CN203702241U - Unloading pit connecting unloading chamber and drop shaft - Google Patents

Unloading pit connecting unloading chamber and drop shaft Download PDF

Info

Publication number
CN203702241U
CN203702241U CN201420029875.XU CN201420029875U CN203702241U CN 203702241 U CN203702241 U CN 203702241U CN 201420029875 U CN201420029875 U CN 201420029875U CN 203702241 U CN203702241 U CN 203702241U
Authority
CN
China
Prior art keywords
drop shaft
unloading
materials
unloading pit
pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420029875.XU
Other languages
Chinese (zh)
Inventor
张小飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CINF Engineering Corp Ltd
Original Assignee
CINF Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CINF Engineering Corp Ltd filed Critical CINF Engineering Corp Ltd
Priority to CN201420029875.XU priority Critical patent/CN203702241U/en
Application granted granted Critical
Publication of CN203702241U publication Critical patent/CN203702241U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Blast Furnaces (AREA)

Abstract

The utility model discloses an unloading pit connecting an unloading chamber and a drop shaft. The bottom of the unloading pit adopts a flat bottom structure, so that a blind stock heap is formed, direct impact and abrasion to the unloading pit from materials are reduced, and the speed of the materials is lowered. A central material dropping structure is arranged, the materials are gathered, direct impact and damage to the drop shaft are reduced, and the drop shaft is well protected. The unloading pit is of a flat-bottom structure, the blind stock heap is formed when the materials pass through the bottom of the unloading pit, and the unloading pit is protected against direct impact and damage. The central material dropping structure is arranged at the bottom of the unloading pit, the materials are gathered, and the drop shaft at the lower portion is prevented from being directly impacted by the materials. The impact and abrasion strength of the central material dropping structure is improved, and the inner wall and the upper end surface of the central material dropping structure are provided with abrasion-resistant lining plates. As the central material dropping structure is arranged on the unloading pit at the upper portion of the opening of the drop shaft, the defect that the materials directly impact and abrade the unloading pit and the drop shaft is avoided, and the service life of the drop shaft is prolonged.

Description

Connect the unloading hole of unloading chamber and drop shaft
Technical field
The utility model relates to a kind of mining drop shaft system, is specifically related to a kind of hole and structure with drop shaft junction of unloading.
Background technology
Drop shaft system is that underground mine is produced one of most important mining engineering, the material of underground mining collects storage and transhipment thus, whether unimpeded stablizing of it be very big to mine Influence of production, produce once destroy not only impact, and the safety that threatens whole drop shaft system and main shaft.Drop shaft system generally comprises unloading chamber, drop shaft, ore storage bin and bottom feed chamber etc.Due to drop shaft engineering-environment complexity, the load that is hit for a long time again, the large and soft broken mine of ore deposit rock of some production capacity all exists drop shaft gross distortion to destroy problem.Destruction the lighter need stop production and reprocess for a long time, and severe patient pit shaft is scrapped, and produces and has caused huge economic loss to mine.The failure mechanism of further investigated drop shaft, the thin portion of the effective drop shaft of reasonable structure, directly impacts and wearing and tearing drop shaft to reduce material, to ensureing that normal production of mine safety is extremely important.Unloading chamber unloading hole is structure of drop shaft system topmost, the general inclined-plane that adopts, bottom, unloading hole at present, and unloading hole is identical with drop shaft section with drop shaft coupling part section, and this structure makes material impact destruction to drop shaft wall.
Utility model content
The purpose of this utility model is to provide a kind of and converges material, avoids drop shaft to avoid the unloading hole structure of the direct impact failure of material.
The unloading hole of the disclosed this connection unloading chamber of the utility model and drop shaft, this unloading hole forms dead ore deposit heap while material being fallen for flat-bottom structure, be provided with central blanking structure and converge material to reduce the direct impact failure of material to drop shaft on flat-bottom structure.
Described central blanking structure adopts reinforced concrete structure, and its diameter is less than drop shaft diameter.
Inwall and the upper surface of described central blanking structure are provided with abrasion-proof backing block.
The diameter d of described central blanking structure is at least 3 times of the maximum lumpiness of material.
The height of described central blanking structure is at 1m ~ 4m.
The bottom that the utility model is cheated unloading adopts flat-bottom structure, forms dead ore deposit heap, and direct impact and the wearing and tearing that minimizing material is cheated unloading also slow down material speed; Central blanking structure is set, converges material and reduce the direct impact failure of drop shaft, well protect drop shaft.The diameter of central blanking structure is less than drop shaft diameter, material is converged and avoid bottom drop shaft to suffer the direct impact wear of material.The intensity that suffers material wearing and tearing in order to strengthen central blanking structure, wall and upper surface arrange abrasion-proof backing block therein.
The utility model arranges in the unloading hole on drop shaft mouth top the central blanking structure that diameter is less than drop shaft diameter, has avoided the defect of prior art material direct impact wear unloading hole and drop shaft, thereby extends the application life of drop shaft, and cost uses manpower and material resources sparingly.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model.
Fig. 2 is the structural representation of prior art.
Detailed description of the invention
As shown in Figure 1, the unloading hole 2 of the disclosed this connection unloading chamber 1 of the utility model and drop shaft 6, establishes with drop shaft 6 connecting portions the central blanking structure 4 that a diameter is less than drop shaft 6 diameters in 2 bottoms, unloading hole.Unloading hole 2 is flat-bottom structure, forms dead ore deposit heap 3, and dead ore deposit heap 3 has protected unloading hole 2 to avoid the direct impact wear of material.Central blanking structure 4 converges material 7 and reduces the direct impact to drop shaft 6.Central blanking structure 4 adopts reinforced concrete structure, suffers the intensity of material wearing and tearing in order to strengthen central blanking structure 4, and wall and upper surface arrange abrasion-proof backing block 5 therein.
The internal diameter of central blanking structure 4 and highly all definite according to the cohesiveness of material and lumpiness.In order to prevent blockage phenomenon in blanking process, the internal diameter that should ensure central blanking structure 4 is maximum the more than 3 times or 3 times of lumpiness of material, and height h is generally 1m ~ 4m.

