CN204127653U - Reclaim the skid-mounted device of the remaining rock gas of long-tube trailer - Google Patents

Reclaim the skid-mounted device of the remaining rock gas of long-tube trailer Download PDF

Info

Publication number
CN204127653U
CN204127653U CN201420290913.7U CN201420290913U CN204127653U CN 204127653 U CN204127653 U CN 204127653U CN 201420290913 U CN201420290913 U CN 201420290913U CN 204127653 U CN204127653 U CN 204127653U
Authority
CN
China
Prior art keywords
long
cut
tube trailer
valve
skid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420290913.7U
Other languages
Chinese (zh)
Inventor
陈炳良
张湘华
王磊
裴文堂
宗辉
赵庭林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HANGZHOU CITY YIPU GAS Co Ltd
Original Assignee
HANGZHOU CITY YIPU GAS Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HANGZHOU CITY YIPU GAS Co Ltd filed Critical HANGZHOU CITY YIPU GAS Co Ltd
Priority to CN201420290913.7U priority Critical patent/CN204127653U/en
Application granted granted Critical
Publication of CN204127653U publication Critical patent/CN204127653U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

Reclaim a skid-mounted device for the remaining rock gas of long-tube trailer, comprising: control unit, low pressure compressor, knock out drum, the first cut-off valve, the second cut-off valve, pressure-detecting device, gas distribution channel; Control unit is electrically connected with low pressure compressor, the first cut-off valve, the second cut-off valve, pressure-detecting device; Described first cut-off valve is for controlling the opening and closing of gas distribution channel, and described low pressure compressor is connected with knock out drum formation Pressure channel, and described second cut-off valve controls the opening and closing of Pressure channel; Described Pressure channel is with gas distribution channel parallel connection and two ends are connected long-tube trailer and high pressure compressor respectively.The skid-mounted device of the remaining rock gas of described recovery long-tube trailer does not need other structures changing existing aerating flow process, only need to add at long-tube trailer and high pressure compressor the rock gas that described skid-mounted device farthest can reclaim long-tube trailer remnants, cost is lower, and effect is better.

