CN204150970U - Seat ground self-balancing pole - Google Patents
Seat ground self-balancing pole Download PDFInfo
- Publication number
- CN204150970U CN204150970U CN201420400992.2U CN201420400992U CN204150970U CN 204150970 U CN204150970 U CN 204150970U CN 201420400992 U CN201420400992 U CN 201420400992U CN 204150970 U CN204150970 U CN 204150970U
- Authority
- CN
- China
- Prior art keywords
- main
- pole
- tower
- rocker
- lifting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Jib Cranes (AREA)
Abstract
座地自平衡抱杆,涉及一种抱杆。目前,多山地的工程限制多种抱杆及流动式起重机的使用。本实用新型包括位于铁塔中间的底座、主杆、过渡段、回转组件、四通段、主桅杆、转动节、与四通段相连的四摇臂及对应的起吊系统、变幅系统,所述的底座、主杆、过渡段、回转组件、四通段、主桅杆、转动节自下而上设置,四摇臂中两摇臂为主摇臂,两摇臂为副摇臂,所述的主摇臂设有起吊系统及变幅系统,所述的副摇臂的自由端设有与铁塔地面塔腿相连的平衡绳;所述的主杆上设有至少一个腰环,一腰环设有四根腰环拉线以分别与铁塔的四根主材相连。本技术方案不需设置抱杆外拉线,保证复杂地形吊装安全,且便于施工运输与组装。
A ground self-balancing pole holding relates to a pole holding. At present, engineering in mountainous areas restricts the use of various types of poles and mobile cranes. The utility model includes a base located in the middle of the iron tower, a main rod, a transition section, a slewing assembly, a four-way section, a main mast, a rotating joint, four rocker arms connected with the four-way section, and a corresponding lifting system and a luffing system. The base, main rod, transition section, slewing assembly, four-way section, main mast, and rotating joint are arranged from bottom to top. Among the four rocker arms, two rocker arms are the main rocker arms, and the two rocker arms are auxiliary rocker arms. The main rocker arm is provided with a hoisting system and a luffing system, and the free end of the auxiliary rocker arm is provided with a balance rope connected to the tower leg on the ground of the iron tower; the main rod is provided with at least one waist ring, and a waist ring is provided There are four waist ring stay wires to be connected with the four main materials of the iron tower respectively. The technical solution does not need to be equipped with external stay wires for holding poles, which ensures safe hoisting in complex terrain, and is convenient for construction, transportation and assembly.
Description
技术领域 technical field
本实用新型涉及一种抱杆。 The utility model relates to a holding pole.
背景技术 Background technique
近年国内各施工企业结合特高压交流试验示范工程、皖电东送示范工程等特高压线路工程,研制了多种型式的抱杆,以满足不同型式、不同地形的铁塔组立施工要求,特别是在首条双回路全钢管特高压线路工程——皖电东送示范工程,研制了大量的机械化程度、技术水平均较以往有大幅提升的新式组塔抱杆,如座地双平臂抱杆、座地单动臂抱杆、座地双摇臂抱杆等,并结合地形交通条件,合理配置使用流动式起重机,提升组塔施工效率。 In recent years, domestic construction companies have developed various types of poles in combination with ultra-high voltage line projects such as the UHV AC test demonstration project and the Anhui-East Power Transmission demonstration project to meet the construction requirements of iron towers of different types and different terrains, especially In the first double-circuit full-steel UHV line project—the Anhui Electricity Transmission Demonstration Project, a large number of new-style tower poles with a degree of mechanization and technical level that have been greatly improved compared with the past have been developed, such as double-flat arm poles on the ground , Ground-mounted single boom pole, ground-mounted double rocker pole pole, etc., combined with terrain and traffic conditions, rationally configure and use mobile cranes to improve the efficiency of tower construction.
