CN204243887U - A kind of building intelligent power inverter - Google Patents

A kind of building intelligent power inverter Download PDF

Info

Publication number
CN204243887U
CN204243887U CN201420664042.0U CN201420664042U CN204243887U CN 204243887 U CN204243887 U CN 204243887U CN 201420664042 U CN201420664042 U CN 201420664042U CN 204243887 U CN204243887 U CN 204243887U
Authority
CN
China
Prior art keywords
main control
building
control tank
screw thread
power supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420664042.0U
Other languages
Chinese (zh)
Inventor
衡何
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SICHUAN LIANGXUN TECHNOLOGY Co Ltd
Original Assignee
SICHUAN LIANGXUN TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN LIANGXUN TECHNOLOGY Co Ltd filed Critical SICHUAN LIANGXUN TECHNOLOGY Co Ltd
Priority to CN201420664042.0U priority Critical patent/CN204243887U/en
Application granted granted Critical
Publication of CN204243887U publication Critical patent/CN204243887U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The utility model discloses a kind of building intelligent power inverter, Main Control Tank is positioned at building inside, control plate is positioned at Main Control Tank inner upper end eventually, first power supply unit is positioned at controls left end bottom plate eventually, it is connected with Main Control Tank screw thread, second power supply unit, be positioned at and control right-hand member bottom plate eventually, it is connected with Main Control Tank screw thread, change over switch is positioned at Main Control Tank upper end center place, it is connected with Main Control Tank screw thread, transformer is positioned at the control positive right side of face upper end of plate eventually, the two is weldingly connected, pressurizer is positioned at the control positive right side of face lower end of plate eventually, the two is weldingly connected, support is positioned at building top, the two is weldingly connected, polysilicon films is positioned at support middle-end, the two is weldingly connected, fan blade is positioned at cradle top, the two is rotatedly connected.This building intelligent power inverter, by arranging two cover electric power systems, both can ensure normalization and the safe of building electricity consumption, can play again the effect of Save Resource Protect Environment.

