CN204101789U - Auxiliary tool for magnetic jumper optical fiber penetration protection tube - Google Patents

Auxiliary tool for magnetic jumper optical fiber penetration protection tube Download PDF

Info

Publication number
CN204101789U
CN204101789U CN201420635296.XU CN201420635296U CN204101789U CN 204101789 U CN204101789 U CN 204101789U CN 201420635296 U CN201420635296 U CN 201420635296U CN 204101789 U CN204101789 U CN 204101789U
Authority
CN
China
Prior art keywords
optical fiber
base
magnet
jumper
steel ball
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420635296.XU
Other languages
Chinese (zh)
Inventor
公冶祥广
张鹏
吴键
杨庆明
李春玉
孟国刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd
State Grid Corp of China
Original Assignee
Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd
State Grid Corp of China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd, State Grid Corp of China filed Critical Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority to CN201420635296.XU priority Critical patent/CN204101789U/en
Application granted granted Critical
Publication of CN204101789U publication Critical patent/CN204101789U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Light Guides In General And Applications Therefor (AREA)

Abstract

本实用新型公开了一种磁力式跳接光纤贯穿护管辅助工具,包括底座;所述底座上部设有把手,底座下部开有圆弧形凹槽;圆弧形凹槽与磁铁固定连接,所述磁铁下部设有可分离的钢球;所述钢球上设有通孔,所述通孔上连接有牵引线。所述底座和磁铁圆弧形的半径大于等于护管的半径。牵引线的长度大于护管的长度。辅助跳接光纤穿护管,大大节省了人力,提高了作业效率,并且有效保护了跳接光纤,免受外力损坏,增长了跳接光纤的使用寿命。

The utility model discloses an auxiliary tool for jumping optical fiber through protective tubes with magnetic force, which comprises a base; the upper part of the base is provided with a handle, and the lower part of the base is provided with an arc-shaped groove; the arc-shaped groove is fixedly connected with a magnet, and the The lower part of the magnet is provided with a detachable steel ball; the steel ball is provided with a through hole, and a traction line is connected to the through hole. The radius of the arc shape of the base and the magnet is greater than or equal to the radius of the protective tube. The length of the pulling wire is greater than the length of the protective tube. The auxiliary jumper optical fiber wears the protection tube, which greatly saves manpower, improves the working efficiency, and effectively protects the jumper fiber from external damage, and increases the service life of the jumper fiber.

Description

磁力式跳接光纤贯穿护管辅助工具Auxiliary tool for magnetic jumper optical fiber penetration protection tube

技术领域technical field

本实用新型涉及一种磁力式跳接光纤贯穿护管辅助工具。The utility model relates to an auxiliary tool for jumping optical fiber through protective tubes with magnetic force.

背景技术Background technique

随着智能电网的深入发展,新建变电站多以智能变电站为主。与传统变电站相比,大量的二次电缆被光缆替代成为智能变电站的显著特征。随着智能设备、装置的广泛使用,跳接光纤在智能变电站也扮演了极其重要的作用。为了使跳接光纤在复杂的现场环境中免遭损害,一般要对其采用相应的防护措施。常用的防护措施有两种:一是做成光缆,二是加装护管。在智能变电站日常维护中,使用较多的为长度小于20米的跳接光纤,这类跳接光纤,市场上大部分都没有配套的护管设施,且不同使用情况跳接光纤的使用长度不一,难以制定相关的标准。实际工作中,现场一般采用“随用随穿”的工作模式,用多长,穿多长。但由于跳接光纤纤细、柔软,穿管工作费时、费力。正常施工过程中,15米长的光纤,3人协作作业,需要2小时的才能完成,工作效率极低。With the in-depth development of smart grid, new substations are mostly smart substations. Compared with traditional substations, a large number of secondary cables are replaced by optical cables, which has become a prominent feature of smart substations. With the widespread use of smart devices and devices, jumper optical fibers also play an extremely important role in smart substations. In order to prevent the jumper fiber from being damaged in a complex field environment, corresponding protective measures are generally required for it. There are two commonly used protective measures: one is to make an optical cable, and the other is to install a protective tube. In the daily maintenance of smart substations, jumper fibers with a length of less than 20 meters are often used. Most of these jumper fibers in the market do not have supporting protection pipe facilities, and the length of jumper fibers used in different usage conditions varies. First, it is difficult to formulate relevant standards. In actual work, the work mode of "use and wear" is generally adopted on site, and the length of use can be as long as it is worn. However, because the jumper optical fiber is thin and soft, the work of threading the tube is time-consuming and laborious. During the normal construction process, the 15-meter-long optical fiber requires 3 people to work collaboratively, and it takes 2 hours to complete, and the work efficiency is extremely low.

