CN203452227U - Combined shear wall - Google Patents

Combined shear wall Download PDF

Info

Publication number
CN203452227U
CN203452227U CN201320561508.XU CN201320561508U CN203452227U CN 203452227 U CN203452227 U CN 203452227U CN 201320561508 U CN201320561508 U CN 201320561508U CN 203452227 U CN203452227 U CN 203452227U
Authority
CN
China
Prior art keywords
shear wall
double
layer metal
metal plate
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320561508.XU
Other languages
Chinese (zh)
Inventor
蔡健
段伟宁
杨春
陈庆军
姜正荣
左志亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
South China University of Technology
Original Assignee
South China University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by South China University of Technology filed Critical South China University of Technology
Priority to CN201320561508.XU priority Critical patent/CN203452227U/en
Application granted granted Critical
Publication of CN203452227U publication Critical patent/CN203452227U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

本实用新型提供一种组合剪力墙,包括平行设置的双层金属板,双层金属板间形成中空夹层,中空夹层中均匀设置内填混凝土的钢管,钢管与双层金属板固定连接,双层金属板的顶部设置顶梁,顶梁固定钢管的顶端。本实用新型的组合剪力墙,施工过程中不需要支模,施工工艺简单、自重小且抗震性能好。

Figure 201320561508

The utility model provides a combined shear wall, which comprises double-layer metal plates arranged in parallel, a hollow interlayer is formed between the double-layer metal plates, steel pipes filled with concrete are uniformly arranged in the hollow interlayer, and the steel pipes are fixedly connected with the double-layer metal plates. A top beam is arranged on the top of the layer metal plate, and the top beam fixes the top of the steel pipe. The combined shear wall of the utility model does not need formwork during construction, has simple construction technology, small dead weight and good seismic performance.

Figure 201320561508

Description

一种组合剪力墙A composite shear wall

技术领域technical field

本实用新型涉及一种建筑结构,具体涉及一种组合剪力墙。The utility model relates to a building structure, in particular to a combined shear wall.

背景技术Background technique

剪力墙是高层和超高层建筑结构的重要受力构件,其抗震性能对于高层和超高层建筑的安全可靠起到至关重要的作用。伴随我国城市化进程的发展和深入,城市建筑的高度日益增长,超高层建筑的数量愈来愈多,由此对剪力墙抗震性能的要求也越来越高。Shear wall is an important force-bearing component of high-rise and super high-rise building structures, and its seismic performance plays a vital role in the safety and reliability of high-rise and super high-rise buildings. With the development and deepening of my country's urbanization process, the height of urban buildings is increasing day by day, and the number of super high-rise buildings is increasing. Therefore, the requirements for the seismic performance of shear walls are also getting higher and higher.

组合剪力墙通过钢筋混凝土和钢材的合理组合,充分发挥两种材料各自的性能,因而具有技术和经济上的优势。现有的组合剪力墙主要有两大类:Composite shear walls give full play to the respective properties of the two materials through the reasonable combination of reinforced concrete and steel, so they have technical and economic advantages. There are two main types of existing composite shear walls:

第一类:型钢组合剪力墙,其在钢筋混凝土墙体中布置型钢、钢管或冷弯薄壁型钢骨架,从而增加墙体的刚度和延性,但施工工艺复杂,且由于需要支模等工序,工期较长。The first type: section steel composite shear wall, which arranges section steel, steel pipe or cold-formed thin-walled section steel skeleton in the reinforced concrete wall, so as to increase the stiffness and ductility of the wall, but the construction process is complicated, and due to the need for formwork and other processes , the construction period is longer.

第二类:钢板组合剪力墙,包括在钢板的单侧或双侧布置钢筋混凝土墙体、在两片钢板中现浇混凝土墙体等构造形式,使得剪力墙在小震下具有足够的刚度,在大震中利用钢板耗能具有良好的抗震性能,但钢筋混凝土墙体在钢板外侧的形式仍需要支模,施工便利性较差;而内填混凝土墙体的形式虽具有诸多优点,但由于钢板对混凝土的约束仍然有限,且钢板容易发生平面外失稳,对材料性能发挥仍不充分,通常造价较高。The second type: steel plate composite shear wall, including the arrangement of reinforced concrete walls on one or both sides of the steel plate, and the cast-in-place concrete wall in two steel plates, so that the shear wall has sufficient strength under small earthquakes. Rigidity, using steel plates to dissipate energy in large earthquakes has good anti-seismic performance, but the form of reinforced concrete walls on the outside of steel plates still needs formwork, and the construction convenience is poor; while the form of filled concrete walls has many advantages, but Since the restraint of the steel plate on the concrete is still limited, and the steel plate is prone to out-of-plane instability, the performance of the material is still not fully exerted, and the cost is usually high.

