CN203846402U - Steel-concrete superposed beam top plate support-free construction device - Google Patents

Steel-concrete superposed beam top plate support-free construction device Download PDF

Info

Publication number
CN203846402U
CN203846402U CN201420225149.5U CN201420225149U CN203846402U CN 203846402 U CN203846402 U CN 203846402U CN 201420225149 U CN201420225149 U CN 201420225149U CN 203846402 U CN203846402 U CN 203846402U
Authority
CN
China
Prior art keywords
steel
stupefied
point device
indoor
concrete superposed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420225149.5U
Other languages
Chinese (zh)
Inventor
周朝阳
王善波
章洪俊
王依斌
娄晓东
谢含军
陈旭
江炎林
蒋晓孟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Municipal Engineering Construction Group Co Ltd
Original Assignee
Ningbo Municipal Engineering Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Municipal Engineering Construction Group Co Ltd filed Critical Ningbo Municipal Engineering Construction Group Co Ltd
Priority to CN201420225149.5U priority Critical patent/CN203846402U/en
Application granted granted Critical
Publication of CN203846402U publication Critical patent/CN203846402U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A steel-concrete superposed beam top plate support-free construction device comprises a mounting box indoor mandrel supporting device, a steel fulcrum device and cantilever section devices. A mandrel in the mounting box indoor mandrel supporting device is supported by a fastener type steel pipe. A main ridge and a secondary ridge are mounted on the mandrel. A face plate made of bamboo plywood is mounted on the secondary ridge. The steel fulcrum device is arranged at the corresponding position of the top of a steel beam web connected with the mounting box indoor mandrel supporting device. Cross beams are evenly and symmetrically placed on the steel fulcrum device. The bottom faces of the cross beams are closely attached to a steel base plate on the top face of the steel fulcrum device and are connected with the steel base plate in a spot welding mode. Diagonal bracings are arranged on the two sides of the steel fulcrum device. A longitudinal beam is mounted on the cross beams. The cantilever section devices are mounted at the two ends of the longitudinal beam. The steel-concrete superposed beam top plate support-free construction device not only has the functions in the prior art, but also has the advantages of being capable of reducing construction cost, increasing construction speed and not affecting construction quality.

