CN204162747U - A kind of annealing furnace structure - Google Patents

A kind of annealing furnace structure Download PDF

Info

Publication number
CN204162747U
CN204162747U CN201420624432.5U CN201420624432U CN204162747U CN 204162747 U CN204162747 U CN 204162747U CN 201420624432 U CN201420624432 U CN 201420624432U CN 204162747 U CN204162747 U CN 204162747U
Authority
CN
China
Prior art keywords
furnace
heater
roller
room
heat insulating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420624432.5U
Other languages
Chinese (zh)
Inventor
谭柱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FOSHAN JUYA ALUMINUM Co Ltd
Original Assignee
FOSHAN JUYA ALUMINUM Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FOSHAN JUYA ALUMINUM Co Ltd filed Critical FOSHAN JUYA ALUMINUM Co Ltd
Priority to CN201420624432.5U priority Critical patent/CN204162747U/en
Application granted granted Critical
Publication of CN204162747U publication Critical patent/CN204162747U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a kind of annealing furnace structure, comprise body of heater, body of heater comprises furnace bottom room, furnace sidewall, furnace roof room, it is characterized in that: described body of heater is separated by some pieces of heat insulating boards and is divided between several cellular zones, be equipped with hot air circulation blower, furnace roller, electric heating panel between each cellular zone, described hot air circulation blower is installed on furnace roof room, and electric heating panel is installed on furnace bottom room, furnace roller is installed on electric heating panel, has passage between heat insulating board and furnace roller.The utility model is formed between some cellular zones by arranging some pieces of heat insulating boards in body of heater, improves the overall temperature rise rate of body of heater, improves production efficiency, and play heat preservation energy-saving effect.

Description

A kind of annealing furnace structure
Technical field
The utility model relates to a kind of aluminium technical field of processing equipment, particularly a kind of annealing furnace structure.
Background technology
Annealing is a kind of metal heating processing technology, refers to and metal is slowly heated to certain temperature, keeps enough time, then cools with Reasonable Speed.Object reduces hardness, improves deep shaping property; Eliminate unrelieved stress, stable dimensions, reduce distortion and be inclined to crackle; Crystal grain thinning, adjustment tissue, eliminating tissue defects, is therefore also a common technology in the aluminium course of processing.Annealing furnace is processing units indispensable in annealing processing, and large-scale annealing furnace is in annealing process or consume a large amount of electric energy, causes the waste of the energy.
Summary of the invention
In order to overcome above-mentioned the deficiencies in the prior art, the utility model provides that a kind of heat-up rate is fast, the annealing furnace structure of heat preservation energy-saving.
The technical solution of the utility model is: a kind of annealing furnace structure, comprise body of heater, body of heater comprises furnace bottom room, furnace sidewall, furnace roof room, it is characterized in that: described body of heater is separated by some pieces of heat insulating boards and is divided between several cellular zones, be equipped with hot air circulation blower, furnace roller, electric heating panel between each cellular zone, described hot air circulation blower is installed on furnace roof room, and electric heating panel is installed on furnace bottom room, furnace roller is installed on electric heating panel, has passage between heat insulating board and furnace roller.
Described heat insulating board is made up of interior lining panel and stainless steel plate, centre is interior lining panel, both sides are stainless steel plate, described interior lining panel is ceramic beaverboard, by heat insulating board, the temperature between cellular zone is not easily run off while rising, improve the overall temperature rise rate of body of heater, sustainable maintenance temperature constant state, play heat preservation energy-saving effect, thus improve production efficiency.
Described heat insulating board is connected on furnace roof room, can be for convenience detach.
Described furnace roller is used for holding up and transmitting aluminium strip, and furnace roller can be ceramics furnace roller, silicon carbide furnace roller, steel alloy spraying roller.
Described hot air circulation blower blowing mouth has air channel, and air channel is provided with winding-up mouth, and the hot blast of circulation can blow on aluminium strip and heat aluminium strip surface by winding-up mouth, can further improve the temperature rise rate of body of heater, also plays energy-conservation effect.
Described body of heater side is provided with some maintenance monitoring doors.
The beneficial effects of the utility model are: the utility model is formed between some cellular zones by arranging some pieces of heat insulating boards in body of heater, improve the overall temperature rise rate of body of heater, improve production efficiency, and play heat preservation energy-saving effect, further, air channel is provided with some ejiction openings, hot air circulation utilizes and heats aluminium strip surface, improves temperature rise rate, has energy-conserving action.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
In figure, 1-body of heater, 2-furnace roof room, 3-furnace bottom room, 4-heat insulating board, 5-hot air circulation blower, 6-furnace roller, 7-electric heating panel, 8-air channel, 9-ejiction opening.
Embodiment
Below in conjunction with drawings and Examples, the utility model is described in further detail.
As shown in Figure 1, a kind of annealing furnace structure, comprise body of heater 1, body of heater comprises furnace roof room 2, furnace sidewall, furnace bottom room 3, described body of heater 1 is separated by some pieces of heat insulating boards 4 and is divided between several cellular zones, hot air circulation blower 5 is equipped with between each cellular zone, furnace roller 6, electric heating panel 7, described heat insulating board 4 to be connected on furnace roof room 2 and and form a passage that can pass through for aluminium strip between furnace roller 6, removing and installing of heat insulating board 4 can be facilitated by the mode of clamping, thus according to practical situation installing heat insulating board 4, heat insulating board 4 is made up of interior lining panel and stainless steel plate, centre is interior lining panel, both sides are stainless steel plate, described interior lining panel is ceramic beaverboard, the temperature between cellular zone is made to raise fast and not easily to run off by heat insulating board 4, sustainable maintenance temperature constant state, play heat preservation energy-saving effect, improve the overall temperature rise rate of body of heater, thus improve production efficiency.
Described hot air circulation blower 5 is installed on furnace roof room 2, hot air circulation blower 5 blowing mouth has air channel 8, air channel 8 is provided with winding-up mouth 9 and air suction inlet, hot blast by air suction inlet by blower fan suck again by blower fan blow out through winding-up mouth 9 so circulation aluminium strip surface is heated it.
Described electric heating panel 7 is installed on furnace bottom room 3, and furnace roller 6 is installed on electric heating panel 7.
Described furnace roller 6 is for holding up and transmitting aluminium strip, and furnace roller can be ceramics furnace roller, silicon carbide furnace roller, steel alloy spraying roller.
Described body of heater 1 side is provided with some maintenance monitoring doors.
The utility model is formed between some cellular zones by arranging some pieces of heat insulating boards in body of heater, improve the overall temperature rise rate of body of heater, improve production efficiency, and play heat preservation energy-saving effect, further, air channel is provided with some ejiction openings, hot air circulation utilizes and heats aluminium strip surface, improves temperature rise rate, has energy-conserving action.
In addition to the implementation, the utility model can also have alternate manner.The technical scheme that all employings are replaced on an equal basis or equivalent transformation becomes, all drops on the protection domain of the utility model requirement.