Description

Reclaim the skid-mounted device of the remaining rock gas of long-tube trailer
Technical field
The utility model relates to CNG aerating field, particularly reclaims the skid-mounted device of the remaining rock gas of long-tube trailer in a kind of CNG automobile air entraining substation.
Background technique
At present, the CNG automobile gas station aerating flow process of domestic construction comprises: CNG (compressed natural gas) long-tube trailer is transported to CNG automobile gas station, utilize sequence control dish and high pressure compressor by natural gas storing in senior middle school's low pressure air cylinder 3, then through CNG filling machine to Natural gas vehicles aerating.And compressor is all one stage of compression (import) or two stage compression (domestic).
But existing CNG long-tube trailer is had an appointment all the time, the rock gas of 600 ~ 700 sides exists in long-tube trailer and can not release, and causes long-tube trailer utilization ratio and reduces by 15% ~ 20%, is unfavorable for the cost of transportation reducing rock gas.
Model utility content
The problem that the utility model solves is to provide a kind of skid-mounted device reclaiming the remaining rock gas of long-tube trailer, and can reclaim rock gas remaining in long-tube trailer completely, cost is lower.
For solving the problem, the utility model embodiment provides a kind of skid-mounted device reclaiming the remaining rock gas of long-tube trailer, comprising: control unit, low pressure compressor, knock out drum, the first cut-off valve, the second cut-off valve, pressure-detecting device, gas distribution channel; Control unit is electrically connected with low pressure compressor, the first cut-off valve, the second cut-off valve, pressure-detecting device; Described first cut-off valve is for controlling the opening and closing of gas distribution channel, and described low pressure compressor is connected with knock out drum formation Pressure channel, and described second cut-off valve controls the opening and closing of Pressure channel; Described Pressure channel is with gas distribution channel parallel connection and two ends are connected long-tube trailer and high pressure compressor respectively.
Optionally, described second cut-off valve is between high pressure compressor and knock out drum.
Optionally, also comprise the 3rd cut-off valve, described 3rd cut-off valve is between long-tube trailer and low pressure compressor.
Optionally, described low pressure compressor is air-cooled or water-cooled piston formula compressor.
Optionally, described low pressure compressor is stage compressor or two stage compressor.
Optionally, described control unit is PLC control system.
Optionally, after pressure-detecting device detects that the air pressure of long-tube trailer is lower than predetermined value, working signal is sent to control unit, control unit is by controlling low pressure compressor, knock out drum, the first cut-off valve, the second cut-off valve, close gas distribution channel, open low pressure compressor, bleed to carry out being compressed to knock out drum in long-tube trailer and carry out voltage stabilizing, to ensure that high pressure compressor inlet pressure is stablized; After pressure-detecting device detects that the air pressure of long-tube trailer is lower than minimum, silence signal is sent to control unit, closes Pressure channel.
Optionally, described predetermined value is 3MPa, and minimum is 0.3MPa.
Optionally, also comprise display unit, described display unit is connected with control unit, can show the force value that pressure-detecting device obtains in real time.
Compared with prior art, the technical program has the following advantages:
The skid-mounted device of the remaining rock gas of described recovery long-tube trailer does not need other structures changing existing aerating flow process, only need to add at long-tube trailer and high pressure compressor the rock gas that described skid-mounted device farthest can reclaim long-tube trailer remnants, cost is lower, and effect is better.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of the aerating flow process of the CNG automobile air entraining substation of the utility model embodiment;
Fig. 2 is the structural representation of the skid-mounted device of the remaining rock gas of recovery long-tube trailer of the utility model embodiment.
Embodiment
In existing aerating flow process, after long-tube trailer drops to about 2.5 ~ 3MPa gradually by initial pressure 20MPa, high pressure compressor by compression than the pressure that restricts export do not reach the 20MPa of design, therefore will change long-tube trailer, long-tube trailer has the rock gas residue of 3MPa.In order to solve the problem, prior art is improved for high pressure compressor.And inventor is through research, provide a kind of skid-mounted device reclaiming the remaining rock gas of long-tube trailer, cost is lower, also can reclaim rock gas remaining in long-tube trailer, can not change the structure of high pressure compressor simultaneously.
Below in conjunction with accompanying drawing, by specific embodiment, clear, complete description is carried out to the technical solution of the utility model.
Please refer to Fig. 1, for the schematic diagram of the aerating flow process of the CNG automobile air entraining substation of the utility model embodiment, comprise: CNG long-tube trailer 1 is transported to CNG automobile gas station, the skid-mounted device 2 of the remaining rock gas of described recovery long-tube trailer is utilized to be connected with high pressure compressor 3, natural gas storing in the air cylinder group 4 of senior middle school's low pressure, is then given Natural gas vehicles 6 aerating through CNG filling machine 5 by high pressure compressor 3.
Please refer to Fig. 2, the structural representation of the skid-mounted device of the remaining rock gas of the recovery long-tube trailer for the utility model embodiment, comprising: control unit 10, low pressure compressor 20, knock out drum 30, first cut-off valve 40, second cut-off valve 50, the 3rd cut-off valve 60, pressure-detecting device 70, gas distribution channel 80; Control unit 10 is electrically connected with low pressure compressor 20, first cut-off valve 40, second cut-off valve 50, the 3rd cut-off valve 60, pressure-detecting device 70; Described low pressure compressor 20 is connected with knock out drum 30 formation Pressure channel, described Pressure channel is with gas distribution channel 80 parallel connection and two ends are connected long-tube trailer 1 and high pressure compressor 3 respectively, described first cut-off valve 40 is for controlling the opening and closing of gas distribution channel, described second cut-off valve 50 is between high pressure compressor 3 and knock out drum 30, and described 3rd cut-off valve 60 is between long-tube trailer 1 and low pressure compressor 20.
In the present embodiment, described low pressure compressor is air-cooled or water-cooled piston formula compressor.In other embodiments, described low pressure compressor also can be other low pressure compressors.
Described low pressure compressor is stage compressor or two stage compressor, because two stage compressor cost is lower, and compresses less demanding, therefore adopts two stage compressor in the present embodiment.
In the present embodiment, described control unit is PLC control system.The timer be made up of semiconductor circuit in PLC inside and the clock pulse timing produced by crystal oscillator, timing accuracy is high, and flexibility is large, and timing is not affected by environment.Its inner specific counter in addition, can realize the step motion control to manufacturing mechanism.And PLC adopts microelectronic technology, inner switch motion has come by contactless semiconductor circuit, and the life-span is long, and reliability is high, and can be shown to operator at any time, the practice condition of timely supervisory control program, for field adjustable and maintenance provide convenient.
In other embodiments, the skid-mounted device of the remaining rock gas of described recovery long-tube trailer also has display unit, and described display unit is connected with PLC control system, can show the force value that pressure-detecting device obtains in real time.
When high pressure compressor is when bleeding, gas distribution channel is in opening state, after pressure-detecting device detects that the air pressure of long-tube trailer is lower than predetermined value, working signal is sent to control unit, control unit is by controlling low pressure compressor, knock out drum, the first cut-off valve, the second cut-off valve, the 3rd cut-off valve, close gas distribution channel, open Pressure channel, open low pressure compressor simultaneously, bleed to carry out being compressed to knock out drum in long-tube trailer and carry out voltage stabilizing, to ensure that high pressure compressor inlet pressure is stablized; After pressure-detecting device detects that the air pressure of long-tube trailer is lower than minimum, silence signal is sent to control unit, closes Pressure channel.The utility model can carry out voltage stabilizing owing to only need utilize in knock out drum, and does not need to change high pressure compressor, and cost is low, and almost the rock gas of long-tube trailer remnants can be reclaimed completely, to improve the utilization ratio of long-tube trailer, reduce natural gas transportation cost, increase economic benefit.
In the present embodiment, described predetermined value is 3MPa, and minimum is 0.3MPa.In other embodiments, described predetermined value and minimum also can be other suitable values.
Although the utility model with preferred embodiment openly as above; but it is not for limiting the utility model; any those skilled in the art are not departing from spirit and scope of the present utility model; the Method and Technology content of above-mentioned announcement can be utilized to make possible variation and amendment to technical solutions of the utility model; therefore; every content not departing from technical solutions of the utility model; the any simple modification done above embodiment according to technical spirit of the present utility model, equivalent variations and modification, all belong to the protection domain of technical solutions of the utility model.