此外,型钢组合剪力墙和钢板组合剪力墙还存在墙体自重大的不足,增加了结构在地震中的反应。In addition, the section steel composite shear wall and the steel plate composite shear wall also have insufficient self-weight of the wall, which increases the response of the structure in earthquakes.

实用新型内容Utility model content

本实用新型的目的在于克服现有技术存在的缺点与不足,提供一种施工时不需要支模的组合剪力墙,其施工工艺简单、自重小、对混凝土的约束强且抗震性能好。The purpose of the utility model is to overcome the shortcomings and deficiencies of the prior art, and provide a combined shear wall that does not require formwork during construction. The construction process is simple, the dead weight is small, the constraint on the concrete is strong, and the seismic performance is good.

本实用新型的目的通过下述技术方案实现:The purpose of this utility model is achieved through the following technical solutions:

一种组合剪力墙,包括平行设置的双层金属板,双层金属板间形成中空夹层,中空夹层中均匀设置内填混凝土的钢管,钢管与双层金属板固定连接,双层金属板的顶部设置顶梁,顶梁固定钢管的顶端。A combined shear wall, comprising double-layer metal plates arranged in parallel, a hollow interlayer is formed between the double-layer metal plates, steel pipes filled with concrete are evenly arranged in the hollow interlayer, the steel pipes are fixedly connected to the double-layer metal plates, and the double-layer metal plates A top beam is arranged on the top, and the top beam fixes the top of the steel pipe.

所述组合剪力墙还包括设置在双层金属板之间的加劲肋。加劲肋主要作用是作为双层金属板的弹性支撑,改善双侧金属板的屈曲形态,从而提高组合剪力墙墙体的侧向受力性能。The combined shear wall also includes stiffeners arranged between the double-layer metal plates. The main function of the stiffener is to act as the elastic support of the double-layer metal plate, improve the buckling shape of the metal plate on both sides, and thereby improve the lateral force performance of the composite shear wall.

所述加劲肋为多个,均匀设置在双层金属板间。多个均匀设置的加劲肋,在组合剪力墙墙体侧向受力时,对金属板提供均匀的弹性支撑,且在工厂预制时就将加劲肋与双层金属板焊接在一起,焊接时给均匀设置的钢管预留空间,在现场施工时直接将钢管直接吊装至预留空间中,施工较为便利。There are multiple stiffening ribs, which are evenly arranged between the double-layer metal plates. Multiple evenly arranged stiffeners provide uniform elastic support to the metal plate when the composite shear wall is subjected to lateral force, and the stiffeners and double-layer metal plates are welded together during factory prefabrication. Space is reserved for uniformly arranged steel pipes, and the steel pipes are directly hoisted into the reserved space during on-site construction, which is more convenient for construction.

所述组合剪力墙还包括设置在加劲肋与钢管之间的弹性件。弹性件可保证加劲肋和钢管间力的传递,有利于发挥墙体整体性能。The combined shear wall also includes an elastic member arranged between the stiffener and the steel pipe. The elastic part can ensure the force transmission between the stiffener and the steel pipe, which is beneficial to exert the overall performance of the wall.

本实用新型相对于现有技术具有如下的优点及效果:Compared with the prior art, the utility model has the following advantages and effects:

a、施工工艺简单:双层金属板在工厂预制时就已经焊接完毕,金属板之间形成的中空夹层预留有钢管的放置空间,在施工现场只需将钢管吊装至预定位置并与双层金属板固定,然后再将混凝土內填至钢管,整个过程工序少,且不需支模,施工工艺简单。a. The construction process is simple: the double-layer metal plates have been welded during prefabrication in the factory, and the hollow interlayer formed between the metal plates has reserved space for steel pipes. At the construction site, only the steel pipes need to be hoisted to the predetermined position and connected with the double-layer The metal plate is fixed, and then the concrete is filled into the steel pipe. The whole process has fewer procedures and does not require formwork, so the construction process is simple.