Claims (8)

1. an annealing furnace structure, comprise body of heater, body of heater comprises furnace bottom room, furnace sidewall, furnace roof room, it is characterized in that: described body of heater is separated by some pieces of heat insulating boards and is divided between several cellular zones, be equipped with hot air circulation blower, furnace roller, electric heating panel between each cellular zone, described hot air circulation blower is installed on furnace roof room, and electric heating panel is installed on furnace bottom room, furnace roller is installed on electric heating panel, has passage between heat insulating board and furnace roller.
2. annealing furnace structure according to claim 1, is characterized in that: described heat insulating board is made up of interior lining panel and stainless steel plate, and centre is interior lining panel, and both sides are stainless steel plate.
3. annealing furnace structure according to claim 2, is characterized in that: described interior lining panel is ceramic beaverboard.
4. annealing furnace structure according to claim 1 and 2, is characterized in that: described heat insulating board is connected on furnace roof room.
5. annealing furnace structure according to claim 1, is characterized in that: described furnace roller is one of ceramic furnace roller, silicon carbide furnace roller, steel alloy spraying roller.
6. annealing furnace structure according to claim 1, is characterized in that: described hot air circulation blower blowing mouth has air channel.
7. annealing furnace structure according to claim 6, is characterized in that: described air channel is provided with winding-up mouth.
8. annealing furnace structure according to claim 1, is characterized in that: described body of heater side is provided with some maintenance monitoring doors.
CN201420624432.5U 2014-10-27 2014-10-27 A kind of annealing furnace structure Expired - Fee Related CN204162747U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420624432.5U CN204162747U (en) 2014-10-27 2014-10-27 A kind of annealing furnace structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420624432.5U CN204162747U (en) 2014-10-27 2014-10-27 A kind of annealing furnace structure

Publications (1)

Publication Number Publication Date
CN204162747U true CN204162747U (en) 2015-02-18

Family

ID=52536456

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420624432.5U Expired - Fee Related CN204162747U (en) 2014-10-27 2014-10-27 A kind of annealing furnace structure

Country Status (1)

Country Link
CN (1) CN204162747U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106319194A (en) * 2015-06-17 2017-01-11 蒋满珍 Novel annealing furnace

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106319194A (en) * 2015-06-17 2017-01-11 蒋满珍 Novel annealing furnace

Similar Documents

Publication Publication Date Title
CN203923294U (en) A kind of tempering stove
CN203440235U (en) Toughened glass heating furnace
CN201495170U (en) High-pressure air convection circulating heating device
CN204162747U (en) A kind of annealing furnace structure
CN101746946A (en) Secondary homing toughening process for glass toughening furnace
CN201740351U (en) Environment-friendly and energy-saving oven
CN202829814U (en) Automobile front windshield energy-saving suction mould high-speed furnace
CN202945275U (en) Mesh belt type hot air circulation tempering furnace
CN203295558U (en) Novel pit type tempering furnace
CN203440406U (en) Hearth bottom of annealing furnace
CN205024289U (en) Horizontal annealing stove preheating section structure
CN201408801Y (en) Far-infrared drying device for lithium battery pole piece coating
CN203768221U (en) Energy-saving glass tempering furnace
CN204224446U (en) Air knife type forced convection type glass tempering process furnace
CN204848643U (en) Glass fibre reinforced plastics furnace
CN204803353U (en) Energy -efficient annealing stove
CN204128177U (en) A kind of novel hot-air oven
CN202865107U (en) Air supporting structure of ultrathin toughened glass furnace
CN103803784A (en) Simple method for producing tempered glass plate
CN203187710U (en) Box type heating furnace
CN103820605A (en) Mesh belt type hot air circulating tempering furnace
CN204356364U (en) A kind of annealing furnace
CN201368678Y (en) Wind blowing vacuum furnace
CN105219946A (en) A kind of Horizental annealer preheating section structure
CN203922999U (en) Reinforced glass production facility

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150218

Termination date: 20181027