CN203904856U - Movable construction platform for construction outside bridge guardrail - Google Patents
Movable construction platform for construction outside bridge guardrail Download PDFInfo
- Publication number
- CN203904856U CN203904856U CN201420322014.0U CN201420322014U CN203904856U CN 203904856 U CN203904856 U CN 203904856U CN 201420322014 U CN201420322014 U CN 201420322014U CN 203904856 U CN203904856 U CN 203904856U
- Authority
- CN
- China
- Prior art keywords
- cantilever
- cage
- main body
- construction
- body rack
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 29
- 239000002965 rope Substances 0.000 claims abstract description 14
- 229910000831 Steel Inorganic materials 0.000 claims description 8
- 239000010959 steel Substances 0.000 claims description 8
- 235000004443 Ricinus communis Nutrition 0.000 claims description 5
- 230000000149 penetrating Effects 0.000 abstract 1
- 238000004642 transportation engineering Methods 0.000 abstract 1
- 239000011248 coating agent Substances 0.000 description 2
- 238000000576 coating method Methods 0.000 description 2
- 240000000528 Ricinus communis Species 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 239000004035 construction material Substances 0.000 description 1
- 230000002596 correlated Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 231100000817 safety factor Toxicity 0.000 description 1
Abstract
The utility model discloses a movable construction platform for construction outside a bridge guardrail. The platform comprises a movable trolley body provided with trundles and is characterized in that a main support is arranged on the movable trolley body, a transverse cantilever extending towards one side is fixed to the top of the main support, a height adjustable lifting cage is movably connected to the extending end of the transverse cantilever, a fixed pulley is fixed to the portion, between the lifting cage and the main support, of the cantilever, a lifting rope is arranged on the fixed pulley in a penetrating mode, one end of the lifting rope is connected with the lifting cage, and the other end of the lifting rope is connected with the main support. The movable construction platform has the advantages that the movable construction platform can move along the bridge deck conveniently and is simple in structure and convenient to assemble, the height of the lifting cage is adjustable, adaptability is high, transportation and storage are convenient, a segmented structure is adopted, the safety of construction personnel is guaranteed, and working efficiency is improved.
Description
Technical field
The utility model relates to equipment for bridge construction, is specifically related to a kind of mobile operation platform for construction operation outside Bridge guardrail.
Background technology
Anticollision barrier is important traffic infrastructure, highway is all provided with guardrail high more than 2 meters across the both sides of railway bridge bridge floor at present, therefore the two electrical network difficulty of foreign body intrusion monitoring are installed very large in guardrail outside, highway on average has the height of 10 meters of left and right across railway bridge distance High-speed railway track rail level, just in case constructor falls down accidentally, consequence will be extremely serious.The way Shi Xianba highway of current domestic unit in charge of construction is first removed across railway bridge bridge both sides high guardrail more than 2 meters, then makes by oneself on the anti-collision wall that cage is suspended to bridge, and constructor stands in self-control cage and constructs, and guardrail is recovered after waiting construction to finish again.Twist not get off because the bolt of a lot of nonfloating rails has all become rusty, the work of dismounting guardrail is very difficult, also adds and guardrail will be recovered extremely at all.So whole dismounting adds that the workload of recovery guardrail is huge and difficulty is larger.
Summary of the invention
The purpose of this utility model is according to above-mentioned the deficiencies in the prior art part, a kind of mobile operation platform for construction operation outside Bridge guardrail is provided, this moves operation platform by the horizontal cantilever that main body rack is set and extends laterally on can the moving body of traveling, and be flexibly connected adjustable for height cage on the extension end of cantilever, in cage, construct outside bridge to realize constructor's safe ready.
The utility model object realizes and being completed by following technical scheme:
A kind of mobile operation platform for construction operation outside Bridge guardrail, comprise the moving body with castor, it is characterized in that being provided with main body rack on described moving body, be fixed with to the horizontal cantilever of a side extension at described main body rack top, the extension end of described horizontal cantilever is connected with adjustable for height cage, wherein, on the cantilever between described cage and described main body rack, be fixed with a fixed pulley, on described fixed pulley, be equipped with lifting rope, one end of described lifting rope is connected with described cage, and the other end is connected with described main body rack.
On described moving body, be provided with counterweight sandbag.
The height of described main body rack is not less than described guardrail height and described sling height sum.
Described cantilever is telescopic boom.
Described cage is flexibly connected with described cantilever through vertical steel pipe.
Between described main body rack and the epitaxial part of described cantilever, be provided with diagonal brace, the two ends of described diagonal brace are welded and fixed with described main body rack and described cantilever respectively.
The utility model has the advantages that, mobile operation platform can move along bridge floor easily, simple in structure, easy to assembly, sling height is adjustable, strong adaptability, be convenient to carrying and keeping, structure is segmented to be combined, and has not only ensured constructor's safety but also improved operating efficiency.
