CN203452799U - Corrugated steel tunnel supporting structure - Google Patents
Corrugated steel tunnel supporting structure Download PDFInfo
- Publication number
- CN203452799U CN203452799U CN201320390316.7U CN201320390316U CN203452799U CN 203452799 U CN203452799 U CN 203452799U CN 201320390316 U CN201320390316 U CN 201320390316U CN 203452799 U CN203452799 U CN 203452799U
- Authority
- CN
- China
- Prior art keywords
- tunnel
- corrugated steel
- concrete
- supporting
- steel plate
- Prior art date
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 42
- 239000010959 steel Substances 0.000 title claims abstract description 42
- 239000011435 rock Substances 0.000 abstract description 18
- 238000010276 construction Methods 0.000 abstract description 12
- 238000004901 spalling Methods 0.000 abstract description 3
- 238000005260 corrosion Methods 0.000 abstract description 2
- 239000010410 layers Substances 0.000 abstract 1
- 238000009412 basement excavation Methods 0.000 description 5
- 238000000034 methods Methods 0.000 description 4
- 239000003570 air Substances 0.000 description 2
- 239000004570 mortar (masonry) Substances 0.000 description 2
- -1 anchor pole Substances 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 239000002131 composite materials Substances 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 238000010586 diagrams Methods 0.000 description 1
- 238000005516 engineering processes Methods 0.000 description 1
- 238000004642 transportation engineering Methods 0.000 description 1
Abstract
Description
Technical field
The utility model relates to a kind of tunnel support structure, relates in particular to a kind of corrugated steel to be applied in to supporting and protection structure in construction of tunnel.
Background technology
Geostatic stress refers to the inherent strain of rock mass under native state, when tunnel longitudinally passes geostatic stress weak surrounding rock stratum, if the uniaxial compressive strength of country rock (Rb) and major principal stress (σ h, max) ratio is in 4~7 scope time, for high-ground stress, ratio is less than at 4 o'clock, is stress highly.Constructing tunnel is section construction, is about to whole piece tunnel and is divided into multistage tunnel and excavates successively construction.Particularly, first according to the actual conditions of rock mass, determine longitudinal tap length in first paragraph tunnel, excavate this section of tunnel, and in tunnel, implement supporting, after completing, from the end in first paragraph tunnel, continue longitudinally to excavate second segment tunnel, in second segment tunnel, implement supporting, so circulation, until complete the supporting in final stage tunnel, has just completed a complete tunnel support.The effect of tunnel support is to form a tunnel structure system that has safe enough degree with country rock, can bear the various loads that may occur, the use headroom that keeps tunnel cross-section, prevent the country rock deterioration of further caving in, the smooth surface of circulation of air is provided, thus after having excavated every section of tunnel, must carry out in time supporting, and only have the concrete geological conditions of support process and this rock stratum, place to adapt, just can play good resistance to deformation, anti-effect of caving in.
Tunnel support is divided into advance support, preliminary bracing and secondary lining supporting.The general composite support being formed by preliminary bracing and secondary lining supporting that adopts of soft surrounding rock tunnel.Preliminary bracing in existing support process is that direct closely connected tunnel surface is set up rigidity preliminary bracing mostly, specifically adopt sprayed mortar, anchor pole, steel arch frame etc. fits tightly with country rock, constraint surrouding rock deformation, but at this kind of supporting and protection structure high stress in casing outside tunnel passage, often cause concrete cracking, peel off and arch form steelframe torsional deformation, so that the space of secondary lining has been occupied in the distortion of initial support, cause secondary lining to implement, therefore have to remove preliminary bracing supporting again, engineering cost and risk are significantly increased.
Utility model content
Utility model object: the purpose of this utility model is to provide a kind of concrete spalling that can avoid preliminary bracing and corrugated steel tunnel support structure distortion, that possess plasticity, can flexible assembling.
Technical scheme: a kind of corrugated steel tunnel support structure described in the utility model, fixing one deck corrugated steel on the surface of tunnel inner wall, and between tunnel inner wall and corrugated steel fill concrete.
Wherein, described corrugated steel is assembled connection, between adjacent steel plate, is bolted.Described bolt is high-strength bolt.The waveform of described corrugated steel is continuous sine bellows.Described concrete is slightly expanded concrete.
