CN203924077U - A kind of constructing structure for the greening of wound steep rocky slope - Google Patents

A kind of constructing structure for the greening of wound steep rocky slope Download PDF

Info

Publication number
CN203924077U
CN203924077U CN201420103940.9U CN201420103940U CN203924077U CN 203924077 U CN203924077 U CN 203924077U CN 201420103940 U CN201420103940 U CN 201420103940U CN 203924077 U CN203924077 U CN 203924077U
Authority
CN
China
Prior art keywords
baffle plate
slope
concrete baffle
spacer screen
main muscle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420103940.9U
Other languages
Chinese (zh)
Inventor
朱兆华
徐国钢
庞志研
陈晓蓉
曹华英
董沁
周庆
刘杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHENZHEN MASTER ECOLOGICAL ENVIRONMENT Co Ltd
Original Assignee
SHENZHEN MASTER ECOLOGICAL ENVIRONMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHENZHEN MASTER ECOLOGICAL ENVIRONMENT Co Ltd filed Critical SHENZHEN MASTER ECOLOGICAL ENVIRONMENT Co Ltd
Priority to CN201420103940.9U priority Critical patent/CN203924077U/en
Application granted granted Critical
Publication of CN203924077U publication Critical patent/CN203924077U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model discloses a kind of constructing structure for the greening of wound steep rocky slope, be applicable to steep anxious rock side slope spray sowing technique, it comprises the fixing domatic spacer screen of anchor pole on slope; Trend perpendicular to slope above domatic spacer screen is provided with at least one concrete baffle plate; At concrete baffle plate, be embedded with main muscle and horizontal stiffener longitudinally, the bottom of main muscle is exposed concrete baffle plate and is embedded in rock mass; On concrete baffle plate, repave and hang 2 times of one deck mesh to the galvanized wire table net of spacer screen, embed plank, batten or bamboo chip that prior binding becomes " X " type simultaneously, table net with tied silk colligation on the anchor pole of fixing spacer screen.It is domatic that this structure makes galvanized wire spacer screen paste more closely on the one hand, can effectively prevent on the other hand domatic base material landing and wash away, more effectively improve the construction effect of the existing technique of sowing grass seeds by duster, to realize fast indigenous plant in protecting slope ecology, recover to have great importance.

