CN203270529U - 有压隧洞施工支洞封堵结构 - Google Patents

有压隧洞施工支洞封堵结构 Download PDF

Info

Publication number
CN203270529U
CN203270529U CN2013203115205U CN201320311520U CN203270529U CN 203270529 U CN203270529 U CN 203270529U CN 2013203115205 U CN2013203115205 U CN 2013203115205U CN 201320311520 U CN201320311520 U CN 201320311520U CN 203270529 U CN203270529 U CN 203270529U
Authority
CN
China
Prior art keywords
construction
access path
base plate
adit
pressure tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2013203115205U
Other languages
English (en)
Inventor
祖威
陈绍英
陈子海
刘宇
程春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Powerchina Chengdu Engineering Co Ltd
Original Assignee
Chengdu Hydroelectric Investigation and Design Institute of China Hydropower Engineering Consulting Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Hydroelectric Investigation and Design Institute of China Hydropower Engineering Consulting Group filed Critical Chengdu Hydroelectric Investigation and Design Institute of China Hydropower Engineering Consulting Group
Priority to CN2013203115205U priority Critical patent/CN203270529U/zh
Application granted granted Critical
Publication of CN203270529U publication Critical patent/CN203270529U/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Abstract

本实用新型涉及水电建筑领域,尤其是一种有压隧洞施工支洞封堵结构。所要解决的技术问题是提供一种在不增加施工量的前提下,可以降低检修通道抵御有压隧洞内水压力破坏风险的有压隧洞施工支洞封堵结构。所采用的技术方案是:有压隧洞施工支洞封堵结构,包括依次连接的施工支洞、检修通道和有压隧洞,有压隧洞底部的有压隧洞底板位于检修通道底部的检修通道底板所在水平面的下方,有压隧洞底板与检修通道底板之间通过检修通道斜坡连接。通过抬高检修通道底板,建造出一个梯形混凝土底板结构。本实用新型可以广泛应用于水电有压隧洞的施工或检修当中。