浙北-福州特高压交流输变电工程线路工程是我国建设的第三条交流特高压线路,首次大规模采用了酒杯型直线塔,部分塔型三相导线均采用V 型悬垂串布置,大幅增加了塔头的结构尺寸。酒杯型塔的塔头具有大开档、高窗口、长横担、大重量特点,要求配用的抱杆必须有足够的结构强度、吊重能力及作业幅度,而塔位所处的高山、陡坡、交通不便地形及个别塔位邻近电力线的特点,又限制了抱杆外拉线的设置,要求抱杆结构部件的重量及外形尺寸向轻型化发展。以浙江省送变电工程公司施工的11标为例,新建铁塔211基全部为角钢塔,其中酒杯型直线塔150基,全标段34.5%为一般山地,65.5%为高山峻岭,交通条件极其困难,海拔高度500-1000m,且山体坡度以30°~50°为主,地势极为陡峭;酒杯型直线塔全高61.8~103.8m,重量80~188t;直线塔横担长度长,吨位大,其中ZBC2720M24塔横担总长度67.2m,横担总重48t,单只上曲臂重7.6t,单只下曲臂重9.65t。 The North Zhejiang-Fuzhou UHV AC transmission line project is the third AC UHV line constructed in my country. For the first time, wine glass-shaped linear towers are used on a large scale. Some tower-shaped three-phase conductors are arranged in V-shaped hanging strings, which greatly The structure size of the tower head has been increased. The tower head of the wine glass tower has the characteristics of large opening, high window, long cross arm, and heavy weight. It is required that the supporting pole must have sufficient structural strength, lifting capacity and operating range. The characteristics of steep slopes, inconvenient traffic terrain and the proximity of individual towers to power lines also limit the setting of the outer stay wires of the poles, requiring the weight and overall dimensions of the structural components of the poles to be lighter. Taking the construction of the 11th bid of the Zhejiang Power Transmission and Transformation Engineering Company as an example, the 211 bases of the newly built iron towers are all angle steel towers, of which 150 bases are wine glass-shaped straight towers. Extremely difficult, the altitude is 500-1000m, and the slope of the mountain is mainly 30°-50°, the terrain is extremely steep; the wine glass-shaped straight tower has a total height of 61.8-103.8m and a weight of 80-188t; the straight-line tower has a long cross-arm length and a large tonnage. Among them, the total length of the ZBC2720M24 tower cross arm is 67.2m, the total weight of the cross arm is 48t, the weight of a single upper crank arm is 7.6t, and the weight of a single lower crank arm is 9.65t.
工程的现场各因素限制了座地双平臂抱杆、座地单动臂抱杆、座地双摇臂抱杆及流动式起重机的使用。 Various factors on the site of the project limit the use of ground-mounted double-flat-arm poles, ground-mounted single-arm poles, ground-mounted double-rocker poles and mobile cranes.
实用新型内容 Utility model content
本实用新型要解决的技术问题和提出的技术任务是对现有技术方案进行完善与改进,提供座地自平衡抱杆,以保证复杂地形吊装的安全性的目的。为此,本实用新型采取以下技术方案。 The technical problem to be solved and the technical task proposed by the utility model are to perfect and improve the existing technical scheme, and to provide a ground-based self-balancing pole to ensure the safety of hoisting in complex terrain. For this reason, the utility model takes the following technical solutions.
座地自平衡抱杆,其特征在于:包括位于铁塔中间的底座、主杆、过渡段、回转组件、四通段、主桅杆、转动节、与四通段相连的四摇臂及对应的起吊系统、变幅系统,所述的底座、主杆、过渡段、回转组件、四通段、主桅杆、转动节自下而上设置,四摇臂中两摇臂为主摇臂,两摇臂为副摇臂,两主摇臂相对,两副摇臂相对,所述的主摇臂设有起吊系统及变幅系统,当一主摇作为起吊摇臂时,另一主摇臂作为平衡摇臂,所述的副摇臂的自由端设有与铁塔地面塔腿相连的平衡绳;所述的主杆上设有至少一个腰环,一腰环设有四根腰环拉线以分别与铁塔的四根主材相连。 The ground self-balancing pole holding pole is characterized in that it includes a base located in the middle of the iron tower, a main pole, a transition section, a slewing assembly, a four-way section, a main mast, a rotating joint, four rocker arms connected to the four-way section and corresponding lifting system and luffing system, the base, main rod, transition section, slewing assembly, four-way section, main mast, and rotating joint are arranged from bottom to top. Among the four rocker arms, two rocker arms are the main rocker arms, and two rocker arms are the main rocker arms. The two main rocker arms are opposite to each other, and the two auxiliary rocker arms are opposite to each other. The main rocker arm is equipped with a lifting system and a luffing system. When one main rocker is used as a lifting rocker, the other main rocker is used as a balance rocker arm, the free end of the auxiliary rocker arm is provided with a balance rope connected to the tower leg on the ground of the iron tower; the main rod is provided with at least one waist ring, and one waist ring is provided with four waist ring stay wires to connect with the iron tower respectively. The four main materials are connected.
作为对上述技术方案的进一步完善和补充,本实用新型还包括以下附加技术特征。 As a further improvement and supplement to the above technical solution, the utility model also includes the following additional technical features.
所述的起吊滑车组采用1或2个滑车走4道磨绳,起吊滑车组上滑车滑轮固定于摇臂自由端,下滑车采用吊钩自带滑轮;变幅滑车组采用2或3个滑车走6道磨绳,滑车均采用悬挂式,且设有一保险钢丝绳;变幅、起吊用磨绳均从抱杆内部引下,从回转组件以下两节段下方的导向滑轮过渡段引出;副摇臂设有一钢丝绳将摇臂自由端与抱杆顶端连接。 The lifting block set uses 1 or 2 blocks to walk 4 ropes, the upper block pulley of the lifting block block is fixed on the free end of the rocker arm, and the lower block adopts the hook with its own pulley; the luffing block block uses 2 or 3 blocks There are 6 grinding ropes, all the blocks are suspended, and there is a safety wire rope; the grinding ropes for luffing and hoisting are all led down from the inside of the pole, and lead out from the transition section of the guide pulley below the two sections below the slewing assembly; The arm is provided with a wire rope to connect the free end of the rocker arm with the top of the pole.
