CN203178318U - Insulator appliance test stand - Google Patents

Insulator appliance test stand Download PDF

Info

Publication number
CN203178318U
CN203178318U CN2013201450567U CN201320145056U CN203178318U CN 203178318 U CN203178318 U CN 203178318U CN 2013201450567 U CN2013201450567 U CN 2013201450567U CN 201320145056 U CN201320145056 U CN 201320145056U CN 203178318 U CN203178318 U CN 203178318U
Authority
CN
China
Prior art keywords
base
insulation
work tool
bracing frame
testing table
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2013201450567U
Other languages
Chinese (zh)
Inventor
何锐
吴志勇
陈小龙
王杰
王晓康
杨丙寅
马少林
王亚芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NINGXIA POWER Co WUZONG POWER SUPPLY BUREAU
State Grid Corp of China SGCC
Original Assignee
NINGXIA POWER Co WUZONG POWER SUPPLY BUREAU
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NINGXIA POWER Co WUZONG POWER SUPPLY BUREAU, State Grid Corp of China SGCC filed Critical NINGXIA POWER Co WUZONG POWER SUPPLY BUREAU
Priority to CN2013201450567U priority Critical patent/CN203178318U/en
Application granted granted Critical
Publication of CN203178318U publication Critical patent/CN203178318U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Testing Relating To Insulation (AREA)

Abstract

The utility model relates to an insulator appliance test stand. The test stand is characterized in that the test stand comprises a pedestal (5); an insulation support frame (4) is laid on the pedestal (5) and insulation support bars (6) are arranged vertically on four corners of the pedestal (5) respectively; at least one steel plate (3) is installed on the insulation support frame (4); at least two card slots (2) are arranged on the steel plate (3) so as to fix one end of an insulating rod to be measured (1); besides, a grounding terminal is arranged on the steel plate (3). By using the insulator appliance test stand of the utility model, it is proved that an insulation and pressure test performed on insulation gloves, insulation boots, the insulating rod and the like is safe and reliable; test efficiency is increased obviously; and accuracy of a test result is guaranteed.

