CN203545485U - Four-cable eight-section grab bucket for nickel ore - Google Patents

Four-cable eight-section grab bucket for nickel ore Download PDF

Info

Publication number
CN203545485U
CN203545485U CN201320741751.XU CN201320741751U CN203545485U CN 203545485 U CN203545485 U CN 203545485U CN 201320741751 U CN201320741751 U CN 201320741751U CN 203545485 U CN203545485 U CN 203545485U
Authority
CN
China
Prior art keywords
bucket
lobe
support beam
rope
valves
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320741751.XU
Other languages
Chinese (zh)
Inventor
张彦东
刘心华
胡建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI PEINER SMAG MACHINERY CO Ltd
Original Assignee
SHANGHAI PEINER SMAG MACHINERY CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI PEINER SMAG MACHINERY CO Ltd filed Critical SHANGHAI PEINER SMAG MACHINERY CO Ltd
Priority to CN201320741751.XU priority Critical patent/CN203545485U/en
Application granted granted Critical
Publication of CN203545485U publication Critical patent/CN203545485U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model discloses a four-cable eight-section grab bucket for nickel ore. The four-cable eight-section grab bucket comprises bucket valves connected with support bars. The upper end of each support bar is connected with an upper support beam in a rotating mode through a pin shaft. The upper support beam is disposed on a track cable balancing stand, and a fixed pulley block is disposed on the upper support beam. The upper end of each bucket valve is hinged to a lower support beam, a movable pulley block is disposed on the lower support beam, the fixed pulley block and the movable pulley block are connected through a connecting component, the number of the bucket valves is eight, and the eight bucket valves can be combined into a whole closed body. Each bucket valve is connected with the upper support beam through a corresponding support bar, and each bucket valve is hinged to the lower support beam. The number of the bucket valves is changed into eight, the stability of the whole grab bucket becomes higher, and the appearance looks more symmetrical. Seen from the top view of the whole bucket body, the whole body of the bucket valves is in the shape of a hexadecagon, more similar to a circle. Not only is the strength of every single bucket valve increased, but also the actual contact area of materials and each bucket valve is reduced and the bonding area of the bucket valves is decreased.