当铁塔四脚呈正方形布置,所述的腰环通过卸扣、腰环拉线、双钩、卸扣与铁塔主材相连;当铁塔四脚呈长方形布置,腰环接线采用两两交叉方式,所述的腰环通过卸扣、腰环拉线、手扳葫芦、卸扣与铁塔主材相连。 When the four legs of the iron tower are arranged in a square shape, the waist ring is connected to the main material of the iron tower through shackles, waist ring pull wires, double hooks, and shackles; The waist ring is connected to the main material of the iron tower through a shackle, a waist ring pull wire, a lever hoist, and a shackle.
主摇臂的两侧设有防撞块。 Anti-collision blocks are arranged on both sides of the main rocker arm.
抱杆以机动绞磨作为动力系统,包括 2套起吊用机动绞磨,及2套变幅用机动绞磨,设机动纹磨的平台位于塔身构件副吊侧及非横担整体吊装侧,与铁塔中心任务距离不小于塔全高的0.5倍。 The pole-holding uses motorized winches as the power system, including 2 sets of motorized winches for hoisting and 2 sets of motorized winches for luffing. The distance from the center of the tower is not less than 0.5 times the total height of the tower.
所述的主桅杆设有力矩差限制器,所述的力矩差限制器位于设主摇臂侧,起吊系统起重绞磨出绳端前部设有单环式起重限制器。 The main mast is provided with a moment difference limiter, and the moment difference limiter is located on the main rocker arm side, and the hoisting system is equipped with a single-ring type lifting limiter at the front of the hoisting rope end.
有益效果:本技术方案不需设置抱杆外拉线,采用一侧起吊、三侧平衡的方式,控制抱杆的平衡稳定,保证复杂地形酒杯塔曲臂、横担的吊装安全;且便于施工运输与组装。 Beneficial effects: This technical solution does not need to set the outer stay wire of the pole, and adopts the method of lifting on one side and balancing on three sides to control the balance and stability of the pole, ensuring the safety of hoisting the curved arm and cross arm of the wine glass tower in complex terrain; and it is convenient for construction and transportation with assembly.
附图说明 Description of drawings
图1是本实用新型结构示意图。 Fig. 1 is the structural representation of the utility model.
图1-1是90度方向起吊时主摇臂平衡侧布置。 Figure 1-1 shows the layout of the balance side of the main rocker arm when hoisting at a direction of 90 degrees.
图1-2是90度方向起吊时副摇臂平衡布置图。 Figure 1-2 is a diagram of the balance layout of the auxiliary rocker arm when hoisting at a direction of 90 degrees.
图1-3是45度方向起吊时主摇臂平衡侧布置。 Figure 1-3 shows the layout of the balance side of the main rocker arm when hoisting at a direction of 45 degrees.
图1-4是45度方向起吊时副摇臂平衡布置图。 Figure 1-4 is a diagram of the balance layout of the auxiliary rocker arm when hoisting at a direction of 45 degrees.
图1-5是26.6度方向起吊时主摇臂平衡侧布置。 Figure 1-5 shows the layout of the balance side of the main rocker arm when hoisting at a direction of 26.6 degrees.
图1-6是26.6度方向起吊时副摇臂平衡布置图。 Figure 1-6 is a balance layout diagram of the auxiliary rocker arm when hoisting at a direction of 26.6 degrees.
图2是本实用新型顶升装置结构示意图。 Fig. 2 is a structural schematic diagram of the jacking device of the present invention.
图3是本实用新型一种腰环连接结构示意图。 Fig. 3 is a schematic diagram of a connection structure of a waist ring of the present invention.
图4是本实用新型力矩差限制器安装结构示意图。 Fig. 4 is a schematic diagram of the installation structure of the torque difference limiter of the present invention.
图中:1-底座、2-主杆、3-过渡段、4-回转组件、5-四通段、6-主桅杆、7-转动节、8-主摇臂、9-变幅绳、10-吊钩、11-腰环、12-套架、13-底架基础、14-基础底块、15-主材、16-平衡绳、17-保险钢丝绳、18-卸扣、19-手扳葫芦;20-力矩差限制器;21-腰环拉线;22-地面塔腿。 In the figure: 1-base, 2-main pole, 3-transition section, 4-rotary assembly, 5-cross section, 6-main mast, 7-rotary joint, 8-main rocker arm, 9-luffing rope, 10-hook, 11-waist ring, 12-set frame, 13-underframe foundation, 14-base bottom block, 15-main material, 16-balance rope, 17-safety wire rope, 18-shackle, 19-hand Lever block; 20-torque difference limiter; 21-waist ring pull wire; 22-ground tower leg.
具体实施方式 Detailed ways
以下结合说明书附图对本实用新型的技术方案做进一步的详细说明。 The technical solution of the utility model is described in further detail below in conjunction with the accompanying drawings of the description.
