CN203660357U CN201320731126.7U CN201320731126U CN203660357U CN 203660357 U CN203660357 U CN 203660357U CN 201320731126 U CN201320731126 U CN 201320731126U CN 203660357 U CN203660357 U CN 203660357U
Authority
CN
China
Prior art keywords
drop
live
chuck
jumper cable
distribution network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320731126.7U
Other languages
Chinese (zh)
Inventor
丁中华
黄国华
沈长浩
孟祥柱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaibei Power Supply Co of State Grid Anhui Electric Power Co Ltd
State Grid Corp of China SGCC
Original Assignee
Huaibei Power Supply Co of State Grid Anhui Electric Power Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaibei Power Supply Co of State Grid Anhui Electric Power Co Ltd, State Grid Corp of China SGCC filed Critical Huaibei Power Supply Co of State Grid Anhui Electric Power Co Ltd
Priority to CN201320731126.7U priority Critical patent/CN203660357U/en
Application granted granted Critical
Publication of CN203660357U publication Critical patent/CN203660357U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

本实用新型公开了一种10kV负荷切断式引流工具,解决了现有负荷引流工具使用范围少且不方便的问题,其特征在于包括带电卡头、过渡铜鼻子、10kV跌落式熔断器、跳线电缆、跌落式熔断器绝缘护罩,所述的10KV跌落式熔断器上端通过过渡铜鼻子连接一个带电卡头,下端与跳线电缆相连,跳线电缆的另一端也连接一个带电卡头。本实用新型使配网线路的各类事故或缺陷可以不停电进行检修和消缺,使配网带电作业进入到真正的“不停电作业”;简单实用,安全性高,应用范围广,成本低;及时消除事故隐患,提高供电可靠性;可以作为临时切断开关使用,可以临时为运行线路提供故障、过流保护。

The utility model discloses a 10kV load cut-off type drainage tool, which solves the problem that the existing load drainage tool has a small range of use and is inconvenient, and is characterized in that it includes a charged chuck, a transitional copper nose, a 10kV drop type fuse, and a jumper Cable, drop-out fuse insulation cover, the upper end of the 10KV drop-out fuse is connected to a live chuck through a transition copper nose, the lower end is connected to a jumper cable, and the other end of the jumper cable is also connected to a live chuck. The utility model enables all kinds of accidents or defects of the distribution network line to be repaired and eliminated without power failure, so that the live operation of the distribution network enters a real "non-power interruption operation"; it is simple and practical, has high safety, wide application range and low cost ; Eliminate hidden dangers of accidents in time and improve power supply reliability; it can be used as a temporary cut-off switch, and can temporarily provide fault and overcurrent protection for operating lines.

Description

10kV负荷切断式引流工具10kV load cut-off drainage tool

技术领域 technical field

本实用新型涉及一种配网线路的负荷引流工具,更确切地说涉及一种10kV线路的不停电作业中使用的负荷引流工具。 The utility model relates to a load drainage tool for a distribution network line, in particular to a load drainage tool used in the non-stop operation of a 10kV line.

背景技术 Background technique

配网线路,当干支线设备零克或刀闸存有安全隐患时,为了不扩大停电范围,作业人员常采取带电断、接引线的方法来更换零克、刀闸,而这种情况下的带电作业,往往需要将零克或刀闸断开,不带负荷进行作业,虽然停电范围缩小,但也损失了部分电量,影响了配网线路的供电可靠性。 For distribution network lines, when there are potential safety hazards in the zero-gram or knife switch of the trunk and branch line equipment, in order not to expand the scope of power outages, operators often adopt the method of live disconnection and connection of lead wires to replace the zero-gram and knife switch. For live work, it is often necessary to disconnect the zero gram or the knife switch and carry out the work without load. Although the scope of the power outage is reduced, part of the power is also lost, which affects the power supply reliability of the distribution network line.

现代社会由于其发展机制的需要对于供电的持续性要求越来越高,任何短暂时间停电对于线路周围的用户的影响都有可能是巨大的,对于某些工业大厂来说,一次短暂的停电就可能造成巨大的经济损失,稍长时间的断电就会给其正常的工作带来许多棘手的问题,政府机关、医院、银行等基础设施更要保证其用电的可靠性。 Due to the needs of its development mechanism, modern society has higher and higher requirements for the continuity of power supply. Any short-term power outage may have a huge impact on users around the line. For some large industrial plants, a short power outage It may cause huge economic losses, and a long-term power outage will bring many thorny problems to its normal work. Government agencies, hospitals, banks and other infrastructure must ensure the reliability of their power consumption.