Brief description of the drawings
Fig. 1 is mobile operation platform structural representation in the utility model.
Detailed description of the invention
Feature of the present utility model and other correlated characteristic are described in further detail by embodiment below in conjunction with accompanying drawing, so that technician's of the same trade understanding:
As Fig. 1, in figure, mark 1-9 is respectively: castor 1, moving body 2, main body rack 3, cantilever 4, diagonal brace 5, fixed pulley 6, lifting rope 7, vertical steel pipe 8, cage 9.
Embodiment: the present embodiment is specifically related to a kind of mobile operation platform for construction operation outside Bridge guardrail, is intended to solve not removing bridge both sides more than 2 meters in high guardrail, the construction operation that can allow again constructor's safe ready outside Bridge guardrail.
As shown in Figure 1, this moves operation platform and is made up of moving body 2, main body rack 3, cantilever 4 and cage 9.
As shown in Figure 1, moving body 2 is welded by angle steel, and its below is provided with four castors 1, castor 1 is specially universal wheel, can make moving body 2 along any direction traveling, stable in order to ensure constructor's safety and car body, on moving body 2, be provided with counterweight sandbag;
Main body rack 3 is installed on moving body 2, and main body rack 3 is specifically welded by coating steel pipe, and its height should be greater than the height sum of guardrail and cage 9;
Top ends at main body rack 3 is laterally fixed with cantilever 4, and cantilever 4 is welded by coating steel pipe equally, and a part for cantilever 4 is fixedly connected with main body rack 3, and another part extends laterally, and its outside elongated end is used for being flexibly connected cage 9; Wherein, a certain section on cantilever 4 adopts telescopic sleeve pipe syndeton, can adjust according to actual conditions the perimetric length of cantilever 4, between adjustment rear sleeve and sleeve pipe, fixes by bolt tightening; In addition, in order to promote the anti-bending strength of cantilever 4, between cantilever 4 and main body rack 3, diagonal brace 5 is set, the two ends of diagonal brace 5 are welded and fixed with cantilever 4 and main body rack 3 respectively;
Be provided with two vertical steel pipes 8 at the outside of cantilever 4 elongated end, the upper end of vertical steel pipe 8 is flexibly connected with cantilever 4, its lower end is fixedly connected with cage 9, in order to make cage 9 highly adjustable, on the cantilever 4 between cage 9 and main body rack 3, be fixedly installed a fixed pulley 6, on fixed pulley 6, wear lifting rope 7 simultaneously, one end of lifting rope 7 is fixedly connected with main body rack 3, the other end is fixedly connected with cage 9, and constructor is by pulling lifting rope 7 on main body rack 3 can regulate the height of cage 9 in the vertical directions.
As shown in Figure 1, the method for utilizing the mobile operation platform in the present embodiment to carry out construction operation in Bridge guardrail outside is as follows:
First by pulling lifting rope 7 on fixed pulley 6 to regulate the height of cage 9, this height be according to constructor at the height of Bridge guardrail outside construction and fixed, highly after adjusting, one end of lifting rope 7 is fixed with main body rack 3 colligations; On moving body 2, place afterwards counterweight sandbag, the weight of sandbag will ensure constructor's moving body 2 not run-off the straights in the time holding construction material and instrument properly and stand in 9 li of constructions of cage, safety factor in order to ensure that constructor's safety doubles in the present embodiment is placed the counterweight sandbag of 500 kilograms on moving body 2; After preparation is carried out, constructor stands in cage 9, and other auxiliary constructions personnel shift moving body 2 to need the place of construction to carry out construction operation onto from end of the bridge, in guardrail outside, the two electrical networks of foreign body intrusion monitoring or other device is installed; After construction operation, auxiliary construction personnel can be pushed into moving body 2 bridge tail relief constructor and climb out of from cage 9, also can be at the medium position place of bridge, by pulling the above lifting cage 9 of lifting rope 7 on fixed pulley 6, when after the height of cage 9 height higher than guardrail, inwardly promote moving body 2 cage 9 is positioned on bridge floor, finally transfer cage 9, constructor climbs out of from cage 9.
The beneficial effect of the present embodiment is, can be in the situation that not removing bridge guardrails of both sides, the construction operation that allows constructor's safe ready outside Bridge guardrail, be that constructor may stand in the cage of mobile operation platform and constructs, need not remove guardrail, below moving body, there are four universal caster wheels, can conveniently move along bridge floor, simple in structure, easy to assembly, sling height is adjustable, strong adaptability, be convenient to carrying and keeping, structure is segmented to be combined, and has not only ensured constructor's safety but also improved operating efficiency.
Claims (6)
1. the mobile operation platform for construction operation outside Bridge guardrail, comprise the moving body with castor, it is characterized in that being provided with main body rack on described moving body, be fixed with to the horizontal cantilever of a side extension at described main body rack top, the extension end of described horizontal cantilever is connected with adjustable for height cage, wherein, on the cantilever between described cage and described main body rack, be fixed with a fixed pulley, on described fixed pulley, be equipped with lifting rope, one end of described lifting rope is connected with described cage, and the other end is connected with described main body rack.