如图1所示,本实用新型包括位于铁塔中间的底座1、主杆2、过渡段3、回转组件4、四通段5、主桅杆6、转动节7、与四通段5相连的四摇臂及对应的起吊系统、变幅系统,所述的底座1、主杆2、过渡段3、回转组件4、四通段5、主桅杆6、转动节7自下而上设置,四摇臂中两摇臂为主摇臂8,两摇臂为副摇臂,两主摇臂8相对,两副摇臂相对,所述的主摇臂8设有起吊系统及变幅系统,当一主摇臂8作为起吊摇臂时,另一主摇臂8作为平衡摇臂,所述的副摇臂的自由端设有与铁塔地面塔腿22相连的平衡绳16;所述的主杆2上设有至少一个腰环11,一腰环11设有四根腰环拉线21以分别与铁塔的四根主材15相连。摇臂根部段与四通段5以穿心式轴销相连,从而组装成型。 As shown in Figure 1, the utility model includes a base 1 located in the middle of the iron tower, a main pole 2, a transition section 3, a rotary assembly 4, a four-way section 5, a main mast 6, a rotating joint 7, and four-way sections connected to the four-way section 5. The rocker arm and the corresponding lifting system and luffing system, the base 1, the main pole 2, the transition section 3, the slewing assembly 4, the four-way section 5, the main mast 6, and the swivel joint 7 are arranged from bottom to top. The two rocker arms in the arm are the main rocker arms 8, the two rocker arms are auxiliary rocker arms, the two main rocker arms 8 are opposite, and the two auxiliary rocker arms are opposite. When the main rocker arm 8 is used as a lifting rocker arm, the other main rocker arm 8 is used as a balance rocker arm, and the free end of the auxiliary rocker arm is provided with a balance rope 16 connected to the tower leg 22 on the ground of the iron tower; At least one waist ring 11 is provided on the top, and one waist ring 11 is provided with four waist ring stay wires 21 to be respectively connected with the four main materials 15 of the iron tower. The root section of the rocker arm is connected with the four-way section 5 with a through-type shaft pin, so as to be assembled.
主摇臂8起吊滑车组采用1—2滑车组走4道磨绳,起吊滑车组上滑车滑轮固定于摇臂顶部,下滑车采用吊钩10自带滑轮;变幅滑车组采用2—3滑车组走6道磨绳,两滑车均采用悬挂式,另设置一道φ26保险钢丝绳17。变幅、起吊磨绳均采用φ15钢丝绳;变幅、起吊磨绳均从抱杆内部引下,从回转组件4以下两节2m段下方的导向滑轮过渡段3引出。副摇臂无变幅系统,仅采用一道φ26钢丝绳将摇臂头部与抱杆顶端连接,起吊系统采用3道φ15钢丝绳锚固到地面塔腿22。 The 8 hoisting blocks of the main rocker arm use 1-2 blocks to wear 4 ropes. The upper block pulley of the lifting block block is fixed on the top of the rocker arm, and the lower block uses the hook 10 with its own pulley; the luffing block uses 2-3 blocks The group walks 6 grinding ropes, and the two blocks all adopt the suspension type, and a φ26 safety wire rope 17 is set in addition. Both the luffing and hoisting grinding ropes use φ15 steel wire ropes; the luffing and hoisting grinding ropes are all led down from the inside of the pole, and are led out from the transition section 3 of the guide pulley below the two sections 2m below the slewing assembly 4. The auxiliary rocker arm has no luffing system, only one φ26 steel wire rope is used to connect the head of the rocker arm to the top of the pole, and the lifting system is anchored to the tower leg 22 on the ground by three φ15 steel wire ropes.
抱杆主摇臂8位于90°方向进行吊装作业,如水平铁、塔片或地线顶架、横担时,对侧主摇臂8及两侧副摇臂的起吊滑车组塔脚处筋板孔相连,主摇臂8平衡侧布置如图1-1所示,副摇臂平衡布置如图1-2所示。 The main rocker arm 8 on the pole is located in the direction of 90° for hoisting operations, such as horizontal iron, tower piece or ground wire top frame, cross arm, the ribs at the foot of the tower foot of the hoisting block of the main rocker arm 8 on the opposite side and the auxiliary rocker arms on both sides The plate holes are connected, the balance side layout of the main rocker arm 8 is shown in Figure 1-1, and the balance layout of the auxiliary rocker arm is shown in Figure 1-2.
抱杆主摇臂8位于45°方向进行吊装作业,如塔腿主材15时,对侧主摇臂8及两侧副摇臂的起吊滑车组固定于塔脚筋板上,主摇臂8平衡侧布置如图1-3,副摇臂平衡布置如图1-4。 The pole-holding main rocker arm 8 is located in the direction of 45° for hoisting operations. For example, when the main material of the tower leg is 15, the hoisting blocks of the main rocker arm 8 on the opposite side and the lifting blocks of the auxiliary rocker arms on both sides are fixed on the tower hamstring plate, and the main rocker arm 8 The layout of the balance side is shown in Figure 1-3, and the balance layout of the auxiliary rocker arm is shown in Figure 1-4.
