CN203982234U - Power equipment intelligent temperature and humidity control device - Google Patents

Power equipment intelligent temperature and humidity control device Download PDF

Info

Publication number
CN203982234U
CN203982234U CN201420315152.6U CN201420315152U CN203982234U CN 203982234 U CN203982234 U CN 203982234U CN 201420315152 U CN201420315152 U CN 201420315152U CN 203982234 U CN203982234 U CN 203982234U
Authority
CN
China
Prior art keywords
temperature
casing
humidity
control device
power equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420315152.6U
Other languages
Chinese (zh)
Inventor
高明华
马广俊
刘筠
杨秀晶
刘德秀
代永胜
冯永涛
陈燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Chemical Corp
Electric Power Corp of Sinopec Shengli Petroleum Administration Bureau
Original Assignee
China Petroleum and Chemical Corp
Electric Power Corp of Sinopec Shengli Petroleum Administration Bureau
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Chemical Corp, Electric Power Corp of Sinopec Shengli Petroleum Administration Bureau filed Critical China Petroleum and Chemical Corp
Priority to CN201420315152.6U priority Critical patent/CN203982234U/en
Application granted granted Critical
Publication of CN203982234U publication Critical patent/CN203982234U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The utility model relates to a kind of power equipment intelligent temperature and humidity control device.Its technical scheme is: comprise earth leakage circuit-breaker, three-phase ac contactor, GPRS wireless transmission terminal, line voltmeter, operating voltage table, temperature and humidity controller, hand control switch, relay indicating light, power light, casing, humiture collection device, described earth leakage circuit-breaker, three-phase ac contactor and GPRS wireless transmission terminal are arranged in casing, fixing temperature and humidity controller is installed on the outer casing inner wall of casing, hand control switch, on the outer wall of casing, fix humiture collection device, described temperature and humidity controller, after hand control switch parallel connection, be connected to Temperature and Humidity Control loading section.Beneficial effect is: loading section integrated design, reduced the space hold in transformer station, and control device is arranged in casing, and can ensure the working environment that it is good, strengthen its serviceable life.