Description

A kind of building intelligent power inverter
Technical field
The utility model relates to a kind of building electrical energy devices, also relates to a kind of building intelligent power inverter.
Background technology
Along with the development in city, building electricity consumption time and power consumption also growing, need more multiple resource with generating use to meet building, cause serious environmental pollution and resource consumption, in view of stating defect, be necessary that designing a kind of building intelligent power inverter improves in fact.
Utility model content
The purpose of this utility model is just to provide a kind of building intelligent power inverter to solve the problem.
The utility model is achieved through the following technical solutions above-mentioned purpose:
A kind of building intelligent power inverter, comprises building, power unit body, Main Control Tank, control plate eventually, first power supply unit, second power supply unit, change over switch, transformer, pressurizer, support, polysilicon films, fan blade, described Main Control Tank is positioned at building inside, the two screw thread is connected, control plate described end and be positioned at Main Control Tank inner upper end, the two screw thread is connected, and the first described power supply unit is positioned at controls left end bottom plate eventually, it is connected with Main Control Tank screw thread, the second described power supply unit, be positioned at and control right-hand member bottom plate eventually, it is connected with Main Control Tank screw thread, described change over switch is positioned at Main Control Tank upper end center place, it is connected with Main Control Tank screw thread, and described transformer is positioned at the control positive right side of face upper end of plate eventually, and the two is weldingly connected, described pressurizer is positioned at the control positive right side of face lower end of plate eventually, the two is weldingly connected, and described support is positioned at building top, and the two is weldingly connected, described polysilicon films is positioned at support middle-end, the two is weldingly connected, and described fan blade is positioned at cradle top, and the two is rotatedly connected.
Further, described change over switch inside is also provided with voltage monitoring instrument, and the two screw thread is connected.
Further, described master control borad front center is also provided with protection terminal, and the two is weldingly connected.
Further, described Main Control Tank outer upper ends is also provided with alarm, and the two is weldingly connected.
Further, the described protection terminal front side left and right sides is also provided with indicator light, and the two is weldingly connected.
Further, described fan blade bottom is also provided with wind direction board, and it is connected with support welding.
The beneficial effects of the utility model are: this building intelligent power inverter, change by arranging control plate eventually at Main Control Tank to control the overall electric power of commander and distribute, wherein the first power supply unit provides electric energy and traditional supply power mode by electrical network, second power supply unit gathers solar energy by polysilicon films, fan blade gathers the electric power supply of wind energy transformation, when polysilicon films and fan blade collecting energy abundance are stablized, whole control plate commander change over switch activates the second power supply unit and powers to building, first power supply unit dormancy, direct current is become the alternating current of requirement by the energy of polysilicon films and fan blade collection through transformer, carry to building after stable by pressurizer, ensure that power supply quality, this device is by arranging two cover electric power systems, both normalization and the safe of building electricity consumption can have been ensured, the effect of Save Resource Protect Environment can be played again.
Accompanying drawing explanation
Fig. 1 is building intelligent power inverter front view
Fig. 2 is conversion portion partial enlargement front view
Fig. 3 is holder part end view
Building 1 power unit body 2
Main Control Tank 3 is control plate 4 eventually
First power supply unit 5 second power supply unit 6
Change over switch 7 transformer 8
Pressurizer 9 support 10
Polysilicon films 11 fan blade 12
Protection terminal 401 alarm 402
Indicator light 403 voltage monitoring instrument 701
Wind direction board 1201
Following embodiment will further illustrate in conjunction with above-mentioned accompanying drawing.
Embodiment
Below in conjunction with accompanying drawing, the utility model is described in further detail:
As Fig. 1, Fig. 2, shown in Fig. 3, comprise building 1, power unit body 2, Main Control Tank 3, control plate 4 eventually, first power supply unit 5, second power supply unit 6, change over switch 7, transformer 8, pressurizer 9, support 10, polysilicon films 11, fan blade 12, protection terminal 401, alarm 402, indicator light 403, voltage monitoring instrument 701, wind direction board 1201, it is inner that described Main Control Tank 3 is positioned at building 1, the two screw thread is connected, control plate 4 described end and be positioned at Main Control Tank 3 inner upper end, the two screw thread is connected, the first described power supply unit 5 is positioned at controls left end bottom plate 4 eventually, it is connected with Main Control Tank 3 screw thread, the second described power supply unit 6 is positioned at controls right-hand member bottom plate 4 eventually, it is connected with Main Control Tank 3 screw thread, described change over switch 7 is positioned at Main Control Tank 3 upper end center place, it is connected with Main Control Tank 3 screw thread, described transformer 8 is positioned at the positive right side of face upper end of control plate 4 eventually, the two is weldingly connected, described pressurizer 9 is positioned at the positive right side of face lower end of control plate 4 eventually, the two is weldingly connected, described support 10 is positioned at building 1 top, the two is weldingly connected, described polysilicon films 11 is positioned at support 10 middle-end, the two is weldingly connected, described fan blade 12 is positioned at support 10 top, the two is rotatedly connected, described change over switch 7 inside is also provided with voltage monitoring instrument 701, the two screw thread is connected, described master control borad 4 front center is also provided with protection terminal 401, the two is weldingly connected, described Main Control Tank 3 outer upper ends is also provided with alarm 402, the two is weldingly connected, positive 401 left and right sides of described protection terminal are also provided with indicator light 403, the two is weldingly connected, described fan blade 12 bottom is also provided with wind direction board 1201, itself and support 10 are weldingly connected, this building intelligent power inverter, change by arranging control plate 4 eventually at Main Control Tank 3 to control the overall electric power of commander and distribute, wherein the first power supply unit 5 provides electric energy and traditional supply power mode by electrical network, second power supply unit 6 gathers solar energy by polysilicon films 11, fan blade 12 gathers the electric power supply of wind energy transformation, when polysilicon films 11 is stablized with fan blade 12 collecting energy abundance, whole control plate 4 is commanded change over switch 7 to activate the second power supply unit 6 pairs of building 1 and is powered, first power supply unit 5 dormancy, direct current is become the alternating current of requirement by the energy that polysilicon films 11 and fan blade 12 gather through transformer 8, carry to building 1 after stable by pressurizer 9, ensure that power supply quality, in change over switch, the voltage monitoring instrument 701 of 7 can monitor supply power voltage simultaneously, improve electrical safety, when the arbitrary power supply unit of appearance, during power supply electrical anomaly, the protection terminal 401 in control plate 4 front can cut off its power supply eventually, start another power supply unit, ensure that building 1 electricity consumption is unaffected, synchronous alarm 402 can sound, indicator light 403 can light, be beneficial to maintenance personal to keep in repair fast, the wind direction board 1201 of fan blade 12 bottom can effectively regulate fan blade to turn to, make fan blade 12 all the time towards maximum wind direction place, improve the acquisition rate of wind energy.
Above-described embodiment is preferred embodiment of the present utility model; it is not the restriction to technical solutions of the utility model; as long as without the technical scheme that creative work can realize on the basis of above-described embodiment, all should be considered as falling within the scope of the rights protection of the utility model patent.