Description

Four rope eight lobe nickel minerals grab buckets
Technical field
The utility model relates to a kind of grab bucket, relates in particular to a kind of four rope eight lobe nickel minerals grab buckets, is specially adapted to viscosity higher, easily caking, and poor fluidity, is difficult to the nickel minerals bulk material capturing.
Background technology
Grab bucket is in the carriers such as port and pier, power plant, to use comparatively general a kind of bulk handling device, as everyone knows, grab bucket that it is comprised of bucket lobe, deck beam and fixed pulley group, cross sill and running block, strut, sheave, equalizer bar, steel rope etc.Due to the difference of grab multiple, in assembly pulley, include the pulley of different numbers.Steel rope by the drive of pulley make to struggle against lobe closed with open.
Along with importing and exporting the development of port trade, harbour increases the transportation volume of nickel minerals.Because the viscosity of nickel minerals is strong, be difficult to capture, six lobes of routine used and double-jaw grab bucket, in crawl process, actual bucket capacity used only has the half left and right of theoretical displacement, and being equivalent to there is the material of 1/3rd left and right is to be bonded on the inwall of bucket body, is repeated transportation.Nickel minerals easy caking in extruded situation, the bonding granularity of especially air-dry nickel minerals is large and hard, is similar to tabia, and common orange-peel bucket is difficult to incision.So unload a ship, efficiency is very low.
Utility model content
For the problems referred to above, the utility model provides a kind of four rope eight lobe nickel minerals grab buckets, to solve the problem of the theoretical calculated tonnage of material out of reach of the sizing in crawl process and removal in prior art.
To achieve these goals, the technical solution of the utility model is as follows:
Four rope eight lobe nickel minerals grab buckets, comprise the bucket lobe being connected with strut, and the upper end of described strut is rotatably connected by bearing pin and deck beam, and deck beam is arranged on track cable equalizer bar, is provided with fixed pulley group on deck beam; Upper end and the through beam of bucket lobe are hinged, are provided with running block on through beam, between fixed pulley group and running block, by transom, are connected, and it is characterized in that, described bucket lobe has eight, and be combined into can be closed overall; Each bucket lobe all connects deck beam by a corresponding strut, and each bucket lobe is all hinged with through beam.
In a preferred embodiment of the present utility model, described bucket lobe is to be all welded side by side by three arc plates, and is welded with high-intensity wear rib on the medial surface of two arc plates in left and right.
In a preferred embodiment of the present utility model, the front end of described bucket lobe is provided with high-intensity point and long bucket tip.
In a preferred embodiment of the present utility model, the place, maximum cross-section of described bucket lobe outside face is welded with in order to guarantee after bucket lobe unitary closed all inhibiting device on same circumference.Further, described inhibiting device is transverse arc ellbeam.
In a preferred embodiment of the present utility model, described deck beam, through beam are loop configuration.
The utility model changes bucket lobe quantity into eight, and the stability of entirety grab bucket is higher, and outward appearance is more symmetrical.From whole bucket body birds-eye view, entirety bucket lobe is ten hexagons, is more similar to circle.Not only increased the intensity of single bucket lobe, also reduced material and the actual scope contacting of each bucket lobe, thereby reduced to struggle against the bonding region area of lobe.And the quantity of strut also becomes eight, and grasp force improves greatly, make single bucket lobe more easily cut material.
The front end of bucket lobe of the present utility model arranges bucket tip, and not only shape is sharp-pointed and hardness is high, thereby has reduced the incision resistance of bucket lobe.
Feature of the present utility model can be consulted the detailed description of the graphic and following better embodiment of this case and be obtained and be well understood to.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Fig. 2 is birds-eye view of the present utility model.
Fig. 3 is the schematic diagram of single bucket lobe.
Fig. 4 is the left view of Fig. 3.
The specific embodiment
For technological means, creation characteristic that the utility model is realized, reach object and effect is easy to understand, below in conjunction with specific embodiment, further set forth the utility model.
Referring to Fig. 1 and 2, four rope eight lobe nickel minerals grab buckets, comprise the bucket lobe 01 being connected with strut 04 lower end, and the upper end of strut 04 is rotatably connected by bearing pin and deck beam 02, and deck beam 02 is arranged on track cable equalizer bar 05, is provided with fixed pulley group 06 on deck beam; Upper end and the through beam 07 of bucket lobe 01 are hinged, are provided with running block 03 on through beam, between fixed pulley group 06 and running block 03, by transom, are connected, and these are conventional structure, are not described in detail in this.
In the utility model, bucket lobe 01 has eight, and be combined into can closed entirety; Each bucket lobe 01 all connects deck beam 02 by a corresponding strut 04, and each bucket lobe is all hinged with through beam.Deck beam, through beam are loop configuration.
Referring to Fig. 3 and 4, bucket lobe 01 is to be all welded side by side by three arc plates (11,12,13), and is welded with high-intensity wear rib 14 on the medial surface of two of left and right arc plate (11,13).
The front end (lower end) of bucket lobe is provided with high-intensity point and long bucket tip 15, and it adopts high-intensity wear plate cutting to make, thereby has reduced the incision resistance of bucket lobe.
The place, maximum cross-section of bucket lobe outside face is welded with in order to guarantee after bucket lobe unitary closed all inhibiting device on same circumference.In this embodiment, inhibiting device is transverse arc ellbeam 16.
The utility model changes bucket lobe quantity into eight, and the stability of entirety grab bucket is higher, and outward appearance is more symmetrical.From whole bucket body birds-eye view, entirety bucket lobe is ten hexagons, is more similar to circle.Not only increased the intensity of single bucket lobe, also reduced material and the actual scope contacting of each bucket lobe, thereby reduced to struggle against the bonding region area of lobe.And the quantity of strut also becomes eight, and grasp force improves greatly, make single bucket lobe more easily cut material.
More than show and described groundwork of the present utility model, principal character and advantage of the present utility model.The technical personnel of the industry should be understood; the utility model is not restricted to the described embodiments; what in above-described embodiment and specification sheets, describe is principle of the present utility model; under the prerequisite that does not depart from the utility model spirit and scope, the utility model also has various changes and modifications, and these changes and improvements all fall in claimed scope of the present utility model.The protection domain that the utility model requires is defined by appending claims and equivalent thereof.

