CN203361179U - Column pile and high-voltage power line tower base comprising column piles - Google Patents
Column pile and high-voltage power line tower base comprising column piles Download PDFInfo
- Publication number
- CN203361179U CN203361179U CN 201320293422 CN201320293422U CN203361179U CN 203361179 U CN203361179 U CN 203361179U CN 201320293422 CN201320293422 CN 201320293422 CN 201320293422 U CN201320293422 U CN 201320293422U CN 203361179 U CN203361179 U CN 203361179U
- Authority
- CN
- China
- Prior art keywords
- pillar
- motion bar
- actuator
- stanchion
- main body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
- 230000005484 gravity Effects 0.000 claims abstract description 8
- 230000009471 action Effects 0.000 claims abstract description 7
- 230000033001 locomotion Effects 0.000 claims description 52
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims description 41
- 230000005540 biological transmission Effects 0.000 claims description 25
- 230000005611 electricity Effects 0.000 claims description 25
- 239000004575 stone Substances 0.000 claims description 8
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 238000004519 manufacturing process Methods 0.000 abstract description 3
- 230000000087 stabilizing effect Effects 0.000 abstract 4
- 238000005728 strengthening Methods 0.000 abstract 4
- 238000009434 installation Methods 0.000 description 6
- 230000000694 effects Effects 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 3
- 238000013461 design Methods 0.000 description 2
- 238000011161 development Methods 0.000 description 2
- 238000011900 installation process Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 230000001737 promoting effect Effects 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 230000001960 triggered effect Effects 0.000 description 2
- 239000002699 waste material Substances 0.000 description 2
- TVEXGJYMHHTVKP-UHFFFAOYSA-N 6-oxabicyclo[3.2.1]oct-3-en-7-one Chemical compound C1C2C(=O)OC1C=CC2 TVEXGJYMHHTVKP-UHFFFAOYSA-N 0.000 description 1
- 229910052799 carbon Inorganic materials 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 230000005012 migration Effects 0.000 description 1
- 238000013508 migration Methods 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 231100000241 scar Toxicity 0.000 description 1
Images
Landscapes
- Revetment (AREA)
Abstract
The utility model discloses a column pile and a high-voltage power line tower base comprising column piles. The base comprises the column piles and a connecting plate which is used for being connected with a main body of a high-voltage power line tower. The main body of each column pile is a strut, wherein a base stabilizing and strengthening device is arranged inside the strut, extends out of the outer side of the strut under the action of gravity of the main body of the high-voltage power line tower, and can tightly abut against a hillstone wall on the outer side of the strut, and the base stabilizing and strengthening device can automatically retract into the strut after the main body of the high-voltage power line tower is removed. Compared with the prior art, the base is formed by connecting the multiple column piles and the connecting plate, and the base stabilizing and strengthening devices are arranged on all the column piles to ensure that the whole base has sufficient supporting force; besides, the base stabilizing and strengthening devices can automatically return to an initial state after the main body of the high-voltage power line tower is removed, and therefore the base can be taken out conveniently; moreover, the mounting base is simple in overall structure, low in manufacturing cost and capable of being utilized repeatedly, thereby saving resources and causing no harm to the environment.
Description
Technical field
The utility model relates to the technical field of high-tension electricity transmission tower, and specifically, the utility model relates to a kind of stanchion and adopts the power line column foot seat of this stanchion.
Background technology
At present, when the high-tension electricity transmission tower is arranged on high mountain, in order to build a power line column foot seat, usually need to first repair the roads, cut into a mountain and blow out again, and then dig out a hole on the stone of mountain, then in hole, with the mixed earth of reinforcing bar, pour into a mould to build such pedestal, build a pedestal spent time and reach the several months, expense is also very large in addition.Once but the high-tension electricity transmission tower needs migration or removes, the pedestal that adopts the mixed earth cast of reinforcing bar to form exists the problem of removing that is not easy, need the larger financial resources of cost and manpower to remove, if do not remove, base part can become again the waste product of contaminated environment.