Claims (9)

1. reclaim a skid-mounted device for the remaining rock gas of long-tube trailer, it is characterized in that, comprising: control unit, low pressure compressor, knock out drum, the first cut-off valve, the second cut-off valve, pressure-detecting device, gas distribution channel; Control unit is electrically connected with low pressure compressor, the first cut-off valve, the second cut-off valve, pressure-detecting device; Described first cut-off valve is for controlling the opening and closing of gas distribution channel, and described low pressure compressor is connected with knock out drum formation Pressure channel, and described second cut-off valve controls the opening and closing of Pressure channel; Described Pressure channel is with gas distribution channel parallel connection and two ends are connected long-tube trailer and high pressure compressor respectively.
2. the skid-mounted device reclaiming the remaining rock gas of long-tube trailer as claimed in claim 1, it is characterized in that, described second cut-off valve is between high pressure compressor and knock out drum.
3. the skid-mounted device reclaiming the remaining rock gas of long-tube trailer as claimed in claim 1, it is characterized in that, also comprise the 3rd cut-off valve, described 3rd cut-off valve is between long-tube trailer and low pressure compressor.
4. the skid-mounted device reclaiming the remaining rock gas of long-tube trailer as claimed in claim 1, it is characterized in that, described low pressure compressor is air-cooled or water-cooled piston formula compressor.
5. the skid-mounted device reclaiming the remaining rock gas of long-tube trailer as claimed in claim 1, it is characterized in that, described low pressure compressor is stage compressor or two stage compressor.
6. the skid-mounted device reclaiming the remaining rock gas of long-tube trailer as claimed in claim 1, it is characterized in that, described control unit is PLC control system.
7. the skid-mounted device reclaiming the remaining rock gas of long-tube trailer as claimed in claim 1, it is characterized in that, after pressure-detecting device detects that the air pressure of long-tube trailer is lower than predetermined value, working signal is sent to control unit, control unit, by controlling low pressure compressor, knock out drum, the first cut-off valve, the second cut-off valve, is closed gas distribution channel, is opened low pressure compressor, bleed to carry out being compressed to knock out drum in long-tube trailer and carry out voltage stabilizing, to ensure that high pressure compressor inlet pressure is stablized; After pressure-detecting device detects that the air pressure of long-tube trailer is lower than minimum, silence signal is sent to control unit, closes Pressure channel.
8. the skid-mounted device reclaiming the remaining rock gas of long-tube trailer as claimed in claim 7, it is characterized in that, described predetermined value is 3MPa, and minimum is 0.3MPa.
9. the skid-mounted device reclaiming the remaining rock gas of long-tube trailer as claimed in claim 1, it is characterized in that, also comprise display unit, described display unit is connected with control unit, can show the force value that pressure-detecting device obtains in real time.
CN201420290913.7U 2014-05-30 2014-05-30 Reclaim the skid-mounted device of the remaining rock gas of long-tube trailer Expired - Fee Related CN204127653U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420290913.7U CN204127653U (en) 2014-05-30 2014-05-30 Reclaim the skid-mounted device of the remaining rock gas of long-tube trailer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420290913.7U CN204127653U (en) 2014-05-30 2014-05-30 Reclaim the skid-mounted device of the remaining rock gas of long-tube trailer

