CN204079316U - A kind of harmless circular steel tube concrete post tower crane attachment anchor ear device - Google Patents

A kind of harmless circular steel tube concrete post tower crane attachment anchor ear device Download PDF

Info

Publication number
CN204079316U
CN204079316U CN201420496096.0U CN201420496096U CN204079316U CN 204079316 U CN204079316 U CN 204079316U CN 201420496096 U CN201420496096 U CN 201420496096U CN 204079316 U CN204079316 U CN 204079316U
Authority
CN
China
Prior art keywords
attachment
tower crane
circular steel
destructive
hoop
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420496096.0U
Other languages
Chinese (zh)
Inventor
李庆达
曾令锐
罗在娥
方大为
徐佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN201420496096.0U priority Critical patent/CN204079316U/en
Application granted granted Critical
Publication of CN204079316U publication Critical patent/CN204079316U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Jib Cranes (AREA)

Abstract

本实用新型公开了一种无损圆形钢管混凝土柱塔吊附着抱箍装置,包括塔吊附着杆(1)和附着装置(2),其特征是:所述附着装置(2)通过螺栓(7)拼接成抱箍;所述附着装置(2)和外框架圆形钢管柱(4)上固定有连接耳板(5);所述附着装置(2)上还设有附着板(6)和加劲板(8)。所述无损圆形钢管混凝土柱塔吊附着抱箍装置,可大大降低塔吊附着的施工难度,加快附着的施工进度,节约了工期,减少人工费用,且该附着装置安拆方便,可周转使用。极大的降低了施工风险和施工成本,为项目带来了很大的经济效益。本装置适用于塔吊需附着于圆形钢管柱上的工程。

The utility model discloses a non-destructive circular steel pipe concrete column tower crane attachment hoop device, which comprises a tower crane attachment rod (1) and an attachment device (2), and is characterized in that: the attachment device (2) is spliced by bolts (7) into a hoop; the attachment device (2) and the outer frame circular steel pipe column (4) are fixed with a connecting ear plate (5); the attachment device (2) is also provided with an attachment plate (6) and a stiffening plate (8). The non-destructive circular steel tube concrete column tower crane attachment hoop device can greatly reduce the construction difficulty of tower crane attachment, speed up the construction progress of attachment, save the construction period and reduce labor costs, and the attachment device is easy to install and disassemble, and can be used repeatedly. It greatly reduces the construction risk and construction cost, and brings great economic benefits to the project. This device is suitable for projects where the tower crane needs to be attached to the circular steel pipe column.

Description

一种无损圆形钢管混凝土柱塔吊附着抱箍装置A non-destructive circular steel tube concrete column tower crane attachment hoop device

技术领域technical field

本实用新型涉及一种建筑塔吊,尤其涉及一种无损圆形钢管混凝土柱塔吊附着抱箍装置,属于建筑施工领域。The utility model relates to a building tower crane, in particular to a hoop attachment device for a non-destructive circular steel pipe concrete column tower crane, which belongs to the field of building construction.

背景技术Background technique

随着建筑业的发展,高层建筑越来越多,其中多数建筑结构形式是内框筒为钢筋混凝土核心筒,外部框架为钢结构、劲性结构或钢筋混凝土结构形式。出于建筑本身使用功能的考虑,钢筋混凝土核心筒内框筒的使用功能多为各类管井、机房、楼梯和电梯间,钢结构、劲性结构或钢筋混凝土结构外部框架的使用功能多为办公房间。为追求办公的大空间,外部框架的外边缘距内部核心筒的距离较大,大部分在15m以上。With the development of the construction industry, there are more and more high-rise buildings, most of which are built with a reinforced concrete core tube as the inner frame tube and a steel structure, rigid structure or reinforced concrete structure as the external frame. Considering the use function of the building itself, the use function of the inner frame of the reinforced concrete core tube is mostly various tube wells, machine rooms, stairs and elevator rooms, and the use function of the outer frame of the steel structure, stiff structure or reinforced concrete structure is mostly office Room. In order to pursue a large office space, the distance between the outer edge of the outer frame and the inner core tube is relatively large, most of which are more than 15m.