2. a kind of mobile operation platform for construction operation outside Bridge guardrail according to claim 1, is characterized in that being provided with on described moving body counterweight sandbag.
3. a kind of mobile operation platform for construction operation outside Bridge guardrail according to claim 1, is characterized in that the height of described main body rack is not less than described guardrail height and described sling height sum.
4. a kind of mobile operation platform for construction operation outside Bridge guardrail according to claim 1, is characterized in that described cantilever is telescopic boom.
5. a kind of mobile operation platform for construction operation outside Bridge guardrail according to claim 1, is characterized in that described cage is flexibly connected with described cantilever through vertical steel pipe.
6. a kind of mobile operation platform for construction operation outside Bridge guardrail according to claim 1, it is characterized in that being provided with diagonal brace between described main body rack and the epitaxial part of described cantilever, the two ends of described diagonal brace are welded and fixed with described main body rack and described cantilever respectively.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420322014.0U CN203904856U (en) | 2014-06-17 | 2014-06-17 | Movable construction platform for construction outside bridge guardrail |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420322014.0U CN203904856U (en) | 2014-06-17 | 2014-06-17 | Movable construction platform for construction outside bridge guardrail |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203904856U true CN203904856U (en) | 2014-10-29 |
Family
ID=51779146
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420322014.0U Active CN203904856U (en) | 2014-06-17 | 2014-06-17 | Movable construction platform for construction outside bridge guardrail |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203904856U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107059610A (en) * | 2017-05-10 | 2017-08-18 | 南昌大学 | Light movable packaged type bridges overhaul assistance platform |
CN107117546A (en) * | 2017-06-12 | 2017-09-01 | 无锡石油化工起重机有限公司 | Pour the derrick crane of Multi-functional disk base reinforcing |
CN108203924A (en) * | 2016-12-18 | 2018-06-26 | 邬惠林 | The bike lane's special mobile installation vehicle sling under overpass |
-
2014
- 2014-06-17 CN CN201420322014.0U patent/CN203904856U/en active Active
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108203924A (en) * | 2016-12-18 | 2018-06-26 | 邬惠林 | The bike lane's special mobile installation vehicle sling under overpass |
CN108203924B (en) * | 2016-12-18 | 2019-04-23 | 邬惠林 | The bike lane's special mobile installation vehicle sling under overpass |
CN107059610A (en) * | 2017-05-10 | 2017-08-18 | 南昌大学 | Light movable packaged type bridges overhaul assistance platform |
CN107117546A (en) * | 2017-06-12 | 2017-09-01 | 无锡石油化工起重机有限公司 | Pour the derrick crane of Multi-functional disk base reinforcing |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2014015757A1 (en) | Bridge maintenance vehicle with hinge-connected type hanging bracket and capable of avoiding bridge-side obstacles | |
CN104453231A (en) | Gantry type building construction lifting device as well as manufacturing method and construction method thereof | |
CN107178035A (en) | Bridge side work high above the ground Electronic control stage apparatus | |
CN203904856U (en) | Movable construction platform for construction outside bridge guardrail | |
CN205152788U (en) | But telescopic bridge testing platform of antihunting | |
CN202751338U (en) | Rail type suspension basket | |
CN103663300A (en) | Track type telescopic hanging basket special for bridge | |
CN203834373U (en) | Lifting movement mold carriage trolley for box culvert side wall formwork | |
CN203451070U (en) | Movable type gantry | |
CN204139057U (en) | Deflection framework beam type bridge-checking vehicle | |
CN202879487U (en) | Transfer carriage in steel box | |
CN201933415U (en) | Highway and railway twin-girder bridge erection machine | |
CN206554524U (en) | A kind of construction discharging platform | |
CN210713752U (en) | High-altitude operation construction hanging basket capable of moving in three-dimensional space | |
CN102837705B (en) | Traveling bogie in steel box | |
CN204608602U (en) | Novel bridge maintenance protection installation work car | |
CN204474174U (en) | A kind of general-purpose overhead crane | |
CN206769343U (en) | It is a kind of to be used for the travelling bridge that guardrail is constructed that builds a bridge | |
CN205893930U (en) | Self -propelled hanging flower basket device | |
CN204823870U (en) | Bridge crane and dolly | |
CN205116006U (en) | High -speed railway bridge longmen walking maintenance detection device | |
CN211687992U (en) | Movable shield tunnel construction operation platform with lifting equipment | |
CN203555689U (en) | Electric hanging basket for vertical shaft | |
CN207672429U (en) | A kind of cast-in-place guardrail activity tool car of highway bridge | |
CN206917597U (en) | A kind of contact net power equipment maintaining step ladder |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |