CN204067610U - Power transmission lines overhauling ground wire articulated device - Google Patents
Power transmission lines overhauling ground wire articulated device Download PDFInfo
- Publication number
- CN204067610U CN204067610U CN201420497028.6U CN201420497028U CN204067610U CN 204067610 U CN204067610 U CN 204067610U CN 201420497028 U CN201420497028 U CN 201420497028U CN 204067610 U CN204067610 U CN 204067610U
- Authority
- CN
- China
- Prior art keywords
- casing
- clamp
- ground wire
- connecting plate
- insulating rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Electric Cable Installation (AREA)
Abstract
一种电力安装工具输电线路检修地线挂接器,包括线夹(1),其特点是:所述线夹(1)上安装一个接头(2),接头(2)有一片连板(3),连板(3)下面与线夹(1)相连接,连板(3)上面设有套管(5),套管(5)的中上部管壁设有豁口(7),管壁一侧设有侧口(6),侧口(6)延伸到套管(5)中部,且与套管(5)壁上的豁口(7)相连通,接头(2)配有一支细长的绝缘杆(8),绝缘杆(8)前端有一段与套管(5)相配合的插杆(9),插杆(9)一侧有一个凸柱(10)。使用时,绝缘杆的插杆插入套管,凸柱经侧口转到豁口内即可锁定线夹,再推送绝缘杆即可把线夹与地线接合。其有益效果是:不用抛掷线夹即可安装地线,时间缩短70—80%,且结构简单、造价低廉、便于携带,可望成为检修作业必备工具。
An electric power installation tool transmission line maintenance ground wire coupler, including a wire clip (1), characterized in that: a connector (2) is installed on the wire clip (1), and the connector (2) has a connecting plate (3 ), the lower part of the connecting plate (3) is connected with the clamp (1), the upper part of the connecting plate (3) is provided with a casing (5), and the middle and upper part of the casing (5) is provided with a notch (7), and the pipe wall One side is provided with a side port (6), which extends to the middle of the casing (5) and communicates with the notch (7) on the wall of the casing (5), and the joint (2) is equipped with a slender Insulating rod (8), insulating rod (8) front end has a section of inserting rod (9) that matches with sleeve pipe (5), and inserting rod (9) one side has a boss (10). When in use, the inserting rod of the insulating rod is inserted into the casing, the protruding column is turned into the notch through the side opening to lock the clamp, and then the insulating rod is pushed to join the clamp with the ground wire. The beneficial effect is that the ground wire can be installed without throwing the wire clamp, the time is shortened by 70-80%, and the structure is simple, the cost is low, and the utility model is easy to carry, so it is expected to become an essential tool for maintenance work.
Description
技术领域technical field
本实用新型涉及一种电力安装工具,即一种输电线路检修地线挂接器。The utility model relates to an electric power installation tool, namely a ground wire coupler for maintenance of power transmission lines.
背景技术Background technique
输电线路停电检修需要抛挂220kV接地线,操作人员要把接线的线夹夹持在地线上。由于地线在转角耐张塔外角侧,与杆塔还有一段距离,操作人员要把线夹抛出,挂到地线上。由于地线容易摆动,超过3级风力时,塔上作业人员很难一次抛挂成功,每相导线抛挂地线的时间需要15分钟左右,三相导线抛挂地线的时间需要45分钟左右,降低了工作效率,增加了停电时间。The 220kV grounding wire needs to be dropped for power outage inspection and maintenance of the transmission line, and the operator should clamp the wiring clamp to the grounding wire. Since the ground wire is on the outer corner side of the corner strain tower, and there is still a distance from the pole tower, the operator should throw out the clamp and hang it on the ground wire. Because the ground wire is easy to swing, when the wind force exceeds level 3, it is difficult for the operators on the tower to successfully hang it at one time. It takes about 15 minutes for each phase wire to hang the ground wire, and it takes about 45 minutes for the three-phase wire to hang the ground wire. , reducing work efficiency and increasing power outage time.
发明内容Contents of the invention
本实用新型的目的是提供一种不用抛掷,即可把线夹准确的夹持在地线上,操作简单,节省时间,停电时间大幅缩短的输电线路检修地线挂接器。The purpose of the utility model is to provide a ground wire coupler for maintenance of power transmission lines that can accurately clamp the wire clip on the ground wire without throwing, is easy to operate, saves time, and greatly shortens the power failure time.