Description

A kind of constructing structure for the greening of wound steep rocky slope
Technical field
The utility model relates to a kind of greening side slope constructing structure, especially relates to a kind of permanent afforesting constructing structure that is applied to the exposed rock abrupt slope vegetation recovery of wound and ecological protection.
Background technology
In recent years, the quick propelling along with Chinese society rapid development of economy and urbanization process, can't bear the heavy load to the consumption of the destruction of ecological environment and resource, has restricted the sustainable development of national economy.Modern construction has caused a large amount of wound bare side slopings, and surface environment has been caused to serious destruction.Wound bare side sloping source mainly contains three approach: the one, and transport development, as speedway, urban and rural highway net, railway (comprising high-speed railway); The 2nd, cut into a mountain for quarrying and exploitation of mineral resources; The 3rd, the engineering construction of real estate and other construction project.Wound bare side sloping is particularly serious to the destruction of ecology, view and urban safety, becomes the technical barrier of current ecological management and the focus of social concerns.
Improvement for massif wound bare side sloping; conventionally adopted simple engineering protection in the past; as grout or dry plate stone, spray anchor protection etc.; these engineering measures have produced certain protection effect; but there is the drawbacks such as power consumption is large, cost is high, landscape effect is poor, unsustainable, be difficult in the target that fundamentally realizes ecological management and environmental protection.Based on this, people, in the practice of slope treatment, start to pay attention to utilizing the ecological Gu Po effect of plant.
China, from late nineteen nineties in last century from external introduction spraying and sowing plant growth correlation technique, popularizes in an all-round way in the whole nation at present.During the last ten years, adopt this technology, a large amount of road slope of China, quarry, real estate side slope etc. have been carried out to restoration of the ecosystem.But, in engineering practice process, due to the domatic excavation of part not science, unreasonable and construction period the reason such as excessive rainfall, there is a series of problems that are difficult to overcome and drawback.Be mainly manifested in: (1) is domatic too precipitous, slope ratio is greater than 1: 0.75, and the common technology of sowing grass seeds by duster is difficult to firmly adhere to the base material of sowing grass seeds by duster; (2) domatic excavation out-of-flatness, the common linked network of sowing grass seeds by duster is difficult to be adjacent to domatic; (3) south China area is longer rainy season, and instantaneous rainfall is generally larger, for rainy season construction, has certain difficulty, washes away serious; (4) the domatic base material that adheres to is easily degenerated, and is unfavorable for long-term stability and the succession of vegetation, thereby causes the further degeneration of vegetation.
For this reason, the utility model provides a kind of constructing structure for the greening of wound steep rocky slope, with the problems that overcome and avoid conventional spraying and sowing plant growth to exist.
Summary of the invention
The purpose of this utility model is to provide a kind of constructing structure for the greening of wound steep rocky slope, with strengthening, plant the fixing of raw base material and adhere to, more effectively prevent that construction period rainwater is to domatic washing away, reduce engineering construction and management cost, thus many disadvantages and the drawback of avoiding conventional spraying and sowing plant growth technology to exist.
For achieving the above object, the utility model adopts following technical scheme: a kind of constructing structure for the greening of wound steep rocky slope, comprises that slope consists of rock mass with the fixing galvanized wire spacer screen on the slope of anchor pole.Trend perpendicular to slope above domatic galvanized wire spacer screen is provided with at least one concrete baffle plate; At concrete baffle plate, be embedded with main muscle and horizontal stiffener longitudinally, the bottom of main muscle is exposed concrete baffle plate and is embedded in Slope Rock Mass; On concrete baffle plate, repave and hang 2 times of one deck mesh to the galvanized wire table net of spacer screen, to cover web, be embedded in plank, batten or the bamboo chip that prior binding becomes " X " type simultaneously, galvanized wire table net with tied silk colligation on the anchor pole of fixing spacer screen.
Described concrete baffle plate and slope angle are between 45 ° to 90 °, and concrete barrier width is 10~15cm, and thickness is 3~6cm.
When described galvanized wire spacer screen top is provided with a plurality of concrete baffle plate, the spacing between concrete baffle plate is 1.0~2.0m.
In described concrete baffle plate, every 30~50cm, be provided with a main muscle, stiffener is to be connected to the row of two between main muscle hand-drawn wire.Main muscle is that diameter is the screw-thread steel of 12~14mm, and stiffener diameter is 5~8mm; Main muscle length is 30~35cm, and wherein 20cm is positioned at rock mass, and 10~15cm is positioned at concrete baffle plate.
After above-mentioned constructing structure has been mated formation, adopt the mode of alien earth sparging to plant life.
The beneficial effect of doing is like this, arrange on the slope galvanized wire spacer screen and fixing with anchor pole after, concrete baffle plate is directly set on the slope, the main muscle of concrete baffle plate is anchored in rock mass, can form the effect that compresses galvanized wire spacer screen, spacer screen can play the attached spraying and sowing plant growth base material of pocket, fixedly plant, firm domatic effect; The space that concrete baffle plate forms can be filled and be planted raw base material and prevent base material landing, and " X " type plank, batten or the bamboo chip of table net and embedding can improve and stop and plant that raw base material comes off and fixing plant, firmly domatic; Plank, batten or bamboo chip can also supplement and plant raw base material organic content and mineral nutrient after rotting.Reinforcing bar, concrete, galvanized wire mesh that this constructing structure adopts have permanent, durability, can effectively prevent that domatic base material is by rain drop erosion, improve the construction effect of the existing technique of sowing grass seeds by duster, especially for slope, compare vegetation recovery and the ecological protection at more than 1: 0.75 steep rocky slope, effect is especially remarkable.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the utility model is described further:
Fig. 1 is sectional view of the present utility model.
Fig. 2 is the perspective view of the utility model embodiment concrete baffle plate.
The specific embodiment
As shown in Figure 2, a kind of constructing structure for the greening of wound steep rocky slope, comprises the slope (6) with rock mass (3), and on slope, (6) are upper is fixed with galvanized wire spacer screen (1) with anchor pole.Trend in galvanized wire spacer screen (1) top perpendicular to slope (6) is provided with at least one concrete baffle plate (2); At concrete baffle plate (2), be embedded with main muscle (4) and horizontal stiffener (5) longitudinally, the bottom of main muscle (4) is exposed concrete baffle plate (2) and is embedded in rock mass (3).
Concrete baffle plate (2) is (6) and galvanized wire spacer screen (1) upper on slope directly, can form the effect that compresses galvanized wire spacer screen (1).Described concrete baffle plate (2) and slope (6) angle, between 45 ° to 90 °, form according to the domatic situation of reality the angle that can adhere to base material.
In the present embodiment, concrete baffle plate (2) is highly 10cm, and thickness is 5cm, and length is not limit, and can along slope, infinitely extend by (6) isohypse, increases the area of anti-skidding antiscour.In described concrete baffle plate (2), every 40cm, be provided with a main muscle (4), stiffener (5) is for being connected to the row of two between main muscle (4) hand-drawn wire.The screw-thread steel that main muscle (4) is 14mm for diameter, stiffener (5) diameter is 6mm; Main muscle (4) length is 30cm, and wherein 20cm is anchored in rock mass (3), and 10cm is cast in concrete baffle plate (2).
As shown in Figure 2, larger slope (6) are upper in the present embodiment, cast multiple tracks concrete baffle plate (2), and the spacing between concrete baffle plate (2) is 1.0m, not only having met base material adheres to and the needs of plant growth but also cost-saving as much as possible.
As shown in Figure 1, on concrete baffle plate (2), repave and hang 2 times of one deck mesh to the galvanized wire table net (8) of spacer screen, simultaneously to table net (8), be embedded in plank, batten or the bamboo chip (7) that prior binding becomes " X " type, galvanized wire table net (8) with tied silk colligation on the anchor pole of fixing spacer screen (1).
The utility model is a kind of domatic construction auxiliary process based on spray sowing technique---the anti-skidding constructing structure of permanent base material, it is generally applied to the abrupt slope that slope ratio is greater than 1: 0.75, application slope body generally belongs to weak weathering or non-efflorescing cementitious rock matter slope body, and during its construction, technological process comprises: side slope cleaning, measure that unwrapping wire, paving hang that galvanized wire spacer screen, anchor pole are fixed, concreting baffle plate, embedding " X " type plank, batten or bamboo chip, paving hang galvanized wire table net, base material stirring, alien earth sparging, lid nonwoven, maintenance management.
Constructing structure described in the utility model, for precipitous rock side slope linked network spraying and sowing plant growth technique, is particluarly suitable for adopting in Used in Rainy Seasons of Southern Cities work progress, can effectively prevent domatic base material landing and wash away, and improves the construction effect of the existing technique of sowing grass seeds by duster.Overcome or avoided conventional spraying and sowing plant growth technique to exist planting that raw base material easily washes away, landing, nutrient are easily run off, the easy problem such as degeneration of vegetation, promotional value is high, has a extensive future.