Description

Insulation Work tool testing table
Technical field
The utility model relates to a kind of insulation Work tool testing table.
Background technology
Adopting with the basin during tradition insulation Work tool (insulating glove, insulating boot, insulating bar) test is the test method of carrier.And for the requirement of the desired insulating bar of insulation Work tool testing regulations by the length pressurization, traditional experiment then adopts artificial estimation.
According to 2008 editions " security risk assessment standards " to tradition insulation Work tool test assess, draw the test of tradition insulation Work tool for uncontrollable by assessment.Wherein, when adopting tradition insulation Work tool testing table to test, be carrier with the basin, and the fixing of insulating glove and insulating boot can't guarantee, often take place that test specimen is toppled over and the failure of pressurize, test length consuming time, the danger height.When insulating bar was tested, therefore the insulating bar of different electric pressures pressurization length difference needed the rule repeated measurement simultaneously, and insulating bar can not guarantee that insulating bar tumbles and happens occasionally owing to fix in process of the test.Jeopardize testing equipment and test clerk.
The utility model content
The purpose of this utility model provides a kind of insulation Work tool testing table, can improve the accuracy in the process of the test and guarantee testing crew safety.
A kind of insulation Work tool testing table, its special feature is: comprise base, be equipped with the insulation bracing frame at this base, and on four angles of this base, erect respectively insulating support rod is arranged, at the insulation bracing frame at least one block plate is installed, thereby be provided with the end that at least 2 draw-in grooves are fixed insulating bar to be measured at this steel plate, be provided with ground terminal at steel plate in addition.
Four universal wheels wherein are installed below base, and in a side of base pull bar are installed.
The bracing frame that wherein insulate is made up of one deck epoxy resin board and one deck rubber blanket.
Wherein draw-in groove is the one section steel pipe that is fixed on the steel plate.
A kind of insulation Work tool testing table, its special feature is: comprise base, be equipped with the insulation bracing frame at this base, and on four angles of this base, erect respectively insulating support rod is arranged, be placed with at least 2 tanks at the insulation bracing frame, also comprise two cross bars, these two cross bar two ends separately are separately fixed at the top of four insulating support rods, and the middle part of these two cross bars links together by two montants, on two montants, all have through hole, also comprise pressure rod, an end of this pressure rod passes its other end of back and stretches in the tank from aforementioned through-hole.
Four universal wheels wherein are installed below base, and in a side of base pull bar are installed.
The bracing frame that wherein insulate is made up of one deck epoxy resin board and one deck rubber blanket.
Through probationary certificate, adopt insulation Work tool testing table of the present utility model after, insulating glove, insulating boot, insulating bar etc. carried out the dielectric voltage withstand test become safe and reliable, and test efficiency obviously improves, accuracy of experimental results also is guaranteed.
Description of drawings
Accompanying drawing 1 is structural representation of the present utility model;
Accompanying drawing 2 is structural representation of the present utility model.
Embodiment
As shown in Figure 1, the utility model is a kind of insulation Work tool testing table, the base 5 that comprises steel, be equipped with insulation bracing frame 4 at this base 5, and on four angles of this base 5, erect respectively insulating support rod 6 is arranged, at insulation bracing frame 4 at least one block plate 3 is installed, thereby is provided with the end that at least 2 draw-in grooves 2 are fixed insulating bars 1 to be measured at this steel plate 3, be provided with ground terminal at steel plate 3 in addition.
Four universal wheels 8 wherein are installed below base 5, and in a side of base 5 pull bar 7 are installed, insulation bracing frame 4 is made up of one deck epoxy resin board and one deck rubber blanket, and draw-in groove 2 is the one section steel pipe that is fixed on the steel plate 3.
Using method of the present utility model is:
As shown in Figure 1, to how insert simultaneously in the draw-in groove 2 with insulating bar 1 to be measured during use,, be connected with high-voltage power supply then with same lead with the equal height place colligation of all insulating bars 1 to be measured together, then the ground terminal on base 5 and the steel plate 3 can be tested with the lead reliable ground.
As shown in Figure 2, the utility model is a kind of insulation Work tool testing table, comprise base 5, be equipped with insulation bracing frame 4 at this base 5, and on four angles of this base 5, erect respectively insulating support rod 6 is arranged, be placed with the tank 11 of at least 2 steels at insulation bracing frame 4, also comprise two cross bars 9, these two cross bar 9 two ends separately are separately fixed at the top of four insulating support rods 6, and the middle part of these two cross bars 9 links together by two montants, all have through hole on two montants, also comprise pressure rod 10, an end of this pressure rod 10 passes its other end of back and stretches in the tank 11 from aforementioned through-hole.
Four universal wheels 8 wherein are installed below base 5, and in a side of base 5 pull bar 7 are installed, insulation bracing frame 4 is made up of one deck epoxy resin board and one deck rubber blanket.
Using method of the present utility model is:
As shown in Figure 2, pack into after during use insulating glove being filled with water in the tank 11, its both sides can be fixed on the tank 11 with common high-potting binding clip, the lead fixed that will be connected with high-voltage power supply can be tested tank 11 reliable grounds of base 5 and rectangular parallelepiped then on pressure rod 10 tops then.

Claims (7)