Along with socioeconomic development, not only require people to cross the low-carbon (LC) life, more require in each enterprise production process, strive accomplishing energy-saving and environmental protection and efficient.Not only efficiency is low for the construction of existing power line column foot seat and dismounting, also environment is produced to certain pollution, and the waste resource, can not adapt to the modern Economy Development requirement simultaneously.
The utility model content
Technical problem to be solved in the utility model is to provide a kind of stanchion of power line column foot seat, and the pedestal that this stanchion forms is made simply, installation and removal are easy.
In order to solve the problems of the technologies described above, the technical scheme that the utility model adopts is: a kind of stanchion, for being arranged on the pedestal of high-tension electricity transmission tower, the main body of described stanchion be one for inserting the pillar of the pedestal installing hole excavated on stone surface, mountain, be provided with the pedestal stretched out towards the pillar outside under the Action of Gravity Field in the main body of high-tension electricity transmission tower and can be pushed against the mountain cliff face in the pillar outside in the inside of pillar and stablize stiffening device, this pedestal is stablized stiffening device and automatically be contracted to pillar inside after the main body of high-tension electricity transmission tower is removed.
Described pillar is columniform steel pipe, pillar is divided into epimere and hypomere, the epimere of pillar is socketed in the top of hypomere in bottom, described pedestal is stablized stiffening device and is comprised many motion bars in the hypomere that laterally is located at pillar, is located at actuator and the return unit for resetting for driving motion bar laterally to stretch out towards the outside of pillar in the epimere of pillar, and on actuator, has and the contacted drive surface of motion bar.
The epimere of described pillar is fixedly installed in the inner bottom part position and is useful on the mounting blocks that described actuator is installed.
Be fixedly installed and be useful on the back-up block that described motion bar is installed in the inside of the hypomere of described pillar, on back-up block, be provided with the centre bore that allows described actuator insert and along horizontally set for laying the pilot hole of motion bar, the drive surface of actuator contacts in centre bore with motion bar, and pilot hole also extends to the outer circumference surface of the hypomere of pillar always.
Be connected with lead between described mounting blocks and described back-up block, an end of lead is fixed on mounting blocks, and the other end passes back-up block, and is provided with limited block at this end, and this limited block can be mounted in the nut on lead.
Described actuator is cone, and the drive surface of actuator is taper seat.
Described actuator and described mounting blocks are formed in one.
The head for pushing against stone surface, mountain of described motion bar is taper.
Described return unit comprises actuator back-moving spring and motion bar back-moving spring, the actuator back-moving spring is located between described mounting blocks and described back-up block, the motion bar back-moving spring is enclosed within on described motion bar, motion bar back-moving spring one end is against on the inwall of described back-up block, and the other end is against on the flange arranged on motion bar.
Described motion bar circumferentially evenly is provided with four along pillar on described pillar.
Another technical problem to be solved in the utility model is to provide that a kind of making is simple, installation and removal are easy to power line column foot seat.
In order to solve the problems of the technologies described above, the technical scheme that the utility model adopts is: a kind of power line column foot seat, comprise the junction plate that above-mentioned stanchion is connected with main body for the high-tension electricity transmission tower, and many stanchions vertically are installed on this junction plate.
The utility model adopts technique scheme, compared with prior art, this pedestal adopts many stanchions and junction plate to connect and compose, on each stanchion, pedestal is set and stablizes stiffening device, this device can be triggered under the Action of Gravity Field of high-tension electricity transmission tower main body, strengthened the stability of single stanchion, thereby strengthened the stability of whole pedestal, guarantee that whole pedestal has enough support forces, this device can automatically restore to original state after high-tension electricity transmission tower main body removes in addition, thereby can take out easily pedestal, and this installation pedestal overall structure is simple, cost of manufacture is low, can also reuse, saving resource, environment is not worked the mischief again.
