CN204258096U CN201420686975.XU CN201420686975U CN204258096U CN 204258096 U CN204258096 U CN 204258096U CN 201420686975 U CN201420686975 U CN 201420686975U CN 204258096 U CN204258096 U CN 204258096U
Authority
CN
China
Prior art keywords
room
cabinet
top cover
switch gear
mounting panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420686975.XU
Other languages
Chinese (zh)
Inventor
李国东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SICHUAN CHUANHONG ELECTRICAL EQUIPMENT Co Ltd
Original Assignee
SICHUAN CHUANHONG ELECTRICAL EQUIPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN CHUANHONG ELECTRICAL EQUIPMENT Co Ltd filed Critical SICHUAN CHUANHONG ELECTRICAL EQUIPMENT Co Ltd
Priority to CN201420686975.XU priority Critical patent/CN204258096U/en
Application granted granted Critical
Publication of CN204258096U publication Critical patent/CN204258096U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Patch Boards (AREA)

Abstract

The utility model discloses a kind of outgoing line cabinet, comprise cabinet, cabinet is provided with bus-bar room, breaker chamber, switch gear room and cable room from top to down successively.The first spare room is provided with between breaker chamber and switch gear room; The second spare room is provided with between switch gear room and cable room; The top of cabinet is provided with the top cover be flexibly connected with it; The middle part of top cover is provided with radiator window, and the top of radiator window is provided with the upper top cover be fixed on top cover.During the device fails of the utility model in breaker chamber and switch gear room, the stand-by equipment directly can extracting spare room out repairs circuit fast, can not stop over the electricity consumption time of user.Further, the top of this outgoing line cabinet be provided with openable top cover, when installing bus bar copper row, can be put into by cabinet top, having saved the set-up time.In addition, top cover is also provided with radiator window, there is good thermolysis.

