CN203251018U CN 201320235734 CN201320235734U CN203251018U CN 203251018 U CN203251018 U CN 203251018U CN 201320235734 CN201320235734 CN 201320235734 CN 201320235734 U CN201320235734 U CN 201320235734U CN 203251018 U CN203251018 U CN 203251018U
Authority
CN
China
Prior art keywords
transmission line
wire
lifting tool
transverse support
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320235734
Other languages
Chinese (zh)
Inventor
侯志锋
方守盛
谢强
刘永强
侯亚波
陆经照
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JINZHONG POWER SUPPLY COMPANY SHANXI ELECTRIC POWER Co
State Grid Corp of China
Original Assignee
Shanxi Electric Power Co Jinzhong Power Supply Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Electric Power Co Jinzhong Power Supply Co filed Critical Shanxi Electric Power Co Jinzhong Power Supply Co
Priority to CN 201320235734 priority Critical patent/CN203251018U/en
Application granted granted Critical
Publication of CN203251018U publication Critical patent/CN203251018U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model provides a transmission line instrument of carrying traditional thread binding putting forward, characterized by including carrying the line hook: the power transmission line lifting tool further comprises a transverse support, two wire hooks are arranged below the transverse support side by side, and two bayonets are arranged on two sides of the transverse support respectively. The design of the two wire hooks can enable the device to directly hoist the wires at the connecting part of the insulator and the wires to transfer loads, so that the operation difficulty is reduced, and the working efficiency is improved.

Description

输电线路提线工具Transmission line lifting tool

技术领域 technical field

本实用新型涉及一种输电线路提线工具。  The utility model relates to a wire lifting tool for transmission lines. the

背景技术 Background technique

在更换直线绝缘子串时,需要将其下方导线提起,转移其负载后才能进行更换,目前常用的方法是用钩子将连接点附近的线勾起,由于输电导线有弧垂,因此需要将导线勾起较多的行程才能转移负载,且稳定性不足。  When replacing a linear insulator string, it is necessary to lift the wire below it and transfer its load before replacing it. At present, the common method is to use a hook to hook up the wire near the connection point. Since the power transmission wire has sag, it is necessary to hook the wire It takes more strokes to transfer the load, and the stability is not enough. the

发明内容 Contents of the invention

针对现有技术的不足,本实用新型提供一种能够在绝缘子和导线连接点处直接转移负载,稳定性高的输电线路提线工具。  Aiming at the deficiencies of the prior art, the utility model provides a high-stability power transmission line lifting tool that can directly transfer loads at the connection point between an insulator and a wire. the

本实用新型采用的技术方案是:一种输电线路提线工具,包括提线钩,其特征是:所述输电线路提线工具还包括横支架,所述横支架下方并排安装两个提线钩,所述横支架两端各有一个卡口。  The technical scheme adopted by the utility model is: a wire lifting tool for a power transmission line, including a wire lifting hook, characterized in that: the wire lifting tool for a power transmission line also includes a horizontal bracket, and two wire lifting hooks are installed side by side under the horizontal bracket , each of the two ends of the horizontal bracket has a bayonet. the

本实用新型的有益效果是:两个导线钩的设计可使装置直接在绝缘子与导线的连接处吊起导线转移负载,减小了操作难度,提高了工作效率。  The beneficial effect of the utility model is that: the design of the two wire hooks enables the device to directly lift the wire at the junction of the insulator and the wire to transfer the load, which reduces the difficulty of operation and improves the work efficiency. the

附图说明 Description of drawings

图1为本实用新型主视结构示意图。  Fig. 1 is a schematic diagram of the front view of the utility model. the

图2为本实用新型左视结构示意图。  Fig. 2 is a schematic diagram of the structure of the utility model left view. the

图3为本实用新型俯视结构示意图。  Fig. 3 is a schematic diagram of the top view structure of the utility model. the

图中,1-提线钩,2-横支架,3-卡口。  In the figure, 1-line lifting hook, 2-horizontal bracket, 3-bayonet. the

具体实施方式 Detailed ways

如图1至3所示,一支钢性横支架2为长条形,下方并排安装两个提线钩1,横支架2两端各有一个卡口3。  As shown in Figures 1 to 3, a steel horizontal support 2 is elongated, and two wire lifting hooks 1 are installed side by side below, and a bayonet 3 is respectively arranged at two ends of the horizontal support 2. the