市场上销售的负荷引流工具,由于重量较重,价格昂贵,配备的供电企业较少,而且该工具使用范围小,实际应用中不方便,只适用于裸导线,需要将绝缘导线剥开才能连接。这将破坏绝缘导线的机械性能和绝缘性能,从而存在一定的安全隐患。 The load drainage tools sold on the market are heavy and expensive, and there are few power supply companies equipped with them. Moreover, the tool has a small range of use, which is inconvenient in practical applications. It is only suitable for bare wires, and the insulated wires need to be stripped to connect. . This will destroy the mechanical properties and insulation properties of the insulated wire, thereby posing certain safety hazards.

发明内容 Contents of the invention

本实用新型的目的在于克服现有技术的不足提供一种10kV 负荷切断式引流工具,使配网线路的各类事故或缺陷可以不停电进行检修和消缺,不但保证了企业和居民用电,还提高了配网线路的供电可靠性。 The purpose of this utility model is to overcome the deficiencies of the prior art and provide a 10kV load cut-off drainage tool, so that various accidents or defects of distribution network lines can be repaired and eliminated without power failure, which not only ensures the electricity consumption of enterprises and residents, It also improves the power supply reliability of the distribution network line.

本实用新型的特征在于:包括带电卡头、过渡铜鼻子、10kV跌落式熔断器、跳线电缆、跌落式熔断器绝缘护罩,所述的10KV 跌落式熔断器上端通过过渡铜鼻子连接一个带电卡头,下端与跳线电缆相连,跳线电缆的另一端也连接一个带电卡头。 The utility model is characterized in that it includes a charged chuck, a transition copper nose, a 10kV drop-out fuse, a jumper cable, and an insulation shield for the drop-out fuse, and the upper end of the 10KV drop-out fuse is connected to a charged The lower end is connected to the jumper cable, and the other end of the jumper cable is also connected to a live chuck.

所述的带电卡头全铝制造,可以间接使用高压操作杆挂在线路上,也可以穿戴绝缘手套、绝缘服用手直接挂在线路上,用于绝缘作业车不能到达的地点;使用简单,造价低,主要在裸露的线路上使用,和绝缘穿刺接地环配合,可以在绝缘导线上使用。 The live chuck is made of all aluminum, can be directly hung on the line by using a high-voltage operating rod, or can be directly hung on the line by wearing insulated gloves and insulated suit hands, and is used in places that cannot be reached by insulated work vehicles; it is easy to use and low in cost. It is mainly used on exposed lines, and it can be used on insulated wires in conjunction with insulation piercing grounding rings.

所述的跳线电缆的外层先用10kV 绝缘自粘带细细缠绕一层,再用 10kV 绝缘热缩管增强其绝缘性能。 The outer layer of the jumper cable is first wound with a 10kV insulating self-adhesive tape, and then a 10kV insulating heat shrinkable tube is used to enhance its insulation performance.

所述的跳线电缆为软芯铜电缆,直径50mm。 The jumper cable is a soft-core copper cable with a diameter of 50mm.