由于塔吊主要用于材料吊运和结构构件的吊装,为方便安装、使用、顶升和拆除,多数高层建筑的塔吊均位于外部框架外,这使得塔吊距钢筋混凝土核心筒的距离较远,传统的塔吊附着于钢筋混凝土核心筒上的做法需要加长塔吊附着杆件,不利于附着杆件受力,且附着杆件会阻碍材料的吊运,给塔吊的安全使用带来隐患。故将塔吊附着于外框架钢管柱上是最理想的方法,其附着节点的设计成为一大难题。Because tower cranes are mainly used for material lifting and structural component hoisting, in order to facilitate installation, use, jacking and dismantling, most tower cranes of high-rise buildings are located outside the external frame, which makes the distance between the tower crane and the reinforced concrete core tube relatively long, traditional The method of attaching the tower crane to the reinforced concrete core tube needs to lengthen the attachment rod of the tower crane, which is not conducive to the force of the attachment rod, and the attachment rod will hinder the lifting of materials, which brings hidden dangers to the safe use of the tower crane. Therefore, it is the most ideal method to attach the tower crane to the steel pipe column of the outer frame, and the design of its attachment node becomes a big problem.

实用新型内容Utility model content

本实用新型所要解决的问题是提供一种建筑塔吊,尤其提供一种无损圆形钢管混凝土柱塔吊附着抱箍装置,克服了上述传统高层建筑塔吊安装于外框架外,附着难度较大的问题。The problem to be solved by the utility model is to provide a construction tower crane, especially to provide a non-destructive circular steel tube concrete column tower crane attachment hoop device, which overcomes the above-mentioned problem that the traditional high-rise building tower crane is installed outside the outer frame and is difficult to attach.

本实用新型所要解决的技术问题是通过以下方法来实现的:The technical problem to be solved by the utility model is achieved by the following methods:

一种无损圆形钢管混凝土柱塔吊附着抱箍装置,包括塔吊附着杆和附着装置,所述附着装置通过螺栓拼接成抱箍;所述附着装置和外框架圆形钢管柱上固定有连接耳板,防止抱箍在外框架圆形钢管柱上转动,给塔吊附着杆件受力带来不利影响;所述附着装置上还设有附着板和加劲板。A non-destructive circular steel pipe concrete column tower crane attachment hoop device, comprising a tower crane attachment rod and an attachment device, the attachment device is spliced into a hoop through bolts; the attachment device and the outer frame circular steel pipe column are fixed with connecting lugs , to prevent the hoop from rotating on the circular steel pipe column of the outer frame, which will adversely affect the stress on the attachment rod of the tower crane; the attachment device is also provided with an attachment plate and a stiffening plate.

所述塔吊附着杆连接于所述附着装置上,并且上下由2块附着板固定。The tower crane attachment rod is connected to the attachment device, and is fixed up and down by two attachment plates.

所述上附着板上和下附着板下分别固定有加劲板,目的是使附着更加牢固。Stiffening plates are respectively fixed under the upper attachment plate and the lower attachment plate to make the attachment more firm.

所述耳板为焊接的5块耳板。The ear plates are 5 welded ear plates.

所述附着装置设于外框架圆形钢管柱外。The attachment device is arranged outside the circular steel pipe column of the outer frame.

所述附着装置通过塔吊附着杆与塔吊相连。The attachment device is connected with the tower crane through the tower crane attachment rod.

所述螺栓为高强螺栓。The bolts are high-strength bolts.

所述所述附着板在附着装置上有3种不同的连接方式。The attachment plate has three different connection modes on the attachment device.