The accompanying drawing explanation
The structural representation that Fig. 1 is pedestal;
The structural representation that Fig. 2 is stanchion;
The structural representation that Fig. 3 is motion bar;
The structural representation that Fig. 4 is back-up block;
The structural representation of the hypomere of the pillar that Fig. 5 is stanchion;
The top view that Fig. 6 is Fig. 5;
The structural representation of the actuator of the upper intersegmental part that Fig. 7 is pillar;
Mark in above-mentioned figure is: 1, junction plate; 2, pillar; 3, epimere; 4, hypomere; 5, motion bar; 6, flange; 7, motion bar back-moving spring; 8, back-up block; 9, pilot hole; 10, centre bore; 11, mounting blocks; 12, actuator; 13, connecting bolt.
The specific embodiment
Be illustrated in figure 1 a kind of power line column foot seat of the present utility model, it comprise the junction plate 1 be connected for the main body with the high-tension electricity transmission tower and vertically be arranged on junction plate 1 for inserting many stanchions of the pedestal installing hole excavated on stone surface, mountain, stanchion is fixedly connected with junction plate 1 at top, and stanchion forms the stable support part of pedestal bottom.
As shown in Figure 2, the main body of stanchion be one for inserting the pillar 2 of the pedestal installing hole excavated on stone surface, mountain, be provided with under the Action of Gravity Field in the main body of high-tension electricity transmission tower and pedestal that can be pushed against the installing hole wall in pillar 2 outsides that stretch out towards the pillar outside in the inside of pillar 2 and stablize stiffening device, this pedestal is stablized stiffening device and automatically be contracted to pillar inside after the main body of high-tension electricity transmission tower is removed.
This pedestal is stablized stiffening device by each stanchion, pedestal being set; this device can be triggered under the Action of Gravity Field of high-tension electricity transmission tower main body; can strengthen the stability of single stanchion; thereby strengthened the stability of whole pedestal; guarantee that whole pedestal has enough support forces; this device can automatically restore to original state after high-tension electricity transmission tower main body removes in addition, thereby can take out easily pedestal, guarantees that pedestal is installed, convenient disassembly.
As shown in Figure 1, junction plate 1 is a block plate, is installed with four pillars 2 in the present embodiment on junction plate 1, and the rectangular distribution of pillar 2 is installed with four connecting bolts 13 on the end face of junction plate 1, for the main body with the high-tension electricity transmission tower, is connected.It can be 3 to 8 that the base of the integral body of high-tension electricity transmission tower can comprise such mounting base.In addition, the pillar 2 on junction plate 1 and the number of connecting bolt 13 can be set as required, in the actual installation process, as long as can guarantee that the junction plate 1 of each mounting base all just can start the installation high-voltage electric wire tower in same horizontal plane.
As depicted in figs. 1 and 2, pillar 2 is columniform steel pipe, pillar 2 is divided into epimere 3 and hypomere 4, the epimere 3 of pillar 2 is socketed in the top of hypomere 4 in bottom, the epimere 3 of pillar 2 can be moved downwards by the outer circumference surface along hypomere 4 under the Action of Gravity Field of the main body of high-tension electricity transmission tower, epimere 3 is identical with the internal-and external diameter of hypomere 4, on the outer circumference surface of locating at the top of hypomere 4, has limited step.Pedestal is stablized stiffening device and is comprised many motion bars 5 in the hypomere 4 that laterally is located at pillar 2, is located at actuator 12 and the return unit for resetting for driving motion bar 5 laterally to stretch out towards the outside of pillar 2 in the epimere 3 of pillar 2, and on actuator 12, has and the contacted drive surface of motion bar 5.Be fixedly installed at the bottom position place and be useful on