CN203989971U - Preliminary sedimentation concentrates reclamation set - Google Patents

Preliminary sedimentation concentrates reclamation set Download PDF

Info

Publication number
CN203989971U
CN203989971U CN201420424580.2U CN201420424580U CN203989971U CN 203989971 U CN203989971 U CN 203989971U CN 201420424580 U CN201420424580 U CN 201420424580U CN 203989971 U CN203989971 U CN 203989971U
Authority
CN
China
Prior art keywords
pond
water
concentrated
effluent trough
preliminary sedimentation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420424580.2U
Other languages
Chinese (zh)
Inventor
许嘉炯
徐俊
张增荣
高志强
尤嬿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201420424580.2U priority Critical patent/CN203989971U/en
Application granted granted Critical
Publication of CN203989971U publication Critical patent/CN203989971U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses the concentrated reclamation set of a kind of preliminary sedimentation, comprise pond body and slush pump room, it is characterized in that arranging in the body of pond the center water distribution bucket with distributing hole, described center water distribution bucket is connected with the water inlet pipe that is arranged on body bottom, pond, the weir plate that the upper end-face edge of pond body is provided with effluent trough and matches with effluent trough, effluent trough is connected with post precipitation pond by outlet pipe, in the body of pond, concentrated mud scraper is set, body bottom, pond arranges mud-removing bucket, body bottom, pond sets out sandpipe and is connected with mud-removing bucket, slush pump room arranges water pump, described water pump is by connecting line and go out sandpipe, water inlet pipe is connected with discharge pipeline.The advantage of this technique is to adapt to different former regimen conditions and service requirement, former water preliminary sedimentation processing and spoil disposal water concentration technique are combined, the seasonal high turbidity of simultaneous adaptation and at ordinary times low turbidity operating mode, efficiently utilize structures disposal ability to save floor occupying area, realize the combination of water-purifying process and production wastewater treatment technique.