实用新型内容Utility model content

本实用新型的目的就是为了解决上述问题,提供了一种磁力式跳接光纤贯穿护管辅助工具,辅助跳接光纤穿上护管,结构简单,实用价值高。The purpose of this utility model is to solve the above problems, providing a magnetic jumper optical fiber through protective tube auxiliary tool, which assists the jumper optical fiber to put on the protective tube, with simple structure and high practical value.

为了实现上述目的,本实用新型采用如下技术方案:In order to achieve the above object, the utility model adopts the following technical solutions:

磁力式跳接光纤贯穿护管辅助工具,包括底座,底座上部设有把手,方便使用;底座下部开有圆弧形凹槽;圆弧形凹槽与磁铁固定连接,底座和磁铁圆弧形的半径大于等于护管的半径,这样磁铁能够更好的与护管贴合;所述磁铁下部设有可分离的钢球;所述钢球上设有通孔,所述通孔上连接有牵引线,牵引线的长度大于护管的长度,保证钢球可以先穿过护管,再牵引跳接光纤通过护管。Auxiliary tool for magnetic jumper optical fiber through the protective tube, including a base, with a handle on the upper part of the base, which is convenient to use; the lower part of the base has an arc-shaped groove; the arc-shaped groove is fixedly connected with the magnet, and the arc-shaped base and magnet The radius is greater than or equal to the radius of the protective tube, so that the magnet can fit better with the protective tube; the lower part of the magnet is provided with a detachable steel ball; the steel ball is provided with a through hole, and the through hole is connected with a traction The length of the pulling line is greater than the length of the protective tube, so that the steel ball can pass through the protective tube first, and then pull the jumper optical fiber through the protective tube.

本实用新型的有益效果:本实用新型结构简单,实用性强,操作简边,辅助跳接光纤穿护管,大大节省了人力,提高了作业效率,并且有效保护了跳接光纤,免受外力损坏,增长了跳接光纤的使用寿命。Beneficial effects of the utility model: the utility model is simple in structure, strong in practicability, easy to operate, and assists the jumper optical fiber to pass through the protective tube, which greatly saves manpower, improves operation efficiency, and effectively protects the jumper optical fiber from external forces damage, which increases the service life of the jumper fiber.

附图说明:Description of drawings:

图1为本实用新型的正视图;Fig. 1 is the front view of the utility model;

图2为本实用新型使用时结构示意图。Fig. 2 is a structural schematic diagram of the utility model when in use.

其中,1.把手,2.底座,3.磁铁,4.钢球,5.跳接光纤,6.护管,7.牵引线。Among them, 1. Handle, 2. Base, 3. Magnet, 4. Steel ball, 5. Jumper optical fiber, 6. Protective tube, 7. Pull wire.

具体实施方式Detailed ways

下面结合附图与实施例对本实用新型作进一步说明。Below in conjunction with accompanying drawing and embodiment the utility model is further described.

如图1所示,磁力式跳接光纤贯穿护管辅助工具,包括底座2,底座2上部设有把手1;底座2下部开有圆弧形凹槽;圆弧形凹槽与磁铁3固定连接,所述磁铁3下部设有可分离的钢球4;所述钢球4上设有通孔,所述通孔上连接有牵引线7。底座2和磁铁3的圆弧形半径大于护管6的半径。As shown in Figure 1, the magnetic jumper optical fiber penetration protective tube auxiliary tool includes a base 2, the upper part of the base 2 is provided with a handle 1; the lower part of the base 2 has an arc-shaped groove; the arc-shaped groove is fixedly connected with the magnet 3 , The lower part of the magnet 3 is provided with a detachable steel ball 4; the steel ball 4 is provided with a through hole, and a pulling wire 7 is connected to the through hole. The arc-shaped radius of the base 2 and the magnet 3 is greater than the radius of the protective tube 6 .

如图2所示,在使用本实用新型时,牵引线7末端捆扎跳接光纤5的头部,另一端固定在钢球4的通孔处,钢球4放入护管6中,将底座2卡在护管外部,磁铁3会吸引钢球4,握住把手1将钢球4沿着护管6向前拉拽,直至钢球4穿过护管6,牵引线7的长度大于护管6的长度,用手拉动牵引线7,待牵引线绷直后将跳接光纤5头部放入护管6中,再次拉动牵引线7,直至跳接光纤5完全贯穿护管6,解下钢球4上的牵引线7。As shown in Figure 2, when using the utility model, the head of the jumper optical fiber 5 is bound at the end of the pulling wire 7, and the other end is fixed at the through hole of the steel ball 4, and the steel ball 4 is put into the protective tube 6, and the base 2 is stuck outside the protective tube, the magnet 3 will attract the steel ball 4, hold the handle 1 and pull the steel ball 4 forward along the protective tube 6 until the steel ball 4 passes through the protective tube 6, the length of the pulling line 7 is longer than the protective tube the length of the tube 6, pull the traction wire 7 by hand, put the jumper fiber 5 head into the protective tube 6 after the traction line is straightened, and pull the traction line 7 again until the jumper fiber 5 completely penetrates the protective tube 6. The traction line 7 on the lower steel ball 4.

