CN203522039U - Overhead intelligent wiring device - Google Patents

Overhead intelligent wiring device Download PDF

Info

Publication number
CN203522039U
CN203522039U CN201320730119.5U CN201320730119U CN203522039U CN 203522039 U CN203522039 U CN 203522039U CN 201320730119 U CN201320730119 U CN 201320730119U CN 203522039 U CN203522039 U CN 203522039U
Authority
CN
China
Prior art keywords
work
altitude
operation bar
fixed
altitude according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320730119.5U
Other languages
Chinese (zh)
Inventor
鲍伟宏
马骁
王益旭
施首健
朱英伟
李策策
程辉阳
赵胜红
陈桂增
陆丰
洪亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JINHUA TRANSMISSION ENGINEERING Co Ltd
State Grid Corp of China SGCC
Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
JINHUA TRANSMISSION ENGINEERING Co Ltd
State Grid Corp of China SGCC
Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JINHUA TRANSMISSION ENGINEERING Co Ltd, State Grid Corp of China SGCC, Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical JINHUA TRANSMISSION ENGINEERING Co Ltd
Priority to CN201320730119.5U priority Critical patent/CN203522039U/en
Application granted granted Critical
Publication of CN203522039U publication Critical patent/CN203522039U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Operating, Guiding And Securing Of Roll- Type Closing Members (AREA)

Abstract

The utility model relates to an overhead intelligent wiring device, which comprises a base frame, a bottom seat fixed on the base frame, an operation rod fixed on the bottom seat, and a wiring assembly movably connected onto the operation rod. A control device for controlling the wiring assembly to move vertically on the operation rod is arranged on the bottom seat, and a power device for driving the control device to work is arranged on the bottom seat. The overhead intelligent wiring device has the advantages that the power device and the control device control the wiring assembly and wiring processing on the overhead equipment can be carried out, safety risks related to the overhead wiring work in the test work can be reduced, safety risks caused by overhead work can be effectively eliminated, the test person can operate distantly, safety of the test person is ensured, and the efficiency of the test work can be greatly improved.