Description

Preliminary sedimentation concentrates reclamation set
Technical field
The utility model is a kind of pretreatment unit relating in water supply and sewage work, specifically a kind of pretreating device of taking high turbidity Yuan Shui waterworks that is applied to.For the former water of high turbidity, former water preliminary sedimentation and mud concentration are combined, realize the former water of high turbidity and alleviate the burden of post precipitation technique by preliminary sedimentation procedure, and realize the new equipment of the concentrated and spoil disposal water reuse function of producing mud simultaneously.
Background technology
In the water inlet of city tap-water factory, contain plurality of impurities, earth surface water source is subject to the factors vary such as flow and water temperature at the change of season, occur that turbidity significantly raises in short-term, water factory's handling process cannot be tackled, produce large volume low-concentration factory effluent simultaneously and discharge technological process as producing accessory substance, surrounding enviroment are produced to larger pressure, become environment and social concern that city tap-water factory must solve.
At present, generally before processing, conventional sedimentation and filtration adopt simple preliminary sedimentation procedure to deal with the seasonal high turbidity water quality who occurs in the waterworks of taking the former water of high turbidity, and contained mud impurity is often treated as pollution sources in factory effluent, by concentrated, natural mummification or mechanical dehydration, contained production mud in factory effluent is transported outward, to reduce the impact on environment with the form of solid body.The major defect of above-mentioned technology is after ultra, raw water of waterworks presents while continuing lower turbidity, preliminary sedimentation procedure cannot play a role in treatment process, and factory effluent drain time is generally comparatively concentrated, process structures floor space larger, operating cost is higher, and concentrated supernatant is the more difficult discharge standard that reaches often, has become the technical barrier of the former water treatment of seasonal high turbidity.
Utility model content
The purpose of this utility model is to provide the concentrated reclamation set of a kind of preliminary sedimentation, be suitable for the pretreatment new equipment under the former water condition of seasonal high turbidity, overcome the conventional art prejudice that water and mud are processed respectively, preliminary sedimentation processing, sludge concentration and dewatering and waste water recycling function are combined, reduce the influent load of sedimentation basin, in guaranteeing that treatment process effluent quality is up to standard, realize the concentrated function of part producing wastewater sludge.
To achieve these goals, the technical solution of the utility model is: a kind of preliminary sedimentation concentrates reclamation set, comprise pond body and slush pump room, it is characterized in that, in the body of pond, water dispensing apparatus is set, described water dispensing apparatus is connected with the water inlet pipe that is arranged on body bottom, pond, in the body of pond, be provided with discharging device, discharging device is connected with post precipitation pond by outlet pipe, in the body of pond, concentrated mud scraper is set, body bottom, pond arranges mud-removing bucket, body bottom, pond sets out sandpipe and is connected with mud-removing bucket, slush pump room arranges water pump, described water pump is by connecting line and go out sandpipe, water inlet pipe is connected with discharge pipeline.On unit fixed on water pump suction pipeline, manually-operated gate is installed, check-valves and manually-operated gate are installed on exit of pump pipeline, go out electrically operated valve is also installed on sandpipe, the inlet pipeline of water pump is by taking out sandpipe and going out sandpipe upstream and be connected, the outlet conduit of water pump by sediment outflow pipe with go out sandpipe downstream and be connected, the inlet pipeline of water pump is connected with water inlet pipe by extraction mud pipe, and the outlet conduit of water pump is also connected with discharge pipeline.Described water dispensing apparatus is the center water distribution bucket with distributing hole, described discharging device comprises and is arranged on the interior effluent trough of body upper end, pond inner side, the outer effluent trough that is arranged on outside, body upper end, pond and the weir plate matching with described interior effluent trough and outer effluent trough, between interior effluent trough and outer effluent trough, be provided with link slot, outer effluent trough is connected with outlet pipe.Pond body bottom sides is provided with evacuated tube.Water inlet pipe also arranges reuse water pipe and is connected with plant area's blowoff basin water side.In the concentrated reclamation set of preliminary sedimentation upper and lower, outdoor fire hydrant is set, going out on sandpipe the cleaning hose with check-valves and manually-operated gate is set, is used as in pond and pipeline cleaning measure.On the water inlet pipe of the concentrated reclamation set of preliminary sedimentation, establishing PAM adds a little.
The utility model concentrates sand setting pretreatment, mud with waste water recovery function and combines.At ordinary times when low turbidity operating mode raw water turbidity lower than 200NTU or silt content lower than 0.20 kg/m 3, former water can surmount the concentrated reclamation set of preliminary sedimentation and directly enter sedimentation basin processing; When raw water turbidity exceedes 200NTU or silt content at 0.20 ~ 3.5kg/m 3time, former water should first enter sedimentation basin processing after the concentrated reclamation set preliminary sedimentation of preliminary sedimentation again; When former water silt content exceedes 3.5kg/m 3time, former water should first be introduced into setting pot sand setting at dry point place, and water outlet enters sedimentation basin processing through the concentrated reclamation set of preliminary sedimentation again.The utility model has the advantage of and can adapt to different former regimen conditions and service requirement, former water preliminary sedimentation processing and spoil disposal water concentration technique are combined, the seasonal high turbidity of simultaneous adaptation and at ordinary times low turbidity operating mode, efficiently utilize structures disposal ability to save floor occupying area, realize the combination of water-purifying process and production wastewater treatment technique.
Brief description of the drawings
Fig. 1 is the utility model horizontal layout schematic diagram.
Fig. 2 is the profile of the utility model along A-A line in Fig. 1.
Fig. 3 is the profile of the utility model along B-B line in Fig. 1.
Fig. 4 is the adjustable perforation effluent trough of the utility model horizontal layout schematic diagram.
Fig. 5 is adjustable perforation effluent trough side arrangement schematic diagram.
Fig. 6 is the profile of adjustable perforation effluent trough along C-C line in Fig. 5.
Fig. 7 is the profile of adjustable perforation effluent trough along D-D line in Fig. 5.
The adjustable profile of tooth weir plate of Fig. 8 the utility model effluent trough is arranged schematic diagram.
Fig. 9 is the profile of tooth weir plate detail drawing of adjustable profile of tooth weir plate effluent trough.