上述虽然结合附图对本实用新型的具体实施方式进行了描述,但并非对本实用新型保护范围的限制,所属领域技术人员应该明白,在本实用新型的技术方案的基础上,本领域技术人员不需要付出创造性劳动即可做出的各种修改或变形仍在本实用新型的保护范围以内。Although the specific implementation of the utility model has been described above in conjunction with the accompanying drawings, it does not limit the protection scope of the utility model. Those skilled in the art should understand that on the basis of the technical solution of the utility model, those skilled in the art do not need to Various modifications or deformations that can be made with creative efforts are still within the protection scope of the present utility model.

Claims (3)

1. magnetic-type jumper connection optical fiber runs through pillar aid, it is characterized in that, comprises base; Described base top is provided with handle, and base bottom has circular groove; Circular groove is fixedly connected with magnet, and described magnet bottom is provided with separable steel ball; Described steel ball is provided with through hole, and described through hole is connected with draught line.
2. magnetic-type jumper connection optical fiber runs through pillar aid as claimed in claim 1, it is characterized in that, the radius of described base and magnet circular arc is more than or equal to the radius of pillar.
3. magnetic-type jumper connection optical fiber runs through pillar aid as claimed in claim 1, it is characterized in that, the length of described draught line is greater than the length of pillar.
CN201420635296.XU 2014-10-29 2014-10-29 Auxiliary tool for magnetic jumper optical fiber penetration protection tube Expired - Fee Related CN204101789U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420635296.XU CN204101789U (en) 2014-10-29 2014-10-29 Auxiliary tool for magnetic jumper optical fiber penetration protection tube

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420635296.XU CN204101789U (en) 2014-10-29 2014-10-29 Auxiliary tool for magnetic jumper optical fiber penetration protection tube

Publications (1)

Publication Number Publication Date
CN204101789U true CN204101789U (en) 2015-01-14

Family

ID=52270206

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420635296.XU Expired - Fee Related CN204101789U (en) 2014-10-29 2014-10-29 Auxiliary tool for magnetic jumper optical fiber penetration protection tube

Country Status (1)

Country Link
CN (1) CN204101789U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105842811A (en) * 2016-05-25 2016-08-10 中国科学院力学研究所 Method and apparatus for long-distance insertion of fiber into capillary tube
CN106154470A (en) * 2016-08-31 2016-11-23 安徽赛福电子有限公司 A kind of fibre-optical splice magnetic force pipe lining device
CN114019613A (en) * 2021-12-02 2022-02-08 湖南玖芯光电科技有限公司 Multi-core optical fiber pipe penetrating process

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105842811A (en) * 2016-05-25 2016-08-10 中国科学院力学研究所 Method and apparatus for long-distance insertion of fiber into capillary tube
CN106154470A (en) * 2016-08-31 2016-11-23 安徽赛福电子有限公司 A kind of fibre-optical splice magnetic force pipe lining device
CN114019613A (en) * 2021-12-02 2022-02-08 湖南玖芯光电科技有限公司 Multi-core optical fiber pipe penetrating process

Similar Documents

Publication Publication Date Title
CN102290647A (en) Earth wire clip for transformer substation
CN204243624U (en) Turning wire dispenser
CN201429653Y (en) Complete set of tower grounding resistance test tools
CN203296451U (en) Pole straightening device
CN204577993U (en) Cable drawing head
CN203312700U (en) Tension tower wire end LF-type yoke plate fixing clamp
CN207067476U (en) A kind of identification cable protection sleeve pipe
CN108331433A (en) A kind of electric pole pole centralizing device and its application method
CN203288999U (en) Special device for operation of grounding pin of power grounding wire
CN201393012Y (en) R pin removal tool
CN204532204U (en) A kind of moveable platen hangnail drags for lance
CN203813326U (en) Wire bending machine
CN202586164U (en) Head clamp of concrete-pole cross arm
CN203356272U (en) Roving frame flyer and spindle blade straightening tool
CN204847631U (en) Swift formula earth connection kinking ware
CN204436307U (en) A kind of hangnail drags for lance
CN203635568U (en) Device for dredging cable duct
CN208056777U (en) A kind of electric pole pole centralizing device
CN202424027U (en) Building wire pulling device
CN205863781U (en) A kind of transmission line of electricity balance line device
CN205791243U (en) Stringing booster is removed when distribution line removes stringing
CN203486660U (en) Bundled wire squaring device
CN205791247U (en) A kind of high-voltage line paying-off implement
CN205294510U (en) Novel multi -functional earth connection winding frame
CN204271525U (en) Cable rolls off the production line fixing plate pulling device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150114

Termination date: 20161029