Description

High-altitude intelligence termination
Technical field
The utility model relates to high-altitude intelligence termination.
Background technology
As everyone knows, along with scientific and technological development, the progress of human society, enlarging and the service work of transformer station are increasing, and operating personnel works also more and more frequent in transformer station.In order to guarantee enough safe distances, much equipment is all arranged on higher position, so testing crew is when carrying out work, need relate to the work of many high-altitude wirings.At present, the high-altitude wiring work that we generally adopt following methods to complete to relate in experimental project.When device height is not while being very high, generally adopt the testing crew equipment of climbing up to complete wiring work; When equipment is higher, by high-altitude clamping pliers, complete wiring; When device height is very high, must temporarily transfers high-altitude operation vehicle and complete wiring work.
In real work, find, the method for current these used altitude test wiring all cannot perfectly complete the high-altitude wiring work relating in process of the test.Employing personnel climb up equipment wiring and can bring no small security risk to experiment work by the mode of high-altitude clamping pliers.And high-altitude operation vehicle resource is less, scene not necessarily has, even if having, is also that many working faces share, and therefore uses high-altitude operation vehicle will affect the efficiency of whole engineering, by the existing altitude test mode of connection, has following several defect:
1, work high above the ground is a great security risk in real work at the scene.When employing personnel climb up equipment wiring, will inevitably can run into the potential safety hazard of falling from high altitude, this has increased the security risk of experiment work greatly.
2,, according to the safety message of Guo Wang company, Test Speciality is used high-altitude clamping pliers to carry out wiring, several high-altitude clamping pliers occurred and topple over, and touches the accident of charging equipment by mistake.Therefore, adopt high-altitude clamping pliers to carry out wiring and also can bring very large security risk to experiment work.
3, when adopting high-altitude operation vehicle to carry out altitude test wiring, experiment work will be often to use high-altitude operation vehicle, and the staff of other teams and groups of working also needs to temporarily transfer high-altitude operation vehicle simultaneously, they carry out our work of work and will delay like this, and we carry out work will affect them, and test cannot synchronously be carried out, cause test duration elongated, the original time of interruption maintenance is very short, if wasted time like this, must increase the weight of task below, even can postpone power-on time.
Utility model content
The technical problems to be solved in the utility model is that existing altitude plant exists potential safety hazard when wiring, and test duration is long, inefficiency, and Practical Performance is poor, thereby high-altitude intelligence termination is provided.
In order to solve the problems of the technologies described above, the utility model is achieved through the following technical solutions: high-altitude intelligence termination, comprise pedestal, be fixed on base on pedestal, be fixed on operation bar on base, be movably connected in the connector assembly on operation bar, described base is provided with controls connector assembly up and down control device on operation bar, and described base is provided with the power set of driving control device work.
Preferably, described control device comprises turbine reduction box, the safety rope being connected with connector assembly, for the reel of safety rope folding and unfolding, described reel is rotatably connected on turbine reduction box by rotating shaft, described power set are connected with rotating shaft transmission, by turbine reduction box realize connector assembly startup, stop and the control of the speed of lifting, by reel, realize the folding and unfolding of safety rope, connect reliable, be convenient to connector assembly lifting, Practical Performance is good, simple to operate.
Preferably, described power set comprise motor, are fixed on the shaft coupling on motor, the circuit board of control machine operation, described shaft coupling is connected with rotating shaft transmission by gear assembly, by circuit board, to motor, provide power, thereby drive its rotation, simple in structure, shaft coupling the stability that has guaranteed transmission is set, result of use is good.
Preferably, described gear assembly comprise the travelling gear that is fixed on shaft coupling, with the driven gear of travelling gear engaged transmission, described travelling gear and driven gear are cylindric straight-tooth gear, connect reliable, cylindric straight-tooth gear transmission is effective, and stability is good.
Preferably, described connector assembly comprise insulation transverse slat, scalable be arranged on insulation transverse slat on wire-clamping device, in described wire-clamping device, be provided with line of pull, described line of pull is provided with card the end of a thread, by line of pull control card the end of a thread, carry out wiring processing, simple to operate, Practical Performance is good.
Preferably, on described operation bar, be rotatably connected to one and be convenient to the mounting panel that circuit board is installed, described mounting panel is provided with mounting panel is locked to the locking device on control lever, described circuit board is provided with overvoltage prior-warning device, controls the control button of machine operation, the safety that has effectively guaranteed circuit board arranges, when needing the voltage of device of wiring excessive, overvoltage prior-warning device sends warning, has improved security performance.
Preferably, the middle part of described operation bar is provided with the groove of being convenient to connector assembly activity, and described power set are fixed on the base of groove bottom, have effectively reduced erection space, simple in structure, and Practical Performance is good.
Preferably, described base is fixed on pedestal by anchor bolt, and anchor bolt connects reliable, and stability is good, is not subject to windage, safe and reliable.
Preferably, described pedestal is the slide plate that bottom is provided with mobile device, and described slide plate is provided with handle, and convenient operation personnel move, and reduces the trouble of testing crew mobile device, and simple in structure, Practical Performance is good.
Preferably, the height of described operation bar is 6~8m, can adapt to the work high above the ground of differing heights, Practical Performance is good, when operation bar height is during higher than 8m, operation bar is when operation, easily be subject to external force to affect generation beat, thereby affect operating personnel, carry out wiring processing, when operation bar height is during lower than 6m, Practical Performance is low, can not adapt to highly very high wiring and process.
In sum, advantage of the present utility model: control connector assembly by power set and control device its altitude plant is carried out to wiring processing, reduced the security risk that relates to high-altitude wiring work in experiment work, effectively eliminated the security risk of bringing due to work high above the ground, testing crew carries out remote operation, ensure the safety of testing crew, greatly improved the efficiency of experiment work.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, the utility model is described in further detail:
Fig. 1 is the structural representation of the utility model high-altitude intelligence termination;
Structural representation when Fig. 2 is the work of the utility model connector assembly.
Embodiment
As Fig. 1, shown in Fig. 2, high-altitude intelligence termination, comprise pedestal 1, be fixed on the base 2 on pedestal 1, be fixed on the operation bar 3 on base 2, be movably connected in the connector assembly 4 on operation bar 3, described base 2 is provided with controls connector assembly 4 up and down control device 5 on operation bar 3, described base 2 is provided with the power set 6 of driving control device 5 work, described control device 5 comprises turbine reduction box 51, the safety rope 52 being connected with connector assembly 4, reel 53 for safety rope 52 folding and unfoldings, described reel 53 is rotatably connected on turbine reduction box 51 by rotating shaft 54, described power set 6 are in transmission connection with rotating shaft 54, by turbine reduction box 51, realize the startup of connector assembly 4, stop and the control of the speed of lifting, by reel 53, realize the folding and unfolding of safety rope 52, connect reliable, be convenient to connector assembly 4 liftings, Practical Performance is good, simple to operate, described power set 6 comprise motor 61, be fixed on the shaft coupling 62 on motor 61, control the circuit board 7 of motor 61 work, described shaft coupling 62 is in transmission connection by gear assembly 9 and rotating shaft 54, by circuit board 7, power is provided to motor 61, thereby drive its rotation, simple in structure, shaft coupling 62 the stability that has guaranteed transmission is set, result of use is good, described gear assembly 9 comprises the travelling gear 91 being fixed on shaft coupling 62, driven gear 92 with travelling gear 91 engaged transmission, described travelling gear 91 and driven gear 92 are cylindric straight-tooth gear, connect reliable, cylindric straight-tooth gear transmission is effective, stability is good, described connector assembly 4 comprises insulation transverse slat 41, the scalable wire-clamping device 42 being arranged on insulation transverse slat 41, in described wire-clamping device 42, be provided with line of pull 411, described line of pull 411 is provided with card the end of a thread 412, by line of pull control card the end of a thread, carry out wiring processing, simple to operate, Practical Performance is good, on described operation bar 3, be rotatably connected to one and be convenient to the mounting panel 31 that circuit board 7 is installed, described mounting panel 31 is provided with mounting panel 31 is locked to the locking device 311 on control lever, described locking device 311 is screw or lockset, described circuit board 7 is provided with overvoltage prior-warning device 71, control the control button 72 of motor 61 work, the safety that has effectively guaranteed circuit board 7 arranges, when needing the voltage of device of wiring excessive, overvoltage prior-warning device sends warning, improved security performance, the middle part of described operation bar 3 is provided with the groove 32 of being convenient to connector assembly 4 activities, described power set 6 are fixed on the base 2 of groove 32 bottoms, effectively reduced erection space, simple in structure, Practical Performance is good, described base 2 is fixed on pedestal 1 by anchor bolt 8, anchor bolt connects reliable, stability is good, be not subject to windage, safe and reliable, described pedestal 1 is provided with the slide plate of mobile device 11 for bottom, described slide plate is provided with handle 12, convenient operation personnel move, reduce the trouble of testing crew mobile device, simple in structure, Practical Performance is good, the height of described operation bar 3 is 6~8m, can adapt to the work high above the ground of differing heights, Practical Performance is good, when operation bar 3 height is during higher than 8m, operation bar 3 is when operation, easily be subject to external force to affect generation beat, thereby affect operating personnel and carry out wiring processing, when operation bar 3 height is during lower than 6m, Practical Performance is low, can not adapt to highly very high wiring processes.
Before use, by handle 11, promoting mobile device 12 makes pedestal 1 move to the position that needs wiring, during use, only need press the control button 72 on circuit board 7, make motor 61 drive reel 54 to rotate, by turbine reduction box 51, realize hoisting of connector assembly 4 and stop, during work, only need pull the line of pull 411 in connector assembly 4, make 412 pairs of equipment of card the end of a thread carry out wiring processing, again pull line of pull 411, clamping joint 412 separation instrumentations, operate successively, just can to equipment, carry out wiring processing quickly and easily.
By power set and control device, control connector assembly its altitude plant is carried out to wiring processing, reduced the security risk that relates to high-altitude wiring work in experiment work, effectively eliminated the security risk of bringing due to work high above the ground, testing crew carries out remote operation, ensure the safety of testing crew, greatly improved the efficiency of experiment work.