the mounting blocks 11 that actuator 12 is installed in the inside of the epimere 3 of pillar 2, as shown in Figure 7, actuator 12 is cone, the drive surface of actuator 12 is taper seat, actuator 12 is arranged on the bottom surface of mounting blocks 11, mounting blocks 11 is cylindrical, and mounting blocks 11 is arranged on the epimere 3 of pillar 2 by bolt, on the outer circumference surface of mounting blocks 11, is provided with screwed hole.Actuator 12 can be formed in one with mounting blocks 11, forms an integral body.As shown in Figure 5 and Figure 6, be fixedly installed and be useful on the back-up block 8 that motion bar 5 is installed in the inside of the hypomere 4 of pillar 2, four motion bars 5 are installed in back-up block 8, motion bar 5 circumferentially is uniformly distributed along back-up block 8, for fixing more firm, further strengthen the stability of pedestal, can increase the number of motion bar 5.As shown in Figure 4, back-up block 8 is cylindrical, be provided with the centre bore 10 that allows actuator 12 insert and along the pilot hole 9 for laying motion bar 5 of horizontally set on back-up block 8, the drive surface of actuator 12 contacts in centre bore 10 with motion bar 5, pilot hole 9 also extends to the outer circumference surface of the hypomere 4 of pillar 2 always, as shown in Figure 5, there is the circular hole be communicated with the pilot hole 9 of back-up block 8 on the outer circumference surface of the hypomere 4 of pillar 2.In addition, be connected with lead between mounting blocks 11 and back-up block 8, one end of lead is fixed on mounting blocks 11, the other end is through back-up block 8, and be provided with limited block at this end, can put at the end of lead a nut uses as limited block, lead guides the movement of the epimere 3 of mounting blocks 11 and pillar 2, and limited block can also prevent that pillar 2 is when resetting, the epimere 3 of pillar 2 exceeds stroke, prevent that pillar 2 epimeres 3 and hypomere 4 break away from, that is to say, lead has also played the effect of epimere 3 and the hypomere 4 of connecting struts 2 simultaneously.As shown in Fig. 4 and Fig. 7, longitudinally all be provided with the hole that allows lead pass on back-up block 8 and mounting blocks 11.
The return unit that pedestal is stablized stiffening device comprises actuator back-moving spring and motion bar back-moving spring 7, the actuator back-moving spring is resetted for promoting actuator 12, longitudinally be located between mounting blocks 11 and back-up block 8, an end is against the bottom surface of mounting blocks 11, and the other end is against the end face of back-up block 8.Motion bar back-moving spring 7 is resetted for promoting motion bar 5, it is enclosed within on motion bar 5, motion bar back-moving spring 7 one ends are against on the inwall of back-up block 8, the other end is against on the flange 6 arranged on motion bar 5, as shown in Figure 3, motion bar 5 is oval bar, and flange 6 is located on the outer circumference surface of motion bar 5, one-body molded with motion bar 5.
In addition, motion bar 5 for inserting fixing head, can be taper, the head of taper is easier to embed the installing hole wall in pillar 2 outsides, to strengthen the stability of pedestal.When the pillar 2 of this pedestal need to be arranged in darker hole, as shown in Figure 1, can connect again at the hypomere 4 of every pillar 2 pillar 2, or more pillars 2, adjacent two pillars 2 can be threaded connection, to extend the length of whole pillar 2.
The stanchion of this pedestal, below stressed scar, at least needs to install two to three of such stanchions, as shown in Figure 1, can connect at the hypomere 4 of every pillar 2 stanchion again, or more stanchions, upper and lower adjacent two stanchions can be threaded connection.When running into hillside, upper end that can the stanchion in massif descending place in place is threaded connection with same steel pipe, to extend the height of whole stanchion, changing sentence says, while running into slope, every stanchion is not equally long, as long as can guarantee that every junction plate 1 can be in same horizontal plane, just can the installation high-voltage electric wire tower.