本实用新型采用上述技术方案具有以下有益效果:The utility model adopts the above-mentioned technical scheme and has the following beneficial effects:

所述无损圆形钢管混凝土柱塔吊附着抱箍装置,可大大降低塔吊附着的施工难度,加快附着的施工进度,节约了工期,减少人工费用,且该附着装置安拆方便,可周转使用。极大的降低了施工风险和施工成本,为项目带来了很大的经济效益。本装置适用于塔吊需附着于圆形钢管柱上的工程。The non-destructive circular steel tube concrete column tower crane attachment hoop device can greatly reduce the construction difficulty of tower crane attachment, speed up the construction progress of attachment, save the construction period, reduce labor costs, and the attachment device is easy to install and disassemble, and can be used repeatedly. It greatly reduces the construction risk and construction cost, and brings great economic benefits to the project. This device is suitable for projects where the tower crane needs to be attached to the circular steel pipe column.

附图内容Attached content

图1-1为本实用新型附着装置一种正面结构侧视图Figure 1-1 is a side view of the front structure of the attachment device of the present invention

图1-2为图1-1的俯视图Figure 1-2 is a top view of Figure 1-1

图1-3为图1-1的正视图Figure 1-3 is the front view of Figure 1-1

图2-1为本实用新型附着装置反面结构侧视图Figure 2-1 is a side view of the reverse structure of the attachment device of the present invention

图2-2为图2-1的俯视图Figure 2-2 is a top view of Figure 2-1

图3-1为本实用新型附着装置另一种正面结构侧视图Figure 3-1 is a side view of another front structure of the attachment device of the present invention

图3-2为图3-1的俯视图Figure 3-2 is a top view of Figure 3-1

图3-3为图3-1的正视图Figure 3-3 is the front view of Figure 3-1

图4为耳板大样图Figure 4 is a large sample of the ear plate

图5为图1-3附着板示意图Figure 5 is a schematic diagram of the attachment plate in Figure 1-3

图6为图3-3附着板示意图Figure 6 is a schematic diagram of the attachment plate in Figure 3-3

图7为本实用新型整体结构示意图Figure 7 is a schematic diagram of the overall structure of the utility model

图中,1-塔吊附着杆,2-附着装置,3-插销,4-外框架圆形钢管柱,5-耳板,6-附着板,7-螺栓,8-加劲板。In the figure, 1-tower crane attachment rod, 2-attachment device, 3-bolt, 4-outer frame circular steel pipe column, 5-ear plate, 6-attachment plate, 7-bolt, 8-stiffening plate.

具体实施方式Detailed ways

如图1-1、图1-2、、图1-3、图2-1、图2-2、图3-1、图3-2、图3-3、图4、图5、图6、图7所示的一种无损圆形钢管混凝土柱塔吊附着抱箍装置,包括塔吊附着杆1,附着装置2,插销3,外框架圆形钢管柱4,耳板5,附着板6,螺栓7,加劲板8。Figure 1-1, Figure 1-2, Figure 1-3, Figure 2-1, Figure 2-2, Figure 3-1, Figure 3-2, Figure 3-3, Figure 4, Figure 5, Figure 6 , a non-destructive circular steel pipe concrete column tower crane attachment hoop device shown in Figure 7, including tower crane attachment rod 1, attachment device 2, latch 3, outer frame circular steel pipe column 4, lug plate 5, attachment plate 6, bolts 7. Stiffening plate 8.

在实际安装中,塔吊附着需要3根塔吊附着杆1与外框架圆形钢管柱4连接,其中两根塔吊附着杆1附着于同一根外框架圆形钢管柱4上,另一根塔吊附着杆1附着于另一根框架圆形钢管柱4上。该附着装置2需要在附着板6上开3个孔用于和附着杆件连接,一个附着板6上开2个孔,另外一个附着板6上开1个孔。所述附着装置2是由两个半圆拼接而成的,如图1-1为一半的正视图,1-2为俯视图,图1-1和图1-2均为附着板6为单孔的,是半圆的正面;图3-1为一半的正视图,3-2为俯视图,图3-1和图3-2均为附着板6为双孔的,也是半圆的正面;图2-1为另一半的正视图,2-2为另一半的俯视图,此图表示的为半圆的反面。该部分和附着板6上孔的数量无关,也就是说是通用的。In actual installation, the tower crane attachment requires three tower crane attachment rods 1 to connect with the outer frame circular steel pipe column 4, two of the tower crane attachment rods 1 are attached to the same outer frame circular steel pipe column 4, and the other tower crane attachment rod 1 is attached to another frame circular steel pipe column 4. The attachment device 2 needs to open 3 holes on the attachment plate 6 for connecting with the attachment rod, 2 holes are opened on one attachment plate 6 , and 1 hole is opened on the other attachment plate 6 . The attachment device 2 is spliced by two semicircles, as shown in Fig. 1-1 is a half front view, 1-2 is a top view, Fig. 1-1 and Fig. 1-2 both have a single hole for the attachment plate 6 , is the front of the semicircle; Figure 3-1 is a half front view, 3-2 is a top view, both Figure 3-1 and Figure 3-2 are double-hole attachment plate 6, which is also a semicircle front; Figure 2-1 It is the front view of the other half, and 2-2 is the top view of the other half, and what this figure represents is the opposite side of the semicircle. This part is independent of the number of holes on the attachment plate 6, that is to say universal.