Description

有压隧洞施工支洞封堵结构
技术领域
[0001] 本实用新型涉及水电建筑领域,尤其是一种有压隧洞施工支洞封堵结构。
背景技术
[0002] 水利水电工程的结构中,有压隧洞内多数情况下储存有大量的水。在达到规定检修期限后,需要对有压隧洞进行检修。在检修时,检修人员是通过设置于有压隧洞一侧的检修通道进入有压隧洞的,而检修通道的另一端则与施工支洞相通。
[0003]目前在实际的应用中,传统方案一是:绝大多数的有压隧洞的有压隧洞底板和检修通道的检修通道底板是在同一水平面的。但是,这样的结构其基础较为薄弱,且由于有压隧洞内水压的作用,存在被有压隧洞内水压力破坏的风险。
[0004] 传统方案二是:将检修通道下方的混凝土厚度,即检修通道底板位置低于有压隧洞底板。这样的结构固然可以更加稳固,但这样会导致施工支洞底板扩挖对主洞的衬砌干扰大,并增加了支洞封堵的工程量和工期,故也有其缺陷。
实用新型内容
[0005] 本实用新型所要解决的技术问题是提供一种在不增加施工量的前提下,可以降低检修通道抵御有压隧洞内水压力破坏风险的有压隧洞施工支洞封堵结构。
[0006] 本实用新型解决其技术问题所采用的技术方案是:有压隧洞施工支洞封堵结构,包括依次连接的施工支洞、检修通道和有压隧洞,有压隧洞底部的有压隧洞底板位于检修通道底部的检修通道底板所在水平面的下方,所述有压隧洞底板与检修通道底板之间通过检修通道斜坡连接。
[0007] 进一步的是,支洞底板与检修通道底板之间通过支洞斜坡连接。
[0008] 进一步的是,检修通道内设置有检修门。
[0009] 本实用新型的有益效果是:在保证有压隧洞底板不变动的前提下,通过抬高检修通道底板,建造出一个梯形混凝土底板结构。这样的结构既拥有传统方案一中的施工简便的特点,又兼具了传统方案二的结构稳固的好处,设计巧妙且很实用。本实用新型可以广泛应用于水电有压隧洞的施工或检修当中。
附图说明
[0010] 图1是本实用新型的主视图。
[0011] 图中标记为:施工支洞1、支洞底板11、支洞斜坡12、检修通道2、检修通道底板21、检修门22、检修通道斜坡23、梯形混凝土底板24、有压隧洞3、有压隧洞底板31。
具体实施方式
[0012] 下面结合附图对本实用新型做进一步说明。
[0013] 如图1所示的有压隧洞施工支洞封堵结构,包括依次连接的施工支洞1、检修通道2和有压隧洞3,有压隧洞3底部的有压隧洞底板31位于检修通道2底部的检修通道底板21所在水平面的下方,所述有压隧洞底板31与检修通道底板21之间通过检修通道斜坡23连接。
[0014] 在实际施工中,为了防止有压隧洞3内的水进入到施工支洞1,需要在检修通道2内设置封堵结构,这样的封堵结构可以是砌筑墙体、安装防水门等方式。如图1所述,梯形混凝土底板24是由检修通道底板21、检修通道斜坡23和有压隧洞底板31共同围成的。由于检修通道斜坡23的存在,从而使检修通道2底部的检修通道底板21高程高于有压隧洞3底部的有压隧洞底板31高程,所以构成了“梯形”的梯形混凝土底板24,这样的结构是为了加强检修通道2下面的混凝土结构的稳固性。另外,也避免了在支洞底板11所在平面的下部继续施工的必要,减轻了工程量。
[0015] 为了加强施工支洞I底部混凝土结构的稳定性,基于上一个方案的思想,支洞底板11与检修通道底板21之间通过支洞斜坡12连接。同样的,支洞斜坡12可以让混凝土结构深入到施工支洞I底部,加强其稳固性。
[0016]为了方便频繁检修的情况,检修通道2内设置有检修门22。如图1所示,在需要较为频繁的检修时,工作人员可以通过检修门22进入到有压隧洞3内。需要注意的是,在进入之前需要先将有压隧洞3内的水排掉,否则检修门22无法打开。在检修结束后关闭检修门22即可。

Claims (3)

1.有压隧洞施工支洞封堵结构,包括依次连接的施工支洞(I)、检修通道(2)和有压隧洞(3),其特征在于:有压隧洞(3)底部的有压隧洞底板(31)位于检修通道(2)底部的检修通道底板(21)所在水平面的下方,所述有压隧洞底板(31)与检修通道底板(21)之间通过检修通道斜坡(23)连接。
2.如权利要求1所述的有压隧洞施工支洞封堵结构,其特征在于:支洞底板(11)与检修通道底板(21)之间通过支洞斜坡(12)连接。
3.如权利要求1或2所述的有压隧洞施工支洞封堵结构,其特征在于:检修通道(2)内设置有检修门(22)。
CN2013203115205U 2013-05-31 2013-05-31 有压隧洞施工支洞封堵结构 Active CN203270529U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013203115205U CN203270529U (zh) 2013-05-31 2013-05-31 有压隧洞施工支洞封堵结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013203115205U CN203270529U (zh) 2013-05-31 2013-05-31 有压隧洞施工支洞封堵结构

Publications (1)

Publication Number Publication Date
CN203270529U true CN203270529U (zh) 2013-11-06

Family

ID=49500970

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013203115205U Active CN203270529U (zh) 2013-05-31 2013-05-31 有压隧洞施工支洞封堵结构

Country Status (1)