Claims (10)

1. high-altitude intelligence termination, it is characterized in that: comprise pedestal (1), be fixed on base (2) on pedestal (1), be fixed on operation bar (3) on base (2), be movably connected in the connector assembly (4) on operation bar (3), described base (2) is provided with controls connector assembly (4) at the upper up and down control device (5) of operation bar (3), and described base (2) is provided with the power set (6) of driving control device (5) work.
2. high-altitude according to claim 1 intelligence termination, it is characterized in that: described control device (5) comprises turbine reduction box (51), the safety rope (52) being connected with connector assembly (4), for the reel (53) of safety rope (52) folding and unfolding, it is upper that described reel (53) is rotatably connected on turbine reduction box (51) by rotating shaft (54), and described power set (6) are in transmission connection with rotating shaft (54).
3. high-altitude according to claim 1 and 2 intelligence termination, it is characterized in that: described power set (6) comprise motor (61), are fixed on the shaft coupling (62) on motor (61), the circuit board (7) of control motor (61) work, and described shaft coupling (62) is in transmission connection by gear assembly (9) and rotating shaft (54).
4. high-altitude according to claim 3 intelligence termination, it is characterized in that: described gear assembly (9) comprise the travelling gear (91) that is fixed on shaft coupling (62), with the driven gear (92) of travelling gear (91) engaged transmission, described travelling gear (91) and driven gear (92) are cylindric straight-tooth gear.
5. high-altitude according to claim 1 and 2 intelligence termination, it is characterized in that: described connector assembly (4) comprises insulation transverse slat (41), the scalable wire-clamping device (42) being arranged on insulation transverse slat (41), in described wire-clamping device (42), be provided with line of pull (411), described line of pull (42) is provided with card the end of a thread (412).
6. high-altitude according to claim 3 intelligence termination, it is characterized in that: on described operation bar (3), be rotatably connected to one and be convenient to the mounting panel (31) that circuit board (7) is installed, described mounting panel (31) is provided with mounting panel (31) is locked to the locking device (311) on control lever, and described circuit board (7) is provided with overvoltage prior-warning device (71), controls the control button (72) of motor (61) work.
7. high-altitude according to claim 1 intelligence termination, it is characterized in that: the middle part of described operation bar (3) is provided with is convenient to the movable groove (32) of connector assembly (4), and described power set (6) are fixed on the base (2) of groove (32) bottom.
8. high-altitude according to claim 1 intelligence termination, is characterized in that: described base (2) is fixed on pedestal (1) by anchor bolt (8).
9. high-altitude according to claim 1 intelligence termination, is characterized in that: described pedestal (1) is provided with the slide plate of mobile device (11) for bottom, and described slide plate is provided with handle (12).
10. high-altitude according to claim 1 intelligence termination, is characterized in that: the height of described operation bar (3) is 6~8m.
CN201320730119.5U 2013-11-18 2013-11-18 Overhead intelligent wiring device Expired - Fee Related CN203522039U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320730119.5U CN203522039U (en) 2013-11-18 2013-11-18 Overhead intelligent wiring device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320730119.5U CN203522039U (en) 2013-11-18 2013-11-18 Overhead intelligent wiring device