上述技术方案可知,本实用新型具有以下有益效果:1、使配网线路的各类事故或缺陷可以不停电进行检修和消缺,使配网带电作业进入到真正的“不停电作业”,有利于减少用户的停电次数和时间,有利于实现供电企业与用户的双赢;2、简单实用,安全性高,应用范围广,成本低,可在较短的时间内收回成本;3、及时消除事故隐患,提高供电可靠性:由于缩短了设备带病运行时间,减少甚至避免了事故停电,提高了设备全年供电小时数,电网的供电可靠性也得到极大提高;4、可以快速牢固安全地与运行线路相连接,缩短了带电作业时间,降低了劳动强度,提高了工时利用率;5、当配网某运行线路的刀闸、零克存有隐患时,既不利于线路安全运行,又不便于开展带电作业消缺时,本实用新型可以作为临时切断开关使用,保险管内安装一定规格的熔断保险丝,可以临时为运行线路提供故障、过流保护,使该线路的企业用户多创产值,居民用户提高生活质量;6、若与绝缘操作杆配合,可作为线路负荷临时或应急使用;地域适应能力强,不受交通和复杂地形的限制,在绝缘斗臂车无法到达的杆位均可进行使用;7、与现有零克绝缘遮蔽罩相结合,能使该引流工具全绝缘遮蔽,安全防护强,有效地保证了带电作业人员的安全;8、在10kV配网线路使用本实用新型进行不停电作业,以每次带电作业2小时计算,每年开展不停电作业40次,每年可多供电量为14.4万kW.h,为供电企业增加收入7.2万元。 It can be seen from the above technical solution that the utility model has the following beneficial effects: 1. All kinds of accidents or defects of the distribution network line can be repaired and eliminated without power failure, so that the live operation of the distribution network enters the real "non-power interruption operation". It is conducive to reducing the number and time of power outages for users, and is conducive to achieving a win-win situation between power supply companies and users; 2. Simple and practical, high safety, wide application range, low cost, and can recover costs in a short period of time; 3. Eliminate accidents in a timely manner Hidden dangers, improve power supply reliability: due to shortening the running time of equipment in case of illness, reducing or even avoiding accidental power outages, increasing the annual power supply hours of equipment, and greatly improving the power supply reliability of the power grid; 4. It can be quickly, firmly and safely It is connected with the running line, which shortens the live working time, reduces the labor intensity, and improves the utilization rate of working hours; When it is inconvenient to carry out live work to eliminate defects, the utility model can be used as a temporary cut-off switch, and a fuse of a certain specification is installed in the safety tube, which can temporarily provide fault and overcurrent protection for the running line, so that the enterprise users of the line can create more output value, Resident users can improve the quality of life; 6. If it is matched with an insulating operating rod, it can be used as a temporary or emergency use for line loads; it has strong regional adaptability and is not restricted by traffic and complex terrain. 7. Combined with the existing zero-gram insulation shielding cover, the drainage tool can be fully insulated and shielded, and the safety protection is strong, effectively ensuring the safety of live workers; 8. The utility model is used in 10kV distribution network lines Carry out uninterrupted operation, calculated on the basis of 2 hours of live work each time, carry out 40 uninterrupted operations per year, the annual power supply can be increased by 144,000 kW.h, and the income of power supply enterprises can be increased by 72,000 yuan.

附图说明 Description of drawings

图1是本实用新型用于配网线路绝缘导线的结构示意图。 Fig. 1 is a structural schematic view of the utility model used for insulated conductors of distribution network lines.

图2是本实用新型使用跌落式熔断器绝缘护罩使的结构示意图。 Fig. 2 is a schematic diagram of the structure of the utility model using the insulating shield of the drop-out fuse.

图中,1.绝缘穿刺悬挂工具,2.带电卡头,3.过渡铜鼻子,4.10kV跌落式熔断器,5.跳线电缆,6.跌落式熔断器绝缘护罩。 In the figure, 1. Insulation puncture hanging tool, 2. Live chuck, 3. Transition copper nose, 4.10kV drop-out fuse, 5. Jumper cable, 6. Drop-out fuse insulation shield.

具体实施方式 Detailed ways

下面结合附图对本实用新型作进一步的说明。 Below in conjunction with accompanying drawing, the utility model is further described.

如图1所示,本实用新型用于配网线路绝缘导线。先将绝缘穿刺悬挂工具1连接在主绝缘导线上,再把带电卡头2固定在绝缘穿刺悬挂工具1上,带电卡头2通过过渡铜鼻子3连接10KV 跌落式熔断器4上端。拉开10kV跌落式熔断器4的熔管,先将线路负荷断开,将10kV跌落式熔断器4的下端和跳线电缆5连接,跳线电缆5另一端再连接一个带电卡头2,把该带电卡头2固定在支绝缘导线上的绝缘穿刺悬挂工具1上,然后合上10kV跌落式熔断器4的熔管。如图2所示,再使用跌落式熔断器绝缘护罩6把 10kV 跌落式熔断器4全绝缘遮蔽,之后便可以进行零克或刀闸的更换和消缺。 As shown in Figure 1, the utility model is used for insulated conductors of distribution network lines. First connect the insulation piercing suspension tool 1 to the main insulated wire, and then fix the live chuck 2 on the insulation piercing suspension tool 1, and connect the live chuck 2 to the upper end of the 10KV drop-out fuse 4 through the transition copper nose 3. Pull the fuse tube of the 10kV drop-out fuse 4, first disconnect the line load, connect the lower end of the 10kV drop-out fuse 4 to the jumper cable 5, and then connect the other end of the jumper cable 5 to a live chuck 2, and put The charged chuck 2 is fixed on the insulation piercing suspension tool 1 on the branch insulated wire, and then the melting tube of the 10kV drop-out fuse 4 is closed. As shown in Figure 2, the 10kV drop-out fuse 4 is completely insulated and shielded by using the drop-out fuse insulating shield 6, and then the zero-gram or knife switch can be replaced and eliminated.