Claims (6)

1. a building intelligent power inverter, is characterized in that: comprise building, power unit body, Main Control Tank, control plate eventually, first power supply unit, second power supply unit, change over switch, transformer, pressurizer, support, polysilicon films, fan blade, described Main Control Tank is positioned at building inside, the two screw thread is connected, control plate described end and be positioned at Main Control Tank inner upper end, the two screw thread is connected, and the first described power supply unit is positioned at controls left end bottom plate eventually, and it is connected with Main Control Tank screw thread, the second described power supply unit is positioned at controls right-hand member bottom plate eventually, it is connected with Main Control Tank screw thread, and described change over switch is positioned at Main Control Tank upper end center place, and it is connected with Main Control Tank screw thread, described transformer is positioned at the control positive right side of face upper end of plate eventually, the two is weldingly connected, and described pressurizer is positioned at the control positive right side of face lower end of plate eventually, and the two is weldingly connected, described support is positioned at building top, the two is weldingly connected, and described polysilicon films is positioned at support middle-end, and the two is weldingly connected, described fan blade is positioned at cradle top, and the two is rotatedly connected.
2. building intelligent power inverter according to claim 1, is characterized in that: described change over switch inside is also provided with voltage monitoring instrument, and the two screw thread is connected.
3. building intelligent power inverter according to claim 2, is characterized in that: described master control borad front center is also provided with protection terminal, and the two is weldingly connected.
4. building intelligent power inverter according to claim 3, is characterized in that: described Main Control Tank outer upper ends is also provided with alarm, and the two is weldingly connected.
5. building intelligent power inverter according to claim 4, is characterized in that: the described protection terminal front side left and right sides is also provided with indicator light, and the two is weldingly connected.
6. building intelligent power inverter according to claim 5, is characterized in that: described fan blade bottom is also provided with wind direction board, and it is connected with support welding.
CN201420664042.0U 2014-11-07 2014-11-07 A kind of building intelligent power inverter Expired - Fee Related CN204243887U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420664042.0U CN204243887U (en) 2014-11-07 2014-11-07 A kind of building intelligent power inverter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420664042.0U CN204243887U (en) 2014-11-07 2014-11-07 A kind of building intelligent power inverter

Publications (1)

Publication Number Publication Date
CN204243887U true CN204243887U (en) 2015-04-01

Family

ID=52773332

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420664042.0U Expired - Fee Related CN204243887U (en) 2014-11-07 2014-11-07 A kind of building intelligent power inverter

Country Status (1)

Country Link
CN (1) CN204243887U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104300667A (en) * 2014-11-07 2015-01-21 四川量迅科技有限公司 Intelligent power conversion device for building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104300667A (en) * 2014-11-07 2015-01-21 四川量迅科技有限公司 Intelligent power conversion device for building

Similar Documents

Publication Publication Date Title
CN203339789U (en) Portable Multifunctional Power Box
CN205829186U (en) Building electric power system
CN204243887U (en) A kind of building intelligent power inverter
CN204206562U (en) A kind of building intelligent power inverter
CN205104973U (en) Novel low pressure power supply is concentrated to photovoltaic device
CN204285267U (en) A kind of Table lamp controlled by sound
CN104300667A (en) Intelligent power conversion device for building
CN204809965U (en) Novel light cat wireless routing all -in -one device
CN202444447U (en) Portable solar power generation control device
CN202285804U (en) Solar shearing machine
CN203352249U (en) Wall mounted solar energy household stand-by power supply
CN204290463U (en) A kind of Electrical Safety device
CN204119118U (en) Type hand field Blast Furnace Top Gas Recovery Turbine Unit (TRT)
CN205335961U (en) Photovoltaic monitoring system based on MPPT controller
CN204361698U (en) Online solar power station PID recovery system
CN203632615U (en) Greenhouse power generation system
CN202899476U (en) Solar tile
CN201866680U (en) Two-purpose street lamp for solar energy and utility power
CN209046355U (en) A dual-mode power supply device
CN203442875U (en) Boiler variable-frequency energy-saving system
CN204886256U (en) Broadcasting power control system
CN202900704U (en) Solar-energy power-saving fan
CN205070579U (en) Box -type substation secondary photovoltaic power
CN204611383U (en) A kind of energy-saving flashlight
CN204205649U (en) A kind of mobile inverter of many charging modes of Based Intelligent Control

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150401

Termination date: 20151107

EXPY Termination of patent right or utility model