更换作业时,用绳索及卡具通过卡口3将提线工具升起至适当高度,两个提线钩2分别从绝缘子与导线连接处的两端勾起导线,转移负荷,即可开始拆卸绝缘子串。当新绝缘子串安装完毕后,绝缘子串的下连接点扔对准处于两导线钩1之间的导线连接处,连接稳定后将提线装置取下,完成更换。  When replacing the operation, use the rope and fixture to raise the wire lifting tool to an appropriate height through the bayonet 3, and the two wire lifting hooks 2 respectively lift the wire from the two ends of the connection between the insulator and the wire, transfer the load, and then start disassembly insulator string. After the new insulator string is installed, the lower connection point of the insulator string is thrown to align with the wire connection between the two wire hooks 1, and after the connection is stable, the wire lifting device is taken off to complete the replacement. the

Claims (1)

1. a transmission line is carried the Line tool, comprise thread-lifting hook (1), it is characterized in that: described transmission line is carried the Line tool and is also comprised lateral frame (2), and described lateral frame (2) below is installed two thread-lifting hooks (1) side by side, and respectively there is a bayonet socket (3) at described lateral frame (2) two ends.
CN 201320235734 2013-05-06 2013-05-06 Transmission line lifting tool Expired - Fee Related CN203251018U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320235734 CN203251018U (en) 2013-05-06 2013-05-06 Transmission line lifting tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320235734 CN203251018U (en) 2013-05-06 2013-05-06 Transmission line lifting tool

Publications (1)

Publication Number Publication Date
CN203251018U true CN203251018U (en) 2013-10-23

Family

ID=49377437

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320235734 Expired - Fee Related CN203251018U (en) 2013-05-06 2013-05-06 Transmission line lifting tool

Country Status (1)

Country Link
CN (1) CN203251018U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR3054835A1 (en) * 2016-08-08 2018-02-09 Manukerque CABLE SUPPORT ADAPTED TO BE MOUNTED ON A LIFTING EQUIPMENT SUCH AS A TELESCOPIC FORKLIFT

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR3054835A1 (en) * 2016-08-08 2018-02-09 Manukerque CABLE SUPPORT ADAPTED TO BE MOUNTED ON A LIFTING EQUIPMENT SUCH AS A TELESCOPIC FORKLIFT

Similar Documents

Publication Publication Date Title
CN201266542Y (en) Suspended core stent of trestle type distribution transformer
CN202856246U (en) Insulator replacement device
CN203690795U (en) Carriage used for overhaul of insulator chain
CN202488034U (en) Lifting device for electric transmission line of angle iron tower
CN203813317U (en) Novel large-tonnage self-lifting type wire lifting device
CN202373939U (en) Live-working double-conductor lifting device
CN103523648B (en) A kind of slush pump mounting suspension of drilling mud system
CN204243605U (en) Power line tension string composite insulator changes hook special
CN203545559U (en) Electric meter box hoisting tool
CN202231353U (en) Special tools for lifting and transporting post insulators
CN202268668U (en) Operating device of line lifter lead screw for transmission line
CN203735078U (en) Large grain tank structure for harvester
CN203079534U (en) Hooking device for lifting pad
CN203423430U (en) Insulator maintenance device
CN202897821U (en) Fixture for baking-free bricks
CN203056457U (en) Double-cross-arm insulation cover for live-line work
CN202488035U (en) Hoisting device for maintenance of power transmission line above concrete poles
CN202268651U (en) Fixing device of transmission wire lifter
CN202424002U (en) Spacer rod hoisting tool used safely
CN203612809U (en) Steel wire coil hoisting fixture
CN203359837U (en) Double-fly-jib device of tire crane
CN202424004U (en) Tool used for maintaining horizontal double bundle conductor
CN104626082A (en) Production line assisting frame
CN203071493U (en) Adjustable line tackle
CN203624809U (en) Steel bar transport hook

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: JINZHONG POWER SUPPLY COMPANY, SHANXI ELECTRIC POW

Effective date: 20140317

Owner name: STATE GRID CORPORATION OF CHINA

Free format text: FORMER OWNER: JINZHONG POWER SUPPLY COMPANY, SHANXI ELECTRIC POWER CO.

Effective date: 20140317

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 030600 JINZHONG, SHAANXI PROVINCE TO: 100031 XICHENG, BEIJING

TR01 Transfer of patent right

Effective date of registration: 20140317

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Patentee after: State Grid Corporation of China

Patentee after: Jinzhong Power Supply Company, Shanxi Electric Power Co.

Address before: 030600 No. 85 Yingbin street, Yuci District, Shanxi, Jinzhong

Patentee before: Jinzhong Power Supply Company, Shanxi Electric Power Co.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131023

Termination date: 20180506

CF01 Termination of patent right due to non-payment of annual fee