如果本实用新型用于配网线路裸导线:则将带电卡头2固定在配网主裸导线上,拉开10kV跌落式熔断器4的熔管,先将线路负荷断开,将10kV跌落式熔断器4的下端和跳线电缆5连接,然后再将另一个带电卡头2固定在支裸导线上,后合上0kV跌落式熔断器4的熔管,再将跌落式熔断器绝缘护罩6使10kV 跌落式熔断器4全绝缘遮蔽,之后便可以进行零克或刀闸的更换和消缺。 If the utility model is used for bare conductors of distribution network lines: fix the live chuck 2 on the main bare conductors of the distribution network, pull the fuse tube of the 10kV drop-out fuse 4, first disconnect the line load, and then connect the 10kV drop-out fuse 4 The lower end of the fuse 4 is connected to the jumper cable 5, and then another live chuck 2 is fixed on the bare wire, and finally the melting tube of the 0kV drop-out fuse 4 is closed, and the insulating shield of the drop-out fuse is 6 Make the 10kV drop-out fuse 4 fully insulated and shielded, and then the zero-gram or knife switch can be replaced and eliminated.

Claims (1)

1. a 10kV load cutting type drainage instrument, it is characterized in that: comprise charged dop (2), transition copper lug (3), 10kV fuse switch (4), jumper cable (5), fuse switch insulating shield (6), described 10KV fuse switch (4) upper end connects a charged dop (2) by transition copper lug (3), lower end is connected with jumper cable (5), and the other end of jumper cable (5) also connects a charged dop 2 (2).
CN201320731126.7U 2013-11-19 2013-11-19 10-kV load cut-off type current drainage tool Expired - Fee Related CN203660357U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320731126.7U CN203660357U (en) 2013-11-19 2013-11-19 10-kV load cut-off type current drainage tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320731126.7U CN203660357U (en) 2013-11-19 2013-11-19 10-kV load cut-off type current drainage tool

Publications (1)

Publication Number Publication Date
CN203660357U true CN203660357U (en) 2014-06-18

Family

ID=50926711

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320731126.7U Expired - Fee Related CN203660357U (en) 2013-11-19 2013-11-19 10-kV load cut-off type current drainage tool

Country Status (1)

Country Link
CN (1) CN203660357U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103560419A (en) * 2013-11-19 2014-02-05 国家电网公司 10kV load disconnection type drainage tool

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103560419A (en) * 2013-11-19 2014-02-05 国家电网公司 10kV load disconnection type drainage tool

Similar Documents

Publication Publication Date Title
CN102611080B (en) Main station type small current grounding control method
CN203422438U (en) Real-time monitoring and fault location system for overhead lines of power distribution network
CN106849369B (en) Energy taking device and method for overhead lightning protection ground wire of power transmission line based on CT electricity taking
CN104375056B (en) Substation cable outgoing line fault monitoring method based on voltage and current initial row waves
CN103336220A (en) Method and apparatus for monitoring and positioning fault in power distribution network
CN103532047B (en) A kind of operational method and device changing fuse switch on 10kV post
CN102931609A (en) Operation method for replacing 10kV drop-out fuse in on-load manner
CN102299558B (en) Method and device for providing electric power system information
CN104113002B (en) A kind of high tension cable cross connection grounding system switching device
CN103560419A (en) 10kV load disconnection type drainage tool
CN203660357U (en) 10-kV load cut-off type current drainage tool
CN203135556U (en) Emergency power supply assembly
CN202817567U (en) Intelligent box-type wind power substation
CN103944163B (en) A kind of compound transformer substation system
CN203150912U (en) High and low voltage switch cabinet with supervision management system
CN201910386U (en) Temporary connecting device for live replacement of fuse tube of drop-out fuse
CN205317886U (en) Undercurrent earth fault route selection system
CN205123368U (en) Portable emergent direct current charging device
CN210693413U (en) A high-strength mandrel-type arrester with visible fracture
CN203787789U (en) A T, π mixed grid connection structure for high voltage power distribution
CN203289003U (en) Multifunctional insulating operating lever of transformer station
CN107947097A (en) A kind of 10kV suspended insulated guide wires with the anti-lightning strike broken string of shielded layer
CN103346509A (en) Improved coaxial cable connector hot-line mounting technology
CN202564903U (en) Lightning protection system of extra-high voltage alternating current double-loop tangent tower
CN204303232U (en) A kind of low-voltage power distribution station area teaching mould

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140618

Termination date: 20201119

CF01 Termination of patent right due to non-payment of annual fee