本工程由于1#塔吊和3#塔吊所在位置均距离核心筒较远,约30m,附着在核心筒上难以实现安全附着且附着难度大,为此,选择了在距离塔吊相对距离近的所述外框架圆形钢管柱4,但考虑附着对外框架圆形钢管柱4及钢框架受力的影响,将普通附着于平面直墙上的附着装置2进行了改进创新,采用所述高强螺栓7将所述附着装置2拼接成抱箍的形式,为防止附着装置2转动,每一个附着装置2加焊5块耳板5,所述耳板5一部分焊接于外框架圆形钢管柱4上,另一部分焊接于附着装置2上。最后将塔吊附着杆1与所述附着装置2连接固定,有效避免了在钢管柱身上的焊接和后期拆卸时的切割,达到无损附着的效果。In this project, since the 1# tower crane and the 3# tower crane are located far away from the core tube, about 30m, it is difficult to achieve safe attachment to the core tube and the attachment is difficult. The circular steel pipe column 4 of the outer frame, but considering the influence of the force attached to the circular steel pipe column 4 of the outer frame and the steel frame, the attachment device 2 attached to the plane straight wall is improved and innovated, and the high-strength bolt 7 is used to The attachment device 2 is spliced into the form of a hoop. In order to prevent the attachment device 2 from rotating, each attachment device 2 is welded with 5 ear plates 5, and a part of the ear plate 5 is welded on the circular steel pipe column 4 of the outer frame. A part is welded on the attachment device 2 . Finally, the tower crane attachment rod 1 is connected and fixed with the attachment device 2, which effectively avoids welding on the steel pipe column and cutting during later disassembly, and achieves the effect of non-destructive attachment.

本工程塔吊附着处钢管柱直径为1200mm,塔吊距附着点的距离约12.0m,最大附着杆长度为13.65m。根据塔吊使用说明书,塔吊在各种工况下所述附着装置2的受力状态分析,附着用杆件最大受力约61.3t,采用ETABS及PKPM分别进行建模及计算,最终取两者计算最大值进行分析,按附着装置加工图加工该附着装置能够满足受力要求,对已经施工完成的钢管混凝土柱和钢梁的稳定性亦不会造成影响。The diameter of the steel pipe column at the attachment point of the tower crane in this project is 1200mm, the distance between the tower crane and the attachment point is about 12.0m, and the maximum attachment rod length is 13.65m. According to the instruction manual of the tower crane, the analysis of the force state of the attachment device 2 under various working conditions of the tower crane shows that the maximum force of the attachment rod is about 61.3t. ETABS and PKPM are used for modeling and calculation respectively, and the two are finally used for calculation. The maximum value is analyzed, and the attachment device can be processed according to the processing drawing of the attachment device to meet the force requirements, and it will not affect the stability of the completed CFST columns and steel beams.

经现场实施,该附着装置在本工程1#塔吊和3#塔吊上成功应用,经检测受力及塔吊使用过程中位移检测,采用该附着装置后的塔吊完全满足使用规范。After on-site implementation, the attachment device has been successfully applied to the 1# tower crane and the 3# tower crane in this project. After testing the force and the displacement detection during the use of the tower crane, the tower crane after using the attachment device fully meets the use specifications.

