CN203161114U - Hydraulic centralizer applicable to multi-stage hydraulic jet fracturing - Google Patents

Hydraulic centralizer applicable to multi-stage hydraulic jet fracturing Download PDF

Info

Publication number
CN203161114U
CN203161114U CN 201320091695 CN201320091695U CN203161114U CN 203161114 U CN203161114 U CN 203161114U CN 201320091695 CN201320091695 CN 201320091695 CN 201320091695 U CN201320091695 U CN 201320091695U CN 203161114 U CN203161114 U CN 203161114U
Authority
CN
China
Prior art keywords
centralizer
elasticity
sandpipe
mounting groove
centralizer body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201320091695
Other languages
Chinese (zh)
Inventor
许建伟
王祖文
张冕
宁治军
苏敏文
张海涛
侯俊耀
隆世明
宫娜娜
杜加玉
齐加德
高毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CNPC Chuanqing Drilling Engineering Co Ltd
Changqing Downhole Operation Co of CNPC Chuanqing Drilling Engineering Co Ltd
Original Assignee
CNPC Chuanqing Drilling Engineering Co Ltd
Changqing Downhole Operation Co of CNPC Chuanqing Drilling Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CNPC Chuanqing Drilling Engineering Co Ltd, Changqing Downhole Operation Co of CNPC Chuanqing Drilling Engineering Co Ltd filed Critical CNPC Chuanqing Drilling Engineering Co Ltd
Priority to CN 201320091695 priority Critical patent/CN203161114U/en
Application granted granted Critical
Publication of CN203161114U publication Critical patent/CN203161114U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to a hydraulic centralizer applicable to multi-stage hydraulic jet fracturing. The hydraulic centralizer comprises a centralizer body, a centralization ridge and a centralization block, wherein the centralization ridge is provided with a mounting groove, the centralization block is embedded in the mounting groove from the inside of the centralizer body, an elastic sand preventing pipe is sleeved on the inner wall of the centralizer body, and the outer wall of the elastic sand preventing pipe closes the position where the mounting groove and an inner cavity of the centralizer body are communicated. According to the hydraulic centralizer, sand in liquids cannot enter the mounting groove, the centralization block cannot be blocked by the sand, and the sand blocking risk can be effectively reduced.

