of usings method, first be in the trough-electricity stage, first electric energy enters electric energy switch room 25, with wind power equipment 1, the energy that photovoltaic solar equipment 2 produces, change through electric energy converting equipment 26 at this, jointly being converted to can for the power supply of the charging device 24 in charging device room 23, one is charge to the energy storage battery 5 in energy storage battery room 22, again the energy storage battery to be charged on charging energy-storing accumulator stand 6 is charged through energy storage battery 5, two is directly charge to the energy storage battery to be charged on charging energy-storing accumulator stand 6, next is that direct energy storage battery to be charged on charging device 24 pairs of charging energy-storing accumulator stands 6 charges, directly besides provide power supply for daily electricity consumption.
Wind power equipment 1, first the energy that photovoltaic solar equipment 2 produces be converted to the alternating current and direct current that are applicable to application through electric energy converting equipment 26, alternating current is first for daily electricity consumption provides power supply, the rich energy storage battery to be charged on charging device 24 pairs of charging energy-storing accumulator stands 6 charges, direct current directly charges to energy storage battery 5, when national grid breaks down, energy storage battery 5 can change stand-by power supply through electric energy converting equipment 26, for the energy storage battery charging to be charged on charging energy-storing accumulator stand 6 and daily electricity consumption provide power supply, the ruuning situation of whole electrical changing station and charging process etc. are all monitored through safety supervision room 17, the related data of rechargeable battery can be transferred to center monitoring room 16 in time, information is synchronously reached central network management and dispatching command centre by center monitoring room 16 after data processing.
Described in upper, be only preferred embodiment of the present utility model, be not restriction utility model being made to other form, any those skilled in the art may utilize the technology contents of above-mentioned announcement to be changed or be modified as the Equivalent embodiments of equivalent variations; But everyly do not depart from technical solutions of the utility model content, any simple modification, equivalent variations and the remodeling done above embodiment according to technical spirit of the present utility model, still belong to the protection range of technical solutions of the utility model.

Claims (10)

1. box-like the filling of green flexible stereo smart group changes electric the complete sets of equipment, comprises filling and changes electric room, it is characterized in that: fill the wind power equipment (1) and photovoltaic solar equipment (2) that change and to be provided with directly over electric room for generating electricity; Fill and change electric room by being used as high level that charging and electric energy change, forming as the middle level of Measuring error, the low layer that changes electricity as electric automobile, high-rise, between middle level and low layer, pass through lowering or hoisting gear (7) UNICOM; High-rise inside is provided with charging device (24), energy storage battery (5), electric energy converting equipment (26), inside, middle level is provided with checkout equipment (8), and electric energy converting equipment (26) is electrically connected with wind power equipment (1), photovoltaic solar equipment (2) respectively.
2. box-like the filling of green flexible stereo smart group according to claim 1 changes electric the complete sets of equipment, it is characterized in that: described high-rise interior separation have the energy storage battery room (22) for installing energy storage battery (5), for install charging device (24) charging device room (23), for installing the electric energy switch room (25) of electric energy converting equipment (26), high-rise inside is also provided with the charging energy-storing accumulator stand (6) for placing energy storage battery (5).
3. box-like the filling of green flexible stereo smart group according to claim 1 changes electric the complete sets of equipment, it is characterized in that: inside, described middle level is provided with safety supervision room (17), Maintenance Room (18) and the sensing chamber (19) for installation and measuring equipment (8), inside, middle level is also provided with the energy storage battery frame (9) to be detected for putting energy storage battery (5) to be detected.
4. box-like the filling of green flexible stereo smart group according to claim 1 changes electric the complete sets of equipment, it is characterized in that: described low layer interior separation has electric automobile designated lane (13), transformer room (14), night shift room (15) and center monitoring room (16), is provided with Intelligent infrared inductive probe and RFID detector in center monitoring room (16).
5. box-like the filling of green flexible stereo smart group according to claim 1 changes electric the complete sets of equipment, it is characterized in that: described in fill the steel construction (10) changed as skeleton in electric room and connect with bolt as a whole by flange, outer wall template (4) is by grafting or be bolted between steel construction (10) as body of wall; Fill and change electric room and be fixed on ground (27) by lower margin flange and the bolt (11) that is embedded in ground.
6. box-like the filling of green flexible stereo smart group according to claim 1 changes electric the complete sets of equipment, it is characterized in that: the roof of described high level is provided with greenbelt (28), high level, middle level and low layer are provided with the greening fence (3) of green plants of can planting respectively on the exterior wall at its roof place.
7. box-like the filling of green flexible stereo smart group according to claim 1 changes electric the complete sets of equipment, it is characterized in that: described high level, middle level and low layer are equipped with the hatchway (21) for being connected lowering or hoisting gear (7), the inside of high-rise, middle level and low layer is equipped with the moving track (20) for transporting energy storage battery, and the initiating terminal of moving track (20) is connected with hatchway (21).
8. box-like the filling of green flexible stereo smart group according to claim 1 changes electric the complete sets of equipment, it is characterized in that: described wind power equipment (1) and photovoltaic solar equipment (2) are fixed on to fill by bracing frame and change directly over electric room, wind power equipment (1) and photovoltaic solar equipment (2) and fill change electric room roof between leave space.
9. box-like the filling of green flexible stereo smart group according to claim 1 changes electric the complete sets of equipment, it is characterized in that: described in fill and change electric room flank wall external body wind power equipment (1) and photovoltaic solar equipment (2) are installed.
10. box-like the filling of green flexible stereo smart group according to claim 1 changes electric the complete sets of equipment, it is characterized in that: described energy storage battery (5) is provided with RFID label tag, GPS chip and scanning Quick Response Code.
CN201420865020.0U 2014-12-31 2014-12-31 Box-like the filling of green flexible stereo smart group changes electric the complete sets of equipment Expired - Fee Related CN204349507U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420865020.0U CN204349507U (en) 2014-12-31 2014-12-31 Box-like the filling of green flexible stereo smart group changes electric the complete sets of equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420865020.0U CN204349507U (en) 2014-12-31 2014-12-31 Box-like the filling of green flexible stereo smart group changes electric the complete sets of equipment