1. insulation Work tool testing table, it is characterized in that: comprise base (5), be equipped with insulation bracing frame (4) at this base (5), and on four angles of this base (5), erect respectively insulating support rod (6) is arranged, at insulation bracing frame (4) at least one block plate (3) is installed, this steel plate (3) be provided with at least 2 draw-in grooves (2) thus an end of fixing insulating bar to be measured (1) is provided with ground terminal at steel plate (3) in addition.
2. insulation Work tool testing table as claimed in claim 1 is characterized in that: wherein in base (5) below four universal wheels (8) are installed, and in a side of base (5) pull bar (7) are installed.
3. insulation Work tool testing table as claimed in claim 1, it is characterized in that: the bracing frame that wherein insulate (4) is made up of one deck epoxy resin board and one deck rubber blanket.
4. insulation Work tool testing table as claimed in claim 1, it is characterized in that: wherein draw-in groove (2) is the one section steel pipe that is fixed on the steel plate (3).
5. insulation Work tool testing table, it is characterized in that: comprise base (5), be equipped with insulation bracing frame (4) at this base (5), and on four angles of this base (5), erect respectively insulating support rod (6) is arranged, be placed with at least 2 tanks (11) at insulation bracing frame (4), also comprise two cross bars (9), these two cross bars (9) two ends separately are separately fixed at the top of four insulating support rods (6), and the middle part of these two cross bars (9) links together by two montants, on two montants, all have through hole, also comprise pressure rod (10), an end of this pressure rod (10) passes its other end of back and stretches in the tank (11) from aforementioned through-hole.
6. insulation Work tool testing table as claimed in claim 5 is characterized in that: wherein in base (5) below four universal wheels (8) are installed, and in a side of base (5) pull bar (7) are installed.
7. insulation Work tool testing table as claimed in claim 5, it is characterized in that: the bracing frame that wherein insulate (4) is made up of one deck epoxy resin board and one deck rubber blanket.
CN2013201450567U 2013-03-18 2013-03-27 Insulator appliance test stand Expired - Fee Related CN203178318U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013201450567U CN203178318U (en) 2013-03-18 2013-03-27 Insulator appliance test stand

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN201320121868 2013-03-18
CN201320121868.8 2013-03-18
CN2013201450567U CN203178318U (en) 2013-03-18 2013-03-27 Insulator appliance test stand

Publications (1)

Publication Number Publication Date
CN203178318U true CN203178318U (en) 2013-09-04

Family

ID=49074997

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013201450567U Expired - Fee Related CN203178318U (en) 2013-03-18 2013-03-27 Insulator appliance test stand

Country Status (1)

Country Link
CN (1) CN203178318U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103235243A (en) * 2013-03-18 2013-08-07 国家电网公司 Test stand for insulating instruments
CN104035011A (en) * 2014-06-27 2014-09-10 国家电网公司 Pressure-tight test device of insulation and protection equipment

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103235243A (en) * 2013-03-18 2013-08-07 国家电网公司 Test stand for insulating instruments
CN103235243B (en) * 2013-03-18 2016-06-22 国家电网公司 Insulating tool testing stand
CN104035011A (en) * 2014-06-27 2014-09-10 国家电网公司 Pressure-tight test device of insulation and protection equipment

Similar Documents

Publication Publication Date Title
CN103235243A (en) Test stand for insulating instruments
CN106324294B (en) A kind of insulating bar pressure test frame
CN205427116U (en) Insulating gloves and insulating boot pressure resistance test installation
CN203178318U (en) Insulator appliance test stand
CN102680865B (en) Integrated device for insulation test of insulation glove
CN202562960U (en) 10-kilovolt (kV) arrester test-bed rack
CN103235247B (en) Insulating boot and insulating glove alternating-current voltage resistance test device
CN202548284U (en) Test box for insulation test on insulating gloves
CN204595023U (en) A kind of 10kV arrester testing support
CN103852601A (en) Alternating-current withstand voltage support of insulating rods
CN203895807U (en) Special-purpose safety belt high hanging support rack for isolating switch
CN202599990U (en) Portable safety tool testing shelf
CN204142771U (en) A kind of connection terminal connector of test voltage mutual inductor
CN203643561U (en) Standardized testing device for cross-arm shielding covers
CN203054017U (en) Insulating support frame for improving high-voltage lead arrangement in alternating current voltage withstanding test
CN205229395U (en) A pressure resistance test installation for insulator spindle or earth bar
CN203232058U (en) Lightning arrester test frame
CN204008980U (en) The calibration equipment of a kind of insulating glove, insulated shoes
CN207623374U (en) A kind of simple auxiliary connection device based on converter valve thyristor level ability meter
CN202548283U (en) Integrated device for insulation test of insulating glove
CN205484662U (en) A portable test bench for withstand voltage is experimental in batches
CN201724954U (en) Rack dedicated for lightning arrester experiments
CN204028303U (en) A kind of proving installation of protecting adaptation board
CN203811633U (en) Novel clamp of real electrical measuring device
CN203241512U (en) AC withstand voltage testing device for insulation boots and insulation gloves

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130904

Termination date: 20140327