Beneficial effect: the utility model compared with prior art, its advantage be this supporting and protection structure high strength, corrosion-resistant, can assemble on request, easy construction etc.; Corrugated steel and concrete and tunnel surrounding interact, and form tunnel safety structural system; Corrugated steel itself is a kind of flexible structure simultaneously, deform in same pace when surrouding rock deformation, makes the high-ground stress in country rock obtain release, avoids the high-ground stress of country rock to cause concrete spalling, the distortion of preliminary bracing, cause secondary lining space to be occupied, guarantee carrying out smoothly of constructing tunnel; Because preliminary bracing can be not destroyed, can in tunnel, assemble corrugated steel and supporting and protection structure is installed, and corrugated steel is lightweight, be easy to transportation, be conducive to improve safety for tunnel engineering and the efficiency in area, high-ground stress rock stratum, reduce construction cost and construction risk.
Accompanying drawing explanation
Fig. 1 is tunnel cross-section schematic diagram;
Fig. 2 is the A-A sectional view of Fig. 1;
Fig. 3 is the schematic cross-section of corrugated steel;
Fig. 4 is the B-B sectional view of Fig. 3.
The specific embodiment
Before tunnel construction engineering construction, the key step of clear and definite engineering construction in schematic design, comprising determining the division of tunnel passage, shape and the size of excavation contour line.When constructing tunnel, first dig out one section of both measured length and meet the passage of design section size, in the assembled corrugated steel supporting of channel interior, as shown in Figure 3,4 according to construction drawing requirement, in factory, process in advance the burst of the corrugated steel 2 that meets tunnel cross-section size, then be transported in passage and assemble, adjacent steel plate connects with high-strength bolt 4.Gap air placed concrete 3 between corrugated steel supporting and tunneling inwall 1, fits tightly at tunnel excavation face, as shown in Figure 1, 2 the outside of corrugated steel.And then based on this section of tunnel, carry out excavation and the supporting in next section of tunnel, also can excavation and supporting synchronously be carried out during to certain length at tunnel excavation, to improve safety index in efficiency of construction and tunnel.Corrugated steel 2 can be done at different length place according to different geostatic stress and cut off process, and makes supporting and protection structure produce minimum distortion under the condition of stress differently.Corrugated steel supporting and protection structure is a kind of flexible structure, and it allows corrugated steel section to produce certain distortion, and does not affect the function of corrugated steel supporting and protection structure.Also can, first at tunnel surface sprayed mortar, corrugated steel supporting and protection structure be installed after concrete coagulation.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320390316.7U CN203452799U (en) | 2013-07-02 | 2013-07-02 | Corrugated steel tunnel supporting structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320390316.7U CN203452799U (en) | 2013-07-02 | 2013-07-02 | Corrugated steel tunnel supporting structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203452799U true CN203452799U (en) | 2014-02-26 |
Family
ID=50132683
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320390316.7U CN203452799U (en) | 2013-07-02 | 2013-07-02 | Corrugated steel tunnel supporting structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203452799U (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103908893A (en) * | 2014-04-18 | 2014-07-09 | 王驷壮 | Method for purifying air inside tunnel |
CN104389612A (en) * | 2014-11-21 | 2015-03-04 | 中南大学 | Treatment method for tunnel local collapse |
CN104775832A (en) * | 2015-04-21 | 2015-07-15 | 云南公投建设集团有限公司 | Primary support structure of corrugated steel tunnel |
CN104863614A (en) * | 2015-05-15 | 2015-08-26 | 河北腾是达金属结构有限公司 | Method for primary support with corrugated steel plate and concrete combined structure taking place of steel grating |
CN106593466A (en) * | 2017-01-19 | 2017-04-26 | 兰州交通大学 | Method for reinforcing fractured lining of existing railway tunnel |
CN106894830A (en) * | 2017-03-21 | 2017-06-27 | 西南交通大学 | A kind of double curvature arch supporting construction and construction method for underground engineering |
CN108397215A (en) * | 2018-04-11 | 2018-08-14 | 云南公建科技有限公司 | A kind of tunnel assembled corrugated steel preliminary bracing structure and its installation method |