This pedestal, in the actual installation process, at first needs to carry out geological prospecting, then in massif or mountain stone, gets out installing hole, so that insertion stanchion, certainly before the installation high-voltage electric wire tower, measure in advance orientation and the degree of depth of each installing hole, calculate the every length that stanchion is required.At the bottom of the hypomere 4 of guaranteeing pillar 2 will be pressed in hole.Along with pressing down of high-tension electricity transmission tower main body, the epimere 3 of pillar 2 can move down thereupon, be fixedly mounted on actuator 12 on pillar 2 epimeres 3 and move down and drive motion bar 5 to stretch out towards the outside of pillar 2, be pushed against on the wall of installing hole at each pillar 2 places, strengthen the stability of pedestal; When needs dismounting high-tension electricity transmission tower, after removing the main body of high-tension electricity transmission tower, the gravity of high-tension electricity transmission tower is eliminated, epimere 3 and the motion bar 5 of pillar 2 are resetted under the effect of back-moving spring, motion bar 5 restores under the effect of spring, stanchion returns to original state, and now pedestal can take out very easily, time saving and energy saving.
The above is exemplarily described the utility model by reference to the accompanying drawings; obviously the utility model specific implementation is not subject to the restrictions described above; as long as adopted the improvement of the various unsubstantialities that method of the present utility model design and technical scheme carry out; or without improving, design of the present utility model and technical scheme are directly applied to other occasion, all within protection domain of the present utility model.
Claims (10)
1. a stanchion, for being arranged on the pedestal of high-tension electricity transmission tower, it is characterized in that: the main body of described stanchion be one for inserting the pillar (2) of the pedestal installing hole excavated on stone surface, mountain, be provided with the pedestal stretched out towards pillar (2) outside under the Action of Gravity Field in the main body of high-tension electricity transmission tower and can be pushed against the mountain cliff face in pillar (2) outside in the inside of pillar (2) and stablize stiffening device, this pedestal is stablized stiffening device and automatically be contracted to pillar (2) inside after the main body of high-tension electricity transmission tower is removed.
2. stanchion according to claim 1, it is characterized in that: described pillar (2) is columniform steel pipe, pillar (2) is divided into epimere (3) and hypomere (4), the epimere (3) of pillar (2) is socketed in the top of hypomere (4) in bottom, described pedestal is stablized stiffening device and is comprised the many motion bars (5) in the hypomere (4) that laterally is located at pillar (2), be located at actuator (12) and the return unit for resetting for driving motion bar (5) laterally to stretch out towards the outside of pillar (2) in the epimere (3) of pillar (2), on actuator (12), have and the contacted drive surface of motion bar (5).
3. stanchion according to claim 2 is characterized in that: the epimere (3) of described pillar (2) is fixedly installed in the inner bottom part position and is useful on the mounting blocks (11) that described actuator (12) is installed.
4. stanchion according to claim 3, it is characterized in that: in the inside of the hypomere (4) of described pillar (2), be fixedly installed and be useful on the back-up block (8) that described motion bar (5) is installed, be provided with the centre bore (10) that allows described actuator (12) insert and along the pilot hole (9) for laying motion bar (5) of horizontally set on back-up block (8), the drive surface of actuator (12) contacts in centre bore (10) with motion bar (5), and pilot hole (9) also extends to the outer circumference surface of the hypomere (4) of pillar (2) always.
5. stanchion according to claim 4, it is characterized in that: between described mounting blocks (11) and described back-up block (8), be connected with lead, it is upper that one end of lead is fixed on mounting blocks (11), and the other end passes back-up block (8), and is provided with limited block at this end.
6. according to claim 2 or 3 or 4 or 5 described stanchions, it is characterized in that: described actuator (12) is cone, and the drive surface of actuator (12) is taper seat.
7. stanchion according to claim 6, it is characterized in that: the head for pushing against stone surface, mountain of described motion bar (5) is taper.
8. stanchion according to claim 6, it is characterized in that: described return unit comprises actuator back-moving spring and motion bar back-moving spring (7), the actuator back-moving spring is located between described mounting blocks (11) and described back-up block (8), motion bar back-moving spring (7) is enclosed within on described motion bar (5), motion bar back-moving spring (7) one ends are against on the inwall of described back-up block (8), and the other end is against on the upper flange (6) arranged of motion bar (5).