应当注意的是,以上所述的实施例,只是本实用新型所选的具体实施方式的一种,而并非对实施方式的限定。对于本领域的技术人员来说,在上述说明的基础上还可以做出其它不同形式的变动。由此引申出的显而易见的变化和替换都应包含在本实用新型的保护范围内。It should be noted that the above-mentioned embodiments are only one of the selected specific implementation modes of the present utility model, rather than limiting the implementation modes. For those skilled in the art, other changes in different forms can also be made on the basis of the above description. The obvious changes and substitutions derived therefrom shall be included in the protection scope of the present utility model.

Claims (8)

1.一种无损圆形钢管混凝土柱塔吊附着抱箍装置,包括塔吊附着杆(1)和附着装置(2),其特征是:所述附着装置(2)通过螺栓(7)拼接成抱箍;所述附着装置(2)和外框架圆形钢管柱(4)上固定有连接耳板(5);所述附着装置(2)上下还设有附着板(6)和加劲板(8)。1. A non-destructive circular steel tube concrete column tower crane attachment hoop device, comprising a tower crane attachment rod (1) and an attachment device (2), characterized in that: the attachment device (2) is spliced into a hoop by bolts (7) ; The attachment device (2) and the outer frame circular steel pipe column (4) are fixed with a connecting ear plate (5); the attachment device (2) is also provided with an attachment plate (6) and a stiffening plate (8) up and down . 2.根据权利要求1所述的无损圆形钢管混凝土柱塔吊附着抱箍装置,其特征是:所述塔吊附着杆(1)连接于所述附着装置(2)上,并且上下由2块附着板(6)固定。2. The non-destructive circular steel tube concrete column tower crane attachment hoop device according to claim 1, characterized in that: the tower crane attachment rod (1) is connected to the attachment device (2), and the upper and lower parts are attached by two pieces The plate (6) is fixed. 3.根据权利要求1所述的无损圆形钢管混凝土柱塔吊附着抱箍装置,其特征是:所述上附着板(6)上和下附着板(6)下分别固定有加劲板(8)。3. The non-destructive circular steel tube concrete column tower crane attachment hoop device according to claim 1, characterized in that: the upper attachment plate (6) and the lower attachment plate (6) are respectively fixed with stiffening plates (8) . 4.根据权利要求1所述的无损圆形钢管混凝土柱塔吊附着抱箍装置,其特征是:所述耳板(5)为焊接的5块耳板。4. The non-destructive circular steel tube concrete column tower crane attachment hoop device according to claim 1, characterized in that: the lugs (5) are 5 welded lugs. 5.根据权利要求1所述的无损圆形钢管混凝土柱塔吊附着抱箍装置,其特征是:所述附着装置(2)设于外框架圆形钢管柱(4)外。5. The non-destructive circular steel pipe concrete column tower crane attachment hoop device according to claim 1, characterized in that: the attachment device (2) is arranged outside the outer frame circular steel pipe column (4). 6.根据权利要求1所述的无损圆形钢管混凝土柱塔吊附着抱箍装置,其特征是:所述附着装置(2)通过塔吊附着杆(1)与塔吊相连。6. The attachment hoop device for the tower crane of the non-destructive round concrete-filled steel tube column according to claim 1, characterized in that: the attachment device (2) is connected to the tower crane through the tower crane attachment rod (1). 7.根据权利要求1所述的无损圆形钢管混凝土柱塔吊附着抱箍装置,其特征是:所述螺栓(7)为高强螺栓。7. The non-destructive circular concrete-filled steel tube tower crane attachment hoop device according to claim 1, characterized in that: the bolts (7) are high-strength bolts. 8.根据权利要求1所述的无损圆形钢管混凝土柱塔吊附着抱箍装置,其特征是:所述附着板(6)在附着装置(2)上有3种不同的连接方式。8. The attachment hoop device of the non-destructive circular steel pipe concrete column tower crane according to claim 1, characterized in that: the attachment plate (6) has three different connection modes on the attachment device (2).
CN201420496096.0U 2014-08-29 2014-08-29 A kind of harmless circular steel tube concrete post tower crane attachment anchor ear device Expired - Lifetime CN204079316U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420496096.0U CN204079316U (en) 2014-08-29 2014-08-29 A kind of harmless circular steel tube concrete post tower crane attachment anchor ear device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420496096.0U CN204079316U (en) 2014-08-29 2014-08-29 A kind of harmless circular steel tube concrete post tower crane attachment anchor ear device