Country Link
CN (1) CN203270529U (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590379A (zh) * 2013-11-25 2014-02-19 中国能源建设集团广东省电力设计研究院 电厂循环水系统的易装拆式隧洞口挡水装置及其施工方法
CN104141286A (zh) * 2014-01-09 2014-11-12 成都绿迪科技有限公司 施工支洞封堵结构
CN105586858A (zh) * 2016-03-10 2016-05-18 中国电建集团成都勘测设计研究院有限公司 一种导流隧洞封堵结构

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590379A (zh) * 2013-11-25 2014-02-19 中国能源建设集团广东省电力设计研究院 电厂循环水系统的易装拆式隧洞口挡水装置及其施工方法
CN103590379B (zh) * 2013-11-25 2016-02-03 中国能源建设集团广东省电力设计研究院有限公司 电厂循环水系统的易装拆式隧洞口挡水装置及其施工方法
CN104141286A (zh) * 2014-01-09 2014-11-12 成都绿迪科技有限公司 施工支洞封堵结构
CN105586858A (zh) * 2016-03-10 2016-05-18 中国电建集团成都勘测设计研究院有限公司 一种导流隧洞封堵结构
CN105586858B (zh) * 2016-03-10 2018-11-30 中国电建集团成都勘测设计研究院有限公司 一种导流隧洞封堵结构

Similar Documents

Publication Publication Date Title
CN203270529U (zh) 有压隧洞施工支洞封堵结构
CN202745940U (zh) 采空区封闭结构
CN204782506U (zh) 一种t型中梃型材
CN203594055U (zh) 一种地下室导墙处防水砼水平施工缝的构造
CN203296026U (zh) 用于导流洞下闸和封堵后的排气装置
CN204715555U (zh) 组合式外墙保温板
CN205617571U (zh) 一种易拆装的预制装配式房屋
CN211228925U (zh) 一种土建施工用混凝土预埋件
CN206457830U (zh) 一种建筑施工预制构件装配结构
CN203684247U (zh) 一种多层建筑的抗震基础
CN105134275A (zh) 一种三软煤层采煤工作面液压支架辅助支撑装置
CN204457532U (zh) 深长测斜管下管装置
CN204876278U (zh) 一种空心砖结构
CN204023551U (zh) 一种围护桩桩间快速止水结构
CN205025482U (zh) 一种三软煤层采煤工作面液压支架辅助支撑装置
CN204441497U (zh) 地桩结构
CN204212169U (zh) 集水坑自动抽水装置
CN201339315Y (zh) 一种附着式升降脚手架的连墙装置
CN204551378U (zh) 一种堆石坝上游面表层的防渗结构
CN204098373U (zh) 活动雨棚
CN103452128A (zh) 一种采用钢管接腿输电线路杆塔基面抬升方法
CN203701282U (zh) 一种预埋槽道及与其相匹配的支架结构
CN203700970U (zh) 桥梁顶升装置
CN208815554U (zh) 一种在富水深卵砾漂石地层中超前预注浆的止水结构
CN203440801U (zh) 地下厂房帷幕灌浆排水廊道

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: The North Qingyang District of Chengdu City, Sichuan Province, No. 610072

Patentee after: Chengdu Hydroelectric Investigation & Design Institute of SPC

Address before: The North Qingyang District of Chengdu City, Sichuan Province, No. 610072

Patentee before: Chengdu Hydroelectric Investigation & Design Institute of China Hydropower Consu

C56 Change in the name or address of the patentee

Owner name: CHINA POWER GROUP CHENGDU INVESTIGATION DESIGN + R

Free format text: FORMER NAME: CHENGDU HYDROELECTRIC INVESTIGATION + DESIGN INSTITUTE OF SPC

CP01 Change in the name or title of a patent holder

Address after: The North Qingyang District of Chengdu City, Sichuan Province, No. 610072

Patentee after: Co., Ltd of Chengdu survey and design academy of electricity Jian group of China

Address before: The North Qingyang District of Chengdu City, Sichuan Province, No. 610072

Patentee before: Chengdu Hydroelectric Investigation & Design Institute of SPC