CN203481644U - Open bus-bar installation complete-set power distribution cabinet - Google Patents

Open bus-bar installation complete-set power distribution cabinet Download PDF

Info

Publication number
CN203481644U
CN203481644U CN201320534265.0U CN201320534265U CN203481644U CN 203481644 U CN203481644 U CN 203481644U CN 201320534265 U CN201320534265 U CN 201320534265U CN 203481644 U CN203481644 U CN 203481644U
Authority
CN
China
Prior art keywords
power distribution
distribution cabinet
bus
busbar
bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320534265.0U
Other languages
Chinese (zh)
Inventor
吴张平
肖云
王佳翔
金辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIAXING FANRONG ELECTRICAL APPARATUS CO Ltd
Original Assignee
JIAXING FANRONG ELECTRICAL APPARATUS CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIAXING FANRONG ELECTRICAL APPARATUS CO Ltd filed Critical JIAXING FANRONG ELECTRICAL APPARATUS CO Ltd
Priority to CN201320534265.0U priority Critical patent/CN203481644U/en
Application granted granted Critical
Publication of CN203481644U publication Critical patent/CN203481644U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Patch Boards (AREA)

Abstract

The utility model relates to an open bus-bar installation complete-set power distribution cabinet. Bus-bar installation is often subject to limit of the wall of an installation site, and because of the narrow space, a bus-bar cannot penetrate through a bus-bar installation room from the side, which results in damage to the existing building wall structure and unreasonable and difficult installation. In order to solve the problem, the utility model provides an open bus-bar installation complete-set power distribution cabinet which makes bus-bar installation convenient. The power distribution cabinet comprises a power distribution cabinet body and a bus-bar, wherein the power distribution cabinet body is equipped with a bus room door. The power distribution cabinet is characterized in that the power distribution cabinet further comprises a framework which is fixed on the power distribution cabinet body, a bus-bar installation room is formed between the framework and the power distribution cabinet body, the framework is provided with a gap used for installing the bus-bar, and the bus-bar is installed in the bus-bar installation room. The bus-bar can be directly installed from the gap of the framework, installation is very convenient, and the existing building wall structure does not need to be destroyed.

Description

A kind of open busbar is installed complete power distribution cabinet
Technical field
The utility model relates to a kind of power distribution cabinet, especially relates to a kind of open busbar complete power distribution cabinet is installed.
Background technology
At present, power distribution cabinet comprises power distribution cabinet body, power distribution cabinet body is provided with skeleton, skeleton is surrounded the shape of surrounding sealing by column and crossbeam, when busbar is installed, be usually subject to the wall restriction of erecting bed, due to narrow space, cannot penetrate from the side busbar installation room, cause destroying existing building wall body structure, cause unreasonable and installation difficulty.
Utility model content
The purpose of this utility model is to overcome above shortcomings in prior art, and a kind of reasonable in design is provided, and busbar open busbar easy for installation is installed complete power distribution cabinet.
The technical scheme in the invention for solving the above technical problem is: this open busbar is installed complete power distribution cabinet, comprise power distribution cabinet body and busbar, on described power distribution cabinet body, bus-bar room door is installed, it is characterized in that: also comprise skeleton, described skeleton is fixed on power distribution cabinet body, between described skeleton and power distribution cabinet body, form busbar installation room, have for the breach of busbar is installed on described skeleton, described busbar is arranged in busbar installation room.When busbar is installed, the bus-bar room door that only need dismantle corresponding with indentation, there, directly puts into busbar from indentation, there, install very convenient.
Skeleton described in the utility model comprises a crossbeam, No. two crossbeams, a column and No. two columns, described No. two crossbeam one end are fixed on the middle and upper part of No. two columns, the other end is fixed on the top of a column, a described crossbeam is fixed on column top No. two, and a described crossbeam, No. two crossbeams and No. two columns surround tool busbar installation room jaggy.Skeleton structure is simple, only needs an original column to shorten, and No. two crossbeams are extended to the top of a column and fix with a column, and a column shortens part and is for the breach of busbar is installed.
The utility model also comprises support corner block, and described support corner block is arranged between a crossbeam and No. two columns.Support corner block is for strengthening the bonding strength between a crossbeam and No. two columns.
The utility model compared with prior art, has the following advantages and effect: simple in structure, reasonable in design, can directly from the indentation, there of skeleton, carry out the installation of busbar, install very convenient, without destroying existing building wall body structure.
Accompanying drawing explanation
Fig. 1 is the structural representation that in the utility model embodiment, open busbar is installed complete power distribution cabinet.
Fig. 2 is the enlarged drawing at A place in Fig. 1.
Embodiment
Below in conjunction with accompanying drawing and by embodiment, the utility model is described in further detail, and following examples are to explanation of the present utility model and the utility model is not limited to following examples.
Embodiment.
Referring to Fig. 1 to Fig. 2, the open busbar in the present embodiment is installed complete power distribution cabinet and is comprised power distribution cabinet body 1, busbar 2, skeleton 3, bus-bar room door 4, busbar installation room 5 and support corner block 6.
Skeleton 3 in the present embodiment comprises breach 31, a crossbeam 32, No. two crossbeams 33, a column 34 and No. two columns 35, the length of No. two columns 35 is longer than column 34 No. one, No. two crossbeam 33 one end are fixed on the middle and upper part of No. two columns 35, the other end is fixed on the top of a column 34, No. one crossbeam 32 is fixed on column 35 tops No. two, a crossbeam 32, No. two crossbeams 33 and No. two columns 35 surround the busbar installation room 5 with breach 31, breach 31 is for installing busbar 2, compared to existing technology, only need an original column 34 to shorten, and No. two crossbeams 33 are extended to the top of a column 34 and fix with a column 34, a column 34 shortens part and is for the breach 31 of busbar 2 is installed.In the present embodiment, support corner block 6 is arranged between a crossbeam 32 and No. two columns 35, and support corner block 6 is for strengthening the bonding strength between a crossbeam 32 and No. two columns 35.
Bus-bar room door 4 is installed on power distribution cabinet body 1 in the present embodiment, bus-bar room door 4 is detachable, skeleton 3 is fixed on power distribution cabinet body 1,1 of skeleton 3 and power distribution cabinet body form busbar installation room 5, busbar 2 is arranged in busbar installation room 5, when busbar 2 is installed, and the bus-bar room door 4 corresponding with breach 31 places of only need dismantling, busbar 2 is directly put into from breach 31, installed very convenient.
In addition, it should be noted that, the specific embodiment described in this specification, the shape of its parts and components, institute's title of being named etc. can be different, and the above content described in this specification is only to the utility model structure and the explanation of accompanying drawing example.All equivalence variation or simple change of doing according to described structure, feature and the principle of the utility model patent design, are included in the protection range of the utility model patent.The utility model person of ordinary skill in the field can make various modifications or supplements or adopt similar mode to substitute described specific embodiment; only otherwise depart from structure of the present utility model or surmount this scope as defined in the claims, all should belong to protection range of the present utility model.