Claims (6)

1. four rope eight lobe nickel minerals grab buckets, comprise the bucket lobe being connected with strut, and the upper end of described strut is rotatably connected by bearing pin and deck beam, and deck beam is arranged on track cable equalizer bar, is provided with fixed pulley group on deck beam; Upper end and the through beam of bucket lobe are hinged, are provided with running block on through beam, between fixed pulley group and running block, by transom, are connected, and it is characterized in that, described bucket lobe has eight, and be combined into can be closed overall; Each bucket lobe all connects deck beam by a corresponding strut, and each bucket lobe is all hinged with through beam.
2. a kind of four rope eight lobe nickel minerals grab buckets according to claim 1, is characterized in that, described bucket lobe is to be all welded side by side by three arc plates, and is welded with high-intensity wear rib on the medial surface of two arc plates in left and right.
3. a kind of four rope eight lobe nickel minerals grab buckets according to claim 1, is characterized in that, the front end of described bucket lobe is provided with high-intensity point and long bucket tip.
4. a kind of four rope eight lobe nickel minerals grab buckets according to claim 1, is characterized in that, the place, maximum cross-section of described bucket lobe outside face is welded with in order to guarantee after bucket lobe unitary closed all inhibiting device on same circumference.
5. a kind of four rope eight lobe nickel minerals grab buckets according to claim 4, is characterized in that, described inhibiting device is transverse arc ellbeam.
6. a kind of four rope eight lobe nickel minerals grab buckets according to claim 1, is characterized in that, described deck beam, through beam are loop configuration.
CN201320741751.XU 2013-11-22 2013-11-22 Four-cable eight-section grab bucket for nickel ore Expired - Fee Related CN203545485U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320741751.XU CN203545485U (en) 2013-11-22 2013-11-22 Four-cable eight-section grab bucket for nickel ore

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320741751.XU CN203545485U (en) 2013-11-22 2013-11-22 Four-cable eight-section grab bucket for nickel ore

Publications (1)

Publication Number Publication Date
CN203545485U true CN203545485U (en) 2014-04-16

Family

ID=50463632

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320741751.XU Expired - Fee Related CN203545485U (en) 2013-11-22 2013-11-22 Four-cable eight-section grab bucket for nickel ore

Country Status (1)

Country Link
CN (1) CN203545485U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103588086A (en) * 2013-11-22 2014-02-19 上海佩纳沙士吉打机械有限公司 Four-cable eight-piece nickel mineral grab bucket
CN105329773A (en) * 2015-10-28 2016-02-17 无锡市惠泽通用机械有限公司 Orange-peel bucket for crane

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103588086A (en) * 2013-11-22 2014-02-19 上海佩纳沙士吉打机械有限公司 Four-cable eight-piece nickel mineral grab bucket
CN105329773A (en) * 2015-10-28 2016-02-17 无锡市惠泽通用机械有限公司 Orange-peel bucket for crane

Similar Documents

Publication Publication Date Title
CN203545485U (en) Four-cable eight-section grab bucket for nickel ore
CN103588086B (en) Four rope eight lobe nickel minerals grab buckets
CN204607400U (en) A kind of large crawl is grabbed bucket than mechanical type six lobe
CN205616452U (en) Asynchronous orange -peel bucket
CN204590114U (en) A kind of hydraulic rotating grabs stone implement
CN206046149U (en) Ingot-shaped waste disposal tooth
CN202322002U (en) Six-bladed grab bucket with variable bucket capacity
CN203474265U (en) Mechanical dual-jaw grab bucket with high grab ratio
CN201914398U (en) Motorcycle chain plate with reinforced layer
CN203414288U (en) Detacher
CN102795541A (en) Seven-valve grab bucket special for wood chips
CN203728140U (en) Mechanism for overturning and combining staples
CN202706927U (en) Improved structure for polycrystalline diamond compact (PDC) bit
CN202517406U (en) Clamping device of belt
CN209506671U (en) A kind of safety check container
CN207293934U (en) A kind of easy dropping-proof hook of crane
CN203048414U (en) Double-jaw grab bucket body
CN204602603U (en) Chinese chestnut shells the vibratory sieve mechanism of fluffy machine
CN203076839U (en) Rotary hoisting machine frame used for welding workpieces
CN202830203U (en) Tumble feeding and discharging mechanism
CN205398029U (en) Fork truck is with rotatory davit
CN212924139U (en) Four-cable three-tooth timber grab bucket
CN212924137U (en) Hydraulic double-flap rotary grab bucket
CN203604253U (en) Centrifugal pump
CN202746576U (en) Piston rod

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140416

Termination date: 20161122