上述目的是由以下技术方案实现的:研制一种输电线路检修地线挂接器,包括与地线相配合的线夹,其特点是:所述线夹上安装一个接头,接头有一片连板,连板下面与线夹相连接,连板上面设有套管,套管的中上部管壁设有豁口,管壁一侧设有侧口,侧口延伸到套管中部,且与套管壁上的豁口相连通,接头配有一支细长的绝缘杆,绝缘杆前端有一段与套管相配合的插杆,插杆一侧有一个可在侧口内滑动且可转入豁口的凸柱。使用时,绝缘杆前端的插杆插入套管,凸柱经侧口转到豁口内即可锁定线夹,再推送绝缘杆即可把线夹与地线强行接合。The above purpose is achieved by the following technical solutions: develop a power transmission line maintenance ground wire coupler, including a clamp that matches the ground wire, and is characterized in that a joint is installed on the clamp, and the joint has a connecting plate , the lower part of the connecting plate is connected with the clamp, the upper part of the connecting plate is provided with a casing, the middle and upper part of the casing is provided with a gap, one side of the pipe wall is provided with a side port, the side port extends to the middle of the casing, and is connected with the casing The gaps on the wall are connected, and the joint is equipped with a slender insulating rod. The front end of the insulating rod has a section of insertion rod that matches the sleeve. One side of the insertion rod has a protrusion that can slide in the side opening and turn into the gap. . When in use, the insertion rod at the front end of the insulating rod is inserted into the casing, and the protruding column is turned into the gap through the side opening to lock the clamp, and then the insulating rod is pushed to forcibly connect the clamp to the ground wire.
本实用新型的有益效果是:检修人员不用抛掷线夹,即可完成地线安装作业,操作时间缩短70—80%,且具有结构简单、造价低廉、便于携带等优点,可望成为检修作业必备工具。The beneficial effect of the utility model is that the maintenance personnel can complete the installation of the ground wire without throwing the wire clamp, the operation time is shortened by 70-80%, and it has the advantages of simple structure, low cost and easy to carry, and is expected to become a must for maintenance work. equipment.
附图说明Description of drawings
图1是一种实施例的主视图;Fig. 1 is the front view of a kind of embodiment;
图2是这种实施例的左视图;Fig. 2 is the left side view of this embodiment;
图3是这种实施例的俯视图;Figure 3 is a top view of such an embodiment;
图4是这种实施例的部件连板的主视图;Fig. 4 is the front view of the component connecting plate of this embodiment;
图5是这种实施例的部件连板的左视图;Fig. 5 is the left side view of the component connecting plate of this embodiment;
图6是这种实施例的部件连板的俯视图;Fig. 6 is the top view of the component connecting plate of this embodiment;
图7是这种实施例的部件绝缘杆的主视图;Fig. 7 is the front view of the component insulating rod of this embodiment;
图8是这种实施例的使用状态示意图。Fig. 8 is a schematic diagram of the use state of this embodiment.
图中可见:线夹1,接头2,连板3,螺栓4,套管5,侧口6,豁口7,绝缘杆8,插杆9,凸柱10,地线11。It can be seen in the figure: clamp 1, joint 2, connecting plate 3, bolt 4, bushing 5, side opening 6, notch 7, insulating rod 8, insertion rod 9, boss 10, ground wire 11.
具体实施方式Detailed ways
本实用新型总的构思是通过一支绝缘杆把线夹安装到地线上。下面仅例举一个实施例:The general design of the utility model is to install the clamp on the ground by an insulating rod. Only an example is given below:
实施例:如图1、图2、图3所示,这种输电线路检修地线挂接器,是在线夹1上安装一个接头2,结合图4图5图6可见,接头2的主体是一片连板3,连板3下面与线夹1的一支夹柄通过螺栓4相连接,连板3上面设有套管5,套管5中部的管壁正中设有豁口7,管壁一侧设有侧口6,侧口6延伸到套管5中部向上弯折且与套管壁上的豁口7相连通。结合图7可见一支细长的绝缘杆8,绝缘杆8前端有一段与套管5相配合的插杆9,插杆9一侧有一个凸柱10。使用时,绝缘杆前端的插杆9插入套管5,凸柱经侧口6转到豁口7内即可把线夹1固定在绝缘杆8的前端。检修人员攀登到杆塔适当位置,即可推送绝缘杆把线夹1夹在地线11上。随后再扭动绝缘杆8,抽下绝缘杆即可。作业完毕还可以再插接绝缘杆,拉下线夹。Embodiment: As shown in Fig. 1, Fig. 2 and Fig. 3, this kind of power transmission line overhaul ground wire coupler is to install a joint 2 on the line clip 1. It can be seen from Fig. 4, Fig. 5 and Fig. 6 that the main body of the joint 2 is A connecting plate 3, the lower part of the connecting plate 3 is connected with a clamp handle of the wire clamp 1 through a bolt 4, a casing 5 is arranged on the connecting plate 3, a notch 7 is arranged in the middle of the pipe wall in the middle of the casing 5, and a gap 7 is arranged in the middle of the pipe wall. A side port 6 is provided on the side, and the side port 6 extends to the middle of the casing 5 and is bent upwards and communicates with the notch 7 on the wall of the casing. A slender insulating rod 8 can be seen in conjunction with FIG. 7 . The front end of the insulating rod 8 has a section of inserting rod 9 matched with the bushing 5 , and one side of the inserting rod 9 has a protruding post 10 . During use, the inserting rod 9 at the front end of the insulating rod is inserted into the casing 5, and the protruding column is transferred to the gap 7 through the side opening 6 to fix the clamp 1 on the front end of the insulating rod 8. The maintenance personnel climb to the proper position of the pole tower, and then the insulating rod can be pushed to clamp the line clamp 1 on the ground wire 11. Twist insulating rod 8 again subsequently, pull out insulating rod and get final product. After the operation is completed, the insulation rod can be plugged again, and the wire clamp can be pulled down.