Description

Power equipment intelligent temperature and humidity control device
Technical field
The utility model relates to a kind of power equipment temperature and humidity control device, particularly a kind of power equipment intelligent temperature and humidity control device.
Background technology
In electric system, in order to ensure that power equipment in transformer station can safe and stable operation, and long-life operation, must meet temperature, humidity in the scope requiring, current serviceability temperature meters etc. are measured temperature or are used simple instrument to measure humiture, then manually boot the air exhausting devices such as blower fan, in science and technology today with rapid changepl. never-ending changes and improvements, can not meet the needs of intelligent substation.Therefore, set up real-time temperature and humidity monitoring system, the humiture that regulates in real time pulpit and equipment room is the problem that needs at present solution.
Chinese patent literature number is 103513682A, patent name " humidity and temperature control equipment for a kind of transformer station ", comprise temperature detecting module, humidity detecting module, control module, data memory module, gauge tap, drying device, air-cooler, accumulator and solar panel, temperature detecting module is connected with control module, control module is connected with humidity detecting module, data memory module and gauge tap respectively, gauge tap is connected with drying device, air-cooler and accumulator respectively, and accumulator is connected with solar panel.Can keep automatically temperature and humidity in transformer station, extend the serviceable life of transformer station's internal electronic device.But the problem of its existence is: its loading section is placed separately, there is no integrated design, make the space in transformer station compacter.
Summary of the invention
The purpose of this utility model is exactly in view of the foregoing defects the prior art has, and a kind of power equipment intelligent temperature and humidity control device is provided.
Its technical scheme is: comprise earth leakage circuit-breaker, three-phase ac contactor, GPRS wireless transmission terminal, line voltmeter, operating voltage table, temperature and humidity controller, hand control switch, relay indicating light, power light, casing, humiture collection device, described earth leakage circuit-breaker, three-phase ac contactor and GPRS wireless transmission terminal are arranged in casing, fixing temperature and humidity controller is installed on the outer casing inner wall of casing, hand control switch, on the outer wall of casing, fix humiture collection device, described temperature and humidity controller, after hand control switch parallel connection, be connected to Temperature and Humidity Control loading section, described temperature and humidity controller connects line voltmeter, operating voltage table, relay indicating light and power light.
Above-mentioned Temperature and Humidity Control loading section comprises well heater, air-conditioning, blower fan, humidifier, is arranged on casing one side.
Above-mentioned GPRS wireless transmission terminal is arranged in casing, coordinates by wireless transmission with remote computer.
Above-mentioned humiture collection device adopts temperature sensor and humidity sensor, and is connected with temperature and humidity controller.
Above-mentioned temperature and humidity controller adopts single-chip microcomputer.
Above-mentioned well heater, air-conditioning, blower fan, humidifier are integrated, and be provided with well heater, blower fan and humidifier, and be connected with temperature and humidity controller respectively in a side of air-conditioning.
The beneficial effects of the utility model are: by button, temperature, humidity are carried out respectively to upper and lower limit setting and demonstration, thereby make instrument according to field condition, automatically start fan or well heater, actual temperature, the humidity of test environment are regulated automatically; And loading section integrated design, has reduced the space hold in transformer station, and control device is arranged in casing, can ensure the working environment that it is good, strengthened its serviceable life.
Brief description of the drawings
Accompanying drawing 1 is structural representation of the present utility model;
Accompanying drawing 2 is structural drawing of humiture loading section of the present utility model;
In upper figure: earth leakage circuit-breaker 1, three-phase ac contactor 2, GPRS wireless transmission terminal 3, line voltmeter 4, operating voltage table 5, temperature and humidity controller 6, hand control switch 7, relay indicating light 8, power light 9, casing 10, humiture collection device 11; Air-conditioning 12, blower fan 13, well heater 14, humidifier 15.
Embodiment
1-2 by reference to the accompanying drawings, the utility model will be further described:
The utility model comprises earth leakage circuit-breaker 1, three-phase ac contactor 2, GPRS wireless transmission terminal 3, line voltmeter 4, operating voltage table 5, temperature and humidity controller 6, hand control switch 7, relay indicating light 8, power light 9, casing 10, humiture collection device 11, described earth leakage circuit-breaker 1, three-phase ac contactor 2 and GPRS wireless transmission terminal 3 are arranged in casing 10, fixing temperature and humidity controller 6 is installed on the outer casing inner wall of casing 10, hand control switch 7, on the outer wall of casing 10, fix humiture collection device 11, described temperature and humidity controller 6, after hand control switch 7 parallel connections, be connected to Temperature and Humidity Control loading section, described temperature and humidity controller 6 connects line voltmeter 4, operating voltage table 5, relay indicating light 8 and power light 9.
Above-mentioned Temperature and Humidity Control loading section comprises well heater 14, air-conditioning 12, blower fan 13, humidifier 15, is arranged on casing 10 1 sides.Above-mentioned GPRS wireless transmission terminal 3 is arranged in casing 10, coordinates by wireless transmission with remote computer.Above-mentioned humiture collection device 11 adopts temperature sensor and humidity sensor, and is connected with temperature and humidity controller 6.Above-mentioned temperature and humidity controller 6 adopts single-chip microcomputer.Above-mentioned well heater 14, air-conditioning 12, blower fan 13, humidifier 15 are integrated, and are provided with well heater 14, blower fan 13 and humidifier 15 in a side of air-conditioning 12, and are connected with temperature and humidity controller 6 respectively.
This device is taking advanced single-chip microcomputer as control core, adopt Imported High-performance Temperature Humidity Sensor, can measure control to temperature, moisture signal simultaneously, and realize liquid crystal digital show, also can carry out respectively upper and lower limit setting and demonstration to temperature, humidity by button, thereby make device according to field condition, automatically start fan or well heater, actual temperature, the humidity of test environment are regulated automatically.Action instruction, by two normally opened contact outputs, really makes device realize intellectuality and more can adapt to field condition complicated and changeable, thereby reach the object of effective protection equipment.
Using method: Based Intelligent Control flow process: 1 earth leakage circuit-breaker that closes, 4 line voltmeters instructions operating voltage civil powers, 9 power lights are lighted, according to Rule of judgment:
1 indoor humidity-outdoor temperature > AH1 relay closes action (startup)
2 indoor humidities-outdoor temperature < AL1 relay disconnects action (stopping)
After signal that Temperature Humidity Sensor detects is processed, send into single-chip microcomputer and carry out logic judgement, 6 temperature and humidity controller relay tip closures in the time meeting first condition, connect 2 three-phase ac contactors, the instruction of operating voltage table, working power lamp is lighted, and fan power is connected blower fan and started working, otherwise same.Backstage Master Station Software can show that the data that two on-the-spot real time humitures gather are to analyze by GPRS wireless network.

Claims (6)