9. stanchion according to claim 8 is characterized in that: described motion bar (5) circumferentially evenly is provided with four along pillar (2) described pillar (2) is upper.
10. a power line column foot seat, is characterized in that: comprise stanchion claimed in claim 9, also comprise the junction plate (1) be connected for the main body with the high-tension electricity transmission tower, many described stanchions vertically are installed on this junction plate (1).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN 201320293422 CN203361179U (en) | 2013-05-25 | 2013-05-25 | Column pile and high-voltage power line tower base comprising column piles |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN 201320293422 CN203361179U (en) | 2013-05-25 | 2013-05-25 | Column pile and high-voltage power line tower base comprising column piles |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN203361179U true CN203361179U (en) | 2013-12-25 |
Family
ID=49808967
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN 201320293422 Withdrawn - After Issue CN203361179U (en) | 2013-05-25 | 2013-05-25 | Column pile and high-voltage power line tower base comprising column piles |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN203361179U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103255777A (en) * | 2013-05-25 | 2013-08-21 | 芜湖中泰新能源有限公司 | Column piles and high-voltage wire tower substrate utilizing column piles |
| CN107642102A (en) * | 2017-09-30 | 2018-01-30 | 贵州大兴电力设备制造有限公司 | Shock attenuation pole |
-
2013
- 2013-05-25 CN CN 201320293422 patent/CN203361179U/en not_active Withdrawn - After Issue
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103255777A (en) * | 2013-05-25 | 2013-08-21 | 芜湖中泰新能源有限公司 | Column piles and high-voltage wire tower substrate utilizing column piles |
| CN107642102A (en) * | 2017-09-30 | 2018-01-30 | 贵州大兴电力设备制造有限公司 | Shock attenuation pole |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104963301B (en) | The dilatory translation downward putting device and method removed for pier top beam section and bridge pier | |
| CN106194216A (en) | A kind of Rectangular Box Culvert and constructing tunnel chassis | |
| CN203049635U (en) | Static loading test quick linking device by anchor pile method | |
| CN103255777B (en) | Column piles and high-voltage wire tower substrate utilizing column piles | |
| CN203583380U (en) | Movable cast-in-situ culvert cover plate template support | |
| CN214087449U (en) | Lifting device for wind power equipment | |
| CN206245846U (en) | Shaft tower shock-absorption | |
| CN205369277U (en) | Support whole system of transferring in cofferdam | |
| CN104234058A (en) | Diagonal bracing support structure for large foundation pit | |
| CN221345670U (en) | Detachable temporary retaining wall | |
| CN218991156U (en) | Construction fence for municipal works | |
| CN219622457U (en) | Reinforced concrete base | |
| CN109487811B (en) | A kind of lateral tree root digging pile and its installation equipment | |
| KR20200014573A (en) | Concrete screw type underground support device of solar power generation apparatus, method of manufacturing the same, and method of installing the same | |
| CN204609345U (en) | A kind of full dismounting bean column node temporary support lattice column device | |
| CN202742300U (en) | Adjustable fixed support for sleeve bolts | |
| CN203834959U (en) | Safety protective fence used for building construction | |
| CN203700899U (en) | Steel tool-type temporary construction road | |
| CN203113362U (en) | Steel structure factory building prefabricated foundation structure | |
| CN203238973U (en) | Installing and fixing adjustable device for prefabricated column or prefabricated steel column | |
| CN211259850U (en) | Municipal administration pipeline push pipe construction equipment | |
| CN201850655U (en) | T-shaped connector for new and old buildings | |
| CN210239346U (en) | A pin-connected panel encloses fender for building site | |
| CN204597304U (en) | A kind of distributing box fixing device for installing | |
| CN205476783U (en) | Electric power tower fastens mound |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| AV01 | Patent right actively abandoned |
Granted publication date: 20131225 Effective date of abandoning: 20150603 |
|
| RGAV | Abandon patent right to avoid regrant |