CN110593890A (en) * | 2019-08-16 | 2019-12-20 | 同济大学 | Tunnel corrugated steel double-layer primary lining supporting method and structure |
-
2013
- 2013-07-02 CN CN201320390316.7U patent/CN203452799U/en active IP Right Grant
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103908893A (en) * | 2014-04-18 | 2014-07-09 | 王驷壮 | Method for purifying air inside tunnel |
CN104389612A (en) * | 2014-11-21 | 2015-03-04 | 中南大学 | Treatment method for tunnel local collapse |
CN104775832A (en) * | 2015-04-21 | 2015-07-15 | 云南公投建设集团有限公司 | Primary support structure of corrugated steel tunnel |
CN104863614A (en) * | 2015-05-15 | 2015-08-26 | 河北腾是达金属结构有限公司 | Method for primary support with corrugated steel plate and concrete combined structure taking place of steel grating |
CN104863614B (en) * | 2015-05-15 | 2017-02-01 | 河北腾是达金属结构有限公司 | Method for primary support with corrugated steel plate and concrete combined structure taking place of steel grating |
CN106593466A (en) * | 2017-01-19 | 2017-04-26 | 兰州交通大学 | Method for reinforcing fractured lining of existing railway tunnel |
CN106593466B (en) * | 2017-01-19 | 2019-11-19 | 兰州交通大学 | A method of reinforcing the rhegma lining cutting of Existing Railway Line tunnel |
CN106894830A (en) * | 2017-03-21 | 2017-06-27 | 西南交通大学 | A kind of double curvature arch supporting construction and construction method for underground engineering |
CN106894830B (en) * | 2017-03-21 | 2019-10-18 | 西南交通大学 | A kind of double curvature arch supporting construction and construction method for underground engineering |
CN108397215A (en) * | 2018-04-11 | 2018-08-14 | 云南公建科技有限公司 | A kind of tunnel assembled corrugated steel preliminary bracing structure and its installation method |
CN110593890A (en) * | 2019-08-16 | 2019-12-20 | 同济大学 | Tunnel corrugated steel double-layer primary lining supporting method and structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104847374B (en) | Large-deformation tunnel in soft rock support system and its construction method | |
CN103527219B (en) | For the construction of the tunnel support structure on large deformation stratum | |
CN104863614B (en) | Method for primary support with corrugated steel plate and concrete combined structure taking place of steel grating | |
CN204691789U (en) | A kind of adjustable tunnel support structure | |
CN101985882B (en) | Construction method of rigid primary support of mould-building concrete of plateau permafrost tunnel | |
CN102996133B (en) | Construction method applicable to intersection between inclined shaft and slant hole of weak surrounding rock tunnel | |
CN101603336B (en) | Precast concrete short-pier shear wall with infilling wall panel and connecting method thereof | |
CN103912011B (en) | The prefabricated assembled underground structure of open cut | |
CN102587922B (en) | Oblique-crossing inclined shaft upper arc guide top brushing construction method for soft crushed rock layer | |
CN104612698A (en) | Method for constructing upper step middle partition wall of shallow-buried excavation tunnel | |
CN102953739A (en) | Bidirectional punching method for underground excavation of subway station | |
CN101967984A (en) | Deep well tunnel cable anchor rigid-flexible coupling support and surrounding rock overall reinforced support method | |
CN106761810A (en) | A kind of large-deformation tunnel in soft rock supporting structure system and its construction method | |
CN102937030B (en) | Bolting-grouting integrated support method for zonal disintegration of deep roadway surrounding rock | |
CN104878948B (en) | A kind of reinforcement means of rc-frame-beam hogging moment area | |
CN201771517U (en) | Tunnel support structure | |
CN204780994U (en) | Underground continuous wall inwall construction structures | |
CN2878511Y (en) | Tensile compression combined self-anchored rock anchor rod | |
CN107605489B (en) | Three line Large span tunnel inclined shafts are into positive cavity construction method | |
CN101196118A (en) | Advanced double rows slip casting ductule construction technique | |
CN104612696B (en) | Overpass column hole method construction method is passed through in big cross section tunneling subway station in fine sand layer | |
CN101429869B (en) | Double-bending tunnel | |
CN106884655B (en) | A kind of two-way reinforcement means of gob side entry driving coal column | |
CN101614125A (en) | V level surrounding rock tunnel job practices | |
RU2510444C2 (en) | Three-arched underground station of column type and its erection methods (yurkevich device and methods) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
C14 | Grant of patent or utility model |