1. a power equipment intelligent temperature and humidity control device, it is characterized in that: comprise earth leakage circuit-breaker (1), three-phase ac contactor (2), GPRS wireless transmission terminal (3), line voltmeter (4), operating voltage table (5), temperature and humidity controller (6), hand control switch (7), relay indicating light (8), power light (9), casing (10), humiture collection device (11), described earth leakage circuit-breaker (1), three-phase ac contactor (2) and GPRS wireless transmission terminal (3) are arranged in casing (10), fixing temperature and humidity controller (6) is installed on the outer casing inner wall of casing (10), hand control switch (7), on the outer wall of casing (10), fix humiture collection device (11), described temperature and humidity controller (6), after hand control switch (7) parallel connection, be connected to Temperature and Humidity Control loading section, described temperature and humidity controller (6) connects line voltmeter (4), operating voltage table (5), relay indicating light (8) and power light (9).
2. power equipment intelligent temperature and humidity control device according to claim 1, is characterized in that: described Temperature and Humidity Control loading section comprises well heater (14), air-conditioning (12), blower fan (13), humidifier (15), is arranged on casing (10) one sides.
3. power equipment intelligent temperature and humidity control device according to claim 1, is characterized in that: described GPRS wireless transmission terminal (3) is arranged in casing (10), coordinates by wireless transmission with remote computer.
4. power equipment intelligent temperature and humidity control device according to claim 1, is characterized in that: described humiture collection device (11) adopts temperature sensor and humidity sensor, and is connected with temperature and humidity controller (6).
5. power equipment intelligent temperature and humidity control device according to claim 1, is characterized in that: described temperature and humidity controller (6) adopts single-chip microcomputer.
6. power equipment intelligent temperature and humidity control device according to claim 1, it is characterized in that: described well heater (14), air-conditioning (12), blower fan (13), humidifier (15) are integrated, be provided with well heater (14), blower fan (13) and humidifier (15) in a side of air-conditioning (12), and be connected with temperature and humidity controller (6) respectively.
CN201420315152.6U 2014-06-13 2014-06-13 Power equipment intelligent temperature and humidity control device Expired - Fee Related CN203982234U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420315152.6U CN203982234U (en) 2014-06-13 2014-06-13 Power equipment intelligent temperature and humidity control device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420315152.6U CN203982234U (en) 2014-06-13 2014-06-13 Power equipment intelligent temperature and humidity control device

Publications (1)

Publication Number Publication Date
CN203982234U true CN203982234U (en) 2014-12-03

Family

ID=51979667

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420315152.6U Expired - Fee Related CN203982234U (en) 2014-06-13 2014-06-13 Power equipment intelligent temperature and humidity control device

Country Status (1)

Country Link
CN (1) CN203982234U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105356335A (en) * 2015-11-24 2016-02-24 国家电网公司 Intelligent electric power control box
CN106768024A (en) * 2016-12-01 2017-05-31 国家电网公司 A kind of real-time acquisition device installed on power equipment in transit
CN108107847A (en) * 2017-12-22 2018-06-01 大连鑫鑫创世科技发展有限公司 A multi-axis beam processing control device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105356335A (en) * 2015-11-24 2016-02-24 国家电网公司 Intelligent electric power control box
CN106768024A (en) * 2016-12-01 2017-05-31 国家电网公司 A kind of real-time acquisition device installed on power equipment in transit
CN108107847A (en) * 2017-12-22 2018-06-01 大连鑫鑫创世科技发展有限公司 A multi-axis beam processing control device

Similar Documents

Publication Publication Date Title
CN101968459B (en) Detection method of internal faults of switch cabinet
CN107144787A (en) The generator insulating detection means and detection method of a kind of permanent-magnetic wind driven generator
CN204705690U (en) One is visited one house after another investigation equipment
CN205861815U (en) The detecting system of Simple Low Voltage power distribution network leakage current
CN203982234U (en) Power equipment intelligent temperature and humidity control device
CN211905259U (en) SF6 gas monitoring device and monitoring system
CN204538522U (en) A kind of ring main unit of ventilation rainproof heat radiation
CN103869197B (en) Electric automobile charge and discharge device double-fed can test system
CN110221140A (en) Distribution power automation terminal intelligent detecting instrument
CN203396430U (en) Portable monitoring instrument for ground source heat pump
CN208384025U (en) A kind of test macro of direct-current charging post
CN204155435U (en) A kind of wireless temperature acquisition system
CN204924455U (en) Photovoltaic power supply temperature transmitter based on WIA -PA communication
CN105158651B (en) A kind of intelligent partial discharge on-Line Monitor Device based on Wearable
CN107817713A (en) A kind of automatic electric device and control system for detecting humidity
CN104932592A (en) Outdoor terminal box with solar dehumidifying and cooling functions
CN203164350U (en) Intelligent distribution instrument
CN203982237U (en) The anti-condensation supervising device of transformer station
CN205210734U (en) A environmental control unit for communication cabinet
CN204008899U (en) A kind of interchangeability proving installation of power information acquisition terminal communication interface
CN204575116U (en) A kind of humiture trend inspection tour system being applied to current conversion station or transformer station
CN205451456U (en) Real -time temperature measured module of transformer substation based on wifi wireless communication
CN202938923U (en) Electric reactor wireless temperature measuring device
CN203931131U (en) Distributed apparatus abnormal alarm system
CN203984446U (en) The interchangeability testing apparatus of a kind of power information acquisition terminal local communication unit

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141203

Termination date: 20150613

EXPY Termination of patent right or utility model