Publications (1)

Publication Number Publication Date
CN204349507U true CN204349507U (en) 2015-05-20

Family

ID=53232750

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420865020.0U Expired - Fee Related CN204349507U (en) 2014-12-31 2014-12-31 Box-like the filling of green flexible stereo smart group changes electric the complete sets of equipment

Country Status (1)

Country Link
CN (1) CN204349507U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106484390A (en) * 2015-08-28 2017-03-08 松下知识产权经营株式会社 The control method of information terminal and information terminal
JP2020532940A (en) * 2017-09-05 2020-11-12 上海電巴新能源科技有限公司Shanghai Dianba New Energy Technology Co.,Ltd. Full-featured container and container battery replacement station

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106484390A (en) * 2015-08-28 2017-03-08 松下知识产权经营株式会社 The control method of information terminal and information terminal
JP2020532940A (en) * 2017-09-05 2020-11-12 上海電巴新能源科技有限公司Shanghai Dianba New Energy Technology Co.,Ltd. Full-featured container and container battery replacement station

Similar Documents

Publication Publication Date Title
CN103296753B (en) Monitoring system for photovoltaic power station
CN204349507U (en) Box-like the filling of green flexible stereo smart group changes electric the complete sets of equipment
CN104348245B (en) High-efficiency solar charging station for hybrid vehicles
CN104317256A (en) Field remote water resource monitoring apparatus
CN205677319U (en) A kind of vertical lift type stereoscopic electric motor-car parking garage
CN103078361B (en) Centralized transit system for uniform distribution of power storage batteries of electric automobile
CN103259309B (en) Ecological generating system using urban road spaces
CN206514222U (en) A kind of solar street light with system diagnostics function
CN205756153U (en) A kind of wind-light-electricity complementary irrigation by pumping controls device
CN202920086U (en) Control system of wireless wall surface cleaning robot
CN204258099U (en) A kind of distribution box for cable line fault intelligent online monitoring system
CN207419315U (en) A kind of hydraulic roadblock machine control system
CN204452083U (en) A kind of packaged type charging robot
CN204398902U (en) A kind of packaged type charging robot
CN203289160U (en) Novel photovoltaic charging station
CN208314535U (en) A kind of cabin robot inspection system
CN206135433U (en) Get electric installation based on exchange insulating ground wire of overhead transmission line
CN104466746A (en) Distribution box for intelligent cable line fault online monitoring system
CN206038918U (en) Special location sensor system of train
CN206433244U (en) A kind of tunnel vehicle sounds detection means for being used to dim
CN205840432U (en) A kind of light storage integration new forms of energy multi-storied garage
CN107069826A (en) Build multi-energy complementation comprehensive utilization device
CN109100976A (en) The backstage teletransmission of wind-solar hybrid power generation cloud monitors system and method in high-rise cell
CN204407948U (en) A kind of parking lot
CN107769388A (en) Photovoltaic generating system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EXPY Termination of patent right or utility model
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150520