Description

A kind of outgoing line cabinet
Technical field
The utility model relates to a kind of outgoing line cabinet.
Background technology
Current manufacturing enterprise and power supply management all need to use a large amount of outgoing line cabinets or control cabinet etc., in order to lay various control switch, motor, generator or other control appliances.Generally bus-bar room, switch gear room and breaker chamber etc. can be had in outgoing line cabinet.
Existing electric power outgoing line cabinet, the electric device of its inside is hard-wired, if wherein certain electric device breaks down, need to overhaul, then need it to disassemble, and often out of order electric device side also has other electric devices, thus install, dismounting take time very much.So when electric device breaks down and be badly in need of electricity consumption, very inconvenient.And in GGD outgoing line cabinet of the prior art, bus-bar frame installation site is circumferential closed, when in-site installation, can only load bus bar copper row from the side, causes bus bar copper row to penetrate cabinet and extremely requires great effort, increase construction cost greatly, waste the engineering time.
Utility model content
The purpose of this utility model is to provide a kind of outgoing line cabinet, and when device fails in breaker chamber and switch gear room, the stand-by equipment directly can extracting reserve tank out repairs circuit fast, can not stop over the electricity consumption time of user; And this outgoing line cabinet is provided with openable top cover, when installing bus bar copper row, can be put into by cabinet top.
For solving the problems of the technologies described above, the utility model provides a kind of outgoing line cabinet, comprises cabinet, and cabinet is provided with bus-bar room, breaker chamber, switch gear room and cable room from top to down successively; The first spare room is provided with between breaker chamber and switch gear room; The second spare room is provided with between switch gear room and cable room.
Wherein, some first circuit breakers, the second circuit breaker, the 3rd circuit breaker, Surge Protector and kilowatt-hour meter is provided with in breaker chamber; Some time switchs are provided with in switch gear room; Cable indoor are provided with some contactors.Bus is through being connected to time switch through the first circuit breaker, kilowatt-hour meter and the second circuit breaker successively; Bus is connected to ground connection after Surge Protector through the first circuit breaker, kilowatt-hour meter and the 3rd circuit breaker successively.Wherein a part of time switch is connected directly to high-power electric appliance equipment, and a part of time switch is connected to low-power electrical equipment through contactor.
The top of cabinet is provided with the top cover be movably connected on its sidewall; The middle part of top cover is provided with radiator window, and the top of radiator window is provided with the upper top cover be fixed on top cover.
First spare room comprise some first pedestals of being fixed on its rear wall and to be arranged on bottom the first spare room and with the first pedestal the first mounting panel one to one; First mounting panel one end is connected to first pedestal corresponding with it by the first brace, and the upper surface of the other end is provided with the first handle; First mounting panel is provided with some first installing holes; Second spare room comprise some second pedestals of being fixed on its rear wall and to be arranged on bottom the second spare room and with the second pedestal the second mounting panel one to one; One end of second mounting panel is connected to second pedestal corresponding with it by the second brace, and the upper surface of the other end is provided with the second handle; Second mounting panel is provided with some second installing holes.
The beneficial effects of the utility model are:
1, the utility model is equipped with reserve tank in the bottom of breaker chamber and switch gear room, and when device fails in breaker chamber and switch gear room, the stand-by equipment directly can extracting spare room out repairs circuit fast, can not stop over the electricity consumption time of user.
2, the utility model is provided with openable top cover, when installing bus bar copper row, can be put into by cabinet top.
3, the utility model top cover is provided with radiator window, has good radiating effect.
Accompanying drawing explanation
Fig. 1 is the structural representation of the utility model most preferred embodiment;
Fig. 2 is the upward view of the top cover of the utility model most preferred embodiment;
Fig. 3 is the structural representation of the first spare room of the utility model most preferred embodiment;
Fig. 4 is the structural representation of the second spare room of the utility model most preferred embodiment;
Fig. 5 is the electrical principle line chart of the utility model most preferred embodiment.
Wherein: 1, cabinet; 2, top cover; 21, radiator window; 3, upper top cover; 4, bus-bar room; 5, breaker chamber; 51, the first spare room; 52, the first pedestal; 53, the first brace; 54, the first mounting panel; 55, the first installing hole; 56, the first handle; 6, switch gear room; 61, the second spare room; 62, the second pedestal; 63, the second brace; 64, the second mounting panel; 65, the second installing hole; 66, the second handle; 7, cable room.
Embodiment
Below embodiment of the present utility model is described; so that those skilled in the art understand the utility model; but should be clear; the utility model is not limited to the scope of embodiment; to those skilled in the art; as long as various change to limit and in the spirit and scope of the present utility model determined, these changes are apparent, and all innovation and creation utilizing the utility model to conceive are all at the row of protection in appended claim.
Outgoing line cabinet as shown in Figure 1, comprises cabinet 1, and cabinet 1 is provided with bus-bar room 4, breaker chamber 5, switch gear room 6 and cable room 7 from top to down successively; The first spare room 51 is provided with between breaker chamber 5 and switch gear room 6; The second spare room 61 is provided with between switch gear room 6 and cable room 7; The top of cabinet 1 is provided with the top cover 2 be movably connected on its sidewall.As shown in Figure 2, the middle part of top cover 2 is provided with radiator window 21, and the top of radiator window 21 is provided with the upper top cover 3 be fixed on top cover 2.
Wherein, composition graphs 1 and Fig. 5, be provided with the first circuit breaker 1QF, the 3rd circuit breaker 3QF, Surge Protector F, kilowatt-hour meter D and some second circuit breaker 2QF in breaker chamber 5; Some time switch KM are provided with in switch gear room 6; Cable indoor are provided with some contactor FR.Bus is through being connected to time switch KM through the first circuit breaker 1QF, kilowatt-hour meter D and the second circuit breaker 2QF successively; Bus is connected to ground connection after Surge Protector F through the first circuit breaker 1QF, kilowatt-hour meter D and the 3rd circuit breaker 3QF successively.Wherein a part of time switch KM is connected directly to high-power electric appliance equipment, and a part of time switch KM is connected to low-power electrical equipment through contactor FR.
As shown in Figure 3, the first spare room 51 comprise some first pedestals 52 of being fixed on its rear wall and to be arranged on bottom the first spare room 5 and with the first pedestal 52 first mounting panel 54 one to one; First mounting panel 54 one end is connected to first pedestal 52 corresponding with it by the first brace 53, and the upper surface of the other end is provided with the first handle 56; First mounting panel 54 is provided with some first installing holes 55.
As shown in Figure 4, the second spare room 61 comprise some second pedestals 62 of being fixed on its rear wall and to be arranged on bottom the second spare room 6 and with the second pedestal 62 second mounting panel 64 one to one; One end of second mounting panel 64 is connected to second pedestal 62 corresponding with it by the second brace 63, and the upper surface of the other end is provided with the second handle 66; Second mounting panel 64 is provided with some second installing holes 65.
Wherein, the first mounting panel 54 of the first spare room 51 is provided with the first circuit breaker 1QF, the 3rd circuit breaker 3QF, Surge Protector F, kilowatt-hour meter D and the second circuit breaker 2QF; Second mounting panel 64 of the second spare room 61 is provided with some time switch KM.The utility model is in use when device fails in breaker chamber 5 and switch gear room 5, and the stand-by equipment directly can extracting spare room out repairs circuit fast, can not stop over the electricity consumption time of user.Further, the top of this outgoing line cabinet be provided with openable top cover 2, when installing bus bar copper row, can be put into by cabinet top, having saved the set-up time.In addition, top cover 2 is also provided with radiator window 21, there is good thermolysis.