Claims (4)

1. the constructing structure for wound steep rocky slope greening, comprise by anchor pole and be fixed on the galvanized wire spacer screen (1) on slope (6), it is characterized in that: the trend in galvanized wire spacer screen (1) top perpendicular to slope (6) is provided with at least one concrete baffle plate (2); At concrete baffle plate (2), be embedded with main muscle (4) and horizontal stiffener (5) longitudinally, the bottom of main muscle (4) is exposed concrete baffle plate (2) and is embedded in the rock mass (3) of slope (6); On concrete baffle plate (2), repave and hang 2 times of one deck mesh to the galvanized wire table net (8) of spacer screen, simultaneously to table net (8), be embedded in plank, batten or the bamboo chip (7) that prior binding becomes " X " type, galvanized wire table net (8) with tied silk colligation on the anchor pole of fixing spacer screen (1).
2. a kind of constructing structure for wound steep rocky slope greening according to claim 1, it is characterized in that: described concrete baffle plate (2) and slope (6) angle are between 45 ° to 90 °, concrete baffle plate (2) width 10~15cm, thickness 3~6cm.
3. a kind of constructing structure for wound steep rocky slope greening according to claim 1, it is characterized in that: in described concrete baffle plate (2), every 30~50cm, be provided with a main muscle (4), stiffener (5) is for being connected to the row of two between main muscle (4) hand-drawn wire.
4. a kind of constructing structure for wound steep rocky slope greening according to claim 3, is characterized in that: the screw-thread steel that main muscle (4) is 12~14mm for diameter, and stiffener (5) diameter is 5~8mm; Main muscle (4) length is 30~35cm, and wherein 20cm is positioned at rock mass (3), and 10~15cm is positioned at concrete baffle plate (2).
CN201420103940.9U 2014-03-07 2014-03-07 A kind of constructing structure for the greening of wound steep rocky slope Expired - Fee Related CN203924077U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420103940.9U CN203924077U (en) 2014-03-07 2014-03-07 A kind of constructing structure for the greening of wound steep rocky slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420103940.9U CN203924077U (en) 2014-03-07 2014-03-07 A kind of constructing structure for the greening of wound steep rocky slope