Claims (5)

1. one kind connects the unloading hole of unloading chamber and drop shaft, it is characterized in that: this unloading hole forms dead ore deposit heap while material being fallen for flat-bottom structure, is provided with central blanking structure and converges material to reduce the direct impact failure of material to drop shaft on flat-bottom structure.
2. the unloading hole of connection unloading chamber as claimed in claim 1 and drop shaft, is characterized in that: described central blanking structure adopts reinforced concrete structure, and its diameter is less than drop shaft diameter.
3. the unloading hole of connection unloading chamber as claimed in claim 1 and drop shaft, is characterized in that: inwall and the upper surface of described central blanking structure are provided with abrasion-proof backing block.
4. the unloading hole of the unloading chamber of the connection as described in one of claim 1-3 and drop shaft, is characterized in that: the diameter of described central blanking structure is at least 3 times of the maximum lumpiness of material.
5. the unloading hole of the unloading chamber of the connection as described in one of claim 1-3 and drop shaft, is characterized in that: the height of described central blanking structure is at 1m ~ 4m.
CN201420029875.XU 2014-01-17 2014-01-17 Unloading pit connecting unloading chamber and drop shaft Expired - Fee Related CN203702241U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420029875.XU CN203702241U (en) 2014-01-17 2014-01-17 Unloading pit connecting unloading chamber and drop shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420029875.XU CN203702241U (en) 2014-01-17 2014-01-17 Unloading pit connecting unloading chamber and drop shaft

Publications (1)

Publication Number Publication Date
CN203702241U true CN203702241U (en) 2014-07-09

Family

ID=51052696

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420029875.XU Expired - Fee Related CN203702241U (en) 2014-01-17 2014-01-17 Unloading pit connecting unloading chamber and drop shaft

Country Status (1)

Country Link
CN (1) CN203702241U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107676129A (en) * 2017-10-18 2018-02-09 中国恩菲工程技术有限公司 Discharge point
CN110318801A (en) * 2019-07-23 2019-10-11 中国恩菲工程技术有限公司 Boxhole structure and its remodeling method
CN112960427A (en) * 2021-03-04 2021-06-15 中国恩菲工程技术有限公司 Underground mine unloading station
CN113294202A (en) * 2021-04-22 2021-08-24 中国电建集团华东勘测设计研究院有限公司 Big section of connecting broken chamber crowd in pit expands end abrasionproof and prevents stifled drop shaft structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107676129A (en) * 2017-10-18 2018-02-09 中国恩菲工程技术有限公司 Discharge point
CN110318801A (en) * 2019-07-23 2019-10-11 中国恩菲工程技术有限公司 Boxhole structure and its remodeling method
CN112960427A (en) * 2021-03-04 2021-06-15 中国恩菲工程技术有限公司 Underground mine unloading station
CN112960427B (en) * 2021-03-04 2024-10-22 中国恩菲工程技术有限公司 Underground mine unloading station
CN113294202A (en) * 2021-04-22 2021-08-24 中国电建集团华东勘测设计研究院有限公司 Big section of connecting broken chamber crowd in pit expands end abrasionproof and prevents stifled drop shaft structure

Similar Documents

Publication Publication Date Title
CN203702241U (en) Unloading pit connecting unloading chamber and drop shaft
CN201749048U (en) Combined sample preparation system
CN202001055U (en) Ore drawing buffer protection device for branch inclined chute of main chute
CN201610328U (en) Nickel ore discharge hopper with chute
CN202398380U (en) Gyratory crusher provided with cross-beam liner plate for preventing materials from swelling
CN204338258U (en) The shock-resistant shell liner of large-scale semi-autogenous mill
CN204184816U (en) A kind of blanking device
CN203470325U (en) Ore drawing grate sieve for draw shaft
CN201990167U (en) Ore drawing chute with adjustable feed rate
CN202224229U (en) Stepped crushing feeding funnel
CN104481533A (en) Underground mine and ore lifting method
CN102444418A (en) Device for filling roadway
CN205274399U (en) Novel wear -resisting coal breakage pipe
CN205948972U (en) Ring hammer crusher's material distribution apparatus
CN201494864U (en) Wear resistant vibration reduction type lower milling hole
CN203939521U (en) Movable drag conveyor is received coal device
CN208666098U (en) Wear device drops in ore storage bin
CN207583373U (en) A kind of coal mining machine roller cylinder bottom outer ring loads inclined plate
CN205397061U (en) Metallurgical converter loading attachment's lower hopper
CN205146422U (en) Unloading hopper arrangement who shocks resistance
CN104492527B (en) A kind of gyratory crusher upper frame
CN204297411U (en) Vertical silo goes out cash hole preventing clogging up device
CN104368430A (en) Zero energy consumption ore multistage continuous automatic crushing innovation technology
CN205839835U (en) A kind of scraper bowl of open coal mine wheel loader
CN201605283U (en) On-line restoration structure of lining board of charging bucket on blast furnace roof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140709