抱杆主摇臂8位于26.6°方向进行吊装作业,如大斜铁时,对侧主摇臂8及两侧副摇臂的起吊滑车组塔脚处筋板孔相连,主摇臂8平衡侧布置如图1-5,副摇臂平衡布置如图1-6。 The main rocker arm 8 on the pole is located in the direction of 26.6° for hoisting operations. For example, in the case of large inclined iron, the main rocker arm 8 on the opposite side and the hoisting blocks of the auxiliary rocker arms on both sides are connected to the rib plate holes at the tower feet of the hoisting blocks. The balance side of the main rocker arm 8 is The layout is shown in Figure 1-5, and the balance layout of the auxiliary rocker arm is shown in Figure 1-6.
塔身处的抱杆腰环11按50kN设置,45°方向布置四根腰环拉线21,连接方式:腰环11→BW5卸扣18→φ17.5腰环拉线21→50kN双钩→BW5卸扣18→铁塔主材15。当铁塔四腿成长方形布置,如图3所示,则腰环拉线21采用交叉方式打设,交叉布置如图3所示,连接方式;腰环11→BW9.5卸扣18→φ21.5腰环拉线21→90kN手扳葫芦19→BW9.5卸扣18→铁塔主材15。 The pole-holding waist ring 11 at the tower body is set according to 50kN, and four waist ring stays 21 are arranged in a 45° direction. 18→Main material 15 of the iron tower. When the four legs of the iron tower are arranged in a rectangular shape, as shown in Figure 3, the waist ring pull wire 21 is laid in a crossing manner, and the crossing arrangement is shown in Figure 3, the connection method; waist ring 11→BW9.5 shackle 18→φ21.5 Waist ring cable 21→90kN lever hoist 19→BW9.5 shackle 18→main material of iron tower 15.
为提高安全性,所述的主桅杆6设有力矩差限制器20,如图4所示,所述的力矩差限制器20位于设主摇臂8侧,起吊系统起重绞磨出绳端前部设有单环式起重限制器。 In order to improve safety, the main mast 6 is provided with a moment difference limiter 20, as shown in Figure 4, the moment difference limiter 20 is located on the side of the main rocker arm 8, and the hoisting system lifts and winches the end of the rope There is a single-ring lift limiter at the front.
座地自平衡抱杆的安装方法包括以下步骤: The installation method of the ground self-balancing pole includes the following steps:
1)底座1安装 1) Base 1 installation
将铁塔中心2.5×2.5m的范围整平,采用人抬方式直接将底座1安放在铁塔中心,并在四侧基础上锚固收紧; Level the area of 2.5×2.5m in the center of the iron tower, place the base 1 directly in the center of the iron tower by means of human lifting, and anchor and tighten on the four sides of the foundation;
2)标准段及过渡段3本体段安装 2) Standard section and transition section 3 body section installation
A)根部3m直段安装 A) Root 3m straight section installation
抱杆根部第一段直段采用人工抬运安装,先按照线路基础方位抱杆底座1放置在基础中心位置,再人工抬运第一个直段安装在底座1上; The first straight section at the root of the pole is manually lifted and installed. First, the pole-holding base 1 is placed at the center of the foundation according to the basic orientation of the line, and then the first straight section is manually lifted and installed on the base 1;
B)中部直段及过渡段3安装:该部分采用钢管独木抱杆分段吊装; B) Installation of the middle straight section and the transition section 3: this section is hoisted in sections using steel pipes and single wooden poles;
a)抱杆起立:将钢管抱杆由人工在地面立起靠在已安装就位的座地抱杆直段外侧,钢管头部带上起吊滑车、起吊钢丝绳及四根外拉线钢丝绳,起吊滑车及外拉线分别固定于钢管顶部预留孔内,钢管底部及距底部2m处分别绑设承托钢丝套。 a) Standing with the pole: the steel pipe pole is manually erected on the ground and leaned against the outside of the straight section of the ground pole that has been installed in place, and the head of the steel pipe is equipped with a lifting block, a lifting wire rope and four outer wire ropes to lift the block and the outer guy wires are respectively fixed in the reserved holes on the top of the steel pipe, and the bottom of the steel pipe and 2m away from the bottom are respectively tied with supporting wire sleeves.