Description

Be applicable to that multi-stage water power sprays the hydraulic centralizing device of pressure break
Technical field
The utility model relates to a kind of multi-stage water power that is applicable to and sprays the hydraulic centralizing device of pressure break, is used for the completion well stimulation of oil and gas well drilling process, relates to the design and manufacturing technology field of acid fracturing technical tool.
Background technology
Jetting segmentation renovation technique is to grow up the end of the nineties, it is the product that jetting and fracturing technique combine, this technology is beam hole, fracturing yield increasing measure technology, and one-trip string is realized the technology of horizontal well multistage construction, compare with packer, bridging plug, back-up sand, plug technology mode, efficiency of construction can be greatly improved.
In order to realize the multi-stage water power perforating and fracturing, perhaps spray the technology of the real-time pressure break of coil pipe perforation for the multi-stage water power of realizing the proppant packing, prior art all is the jetting process pipe string structure that needs to adopt the various tool serial connection basically, increase along with the oil well horizontal well jetting pressing crack construction number of plies, well depth increases, the instrument that connects at the jetting process pipe string also needs corresponding increase, the increase of instrument causes the length of jetting process pipe string also increasing, therefore, connecting centralizer in tubing string also is very to need, because during horizontal well jetting pressing crack construction, need bigger pump pressure, will tremble at big pump pressure lower tubular column, make tubing string depart from the center line of well, if the construction failure takes place to cause in this situation, so, in the pipe string, needing to connect centralizer, its main purpose is in order to make tubing string stablize tubing string in work progress, keep tubing string at the center of well, reach the high-quality that improves the jetting pressing crack construction.
The centralizer of prior art also has last lower contact, setting upright rib is fixedly installed on the body, in practice of construction, owing between the maximum outside diameter of centralizer and the sleeve pipe certain clearance is arranged, so when pump pressure increases, can produce bigger vibration, this vibration can bring bigger inaccuracy to the accurate position of jetting, the serious damage that also can cause tubing string because of vibration; The centralizer that has set upright the wiper block that rib arranges can be outwards outstanding under the pipe internal pressure, reach with wiper block tightly squeeze on casing wall, realize not trembleing the purpose of setting upright, the disclosed a kind of centralizer of China Patent No. " CN201120355515.5 " for example, open day is on 08 22nd, 2012.But, because the liquid in the pipe has gravel, enter the gap of setting upright rib and wiper block when gravel after, set upright soon and will be blocked by sand, form the sand card, cause setting upright soon and can not be released by the hydraulic pressure in the pipe, so just do not reach and do not tremble the purpose of setting upright.
Multi-stage water power at present newly developed sprays the packing process pipe string, this process pipe string can be by dragging the mode of tubing string in the multi-section multi-layer construction, first perforation and the pressure break connection that carries out three sections with spray gun and the packer of hypomere done, then to open PSK344 waterpower spray gun and packer feed pathway by the mode of pitching, shutoff packer bottom tubing string, again by the mode that drags tubing string three intervals of constructing again, so just can bore for one time six sections are constructed, simplified and gone into well casing post number of times; For the once success that guarantees that multi-stage water power sprays, centralizer is the important step that guarantees that tubing string does not tremble in the work progress, therefore, a plurality of centralizers have been connected in this tubing string, to guarantee the reliability of construction, still, if in work progress, the centralizer that connects has one the sand card takes place, and will influence quality, progress and the safety of whole construction.
Summary of the invention
The purpose of this utility model is to overcome the problems referred to above that existing centralizer exists, provide a kind of multi-stage water power that is applicable to spray the hydraulic centralizing device of pressure break, the utility model can not enter in the mounting groove grit in the liquid, and wiper block can not blocked by sand, can effectively reduce sand card risk.
For achieving the above object, the technical solution adopted in the utility model is as follows:
A kind of multi-stage water power that is applicable to sprays the hydraulic centralizing device of pressure break, comprise centralizer body, set upright rib and wiper block, set upright and have mounting groove on the rib, wiper block outwards embeds in centralizer body and is arranged on the mounting groove, it is characterized in that: be arranged with the anti-sandpipe of elasticity on the described centralizer body inwall, and elasticity is prevented the place that is communicated with of closed front mounting groove with the centralizer body inner chamber of sandpipe.
The length of the anti-sandpipe of described elasticity is communicated with the diameter at place greater than mounting groove and centralizer body inner chamber, and elasticity prevents that the outer wall of sandpipe is connected with the centralizer body inner thread.
The anti-sandpipe outer wall of described wiper block and elasticity closely cooperates.
The described external diameter of rib of setting upright is greater than the external diameter of centralizer body.
Adopt advantage of the present utility model to be:
One, in the utility model, be arranged with the anti-sandpipe of elasticity on the described centralizer body inwall, and the closed front mounting groove of the anti-sandpipe of elasticity and the place that is communicated with of centralizer body inner chamber, adopt this structure, under the pressure effect of intraluminal fluid power, promote the anti-sandpipe of elasticity, because elasticity sand control pipe is flexible, therefore under pressure, the anti-sandpipe of elasticity is expanded in mounting groove, outwards promote wiper block, reach the purpose of hydraulic pressure seat card, and because elasticity is prevented the place that is communicated with of closed front mounting groove with the centralizer body inner chamber of sandpipe, make the grit in the liquid can not enter in the mounting groove, wiper block can not blocked by sand, can effectively reduce sand card risk.