Publications (1)

Publication Number Publication Date
CN203924077U true CN203924077U (en) 2014-11-05

Family

ID=51819931

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420103940.9U Expired - Fee Related CN203924077U (en) 2014-03-07 2014-03-07 A kind of constructing structure for the greening of wound steep rocky slope

Country Status (1)

Country Link
CN (1) CN203924077U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105862887A (en) * 2016-04-18 2016-08-17 江西理工大学 Ecological slope protection structure for ion rare earth mine
CN109371993A (en) * 2018-11-30 2019-02-22 苏州金螳螂园林绿化景观有限公司 Mixed mud abrupt slope ecological afforestation collapse system
CN111820081A (en) * 2019-04-15 2020-10-27 中交路桥建设有限公司 Slope net hanging spray-seeding quick greening construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105862887A (en) * 2016-04-18 2016-08-17 江西理工大学 Ecological slope protection structure for ion rare earth mine
CN105862887B (en) * 2016-04-18 2017-12-15 江西理工大学 A kind of ion type rareearth mine ecological slope protection structure
CN109371993A (en) * 2018-11-30 2019-02-22 苏州金螳螂园林绿化景观有限公司 Mixed mud abrupt slope ecological afforestation collapse system
CN111820081A (en) * 2019-04-15 2020-10-27 中交路桥建设有限公司 Slope net hanging spray-seeding quick greening construction method

Similar Documents

Publication Publication Date Title
CN204590045U (en) A kind of rock side slope lattice ecological safeguard structure
CN201343730Y (en) Ecological protection structure for high rock slope
CN206736931U (en) Highway Lithological Slope liana ecological safeguard structure
CN205035813U (en) Ecological treatment system that softens in stereoplasm abrupt slope
CN108093729A (en) Side-slope greening and protection method
CN101560759A (en) Desert treatment technology
CN106638630A (en) Ecological greening device for side slope with flexible ceramsite plates, and greening method thereof
CN102337744A (en) Preparation and construction method of BSC (Bio-substrate concrete) biological matrix fine aggregate plant-growing concrete
CN203924077U (en) A kind of constructing structure for the greening of wound steep rocky slope
CN203840816U (en) Rock slope vegetation restoration structure
CN104294829A (en) Rock slope combined type protective structure and method
CN203320535U (en) Rock slope green protection structure
CN205591232U (en) Ecological compound green protective structure of rock matter side slope and curing means
CN202000359U (en) Geocell zoology cutting wall
CN204059376U (en) The slope protection greening structure of the steep exposed rock side slope of a kind of urgency
CN104947628B (en) Based on the ecotechnology having the solid bag of otolith cage
CN207295704U (en) A kind of ecology spray anchor protective slope structure
CN206873395U (en) A kind of ecological revetment dike
CN203514330U (en) Environment-friendly ecological reconstruction and restoration structure
CN202755371U (en) Plant protective structure of soil slope protection and slope rain water evacuation
CN207519313U (en) A kind of hillside fields revegetation ecologic structure
CN204418192U (en) Bayonet type grass planting grid
CN104695454A (en) Steep slope reinforcement and protection device and paving method thereof
CN203716136U (en) Stony desertification treatment structure
CN207987627U (en) Railway arid biogeographic zone subgrade engineering afforests safeguard structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141105