Claims (2)

1. an outgoing line cabinet, comprises cabinet, and described cabinet is provided with bus-bar room, breaker chamber, switch gear room and cable room from top to down successively, it is characterized in that: be provided with the first spare room between described breaker chamber and switch gear room; The second spare room is provided with between described switch gear room and cable room; The top of described cabinet is provided with the top cover be flexibly connected with it; The middle part of described top cover is provided with radiator window, and the top of described radiator window is provided with the upper top cover be fixed on top cover;
Described first spare room comprise some first pedestals of being fixed on its rear wall and to be arranged on bottom it and with described first pedestal the first mounting panel one to one; One end of described first mounting panel is connected to described first pedestal corresponding with it by the first brace, and the upper surface of the other end is provided with the first handle; Described first mounting panel is provided with some first installing holes;
Described second spare room comprise some second pedestals of being fixed on its rear wall and to be arranged on bottom it and with described second pedestal the second mounting panel one to one; One end of described second mounting panel is connected to described second pedestal corresponding with it by the second brace, and the upper surface of the other end is provided with the second handle; Described second mounting panel is provided with some second installing holes;
The first circuit breaker, the 3rd circuit breaker, Surge Protector, kilowatt-hour meter and some second circuit breakers is provided with in described breaker chamber; Some time switchs are provided with in described switch gear room; Bus is through being connected to time switch through described first circuit breaker, kilowatt-hour meter and the second circuit breaker successively; The end of incoming cables of described 3rd circuit breaker is connected with described kilowatt-hour meter, and leading-out terminal is ground connection after Surge Protector.
2. outgoing line cabinet according to claim 1, is characterized in that: described some second installing holes are matrix form arrangement.
CN201420686975.XU 2014-11-17 2014-11-17 A kind of outgoing line cabinet Expired - Fee Related CN204258096U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420686975.XU CN204258096U (en) 2014-11-17 2014-11-17 A kind of outgoing line cabinet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420686975.XU CN204258096U (en) 2014-11-17 2014-11-17 A kind of outgoing line cabinet

Publications (1)

Publication Number Publication Date
CN204258096U true CN204258096U (en) 2015-04-08

Family

ID=52962364

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420686975.XU Expired - Fee Related CN204258096U (en) 2014-11-17 2014-11-17 A kind of outgoing line cabinet

Country Status (1)

Country Link
CN (1) CN204258096U (en)

Similar Documents

Publication Publication Date Title
CN203503990U (en) AC (alternating current) distribution box
CN203398559U (en) Multi-path electric-quantity monitoring AC distribution box for communication base station
CN204407733U (en) A kind of cable branch box
CN202488148U (en) Low voltage intelligent reactive power compensation device
CN204258096U (en) A kind of outgoing line cabinet
CN203301028U (en) Low-voltage withdrawable switch cabinet
CN205212242U (en) High performance AC low voltage power switch board cabinet
CN205104446U (en) Circuit breaker mount pad
CN204668787U (en) A kind of air-cooled high-tension switch cabinet
CN201956608U (en) Plug structure of moving alternating-current closed switch equipment
CN204964618U (en) Three -phase electric energy meter takes accuse controller
CN105182064A (en) Controller for controlling charges of three-phase electric energy meter
CN203951058U (en) A kind of removable feeder pillar
CN204425842U (en) A kind of industrial frequency control cabinet
CN201430382Y (en) Lightning protection distribution box
CN204258046U (en) A kind of high-voltage metering cubicle
CN203150927U (en) Power distribution box
CN204391516U (en) A kind of electric control cabinet door limiting device
CN204012295U (en) The compact-type low-voltage comprehensive distribution box that a kind of one side opens the door
CN204215955U (en) Contact connecting structure and circuit breaker under a kind of circuit breaker
CN204089145U (en) A kind of enclosed cable feeder pillar
CN203983756U (en) Switch cubicle
CN203445624U (en) Reactive power compensation system for low-voltage network
CN204156338U (en) GCK switch cubicle mounting structure
CN205944858U (en) Novel protection arrester handcart

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150408

Termination date: 20161117

CF01 Termination of patent right due to non-payment of annual fee