b)抱杆提升:先在3m直段顶部设置一导向滑车,同时在直段上端设一道钢丝套将抱杆角钢与抱杆围绑在一起,作为提升腰箍用,然后将提升钢丝绳一端锁于抱杆提升板上,另一端通过导向滑车引到机动绞磨,抱杆提升过程中利用外拉线调整抱杆的正直,使钢管抱杆沿直段主角钢提升到吊装位置,即使钢管抱杆高出直段连接平面6m,提升到位后,将钢管抱杆底部用承托钢丝绳绑扎固定在直段主角钢上,拆除腰箍钢丝套及提升钢绳; b) Pole lifting: first set a guide block on the top of the 3m straight section, and at the same time set a steel wire sleeve on the upper end of the straight section to tie the angle steel of the pole with the surrounding of the pole as a hoop for hoisting, and then lock one end of the hoisting wire rope On the lifting plate of the holding rod, the other end is led to the motorized winch mill through the guide block. During the lifting process of the holding rod, the outer pull wire is used to adjust the uprightness of the holding rod, so that the steel pipe holding rod is lifted to the hoisting position along the straight section of the main steel, even if the steel pipe holding the rod 6m higher than the connecting plane of the straight section. After lifting in place, tie the bottom of the steel pipe holding pole to the leading steel of the straight section with a supporting wire rope, and remove the waist hoop wire sleeve and lifting steel rope;
C)吊装:抱杆提升到吊装位置后,即可进行标准段直段吊装;吊装时使用外拉线,外拉线的对地夹角按45°布置; C) Hoisting: After the pole is lifted to the hoisting position, the standard section straight section can be hoisted; when hoisting, the outer pull wire is used, and the angle of the outer pull wire to the ground is arranged at 45°;
D)抱杆内拉线打设:回转组件4吊装完成后,在回转组件4下部的45°方向上打设内拉线,内拉线对地夹角≤60°; D) Laying of the inner stay wire on the pole: After the hoisting of the slewing assembly 4 is completed, the inner stay wire is laid in the 45° direction of the lower part of the slewing assembly 4, and the angle between the inner stay wire and the ground is ≤ 60°;
E)内拉线打设好后,继续吊装四通段5及抱杆桅杆段;一次只吊装一节主杆2; E) After the inner cable is laid, continue to hoist the four-way section 5 and the mast section; only hoist one section of the main pole 2 at a time;
3)钢管抱杆卸除 3) Removal of the steel pipe holding pole
抱杆主杆2吊装完成,即可拆除钢管抱杆;抱杆的卸除按提升的反程序进行,提起抱杆,拆除绑扎固定的承托绳,打好抱杆顶部的腰环11绳套,先将钢管抱杆松下7m,即头部下至抱杆顶部下方1m,此时将提升钢丝绳的提升端头由抱杆根部移至顶部,另一端经顶部及地面导向滑车进绞磨; After the hoisting of the main pole 2 of the holding pole is completed, the steel pipe holding pole can be removed; the removal of the holding pole is carried out according to the reverse procedure of lifting. Firstly, the steel pipe is held by the pole for 7m, that is, the head is lowered to 1m below the top of the pole. At this time, the lifting end of the hoisting wire rope is moved from the root of the pole to the top, and the other end enters the winch through the top and the ground guide block;
4) 摇臂的吊装 4) Hoisting of the rocker arm
四摇臂分别在地面组成整体,利用组好的抱杆主杆2进行吊装; The four rocker arms are formed as a whole on the ground, and are hoisted by using the assembled pole main pole 2;
在抱杆主杆2顶部挂一起重滑车,吊装磨绳一端锁于摇臂顶部,另一端经抱杆顶部及地面导向滑车后进绞磨,用绞磨将摇臂吊装就位; Hang a heavy block on the top of the main pole 2 of the holding pole, one end of the hoisting grinding rope is locked on the top of the rocker arm, and the other end passes through the top of the holding pole and the ground guide block to enter the winch, and the rocker arm is hoisted in place with the winch;
摇臂吊装完毕后,对主摇臂8安装变幅、起吊系统、保险绳,放平摇臂,对副摇臂安装平衡绳16。 After the rocker arm hoisting was completed, luffing, hoisting system and safety rope were installed to the main rocker arm 8, and the rocker arm was leveled, and the balance rope 16 was installed to the auxiliary rocker arm.
抱杆提升采用液压顶升加高的方式;抱杆提升装置如图2所示,包括基础底块14、底架基础13、套架12,基础底块14位于最下端,其上方设有底架基础13,底架基础上方为套架12。 The lifting of the pole adopts the method of hydraulic jacking and heightening; the lifting device of the pole is shown in Figure 2, including the base block 14, the base frame foundation 13, and the sleeve frame 12. The base block 14 is located at the bottom end, and there is a bottom Frame foundation 13, the bottom frame foundation top is sleeve frame 12.