Description

A kind of steel concrete superposed beam top board erection without scaffolding device
Technical field
The utility model belongs to bridge construction field of engineering technology, relates in particular to a kind of steel-concrete superposed beam top board erection without scaffolding device.
Background technology
The Support Methods that adopt of steel-concrete superposed beam concrete roof construction are at present constructed more, meet across traffic intersection, river course, must set up door opening or rack platform.In use all there is certain limit in this method, utilize support to do operation platform or set up door opening or set up rack platform in river course at traffic intersection, input material is large, construction cost is high, long construction period, and divide between the sedimentation and deformation of concrete support under load action and girder steel and have certain distortion settlement difference choosing arm, easily make to choose arm and divide the joint portion of concrete bottom and girder steel to produce the open defects such as faulting of slab ends, spillage.
Summary of the invention
The purpose of this utility model is to overcome the deficiency that prior art exists, and a kind of function that possesses prior art is provided, and can save again construction cost, accelerates speed of application and does not affect steel-concrete superposed beam top board erection without scaffolding device of construction quality.
The purpose of this utility model completes by following technical solution, comprise the indoor mandrel support device of install bin, steel point device and choose arm section apparatus, core in the indoor mandrel support device of described install bin adopts fastener type steel pipe to support, on this core, be provided with main stupefied, inferior stupefiedly, the panel that adopts bamboo offset plate be installed at this time on stupefied; On the steel beam web plate top correspondence position being connected with the indoor mandrel support device of this install bin, be provided with steel point device, on this steel point device symmetrically be shelved with crossbeam, crossbeam bottom surface is close to the billet of steel point device end face and spot welding is connected, and in steel point device both sides, diagonal brace is set; On described crossbeam, longeron is installed, the two ends of this longeron are provided with chooses arm section apparatus.
As preferably, described steel point device comprises Two bors d's oeuveres i iron, and the two ends of this Two bors d's oeuveres i iron are provided with billet, and the billet of Two bors d's oeuveres i iron bottom surface is connected with the girder steel panel spot welding at steel beam web plate top, and overcoat pvc pipe.
As preferably, described choose arm section apparatus by suspension rod, choose arm template, inferior stupefied, main stupefied composition, described in choose arm template below time stupefied and main stupefied soffit formwork skeleton that is combined into is installed, this soffit formwork skeleton is interspersed with suspension rod, this suspension rod is anchored on longeron; The girder steel face plate edge splicing seams place pointing of choosing arm template and steel beam web plate top has glass cement.
The beneficial effects of the utility model are:
1, in steel-concrete superposed beam concrete roof work progress, guarantee high-altitude safe operation, accelerated construction speed, reduced construction cost;
2, shorten construction period: utilize shaped steel to choose arm support, saved ground directly, traffic door opening or underwater platform, construct more convenient, quick;
3, construction quality: the support system of Cast-in-place concrete top board is set with girder steel self-bearing capacity, has effectively ensured the synchronism of girder steel compressive deformation and wing plate distortion.
4, save material: utilize shaped steel to choose arm support, saved ground directly, traffic door opening or underwater platform; Shaped steel is chosen arm support and is once dropped into, and can use by iterative cycles.
Brief description of the drawings
Fig. 1 is superposed beam girder plane of arrangement figure of the present utility model.
Fig. 2 is superposed beam construction profile of the present utility model.
Fig. 3 is the A place structure for amplifying schematic diagram of Fig. 1.
Fig. 4 is steel point device section structure schematic diagram of the present utility model.
Label in accompanying drawing is respectively: 1, the indoor mandrel support device of install bin; 2, steel point device; 3, choose arm section apparatus; 4, main stupefied; 5, inferior stupefied; 6, panel; 7, steel beam web plate; 8, crossbeam; 9, longeron; 11, core; 21, Two bors d's oeuveres i iron; 22, billet; 23, pvc pipe; 31, suspension rod; 32, choose arm template; 71, girder steel panel.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is done to detailed introduction: as shown in accompanying drawing 1,2, the utility model comprises the indoor mandrel support device 1 of install bin, steel point device 2 and chooses arm section apparatus 3, core 11 in the indoor mandrel support device 1 of described install bin adopts fastener type steel pipe to support, on this core 11, be provided with main stupefied 4, inferior stupefiedly 5, the panel 6 that adopts bamboo offset plate is installed on this time stupefied 5; Make girder steel end face form spaciousness, smooth operating platform, for safety condition is created in the installation of choosing arm section apparatus 3.The interior headway of the indoor mandrel support device 1 of install bin is limited, and core skeleton and steel pipe support design should be optimized as far as possible, take up space less, are beneficial to manual demolition.And reserved manhole, so that the indoor core 11 of case is removed.On the steel beam web plate 7 top correspondence positions that are connected with the indoor mandrel support device 1 of this install bin, be provided with steel point device 2, guarantee that there are enough strength and stiffness at fulcrum place, can make load fully pass to steel beam web plate 7 and reduce eccentric force as far as possible; On this steel point device 2 symmetrically be shelved with crossbeam 8, crossbeam 8 bottom surfaces are close to the billet 22 of steel point device 2 end faces and spot welding is connected, if any space, adopt steel sheet embedding real, and in steel point device 2 both sides, diagonal brace are set, and guarantee that crossbeam 8 stablizes; On described crossbeam 8, longeron 9 is installed, the two ends of this longeron 9 are provided with chooses arm section apparatus 3.
As shown in accompanying drawing 3,4, described steel point device 2 comprises Two bors d's oeuveres i iron 21, also can adopt other shaped steel or steel pipe; The two ends of this Two bors d's oeuveres i iron 21 are provided with billet 22, and the billet 22 of Two bors d's oeuveres i iron 21 bottom surfaces is connected with girder steel panel 71 spot welding at steel beam web plate 7 tops, and overcoat pvc pipe 23, are convenient to later stage dismounting.
Described choose arm section apparatus 3 by suspension rod 31, choose arm template 32, inferior stupefied 5, main stupefied 4 and form, described below of choosing arm template 32 is provided with inferior stupefied 5 and main stupefied 4 and is combined into soffit formwork skeleton, soffit formwork skeleton is transported to bridge location place after suspension rod 31 is assembled and put on to ground piecemeal, fasten rope and be promoted to elevation at the bottom of top board by artificial or loop wheel machine piecemeal, this suspension rod 31 is anchored on longeron 9, then carries out accurate adjustment and reach design altitude; Choosing arm template 32 has glass cement with girder steel panel 71 splicing seams place, the edge pointings at steel beam web plate 7 tops, in order to avoid spillage when concreting.
The utility model is not limited to above-mentioned embodiment; no matter do any variation in its shape or material formation; every employing structure design provided by the utility model, is all a kind of distortion of the present utility model, all should think within the utility model protection domain.

Claims (3)

