A kind of heat preservation ditch preformed groove construction equipment
Technical field
The utility model belongs to heat preservation ditch preformed groove technical field of construction in construction of tunnel, is specifically related to a kind of heat preservation ditch preformed groove construction equipment.
Background technology
Heat preservation ditch design is reserved vallecular cavity in position, medium position two side, ditch, prefabricated section is installed in this vallecular cavity and is made prefabricated section stretch out ditch sidewall, heat preservation ditch cover plate is installed on prefabricated section, and reserved vallecular cavity is taking a cover plate longitudinal length as intervals setting, and bilateral symmetry.Although this vallecular cavity size is less, if the mould of reserved vallecular cavity is directly welded in template, when the demoulding, easily vallecular cavity is damaged.
Summary of the invention
The utility model, in order to solve the problem that in the reserved vallecular cavity construction of heat preservation ditch, mould easily damages vallecular cavity, provides a kind of heat preservation ditch preformed groove construction equipment, can well complete the reserved construction of preformed groove, easy and simple to handle, effective, economical and practical.
The utility model adopts following technical scheme to realize: a kind of heat preservation ditch preformed groove construction equipment, comprise preformed groove mould, be located at ditch construction formwork and the fixed bar at preformed groove mould top, preformed groove mould and ditch construction formwork removably connect by syndeton with fixed bar.
Described preformed groove mold bottom is welded with interior hold-down nut, and construction formwork outside in described ditch is fixed with the nut being coaxially set with interior hold-down nut; On the construction formwork of the corresponding ditch of nut, offer intercommunicating pore; Described bottom of fixed is provided with the die end screw thread connecting in interior hold-down nut, and middle part is provided with the template terminal filament button being connected with nut, and welded top has two crisscross circular reinforced steel bar rings.Described preformed groove mould top is fixed with guide pipe by the connecting reinforcement being welded on preformed groove mould side wall, and described guide pipe is corresponding with interior hold-down nut and be coaxially set, and the guide pipe mouth of pipe is mutually neat with preformed groove mould top.Described fixed bar die end screw thread length is less than the length of hold-down nut screw thread in preformed groove mould.Described interior hold-down nut is longitudinally arranged with two, and described guide pipe and nut are corresponding is respectively provided with two, and described fixed bar is two, is processed by round steel.Described preformed groove mould is formed by Plate Welding.
The specific implementation process of heat preservation ditch preformed groove construction equipment is: first make preformed groove mould, be welded with steel sheet, preformed groove mold bottom longitudinally axis is symmetrically welded two interior hold-down nuts, nut center is apart from 1/4 place, the narrow limit of mould, fix two guide pipes on preformed groove mould top by connecting reinforcement along position, nut axis, guide pipe slightly larger in diameter is in interior hold-down nut internal diameter, connecting reinforcement is welded on preformed groove mould side wall, and the guide pipe mouth of pipe is concordant with preformed groove mould top.The ditch construction formwork that is positioned at guide pipe mouth of pipe place is offered intercommunicating pore, in contrast to a nut of the each welding in construction formwork intercommunicating pore position, ditch of guide pipe one side, this nut location is corresponding with the interior hold-down nut position of preformed groove mould guide pipe and preformed groove mould, three is on an axis, and the nut in the interior hold-down nut of preformed groove mould, guide pipe, intercommunicating pore, ditch construction formwork outside forms a passage.
Process fixed bar with round steel, fixed bar external diameter is identical with the interior hold-down nut of preformed groove mould and the nut interior diameter in ditch construction formwork outside; Bottom of fixed arranges die end screw thread, and middle part arranges template terminal filament button corresponding to the nut location on the construction formwork of ditch; Die end screw thread is corresponding with the interior hold-down nut screw thread of preformed groove mould, and length is slightly less than the interior hold-down nut screw thread length of preformed groove mould, and template terminal filament button is corresponding with nut screw thread set on the construction formwork of ditch; Fixed bar is not established two of the welded top circular reinforced steel bar ring of right-angled intersection in length and breadth of screw thread, as the force application part that turns fixed bar.
While construction in ditch, by preformed groove mould brush release agent, preformed groove mould guide pipe is first corresponded to nut location fixing on the construction formwork of ditch, fixed bar is screwed into from nut location, be screwed in the interior hold-down nut of preformed groove mold bottom through after guide pipe, realize the fixing of preformed groove mould, while tightening fixed bar, preformed groove mould to be pressed on the construction formwork of ditch, when seeing that fixed bar is about to stop while being all screwed into nut the application of force corresponding to the screw thread of the nut location on the construction formwork of ditch, the reinforced steel bar ring that passes fixed bar welded top by bar dowel carries out the application of force.When form removal, first fixed bar is deviate from preformed groove mould by the reinforced steel bar ring that rotates fixed bar welded top, then removed ditch construction formwork, the connecting reinforcement that simultaneously adopts Reinforced hook to catch on connection guide pipe is ticked preformed groove mould.
The utlity model has following beneficial effect: preformed groove construction equipment is simple in structure, easy and simple to handle, assembling and disassembling is convenient; Not fragile preformed groove, construction effect is good; Economy and durability, convenient and practical, can repeatedly reuse, save time and cost-saving.
Brief description of the drawings
Fig. 1 is the installation side view of the utility model preformed groove construction equipment; Fig. 2 is the front view of preformed groove mould in the utility model; Fig. 3 is the plan view of preformed groove mould in the utility model; Fig. 4 is I-I sectional drawing of Fig. 3; Fig. 5 is the structural representation of fixed bar.
In figure: 1-preformed groove mould, hold-down nut in 2-, 3-ditch construction formwork, 4-nut, 5-guide pipe, 6-connecting reinforcement, 7-fixed bar, 8-reinforced steel bar ring, 9-die end screw thread, 10-template terminal filament button.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is described in further detail.
A kind of heat preservation ditch preformed groove construction equipment, comprises preformed groove mould 1, is located at ditch construction formwork 3 and the fixed bar 7 at preformed groove mould 1 top, and preformed groove mould 1 removably connects by syndeton with ditch construction formwork 3 use fixed bars 7.
Described preformed groove mould 1 bottom welding has interior hold-down nut 2, and construction formwork 3 outsides, described ditch are fixed with the nut 4 being coaxially set with interior hold-down nut 2; On the corresponding ditch of nut 4 construction formwork 3, offer intercommunicating pore; Described fixed bar 7 bottoms are provided with the die end screw thread 9 being connected with interior hold-down nut, and middle part is provided with the template terminal filament button 10 being connected with nut 4, and welded top has two crisscross circular reinforced steel bar rings 8.Described preformed groove mould 1 top is by being welded in the connecting reinforcement 6 fixed guide pipes 5 of preformed groove mould 1 sidewall, and described guide pipe 5 is corresponding with interior hold-down nut 2 and be coaxially set, and guide pipe 5 mouths of pipe are mutually neat with preformed groove mould 1 top.
Described fixed bar die end screw thread 9 length are less than the length of hold-down nut 2 screw threads in preformed groove mould.Described interior hold-down nut 2 is longitudinally arranged with two, and described guide pipe 5 and nut 4 be corresponding, and to be respectively provided with two fixed bars 7 be two, processed by round steel.Described preformed groove mould 1 is formed by Plate Welding.
The specific implementation process of heat preservation ditch preformed groove construction equipment is: first make preformed groove mould, be welded with steel sheet, preformed groove mold bottom longitudinally axis is symmetrically welded two interior hold-down nuts, nut center is apart from 1/4 place, the narrow limit of mould, fix two guide pipes on preformed groove mould top by connecting reinforcement along position, nut axis, guide pipe slightly larger in diameter is in interior hold-down nut internal diameter, connecting reinforcement is welded on preformed groove mould side wall, and the guide pipe mouth of pipe is concordant with preformed groove mould top.The ditch construction formwork that is positioned at guide pipe mouth of pipe place is offered intercommunicating pore, in contrast to a nut of the each welding in construction formwork intercommunicating pore position, ditch of guide pipe one side, this nut location is corresponding with the interior hold-down nut position of preformed groove mould guide pipe and preformed groove mould, three is on an axis, and the nut in the interior hold-down nut of preformed groove mould, guide pipe, intercommunicating pore, ditch construction formwork outside forms a passage.
Process fixed bar with round steel, fixed bar external diameter is identical with the interior hold-down nut of preformed groove mould and the nut interior diameter in ditch construction formwork outside; Bottom of fixed arranges die end screw thread, and middle part arranges template terminal filament button corresponding to the nut location on the construction formwork of ditch; Die end screw thread is corresponding with the interior hold-down nut screw thread of preformed groove mould, and length is slightly less than the interior hold-down nut screw thread length of preformed groove mould, and template terminal filament button is corresponding with nut screw thread set on the construction formwork of ditch; Fixed bar is not established two of the welded top circular reinforced steel bar ring of right-angled intersection in length and breadth of screw thread, as the force application part that turns fixed bar.
While construction in ditch, by preformed groove mould brush release agent, preformed groove mould guide pipe is first corresponded to nut location fixing on the construction formwork of ditch, fixed bar is screwed into from nut location, be screwed in the interior hold-down nut of preformed groove mold bottom through after guide pipe, realize the fixing of preformed groove mould, while tightening fixed bar, preformed groove mould to be pressed on the construction formwork of ditch, when seeing that fixed bar is about to stop while being all screwed into nut the application of force corresponding to the screw thread of the nut location on the construction formwork of ditch, the reinforced steel bar ring that passes fixed bar welded top by bar dowel carries out the application of force.When form removal, first fixed bar is deviate from preformed groove mould by the reinforced steel bar ring that rotates fixed bar welded top, then removed ditch construction formwork, the connecting reinforcement that simultaneously adopts Reinforced hook to catch on connection guide pipe is ticked preformed groove mould.