Two, in the utility model, the length of the anti-sandpipe of described elasticity is communicated with the diameter at place greater than mounting groove and centralizer body inner chamber, when this structure is expanded the anti-sandpipe of elasticity in the mounting groove under the effect of intraluminal fluid pressure, the anti-sandpipe two ends of elasticity and centralizer body inwall also can be connected firmly, guaranteed the reliability of elasticity sand control duct occlusion connection place, and the outer wall of the anti-sandpipe of elasticity is connected with the centralizer body inner thread, employing is threaded and not only is easy for installation and removal, but also is convenient to adjust the anti-position of sandpipe in centralizer body of elasticity.
Three, in the utility model, the anti-sandpipe outer wall of described wiper block and elasticity closely cooperates, and adopts this structure, when the expansion in the mounting groove of the anti-sandpipe of elasticity hour also can guarantee outwards to promote wiper block, reaches the purpose of hydraulic pressure seat card.
Four, in the utility model, the described external diameter of rib of setting upright is greater than the external diameter of centralizer body, this structure has remedied the gap between centralizer and the sleeve pipe, finish the function that starts grappling, reach the purpose of hydraulic pressure seat card, therefore also just reduce the vibration of tubing string in work progress, can both play important effect to the efficient that improves packer application life and abrasive perforating.
Description of drawings
Fig. 1 is the utility model structural representation
Be labeled as among the figure: 1, centralizer body, 2, set upright rib, 3, wiper block, 4, the anti-sandpipe of elasticity, 5, mounting groove.
The specific embodiment
Embodiment 1
A kind of multi-stage water power that is applicable to sprays the hydraulic centralizing device of pressure break, comprise centralizer body 1, set upright rib 2 and wiper block 3, set upright and have mounting groove 5 on the rib 2, wiper block 3 outwards embeds in centralizer body 1 and is arranged on the mounting groove 5, be arranged with the anti-sandpipe 4 of elasticity on described centralizer body 1 inwall, and elasticity is prevented the place that is communicated with of closed front mounting groove 5 with centralizer body 1 inner chamber of sandpipe 4.The material of the anti-sandpipe 4 of elasticity does not have specific (special) requirements, adopts existing elastomeric material to get final product.
Preferred embodiment of the present utility model is, the length of the anti-sandpipe 4 of described elasticity is communicated with the diameter at place greater than mounting groove 5 and centralizer body 1 inner chamber, and elasticity prevents that the outer wall of sandpipe 4 is connected with centralizer body 1 inner thread.
Another preferred embodiment of the present utility model is, described wiper block 3 closely cooperates with anti-sandpipe 4 outer walls of elasticity, but is not limited to closely cooperate, and also certain clearance can be arranged, as long as in the time of guaranteeing that the anti-sandpipe 4 of elasticity is expanded in the mounting groove, can be with wiper block 3 extrapolated getting final product.
Another preferred embodiment of the present utility model is that the described external diameter of rib 2 of setting upright reduces the gap between centralizer and the sleeve pipe greater than the external diameter of centralizer body 1.
Another preferred embodiment of the present utility model is that the anti-sandpipe 4 of elasticity adopts the structure device of three wings sand control grappling, can effectively improve working security, has prolonged the tubing string life-span.
Operating principle of the present utility model is: under the pressure effect of intraluminal fluid power, outwards promote the anti-sandpipe of elasticity, outwards promote wiper block by the anti-sandpipe of elasticity again, make wiper block outwards mobile, the pipe internal pressure is more big, outwards the dynamics that promotes is also just more big, wiper block is released, realized grappling, simultaneously because the deadening of the anti-sandpipe of elasticity, grit in the liquid can not enter in the mounting groove, guarantees to set upright soon can not blocked by sand.
Embodiment 2
Connection of the present utility model: when needs connect centralizer, earlier with each parts inspection and clean up, particularly be arranged on and set upright the mounting groove 5 that wiper block 3 is installed in rib 2 stage casings, clean up, avoid taking place the blocked portion phenomenon, during installation, earlier wiper block 3 is outwards put into mounting groove in centralizer body 1, set upright the wiper block mounting groove that arranges in the face of accurate, for sand control, the gap can be less, if feel tight a little when putting into, tapping from inside to outside can be packed wiper block 3 into; The elasticity of packing in centralizer body 1 is then prevented sandpipe 4, and the interior circle of the anti-sandpipe 4 of elasticity and centralizer body 1 is by screwed connection.
Embodiment 3
The field conduct example: western somewhere carrying out horizontal well construction at home, the construction layer position is long 3 layers of Triassic Yanchang Formation, schematic design is distinguished adding ceramic 7m for 8 speckings of horizontal segment are carried out the jetting sand fracturing 3+ 10m 3+ 12m 3+ 15m 3+ 15m 3+ 12m 3+ 10m 3+ 7m 3, operating tool string adopts the efficient pipe string combination of horizontal well: 2 7/8 〞 external upset tubing+hydraulic type safety joint+PSK344-110 sprays packer+sliding sleeve and is located joint+one-level waterpower spray gun+K344-108 packer+ball-and-seat+eye pipe+plug.
Earlier with No. 1 spray gun this well four sections (floor) has been carried out the jetting pressing crack construction, after the pressurization, the centralizer on the tubular column structure string is grappling smoothly all, because sand card phenomenon does not take place in effectively stopping of the grit in the anti-4 pairs of liquid of sandpipe of elasticity.
In the work progress, with the one-level spray gun jetting construction is implemented in the 3rd section layer position earlier, begin normal jetting pressing crack construction then, work progress does not tremble, and illustrates that the centralizer grappling that connects is normal.This construction adopts this instrument to carry out the jetting pressure break of four sections (layers) smoothly, has finished construction task fast and effectively, shortens about 1.5 days of construction period.