Figure 10 is the weir plate pad detail drawing of adjustable profile of tooth weir plate effluent trough.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model will be further described.
The utility model is the concentrated reclamation set of a kind of preliminary sedimentation, at ordinary times when low turbidity operating mode raw water turbidity lower than 200NTU or silt content lower than 0.20 kg/m 3, former water can surmount the concentrated reclamation set of preliminary sedimentation and directly enter sedimentation basin processing; When raw water turbidity exceedes 200NTU or silt content at 0.20 ~ 3.5kg/m 3time, former water should first enter sedimentation basin processing after the concentrated reclamation set preliminary sedimentation of preliminary sedimentation again; When former water silt content exceedes 3.5kg/m 3time, former water should first be introduced into setting pot sand setting at dry point place, and water outlet enters sedimentation basin processing through the concentrated reclamation set of preliminary sedimentation again.
The utility model comprises that preliminary sedimentation concentrates reclamation set 1, slush pump room 2 and connecting line 3 three part compositions.The concentrated reclamation set 1 of preliminary sedimentation by pond body 4, concentrated mud scraper 5, mud-removing bucket 6, water inlet pipe 7, band distributing hole 29 center water distribution bucket 8, rectification bucket 9, interior effluent trough 10, outer effluent trough 11, weir plate 12, link slot 13, outlet pipe 14, go out sandpipe 15, blow-down pipe 16 and reuse water pipe 21 and form, interior effluent trough 10 is connected by link slot 13 with outer effluent trough 11; In slush pump room 2, establish the water pump 19 that extracts mud, on water pump 19 inlet pipelines, manually-operated gate 18 is installed, check-valves 20 and manually-operated gate 18 are installed on exit of pump pipeline; Slush pump room 2 water pump 19 inlet pipelines are connected by extraction mud pipe 22 with the concentrated reclamation set water inlet pipe 7 of preliminary sedimentation, and slush pump room 2 water pump 19 inlet pipelines are connected by taking out sandpipe 23 with the upstream that the concentrated reclamation set of preliminary sedimentation goes out sandpipe 15; The downstream that slush pump room 2 water pump 19 outlet conduits can go out sandpipe 15 with the concentrated reclamation set of preliminary sedimentation is connected by sediment outflow pipe 24, also can enter plant area's sewage sludge storage system by discharge pipeline 25.The water inlet pipe 7 of the concentrated reclamation set 1 of preliminary sedimentation, go out sandpipe 15, outlet pipe 14, blow-down pipe 16, extraction mud pipe 22, take out on sandpipe 23 and sediment outflow pipe 24 manually-operated gate 18 is all installed, go out electrically operated valve 17 is also installed on sandpipe 15; Preliminary sedimentation concentrates reclamation set water inlet pipe 7, goes out on sandpipe 15 and blow-down pipe 16 valve well 26 is set.Former water enters center water distribution bucket 8 by water inlet pipe 7 from body 4 bottoms, the concentrated reclamation set pond of preliminary sedimentation, again by distributing hole 29 and rectification bucket 9 water distributions, after preliminary sedimentation, water outlet enters interior effluent trough 10 and outer effluent trough 11 by weir plate 12, water outlet enters post precipitation pond by outlet pipe 14 after being pooled to outer effluent trough 11 by link slot 13 connections, in water, mud collects at mud-removing bucket 6 after concentrating by concentrated mud scraper 5, by going out the outer row of sandpipe 15.The concentrated reclamation set 1 of preliminary sedimentation is established the empty measure of blow-down pipe 16 as pond body overhaul of the equipments and clean and maintenance; Plant area's blowoff basin water outlet accesses the concentrated reclamation set water inlet pipe 7 of preliminary sedimentation by reuse water pipe 21.In slush pump room 2, establish the water pump 19 that extracts mud, can and go out sandpipe 15 at water inlet pipe 7 and stop up time, by extraction mud pipe 22 with take out sandpipe 23 and extract pipeline inner product mud and long-pending sand, can drain into out electrically operated valve 17 downstreams on sandpipe 15 by sediment outflow pipe 24, also can enter plant area's sewage sludge storage system by discharge pipeline 25.Arrange and rinse bolt 27 in the concentrated reclamation set of preliminary sedimentation upper and lower, going out on sandpipe 15 cleaning hose 28 with check-valves 20 and manually-operated gate 18 is set, be used as in pond and pipeline cleaning measure.On the water inlet pipe 7 of the concentrated reclamation set of preliminary sedimentation, establish PAM and add a little 30.
Wherein interior effluent trough and outer effluent trough use adjustable perforation effluent trough or adjustable profile of tooth weir plate effluent trough.
The structure of adjustable perforation effluent trough is as shown in Fig. 4 ~ 7, described adjustable effluent trough comprises perforation effluent trough 101, perforation effluent trough 101 bottoms arrange adjustable plate 104, adjustable plate 104 is connected with screed 105 by adjusting bolt 106, screed 105 is fixed on and supports beam column or bracket 103 tops, and perforation effluent trough 101 is also connected with support beam column or bracket 103 by fixing channel-section steel 102.Perforation effluent trough 101 is connected by connecting bolt 109 with fixing channel-section steel 102, and fixing channel-section steel 102 is fixed on and is supported on beam column or bracket 103 by set bolt 108, on fixing channel-section steel 102, offers the strip adjustment hole 118 matching with set bolt 108.Adjustable plate 104 is respectively arranged with the regulating nut 107 matching with adjusting bolt 106 up and down.Intercommunicating pore 110 is established in perforation effluent trough 101 bottoms, and inlet opening 111 and water-line target line 112 are established in side.Perforation effluent trough 101 is while regulating, first by the adjusting effluent trough 101 both sides adjusting bolt 106 up-down adjustment nuts 107 of boring a hole, the water-line target line 112 of effluent trough side overlapped with pool inner water bit line, then tightens set bolt 108, can complete whole adjustment process.
The structure of adjustable profile of tooth weir plate effluent trough is as shown in Fig. 8 ~ 10, described adjustable profile of tooth weir plate effluent trough comprises armored concrete effluent trough 113, armored concrete effluent trough 113 is provided with profile of tooth weir plate 114, profile of tooth weir plate 114 is connected with armored concrete effluent trough 113 by weir plate pad 115, and profile of tooth weir plate 114 is also connected with armored concrete effluent trough 113 by gripper shoe 116.Profile of tooth weir plate 114 is connected with armored concrete effluent trough 113 with weir plate pad 115 by set bolt 108; Gripper shoe 116 is connected with profile of tooth weir plate 114 by connecting bolt 109, on profile of tooth weir plate 114 and weir plate pad 115, is provided with strip adjustment hole 118, and water-line target line 112 is established in profile of tooth weir plate 114 sides.When profile of tooth weir plate 114 regulates, first regulate gripper shoe 116 and profile of tooth weir plate 114 relative positions that the water-line target line 112 of profile of tooth weir plate 114 sides is overlapped with pool inner water bit line by connecting bolt 109, then tighten set bolt 108, can complete whole adjustment process.
Wherein concentrated mud scraper, mud-removing bucket, center water distribution bucket, rectification bucket are prior art, no longer describe in detail.