Publications (1)

Publication Number Publication Date
CN204079316U true CN204079316U (en) 2015-01-07

Family

ID=52172054

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420496096.0U Expired - Lifetime CN204079316U (en) 2014-08-29 2014-08-29 A kind of harmless circular steel tube concrete post tower crane attachment anchor ear device

Country Status (1)

Country Link
CN (1) CN204079316U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105752864A (en) * 2016-04-14 2016-07-13 成都市第二建筑工程公司 Tower crane attachment joint and construction method thereof
CN110606439A (en) * 2019-10-17 2019-12-24 中铁建工集团有限公司 A small swing arm type electric hoist suitable for transferring materials between floors in the reverse method
CN111483928A (en) * 2020-04-08 2020-08-04 中天建设集团有限公司 Attachment connecting structure between tower crane and steel pipe column and installation method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105752864A (en) * 2016-04-14 2016-07-13 成都市第二建筑工程公司 Tower crane attachment joint and construction method thereof
CN105752864B (en) * 2016-04-14 2017-11-03 成都建筑工程集团总公司 Derrick crane adheres to node and its construction method
CN110606439A (en) * 2019-10-17 2019-12-24 中铁建工集团有限公司 A small swing arm type electric hoist suitable for transferring materials between floors in the reverse method
CN111483928A (en) * 2020-04-08 2020-08-04 中天建设集团有限公司 Attachment connecting structure between tower crane and steel pipe column and installation method

Similar Documents

Publication Publication Date Title
CN102733487B (en) Inner sleeve cylinder T-shaped bolt long circular hole splicing node for square steel tube and construction method for inner sleeve cylinder T-shaped bolt long circular hole splicing node
CN204899180U (en) Steel construction jar body aerial working platform simply sets up device
CN203808484U (en) Integrated cantilevered and attached external scaffolding
CN206903022U (en) A kind of steel bar truss floor support plate
CN204079316U (en) A kind of harmless circular steel tube concrete post tower crane attachment anchor ear device
CN102767282B (en) Prefabricated high formwork construction method for cantilever beam of oversized special-shaped conversion layer
CN209066848U (en) A kind of external hanging type hanging basket holder device
CN204983173U (en) Steel construction beam -column connection node
CN204608825U (en) A kind of three-chip type stone bolt locating rack
CN204343642U (en) Builder's jack corner support frame
CN204551753U (en) Concrete-filled square thin-walled steel tube columns and girder steel assembling type node structure
CN204199667U (en) Detachable builder's jack corner tripod
CN106639042A (en) Dry type connected concrete shear wall and dry type wall connecting method
CN104164889B (en) Demountable tower crane foundation
CN202544138U (en) Opening connecting node of concrete-filled steel tubular frame column and reinforced concrete frame beam
CN211775988U (en) A kind of high-altitude protection device for steel structure high-rise tower
CN205701894U (en) A kind of large-diameter pipeline supports
CN209293510U (en) A water turbine maintenance platform
CN203924362U (en) External strengthening ring type steel beam column node structure
CN103882840B (en) A kind of surge shaft Cast-in-place concrete assembling falsework and mounting method thereof
CN208235587U (en) A kind of large-span deep foundation pit underground power house rack assembling construction platform
CN204551755U (en) A kind of Staggered-truss System post and truss hinged joint
CN204753815U (en) Simple and easy assembly quality of assembled precast concrete post
CN205116854U (en) Coal scuttle is portable platform for aggregate erection
CN212053696U (en) A steel beam wall high-altitude welding safety protection operation platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20150107

CX01 Expiry of patent term