Claims (4)

1. one kind is applicable to that multi-stage water power sprays the hydraulic centralizing device of pressure break, comprise centralizer body (1), set upright rib (2) and wiper block (3), set upright and have mounting groove (5) on the rib (2), wiper block (3) outwards embeds in centralizer body (1) and is arranged on the mounting groove (5), it is characterized in that: be arranged with the anti-sandpipe (4) of elasticity on described centralizer body (1) inwall, and elasticity is prevented the place that is communicated with of closed front mounting groove (5) with centralizer body (1) inner chamber of sandpipe (4).
2. the multi-stage water power that is applicable to according to claim 1 sprays the hydraulic centralizing device of pressure break, it is characterized in that: the length that described elasticity is prevented sandpipe (4) is communicated with the diameter at place greater than mounting groove (5) and centralizer body (1) inner chamber, and the outer wall of the anti-sandpipe (4) of elasticity is connected with centralizer body (1) inner thread.
3. the multi-stage water power that is applicable to according to claim 1 sprays the hydraulic centralizing device of pressure break, it is characterized in that: described wiper block (3) closely cooperates with anti-sandpipe (4) outer wall of elasticity.
4. the multi-stage water power that is applicable to according to claim 1 sprays the hydraulic centralizing device of pressure break, and it is characterized in that: the described external diameter of rib (2) of setting upright is greater than the external diameter of centralizer body (1).
CN 201320091695 2013-02-28 2013-02-28 Hydraulic centralizer applicable to multi-stage hydraulic jet fracturing Expired - Lifetime CN203161114U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320091695 CN203161114U (en) 2013-02-28 2013-02-28 Hydraulic centralizer applicable to multi-stage hydraulic jet fracturing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320091695 CN203161114U (en) 2013-02-28 2013-02-28 Hydraulic centralizer applicable to multi-stage hydraulic jet fracturing

Publications (1)

Publication Number Publication Date
CN203161114U true CN203161114U (en) 2013-08-28

Family

ID=49022307

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320091695 Expired - Lifetime CN203161114U (en) 2013-02-28 2013-02-28 Hydraulic centralizer applicable to multi-stage hydraulic jet fracturing

Country Status (1)

Country Link
CN (1) CN203161114U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105909188A (en) * 2016-06-03 2016-08-31 上海鑫地能源科技有限公司 Hydraulic vibration centering device and drilling method
CN110080696A (en) * 2019-06-04 2019-08-02 武汉金博锐精密制造有限公司 A kind of novel hydropower centralizer
CN112145148A (en) * 2020-10-10 2020-12-29 吕楠 Adjustable sand setting gas anchor for pumping well

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105909188A (en) * 2016-06-03 2016-08-31 上海鑫地能源科技有限公司 Hydraulic vibration centering device and drilling method
CN105909188B (en) * 2016-06-03 2018-02-09 上海鑫地能源科技有限公司 The centralizer and drilling method of hydraulic vibrating
CN110080696A (en) * 2019-06-04 2019-08-02 武汉金博锐精密制造有限公司 A kind of novel hydropower centralizer
CN112145148A (en) * 2020-10-10 2020-12-29 吕楠 Adjustable sand setting gas anchor for pumping well

Similar Documents

Publication Publication Date Title
CN106223922B (en) Shale gas horizontal well proppant intra-seam shielding temporary plugging staged fracturing process
CN103850711B (en) Salt hole air reserved storeroom twin-well banking process
CN108952655B (en) Normal-pressure shale gas screen pipe well completion hydraulic jet volume fracturing method
CN109267983B (en) Horizontal well repeated fracturing device and method based on open hole preset pipe string well completion
CN104612624A (en) Staged fracturing method for degradable bridge plug, timing sliding sleeve, staged fracturing tubular column and strata
RU2537719C1 (en) Method of multiple hydrofracturing of formation in open hole of horizontal well
CN105484719A (en) Method for improving multi-cluster crack initiation effectiveness by blocking seams through multi-scale soluble balls
CN104653153B (en) A kind of split-type reducing ball seat
CN106703774B (en) Drawing type hydraulic jetting fracturing and pitching sliding sleeve sand washing connection make device and method
CN104695923A (en) Method for realizing sectional multi-cluster fracture of horizontal well by adopting soluble balls
CN203161114U (en) Hydraulic centralizer applicable to multi-stage hydraulic jet fracturing
CN111119826B (en) Coiled tubing staged fracturing string and string fracturing method
CN105888638A (en) Timing sliding sleeve fracturing pipe column
CN102953719A (en) Drag type packer-less hydraulic jet pulsating acid fracturing device and method
CN204476347U (en) Degradable bridging plug, timing sliding sleeve and fracturing strings
CN105888639A (en) Feeding-controlling full-bore sliding sleeve sectional fracturing tube column
CN102877824A (en) Horizontal well staged and multi-cluster fracturing method by hydraulic jetting
CN105507867B (en) A kind of device and method for generating wellbore crack
CN105649598B (en) The double cluster hydraulic jetting fracturing integrated pipe columns of Archimedes's double helix shunt
CN102434192A (en) Device and method for enhancing coal seam fracturing effect
CN107025346A (en) Horizontal well integral intelligent well completion design method
CN107654207B (en) Section method for fixed-point preset sand plug of coiled tubing horizontal well
CN104343424A (en) Coalbed-methane horizontal-well PE (poly ethylene) screen pipe well completion application process method
CN203808896U (en) Long-section casing damage well expansion pipe double-card casing pipe layered packing repairing device
CN103195402B (en) A kind of system and method for staged fracturing of coal bed gas well

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130828