1. a steel concrete superposed beam top board erection without scaffolding device, it is characterized in that: comprise the indoor mandrel support device of install bin (1), steel point device (2) and choose arm section apparatus (3), core (11) in the indoor mandrel support device of described install bin (1) adopts fastener type steel pipe to support, main stupefied (4), inferior stupefied (5) are installed on this core (11), the panel (6) that adopts bamboo offset plate is installed on this time stupefied (5); On steel beam web plate (7) the top correspondence position being connected with the indoor mandrel support device of this install bin (1), be provided with steel point device (2), on this steel point device (2) symmetrically be shelved with crossbeam (8), crossbeam (8) bottom surface is close to the billet (22) of steel point device (2) end face and spot welding is connected, and in steel point device (2) both sides, diagonal brace is set; Longeron (9) is installed on described crossbeam (8), and the two ends of this longeron (9) are provided with chooses arm section apparatus (3).
2. steel-concrete superposed beam top board erection without scaffolding device according to claim 1, it is characterized in that: described steel point device (2) comprises Two bors d's oeuveres i iron (21), the two ends of this Two bors d's oeuveres i iron (21) are provided with billet (22), the billet (22) of Two bors d's oeuveres i iron (21) bottom surface is connected with girder steel panel (71) spot welding at steel beam web plate (7) top, and overcoat pvc pipe (23).
3. steel-concrete superposed beam top board erection without scaffolding device according to claim 1, it is characterized in that: described choose arm section apparatus (3) by suspension rod (31), choose arm template (32), inferior stupefied (5), main stupefied (4) and form, time stupefied (5) are installed in described below of choosing arm template (32) and main stupefied (4) are combined into soffit formwork skeleton, this soffit formwork skeleton is interspersed with suspension rod (31), and this suspension rod (31) is anchored on longeron (9); Choose arm template (32) and have glass cement with splicing seams place, girder steel panel (71) the edge pointing at steel beam web plate (7) top.
CN201420225149.5U 2014-05-05 2014-05-05 Steel-concrete superposed beam top plate support-free construction device Expired - Fee Related CN203846402U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420225149.5U CN203846402U (en) 2014-05-05 2014-05-05 Steel-concrete superposed beam top plate support-free construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420225149.5U CN203846402U (en) 2014-05-05 2014-05-05 Steel-concrete superposed beam top plate support-free construction device

Publications (1)

Publication Number Publication Date
CN203846402U true CN203846402U (en) 2014-09-24

Family

ID=51559439

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420225149.5U Expired - Fee Related CN203846402U (en) 2014-05-05 2014-05-05 Steel-concrete superposed beam top plate support-free construction device

Country Status (1)

Country Link
CN (1) CN203846402U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103952979A (en) * 2014-05-05 2014-07-30 宁波市政工程建设集团股份有限公司 Bracket-free construction device and construction method for steel-concrete superposed beam top plate
CN107761571A (en) * 2017-10-30 2018-03-06 中铁二十四局集团安徽工程有限公司 Needle beam combined steel plate beam bridge panel cast-in-place construction sliding form frame system and its application

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103952979A (en) * 2014-05-05 2014-07-30 宁波市政工程建设集团股份有限公司 Bracket-free construction device and construction method for steel-concrete superposed beam top plate
CN103952979B (en) * 2014-05-05 2015-09-09 宁波市政工程建设集团股份有限公司 A kind of steel concrete superposed beam top board erection without scaffolding device and construction method
CN107761571A (en) * 2017-10-30 2018-03-06 中铁二十四局集团安徽工程有限公司 Needle beam combined steel plate beam bridge panel cast-in-place construction sliding form frame system and its application

Similar Documents

Publication Publication Date Title
WO2021147256A1 (en) Single-side integral hoisted large-span overbridge crossing over multiple railway lines, and construction method therefor
CN104480862B (en) A kind of erection method of cable stayed bridge end bay steel truss girder
CN103911956B (en) A kind of large span stayed-cable bridge steel truss girder mounting method
CN103952979B (en) A kind of steel concrete superposed beam top board erection without scaffolding device and construction method
CN107355037A (en) Assembling type steel structure builds self-bearing type steel truss form bracing system and construction method
CN202658532U (en) Bridge wet joint construction template
CN103276893A (en) Novel composite structure for supporting rigid building template and construction method
CN203222738U (en) Steel pipe latticed column temporary buttress supporting device
CN107795124A (en) A kind of laminated floor slab truss support device for steel building
CN106284838B (en) A kind of lattice honeycomb girder segment and large span lattice girder steel and its fabrication and installation method
CN203846402U (en) Steel-concrete superposed beam top plate support-free construction device
CN103469735A (en) Method for mounting curve ultrahigh hollow column plate type pier top solid section template
CN108396632A (en) Reduce the method for PK combination girder stayed-cable bridge auxiliary pier pier top girder hogging moments
CN205116025U (en) Hanger device is pour to self -balancing concrete case roof beam and T beam bridge cantilever edge of a wing secondary
CN202913338U (en) Steel truss full-welded truss piece
CN202809494U (en) Bracket for pouring 0# block to rigid continuous girder bridge
CN203583776U (en) Truss structure of reinforced concrete beam
CN204455850U (en) The interim suspension connection device of Large Steel box beam erection
CN106758857A (en) The construction method of precast block formula secondary prestress Wavelike steel webplate combination beam
CN203213137U (en) Steel raft foundation for installing steel structure roof
CN104612063A (en) Concrete box beam first-aid repair method with prefabricated part on-site assembling combination beam
CN104088232B (en) A kind of emergency first-aid repair method of concrete box girder
CN103790388B (en) Greatly install improve one's methods across the waft high-altitude of eaves of cantilever roofing steel
CN204919363U (en) High mound pin -connected panel strength nature skeleton of anti high wind
CN212404844U (en) Bracket system for cast-in-situ flange plate of I-shaped steel-concrete composite beam

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140924