Claims (9)

1. the concentrated reclamation set of preliminary sedimentation, comprise pond body and slush pump room, it is characterized in that, in the body of pond, water dispensing apparatus is set, described water dispensing apparatus is connected with the water inlet pipe that is arranged on body bottom, pond, in the body of pond, be provided with discharging device, discharging device is connected with post precipitation pond by outlet pipe, in the body of pond, concentrated mud scraper is set, body bottom, pond arranges mud-removing bucket, body bottom, pond sets out sandpipe and is connected with mud-removing bucket, slush pump room arranges water pump, described water pump by connecting line with go out sandpipe, water inlet pipe and discharge pipeline and be connected.
2. the concentrated reclamation set of preliminary sedimentation as claimed in claim 1, the inlet pipeline that it is characterized in that water pump is by taking out sandpipe and going out sandpipe upstream and be connected, the outlet conduit of water pump by sediment outflow pipe with go out sandpipe downstream and be connected, the inlet pipeline of water pump is connected with water inlet pipe by extraction mud pipe, and the outlet conduit of water pump is also connected with discharge pipeline.
3. the concentrated reclamation set of preliminary sedimentation as claimed in claim 1, is characterized in that described water dispensing apparatus is the center water distribution bucket with distributing hole.
4. the concentrated reclamation set of preliminary sedimentation as claimed in claim 1, it is characterized in that described discharging device comprises is arranged on the interior effluent trough of body upper end, pond inner side, the outer effluent trough that is arranged on outside, body upper end, pond and the weir plate matching with described interior effluent trough and outer effluent trough, between interior effluent trough and outer effluent trough, be provided with link slot, outer effluent trough is connected with outlet pipe.
5. the concentrated reclamation set of preliminary sedimentation as claimed in claim 1, is characterized in that pond body bottom sides is provided with evacuated tube.
6. the concentrated reclamation set of preliminary sedimentation as claimed in claim 1, is characterized in that water inlet pipe also arranges reuse water pipe and is connected with plant area's blowoff basin water side.
7. the concentrated reclamation set of preliminary sedimentation as claimed in claim 1, is characterized in that, in the concentrated reclamation set of preliminary sedimentation upper and lower, flushing bolt is set, and is going out the cleaning hose with check-valves and manually-operated gate is set on sandpipe.
8. the concentrated reclamation set of preliminary sedimentation as claimed in claim 1, is characterized in that on the water inlet pipe of the concentrated reclamation set of preliminary sedimentation, establishing PAM adds a little.
9. the concentrated reclamation set of preliminary sedimentation as claimed in claim 1, is characterized in that interior effluent trough and outer effluent trough use adjustable perforation effluent trough or adjustable profile of tooth weir plate effluent trough.
CN201420424580.2U 2014-07-30 2014-07-30 Preliminary sedimentation concentrates reclamation set Expired - Fee Related CN203989971U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420424580.2U CN203989971U (en) 2014-07-30 2014-07-30 Preliminary sedimentation concentrates reclamation set

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420424580.2U CN203989971U (en) 2014-07-30 2014-07-30 Preliminary sedimentation concentrates reclamation set

Publications (1)

Publication Number Publication Date
CN203989971U true CN203989971U (en) 2014-12-10

Family

ID=52030046

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420424580.2U Expired - Fee Related CN203989971U (en) 2014-07-30 2014-07-30 Preliminary sedimentation concentrates reclamation set

Country Status (1)

Country Link
CN (1) CN203989971U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104841170A (en) * 2015-05-12 2015-08-19 浙江天地环保工程有限公司 Hydroelectricity wastewater reuse system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104841170A (en) * 2015-05-12 2015-08-19 浙江天地环保工程有限公司 Hydroelectricity wastewater reuse system

Similar Documents

Publication Publication Date Title
CN101387119B (en) Large-scale factory roof rainwater collection, treatment and reuse system and method thereof
CN106592735A (en) Separate-zone rainwater flow, regulation and storage, and on-line treatment system with obvious initial rainwater feature under separate system and mixed flow system
CN101748913A (en) Automatic sewage disposal method of pool and sewage disposal system thereof
CN105899464B (en) System and method for treating water
CN203989971U (en) Preliminary sedimentation concentrates reclamation set
CN104973707B (en) A kind of seasonal high turbid original sub-block technique
CN101941774A (en) Micro-power dispersion type domestic sewage treatment process
CN203154885U (en) V-shaped sedimentation tank
CN103787550B (en) Sewage treatment systems
CN104128020B (en) Preliminary sedimentation concentrates reuse tank and treatment process thereof
CN106514846A (en) Novel pipe piece water maintenance pool
CN204198514U (en) A kind of desulfurization wastewater separation system
CN205442817U (en) Be fit for a domestic sewage purification system that town used
CN204058089U (en) Seasonal high turbid original sub-block device
CN106638889A (en) Un-obvious initial rain characteristic online fragment treatment discharge system under combined system or mixed system and control method of discharge system
CN205528247U (en) Field town domestic sewage purification system
CN205313316U (en) Adjusting device who is fit for treatment of domestic sewage's intelligent control
CN206220134U (en) A kind of Tailings Dam seeped water collection device
CN205874147U (en) Adjust prefabricated pump station of combination formula
CN103482753A (en) Pulse water distributor
CN205420013U (en) Contain sour kitchen wastewater processing apparatus
CN205313214U (en) Field town sewage treatment system that construction cost is low
CN204714651U (en) One is removed contamination and is shunted plant effluent treatment system
CN207091104U (en) Tower anaerobic pond sewage-treatment plant
RU86487U1 (en) WASTE DISTRIBUTION SYSTEM IN THE BIOLOGICAL CLEANING UNIT OF A WATER TREATMENT STATION

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141210