据实验测定,采用这种装置安装一相地线仅用3—5分钟,比原来减少了10—12分钟。而且操作的难度及操作者的紧张程度明显降低,不再为反复投掷线夹而费神,劳动强度大幅减轻、作业效率显著提高,停电时间大幅缩短,受到实验区用户的好评。According to the test, it takes only 3-5 minutes to install a phase ground wire with this device, which is 10-12 minutes less than the original one. Moreover, the difficulty of operation and the tension of the operator are significantly reduced, and the labor intensity is greatly reduced, the work efficiency is significantly improved, and the power outage time is greatly shortened, which is well received by users in the experimental area.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420497028.6U CN204067610U (en) | 2014-08-29 | 2014-08-29 | Power transmission lines overhauling ground wire articulated device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420497028.6U CN204067610U (en) | 2014-08-29 | 2014-08-29 | Power transmission lines overhauling ground wire articulated device |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204067610U true CN204067610U (en) | 2014-12-31 |
Family
ID=52209060
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201420497028.6U Expired - Lifetime CN204067610U (en) | 2014-08-29 | 2014-08-29 | Power transmission lines overhauling ground wire articulated device |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204067610U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104241885A (en) * | 2014-08-29 | 2014-12-24 | 国家电网公司 | Power transmission line maintenance ground wire hanging device |
-
2014
- 2014-08-29 CN CN201420497028.6U patent/CN204067610U/en not_active Expired - Lifetime
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104241885A (en) * | 2014-08-29 | 2014-12-24 | 国家电网公司 | Power transmission line maintenance ground wire hanging device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN202050150U (en) | Insulating operating lever for hanging ground wire | |
| CN204230457U (en) | Universal connector earth wire operation rod | |
| CN202340114U (en) | Plug type prefabricated cable terminal | |
| CN206195235U (en) | Tail end current potential shifts stick | |
| CN203895869U (en) | Substation secondary cable special threading tool | |
| CN207650315U (en) | Distribution line ground fault detection device | |
| CN202384516U (en) | Secondary voltage drop live-line wiring device | |
| CN201417901Y (en) | Multifunctional cable maintenance grounding wire | |
| CN204067610U (en) | Power transmission lines overhauling ground wire articulated device | |
| CN203707661U (en) | Touch type automatic wire hanging device | |
| CN201060780Y (en) | Insulation operating arm with electroscope | |
| CN103036191A (en) | Cable terminal for European-style branch box and ring main unit | |
| CN104241885A (en) | Power transmission line maintenance ground wire hanging device | |
| CN202075335U (en) | Electricity examining device | |
| CN203166131U (en) | Hook of ground wire | |
| CN203521642U (en) | Novel wire grounding device | |
| CN206834353U (en) | Ultra-high-tension power transmission line assembly and disassembly ground wire servicing unit | |
| CN202422882U (en) | Wind deflection preventing diagonal insulator hardware | |
| CN202034104U (en) | Tube type bus | |
| CN106505419A (en) | A kind of switch cubicle of the quick secondary connection of energy | |
| CN205376793U (en) | Distribution lines overhauls ground wire earthing terminal | |
| CN203932626U (en) | a ground wire | |
| CN204011797U (en) | A kind of earthing wire clip | |
| CN203800341U (en) | Terminal row test connecting head | |
| CN204497660U (en) | A kind of multi-functional pin pulling clamp of insulator R type pin |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CX01 | Expiry of patent term | ||
| CX01 | Expiry of patent term |
Granted publication date: 20141231 |