b、自重小:金属板与圆管之间的空间不再浇筑混凝土,而仅仅在钢管内填混凝土,且只设置单排钢管,在不影响其抗震性能的前提下,有效地减小了组合剪力墙的自重,克服了现有技术中由于墙体自重过大带来的问题;同时减少自重而使金属板与圆管之间中空,这部分竖向荷载由顶梁及其固定的钢管来承担,这样既减小了自重,又不会使组合剪力墙的性能受到影响。b. Small self-weight: the space between the metal plate and the round pipe is no longer poured with concrete, but only filled with concrete in the steel pipe, and only a single row of steel pipes is installed, which effectively reduces the combination without affecting its seismic performance. The self-weight of the shear wall overcomes the problems caused by the excessive self-weight of the wall in the prior art; at the same time, the self-weight is reduced to make the space between the metal plate and the round pipe hollow, and this part of the vertical load is carried by the top beam and its fixed steel pipe To bear, which not only reduces the weight, but also will not affect the performance of the composite shear wall.

c、对混凝土的约束力强:混凝土內填于钢管内部,利用钢管约束混凝土提高混凝土的强度和变形能力,有利于高强混凝土在剪力墙中的采用。c. Strong binding force on concrete: the concrete is filled inside the steel pipe, and the strength and deformation capacity of the concrete are improved by using the steel pipe to restrain the concrete, which is conducive to the adoption of high-strength concrete in the shear wall.

d、抗震性能好:由于组合剪力墙的墙体外部均为金属构件,其屈服强度较高,在正常使用阶段,所受的应力低于屈服强度,故整体处于弹性受力状态,而不会像钢筋混凝土那样产生裂缝,同时金属板直接与均匀设置的钢管固定连接成为一个整体,其侧向受力能力大大增强,且钢管内浇筑有混凝土,使钢管本身的刚度得到提高,充分发挥了组合材料的优势,抗震性能好。d. Good seismic performance: Since the exterior of the combined shear wall is made of metal components, its yield strength is relatively high. In normal use, the stress it receives is lower than the yield strength, so the whole is in a state of elastic stress, not It will produce cracks like reinforced concrete. At the same time, the metal plate is directly fixed and connected with the uniformly arranged steel pipes to form a whole. Combining the advantages of materials, the seismic performance is good.

附图说明Description of drawings

图1为本实用新型一种组合剪力墙立体示意图;Fig. 1 is a three-dimensional schematic diagram of a composite shear wall of the present invention;

图2为本实用新型一种组合剪力墙正面示意图;Fig. 2 is a front schematic view of a composite shear wall of the present invention;

图3为图2的沿A-A剖面图;Fig. 3 is a sectional view along A-A of Fig. 2;

图4为图2的沿B-B剖面图;Fig. 4 is a sectional view along B-B of Fig. 2;

图5为图3的沿C-C剖面图。Fig. 5 is a sectional view along C-C of Fig. 3 .

具体实施方式Detailed ways

如图1、2、3、4、5,一种组合剪力墙,包括平行设置的双层金属板11、12,双层金属板11、12之间均匀设置多个加劲肋2,加劲肋2与钢管之间设置弹性件,如橡胶垫圈、弹簧,双层金属板11、12间形成中空夹层3,中空夹层3中均匀设置内填混凝土的单排钢管4,钢管4与双层金属板11、12通过焊接来固定连接,焊接后形成焊缝5,双层金属板11、12的顶部设置顶梁6,顶部顶梁6固定钢管3的顶端,顶梁6与双层金属板11、12通过焊接来固定连接,形成焊缝7,钢管3的底端固定在下层同样的组合剪力墙的顶梁6中,由此可知组合剪力墙可以根据实际需要自由地组合,施工便利性好。As shown in Figures 1, 2, 3, 4, and 5, a combined shear wall includes double-layer metal plates 11, 12 arranged in parallel, and a plurality of stiffeners 2 are uniformly arranged between the double-layer metal plates 11, 12, and the stiffeners 2 Elastic parts are arranged between the steel pipes, such as rubber washers and springs, and a hollow interlayer 3 is formed between the double-layer metal plates 11 and 12. A single-row steel pipe 4 filled with concrete is evenly arranged in the hollow interlayer 3. The steel pipe 4 and the double-layer metal plate 11,12 are fixedly connected by welding, after welding, weld seam 5 is formed, top beam 6 is arranged on the top of double-layer metal plate 11,12, top beam 6 fixes the top of steel pipe 3, top beam 6 and double-layer metal plate 11, 12 The connection is fixed by welding to form a weld 7, and the bottom end of the steel pipe 3 is fixed in the top beam 6 of the same composite shear wall on the lower floor. From this, it can be seen that the composite shear wall can be freely combined according to actual needs, and the construction is convenient. good.