1)顶升开始前,需将顶升套架12的拉线打设好,在要顶升的标准节上装好爬梯和所需要的平台,每四节一个平台; 1) Before the jacking starts, the pull wires of the jacking frame 12 need to be laid, and the ladder and the required platforms are installed on the standard sections to be lifted, one platform for every four sections;
2)拆除塔身与底架基础13上标准节底座1的连接螺栓组,拆除套架12底横梁; 2) Remove the connecting bolt group between the tower body and the standard section base 1 on the base 13, and remove the bottom beam of the sleeve frame 12;
3)将顶升承台的扳手杆摇起,使套架12爬爪贴近标准节主弦杆踏步,就位后开始顶升油缸,顶升油缸过程中要保证导向滚轮与塔身的间隙在2mm 以上; 3) Shake the wrench lever of the jacking platform, so that the 12 climbing claws of the sleeve frame are close to the main chord of the standard section, and start to lift the cylinder after it is in place. During the process of jacking the cylinder, ensure that the gap between the guide roller and the tower body is within 2mm or more;
4)顶升一段距离后停止,拆去底架基础13上的四个标准节底座1; 4) Stop after jacking up for a certain distance, and remove the four standard section bases 1 on the underframe foundation 13;
5)安装引进组件,用螺栓与底架基础13连接; 5) Install the imported components and connect them with the underframe foundation 13 with bolts;
6)吊装标准节,用人力将标准节抬至引进梁的滚轮结构上,并用销轴连接,开始顶升加高,伸出油缸直至爬爪的顶升面和标准节上的踏步顶升面贴合,扳动摇杆使它处于与标准节主弦杆踏步脱开的位置,继续顶升直至将油缸完全伸出; 6) Hoist the standard section, use manpower to lift the standard section to the roller structure of the introduction beam, and connect it with a pin shaft, start lifting and heightening, extend the oil cylinder until the lifting surface of the climbing claw and the stepping lifting surface on the standard section Fitting, pull the rocker to disengage it from the main chord step of the standard section, and continue to lift until the cylinder is fully extended;
7)再将摇杆摇起,使它贴近标准节主弦杆踏步;就位后开始收回油缸,使摇杆顶面与踏步顶升面完全贴合,然后将顶升承台上的扳手杆摇下,使爬爪离开标准节主弦杆踏步;固定好扳手杆,然后继续完全收回油缸; 7) Then shake the rocker to make it close to the main chord step of the standard section; start retracting the oil cylinder after it is in place, so that the top surface of the rocker and the lifting surface of the step are completely attached, and then lift the wrench lever on the jacking platform Shake down to make the climbing claw leave the main chord rod of the standard section; fix the wrench rod, and then continue to fully retract the cylinder;
8)油缸完全收回后,将摇起扳手杆,使套架12爬爪贴近标准节主弦杆踏步; 8) After the oil cylinder is fully retracted, shake the wrench lever so that the 12 climbing claws of the sleeve frame are close to the main chord of the standard section;
9)回至第7步重复操作,直至油缸完成总共三次顶升行程,第三次顶升后油缸不收回,保持完全伸出状态; 9) Go back to step 7 and repeat the operation until the oil cylinder completes a total of three jacking strokes. After the third jacking, the oil cylinder does not retract and remains fully extended;
10)推进引进梁上的标准节,就位后收回油缸,直至塔身标准节下端面与引进的标准节上端面间距为1 cm -3cm,停止油缸动作;用螺栓组将引进梁上的标准节与上面的标准节连接,然后顶起油缸,拆下引进的标准节上的滚轮结构;再按照步骤8将油缸收回,完成安装一节标准节过程; 10) Advance the standard section on the introduction beam, retract the oil cylinder after it is in place, until the distance between the lower end surface of the tower body standard section and the upper end surface of the imported standard section is 1 cm -3cm, stop the cylinder action; use the bolt group to insert the standard section on the beam The joint is connected with the above standard joint, then the oil cylinder is jacked up, and the roller structure on the imported standard joint is removed; then the oil cylinder is retracted according to step 8, and the process of installing a standard joint is completed;
11)按照前面的步骤继续顶升,直到安装完所有要引进的标准节,最后拆下引进梁,换上标准节底座1,收回油缸,使整个塔身落在标准节底座1上,紧固好标准节底座1与塔身的螺栓,并装上套架12底横梁;至此,一次顶升作业过程全部完成。 11) Continue to lift according to the previous steps until all the standard sections to be introduced are installed, and finally remove the introduction beam, replace the standard section base 1, retract the oil cylinder, make the entire tower fall on the standard section base 1, and fasten it The bolts of the standard section base 1 and the tower body are installed, and the bottom beam of the sleeve frame 12 is installed; so far, a jacking operation process is completely completed.
座地自平衡抱杆工作起吊前,利用腰环11将抱杆杆身调直,将四只摇臂平放,两只副摇臂利用平衡绳16封牢,起吊反侧的起吊绳及变幅绳9尾绳分别引至绞磨并封牢,然后利用绞磨缓慢收紧起吊反侧变幅绳9,使抱杆向起吊反侧预倾10cm~20cm;起吊后,随着起吊受力不断增加,起吊反侧变幅绳9应随之不断收紧,以保证杆顶倾斜控制在10~20cm之内,在就位卸荷时,起吊反侧变幅绳9随之逐步放松。 Before lifting the self-balancing pole on the ground, use the waist ring 11 to straighten the pole body, lay the four rockers flat, seal the two auxiliary rockers with the balance rope 16, and lift the lifting rope and the luffing arm on the opposite side. Lead the tail ropes of the rope 9 to the winch and seal them tightly, and then use the winch to slowly tighten the luffing rope 9 on the opposite side of the hoisting, so that the pole is pre-tilted 10cm to 20cm toward the opposite side of the hoisting; after hoisting, as the hoisting force continues to increase, The luffing rope 9 on the opposite side for lifting should be continuously tightened accordingly to ensure that the inclination of the top of the pole is controlled within 10-20 cm.