Publications (1)

Publication Number Publication Date
CN204127653U true CN204127653U (en) 2015-01-28

Family

ID=52384009

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420290913.7U Expired - Fee Related CN204127653U (en) 2014-05-30 2014-05-30 Reclaim the skid-mounted device of the remaining rock gas of long-tube trailer

Country Status (1)

Country Link
CN (1) CN204127653U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111237637A (en) * 2018-11-29 2020-06-05 苏州工业园区可伦坡系统集成科技有限公司 Be used for gas supply equipment air cylinder to change detection device
CN112303483A (en) * 2019-12-13 2021-02-02 安瑞科(廊坊)能源装备集成有限公司 Air leakage device and air leakage method of hydrogen trailer
CN114321707A (en) * 2020-10-10 2022-04-12 中国石化工程建设有限公司 Method and system for unloading hydrogen from long-tube trailer to hydrogen filling station
US11535207B2 (en) 2018-11-24 2022-12-27 Change Energy Services Compressed-gas distribution associated with vehicle
CN116428512A (en) * 2023-03-06 2023-07-14 郑州大学 An integrated mobile hydrogen refueling station

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11535207B2 (en) 2018-11-24 2022-12-27 Change Energy Services Compressed-gas distribution associated with vehicle
CN111237637A (en) * 2018-11-29 2020-06-05 苏州工业园区可伦坡系统集成科技有限公司 Be used for gas supply equipment air cylinder to change detection device
CN112303483A (en) * 2019-12-13 2021-02-02 安瑞科(廊坊)能源装备集成有限公司 Air leakage device and air leakage method of hydrogen trailer
CN114321707A (en) * 2020-10-10 2022-04-12 中国石化工程建设有限公司 Method and system for unloading hydrogen from long-tube trailer to hydrogen filling station
CN116428512A (en) * 2023-03-06 2023-07-14 郑州大学 An integrated mobile hydrogen refueling station

Similar Documents

Publication Publication Date Title
CN103383172B (en) A kind of method and system recycling azeotrope
CN203594974U (en) Pressure stabilizing and reclaiming device for high-pressure nitrogen
CN201426002Y (en) Carbon dioxide laser gas control device
CN204151077U (en) The device of a kind of Separation and Recovery dithiocarbonic anhydride and nitrogen
CN203421488U (en) Low-temperature liquid filling and gas recovery device
CN202281901U (en) Device capable of reducing waste of photoresist during replacement
CN101303576A (en) A new pulse controller based on matrix output
CN203571420U (en) CNG (compressed natural gas) station
CN202708584U (en) Gas filling system of fuel gas vehicle
CN105387345A (en) Automatic changing cabinet for quantitative-type gas
CN204005229U (en) A kind of argon gas reclaims and fills bottle apparatus
CN203963503U (en) High pressure helium recycle and reuse device in a kind of leak-testing
CN203103394U (en) Vacuum acid adding machine
CN204461049U (en) For the waste heat recovery device of tunnel cave
CN202707416U (en) Water discharge device of air compressor
CN203634848U (en) Heavy turpentine batch distillation device with vacuum residue discharging system
CN204062488U (en) Compressed air conveying system
CN202074226U (en) Air pumping device for reutilizing helium gas in helium cylinder
CN205535040U (en) High suppression gas device of pneumatic cylinder
CN203532822U (en) Cooling device of high-temperature flat valve plate
CN203581698U (en) Elevated barrel for storing aluminiumpaste
CN202274808U (en) Nitrogen filling sealing device for inlet pressing plate and outlet pressing plate of condenser
CN202927490U (en) Material conveying device
CN204128755U (en) A kind of accurate quartz resonator is leak detection pressure helium device at a high speed
CN204328163U (en) Heat recovery quick opening valve opens pneumatic system soon

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150128