Claims (3)

1. an open busbar is installed complete power distribution cabinet, comprise power distribution cabinet body and busbar, on described power distribution cabinet body, bus-bar room door is installed, it is characterized in that: also comprise skeleton, described skeleton is fixed on power distribution cabinet body, between described skeleton and power distribution cabinet body, form busbar installation room, have for the breach of busbar is installed on described skeleton, described busbar is arranged in busbar installation room.
2. open busbar according to claim 1 is installed complete power distribution cabinet, it is characterized in that: described skeleton comprises a crossbeam, No. two crossbeams, a column and No. two columns, described No. two crossbeam one end are fixed on the middle and upper part of No. two columns, the other end is fixed on the top of a column, a described crossbeam is fixed on column top No. two, and a described crossbeam, No. two crossbeams and No. two columns surround tool busbar installation room jaggy.
3. open busbar according to claim 2 is installed complete power distribution cabinet, it is characterized in that: also comprise support corner block, described support corner block is arranged between a crossbeam and No. two columns.
CN201320534265.0U 2013-08-30 2013-08-30 Open bus-bar installation complete-set power distribution cabinet Expired - Fee Related CN203481644U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320534265.0U CN203481644U (en) 2013-08-30 2013-08-30 Open bus-bar installation complete-set power distribution cabinet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320534265.0U CN203481644U (en) 2013-08-30 2013-08-30 Open bus-bar installation complete-set power distribution cabinet

Publications (1)

Publication Number Publication Date
CN203481644U true CN203481644U (en) 2014-03-12

Family

ID=50229900

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320534265.0U Expired - Fee Related CN203481644U (en) 2013-08-30 2013-08-30 Open bus-bar installation complete-set power distribution cabinet

Country Status (1)

Country Link
CN (1) CN203481644U (en)

Similar Documents

Publication Publication Date Title
CN203150936U (en) Power distribution cabinet pedestal
CN203481644U (en) Open bus-bar installation complete-set power distribution cabinet
CN204456542U (en) Bolt device of shifting block type curtain skeleton system
CN204691020U (en) A kind of T-shaped supporting steel keel of curtain wall
CN203571610U (en) Multifunctional vertical rod for construction
CN204424717U (en) A kind of drawer type low-voltage distributing cabinet cabinet cap structure
CN203891514U (en) Main transformer framework for omitting end support in substation
CN202125168U (en) Openable window frame structure on fully-hidden frame aluminum alloy glass curtain wall
CN205444230U (en) Photovoltaic direct current lightning combiner box installs basis
CN204947367U (en) A kind of assembled box-type becomes housing
CN203071408U (en) Heavy electric power control cabinet
CN203034785U (en) Reinforcement mesh scaffold board
CN205070881U (en) Solar bracket
CN204030280U (en) Modularization power distribution cabinet
CN202124977U (en) Semi-hidden-frame aluminum alloy glass curtain wall clamping section bar
CN203977908U (en) A kind of fast assembling operating room
CN205070892U (en) Photovoltaic support
CN204802886U (en) Instrument formula tower crane anchorage device's installation operation and half space
CN204252505U (en) A kind of Simple support frame
CN204012216U (en) A kind of bus bridge frame of high-tension switch cabinet
CN203347375U (en) Refrigerator lock fixing device
CN203983196U (en) Circuit breaker fixture
CN204139198U (en) Combination assembled mesolow electric fixtures basis
CN203976247U (en) A kind of shield handling appliance
CN204385999U (en) The reinforced fin curtain wall system of cross

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140312

Termination date: 20170830