除上述实施方式中在中空夹层3中均匀设置内填混凝土的单排钢管4外,还可以均匀设置两排、三排甚至多排钢管,与双层金属板相邻的钢管与双层金属板固定连接,其他钢管与相邻的钢管固定连接。In addition to the single row of concrete-filled steel pipes 4 uniformly arranged in the hollow interlayer 3 in the above-mentioned embodiment, two, three or even multiple rows of steel pipes can also be evenly arranged, and the steel pipes adjacent to the double-layer metal plate and the double-layer metal plate Fixed connection, other steel pipes are fixedly connected with adjacent steel pipes.

上述实施例为本实用新型较佳的实施方式,但本实用新型的实施方式并不受上述实施例的限制,其他的任何未背离本实用新型的精神实质与原理下所作的改变、修饰、替代、组合、简化,均应为等效的置换方式,都包含在本实用新型的保护范围之内。The above-mentioned embodiment is a preferred implementation mode of the present utility model, but the implementation mode of the present utility model is not limited by the above-mentioned embodiment, and any other changes, modifications and substitutions made without departing from the spirit and principle of the present utility model , combination, and simplification, all should be equivalent replacement methods, and are all included in the protection scope of the present utility model.

Claims (4)

1. a compound shear wall, it is characterized in that: comprise the double-level-metal plate be arrangeding in parallel, between double-level-metal plate, form hollow sandwich, the steel pipe of concrete filled is evenly set in hollow sandwich, steel pipe is fixedly connected with double-level-metal plate, the top of double-level-metal plate arranges back timber, and back timber is the top of steel pipe fixedly.
2. compound shear wall according to claim 1, is characterized in that: described compound shear wall also comprises the stiffening rib being arranged between double-level-metal plate.
3. compound shear wall according to claim 2, is characterized in that: described stiffening rib is a plurality of, is evenly arranged between double-level-metal plate.
4. compound shear wall according to claim 2, is characterized in that: described compound shear wall also comprises the elastic component being arranged between stiffening rib and steel pipe.
CN201320561508.XU 2013-09-10 2013-09-10 Combined shear wall Expired - Fee Related CN203452227U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320561508.XU CN203452227U (en) 2013-09-10 2013-09-10 Combined shear wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320561508.XU CN203452227U (en) 2013-09-10 2013-09-10 Combined shear wall

Publications (1)

Publication Number Publication Date
CN203452227U true CN203452227U (en) 2014-02-26

Family

ID=50132116

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320561508.XU Expired - Fee Related CN203452227U (en) 2013-09-10 2013-09-10 Combined shear wall

Country Status (1)

Country Link
CN (1) CN203452227U (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485441A (en) * 2013-09-10 2014-01-01 华南理工大学 Combined shearing wall
CN104775578A (en) * 2015-02-10 2015-07-15 湖北弘毅建设有限公司 Prefabricated metal finish concrete outer wall plate
CN105863107A (en) * 2016-04-05 2016-08-17 天津城建大学 Sandwich-pipe low-yield-point steel plate shear wall and manufacturing method
CN107419846A (en) * 2017-08-28 2017-12-01 河南永威教育发展有限公司 A kind of galvanized steel plain sheet assembled heat-insulation wall material
CN108678218A (en) * 2018-05-15 2018-10-19 孟凡林 Assembly concrete shear wall and its method of construction based on multipurpose thin-wall steel tube
CN109339292A (en) * 2018-11-22 2019-02-15 尹雄 A kind of steel composite double steel plate concrete composite shear wall
CN110748042A (en) * 2019-10-24 2020-02-04 中国十七冶集团有限公司 Sound insulation type steel plate concrete shear wall for high-rise building
CN111042373A (en) * 2019-12-16 2020-04-21 张效思 Assembled concrete-filled steel tube-wood composite wall for building and manufacturing method thereof
CN111206700A (en) * 2020-03-12 2020-05-29 中国矿业大学 Concrete-filled steel tube shear wall with concrete wrapped on side surface
CN114753524A (en) * 2022-04-14 2022-07-15 北京工业大学 Built-in densely-distributed column type double-layer corrugated steel plate composite shear wall
CN114922318A (en) * 2022-04-14 2022-08-19 北京工业大学 Built-in densely-distributed column type double-steel-plate shear wall