以上图1-4所示的座地自平衡抱杆是本实用新型的具体实施例,已经体现出本实用新型实质性特点和进步,可根据实际的使用需要,在本实用新型的启示下,对其进行形状、结构等方面的等同修改,均在本方案的保护范围之列。 The ground self-balancing holding pole shown in Figures 1-4 above is a specific embodiment of the utility model, which has already reflected the substantive features and progress of the utility model, and can be used according to actual needs, under the inspiration of the utility model, Equivalent modification of its shape, structure and other aspects are all within the scope of protection of this scheme.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420400992.2U CN204150970U (en) | 2014-07-18 | 2014-07-18 | Seat ground self-balancing pole |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420400992.2U CN204150970U (en) | 2014-07-18 | 2014-07-18 | Seat ground self-balancing pole |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204150970U true CN204150970U (en) | 2015-02-11 |
Family
ID=52509106
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201420400992.2U Expired - Lifetime CN204150970U (en) | 2014-07-18 | 2014-07-18 | Seat ground self-balancing pole |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204150970U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104276514A (en) * | 2014-07-18 | 2015-01-14 | 国家电网公司 | Ground self-balancing pole and its installation and use method |
| CN105271009A (en) * | 2015-10-09 | 2016-01-27 | 徐州建机工程机械有限公司 | Double-horizontal-boom crane |
| CN105804484A (en) * | 2016-02-17 | 2016-07-27 | 浙江省送变电工程公司 | Anti-wear and anti-groove-skipping tool for ground pulley blocks for lifting high tower derrick and using method |
-
2014
- 2014-07-18 CN CN201420400992.2U patent/CN204150970U/en not_active Expired - Lifetime
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104276514A (en) * | 2014-07-18 | 2015-01-14 | 国家电网公司 | Ground self-balancing pole and its installation and use method |
| CN105271009A (en) * | 2015-10-09 | 2016-01-27 | 徐州建机工程机械有限公司 | Double-horizontal-boom crane |
| CN105804484A (en) * | 2016-02-17 | 2016-07-27 | 浙江省送变电工程公司 | Anti-wear and anti-groove-skipping tool for ground pulley blocks for lifting high tower derrick and using method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104276514B (en) | Installation method of ground self-balancing pole | |
| CN102359303B (en) | UHV ordinary line iron tower assembly method | |
| CN102359302B (en) | UHV long-span iron tower assembly method | |
| CN202346637U (en) | Holding rod of double-flat-arm spinning self-lifting seat | |
| CN205387439U (en) | Mast hoisting accessory | |
| CN205955358U (en) | Group's tower device of interior floated armful of pole of acting as go -between | |
| CN202187601U (en) | Single-twisting-grinder double-pole iron tower erecting device of high-voltage power transmission line | |
| CN102535939B (en) | Inversely assembling process for standing stay wire V-type tower | |
| CN106368493A (en) | Two-arm hydraulic drive-in type hard capping lattice type crossing frame | |
| CN202530769U (en) | Large span steel structure high-altitude subsection hoisting support system | |
| CN216341336U (en) | Adjustable inverted frame structure of 750 x 750mm cross-section holding rod system | |
| CN204150970U (en) | Seat ground self-balancing pole | |
| CN103243963B (en) | A kind of suspended holding pole segmental hoisting steel pipe pole method | |
| CN204999517U (en) | Coal transporting trestle steel truss hoist device in power plant's chimney | |
| CN103738861B (en) | A kind of ultra-high voltage transformer station type column of steel pipe integral hoisting method | |
| CN105822132A (en) | Unit type assembly and erection method of extra-high-voltage power transmission iron pylon | |
| CN209276035U (en) | A kind of self-supporting superelevation Lift-on/Lift-off System | |
| CN216240042U (en) | A pole holding device | |
| CN110359756A (en) | 750kV booster stations framework installation method | |
| CN206189985U (en) | Both arms hydraulic pressure propulsion type lattice formula crossing structure that binds firmly | |
| CN112412146B (en) | Attached light holding pole construction process for extra-high voltage transmission line | |
| CN113931516A (en) | Holding pole standing device | |
| CN203065046U (en) | Self-stabilizing double-rocker-arm lifting device for installation of high-rise tower | |
| CN213015693U (en) | Self-lifting vertical tower device based on semi-rigid composite tower crane | |
| CN103072903B (en) | Method for mounting high-rise pylon by using self-stable double-rocker elevating device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CX01 | Expiry of patent term | ||
| CX01 | Expiry of patent term |
Granted publication date: 20150211 |