Publications (1)

Publication Number Publication Date
CN203522039U true CN203522039U (en) 2014-04-02

Family

ID=50380914

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320730119.5U Expired - Fee Related CN203522039U (en) 2013-11-18 2013-11-18 Overhead intelligent wiring device

Country Status (1)

Country Link
CN (1) CN203522039U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106207861A (en) * 2016-09-21 2016-12-07 广西大学 A kind of transformer substation system high-tension line safeguards that gear drive lift operates device
CN114362016A (en) * 2021-11-29 2022-04-15 国网河南省电力公司驻马店供电公司 Power metering box incoming cable auxiliary installation device and use method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106207861A (en) * 2016-09-21 2016-12-07 广西大学 A kind of transformer substation system high-tension line safeguards that gear drive lift operates device
CN106207861B (en) * 2016-09-21 2018-01-23 广西大学 A kind of transformer substation system high-tension line safeguards gear drive lift operation device
CN114362016A (en) * 2021-11-29 2022-04-15 国网河南省电力公司驻马店供电公司 Power metering box incoming cable auxiliary installation device and use method
CN114362016B (en) * 2021-11-29 2023-08-11 国网河南省电力公司驻马店供电公司 Auxiliary installation device for incoming cable of power metering box and use method

Similar Documents

Publication Publication Date Title
CN204835320U (en) Hand propelled automatic rising substation equipment overhauls device
CN103633581A (en) Multifunctional aerial operation platform for power transmission line and use method of aerial operation platform
CN104332891A (en) Six-rotor aircraft platform-based cutter for hanging objects on guide wires and ground wires of power transmission lines
CN203522039U (en) Overhead intelligent wiring device
CN105006661A (en) Grounding device
CN105439052A (en) Aerial work platform
WO2018045631A1 (en) Debugging system for traction converter of internal combustion locomotive
CN113328405B (en) Full-automatic direct current ice-melt short circuit control device of 220kV transmission line wire
CN103683073A (en) High-voltage electrified fixed-phase safety stop plate separation tool of switch cabinet
CN206863145U (en) A kind of distribution line status display apparatus
CN203632109U (en) Cable robot running device
CN204230758U (en) Based on power line conductive, the ground wire hanger cutter of six gyroplane carrying platforms
CN207858884U (en) A kind of livewire work dielectric level Telescopic boom mechanism
CN206114800U (en) Diesel locomotive traction current transformation cabinet debug system
CN204917711U (en) Device of driving current collection gas ware dual supply
CN204966932U (en) Wireless remote control high altitude earthing device that hydraulic pressure goes up and down
CN204980888U (en) Electric block controlling means
CN109814469B (en) Electric control device for attached lifting scaffold
CN201821035U (en) Foreign-matter electrical treatment device for four-bundle conductor of transmission line
CN207581073U (en) Movable insulating cord draw off gear
CN106208730A (en) A kind of new type inverter of controlled rectifier
CN112260141A (en) On-line uninterrupted operation robot
CN204906535U (en) Keep watch on wireless video monitoring device of tower crane lifting hook position
CN205928675U (en) A robot for installing high altitude transmission line
CN205304046U (en) Electrified disconnect device of transformer substation's pigtail splice

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140402

Termination date: 20201118

CF01 Termination of patent right due to non-payment of annual fee