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485441A (en) * 2013-09-10 2014-01-01 华南理工大学 Combined shearing wall
CN104775578A (en) * 2015-02-10 2015-07-15 湖北弘毅建设有限公司 Prefabricated metal finish concrete outer wall plate
CN105863107A (en) * 2016-04-05 2016-08-17 天津城建大学 Sandwich-pipe low-yield-point steel plate shear wall and manufacturing method
CN107419846A (en) * 2017-08-28 2017-12-01 河南永威教育发展有限公司 A kind of galvanized steel plain sheet assembled heat-insulation wall material
CN107419846B (en) * 2017-08-28 2023-01-03 河南永威安防股份有限公司 Galvanized steel sheet assembled heat insulation wall material
CN108678218A (en) * 2018-05-15 2018-10-19 孟凡林 Assembly concrete shear wall and its method of construction based on multipurpose thin-wall steel tube
CN109339292A (en) * 2018-11-22 2019-02-15 尹雄 A kind of steel composite double steel plate concrete composite shear wall
CN110748042A (en) * 2019-10-24 2020-02-04 中国十七冶集团有限公司 Sound insulation type steel plate concrete shear wall for high-rise building
CN111042373A (en) * 2019-12-16 2020-04-21 张效思 Assembled concrete-filled steel tube-wood composite wall for building and manufacturing method thereof
CN111206700A (en) * 2020-03-12 2020-05-29 中国矿业大学 Concrete-filled steel tube shear wall with concrete wrapped on side surface
CN114753524A (en) * 2022-04-14 2022-07-15 北京工业大学 Built-in densely-distributed column type double-layer corrugated steel plate composite shear wall
CN114922318A (en) * 2022-04-14 2022-08-19 北京工业大学 Built-in densely-distributed column type double-steel-plate shear wall

Similar Documents

Publication Publication Date Title
CN101761154B (en) Shear wall with inbuilt continuous-row steel tube concrete core column and soft steel energy consumption bond and manufacturing method thereof
CN103485441A (en) Combined shearing wall
CN202124961U (en) Profile steel concrete shear wall
CN102444224A (en) Concrete Composite Shear Wall
CN205653923U (en) Novel big board shear wall structure is secretly supported in prefabricated assembled area of connecting from top to bottom
CN105544801A (en) Bolted connection technique for prefabricated large plate shear wall provided with concealed bracing and construction method
CN205954921U (en) Novel big board shear wall structure is secretly supported in bolted connection's prefabricated assembled area
CN204715576U (en) A kind of antidetonation can repair Self-resetting framework-Mi rib metal wall structure
CN202298983U (en) Concrete composite shear wall
CN203808295U (en) Concrete-filled steel tube and double steel plate outer wrapped concrete combined shear wall
CN102704593A (en) Steel tube reinforced concrete composite column-steel beam-lattice steel support shear wall and manufacturing method
CN102409783A (en) The steel plate shear wall and its method with built-in steel plate shear wall in double overlapping steel concrete frame at the bottom
CN103485443A (en) Window-shaped-steel-plate concrete shear wall and manufacturing method thereof
CN107246085A (en) Built-in soap-free emulsion polymeization steel plate concealed bracings prestressing force automatic reset concrete shear wall
CN103953134B (en) Shear wall with energy-consuming strips embedded between border and built-in steel plates and steel braces, and making method
CN203782979U (en) FRP stiffening concrete filled steel tube composite column
CN103711231A (en) Combined shear wall formed by steel pipe concrete frame, double-steel-plate shear wall and inside welded concealed bracing mild steel plates under equivalent steel
CN203403358U (en) Latticed bridge tower of concrete filled steel pipe
CN201358528Y (en) Steel-truss-steel-plate combination shear wall
CN102704596A (en) Combined shear wall with concrete wrapped steel plate dense beam embedded between profile steel overlapped columns and externally wrapping concrete and manufacturing method
CN102561552A (en) Steel tube concrete shear wall comprising vertical soft steel energy consuming straps with horizontal seams and manufacturing method
CN102704597A (en) Encased concrete composite shear wall embedded with dense steel plate beams between concrete-filled steel tube columns and construction method thereof
CN103883032A (en) I-shaped steel plate shear wall with built-in round steel reinforcement cages and externally-attached steel plate supports and manufacturing method
CN205557906U (en) Steel pipe concrete frame post - steel sheet shear force wall body system
CN201358529Y (en) Steel-truss-steel-plate-concrete combination shear wall

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140226

Termination date: 20170910

CF01 Termination of patent right due to non-payment of annual fee