CN202925714U - Thick wall - Google Patents
Thick wall Download PDFInfo
- Publication number
- CN202925714U CN202925714U CN 201220593883 CN201220593883U CN202925714U CN 202925714 U CN202925714 U CN 202925714U CN 201220593883 CN201220593883 CN 201220593883 CN 201220593883 U CN201220593883 U CN 201220593883U CN 202925714 U CN202925714 U CN 202925714U
- Authority
- CN
- China
- Prior art keywords
- thick wall
- concrete
- bottom plate
- wall
- concrete block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
Description
技术领域 technical field
本申请属于土木工程领域。This application belongs to the field of civil engineering.
背景技术 Background technique
土木工程中很多工程需要采用尺寸较大的厚墙,比如:核电站、军用掩体、大坝、金库、重力式挡土墙等等。这些建筑物或构筑物中的墙体厚度经常会达到几米-几百米,目前我们修筑厚墙时首选材料为钢筋混凝土,因此会不可避免的遇到大体积混凝土浇筑这个工程难题。Many projects in civil engineering require the use of large thick walls, such as: nuclear power plants, military bunkers, dams, vaults, gravity retaining walls, etc. The thickness of the walls in these buildings or structures often reaches several meters to hundreds of meters. At present, when we build thick walls, the preferred material is reinforced concrete, so it is inevitable to encounter the engineering problem of mass concrete pouring.
大体积混凝土的浇筑时在支模过程中要使用大量的模板,且对模板的刚度,支撑的强度有很高的要求。在大体积混凝土浇筑过程中,跑模、垮模等问题不仅使工程的质量难以得到保证,而且对施工人员的安全构成威胁。When pouring mass concrete, a large number of templates are used in the process of setting up the formwork, and there are high requirements for the rigidity of the template and the strength of the support. In the process of mass concrete pouring, problems such as mold runout and mold collapse not only make it difficult to guarantee the quality of the project, but also pose a threat to the safety of construction personnel.
水化热是大体积混凝土浇筑过程中最难解决的问题。由于水泥在水化时会释放一定的热量,而混凝土的导热系数较小,因此热量难以散发出来会在混凝土中积聚,在浇筑后2-3天内会达到大值,混凝土表面和中心温差高达50摄氏度,由于混凝土的热胀冷缩会把外层的混凝土胀开,在冷却过程中,内部混凝土收缩也会使混凝土产生裂缝。虽然现有施工技术中采用了一系列的冷却降温方法,同时还采用分层、分段浇筑方法,但这种方法的施工间歇期长达5天以上,施工进度慢,因此饱受工程界诟病。Heat of hydration is the most difficult problem to solve in the process of mass concrete pouring. Because cement will release a certain amount of heat when it is hydrated, and the thermal conductivity of concrete is small, so the heat is difficult to dissipate and will accumulate in the concrete, which will reach a maximum value within 2-3 days after pouring, and the temperature difference between the surface and the center of the concrete is as high as 50 Celsius, due to the thermal expansion and contraction of concrete, the outer layer of concrete will expand, and during the cooling process, the inner concrete will shrink and cause cracks in the concrete. Although a series of cooling and cooling methods are used in the existing construction technology, layered and segmented pouring methods are also used, but the construction interval of this method is as long as more than 5 days, and the construction progress is slow, so it has been criticized by the engineering community .
在厚墙设计中,配筋方法往往是构造配筋,而不是计算配筋,而且构造配筋的钢筋用量是计算配筋的2倍左右,而我们构造配筋的钢筋用量的决定因素是混凝土的水化热产生的胀缩作用。因此如果能解决厚墙浇筑过程中水化热积聚的问题,在实际工程中就可以节约大约50%的钢筋用量,为工程带来极大的经济效益,也节省了大量的资源。In the design of thick walls, the reinforcement method is often structural reinforcement, rather than calculated reinforcement, and the amount of steel reinforcement used for structural reinforcement is about 2 times that of calculated reinforcement, and the decisive factor for the amount of steel reinforcement used in our structural reinforcement is concrete Expansion and contraction caused by the heat of hydration. Therefore, if the problem of hydration heat accumulation in the process of pouring thick walls can be solved, about 50% of the steel bar consumption can be saved in actual engineering, which will bring great economic benefits to the project and save a lot of resources.
现有技术还采用水化热较小的水泥,减小水泥量用量,增加灰煤灰等掺和料的用量,添加减水剂等措施来减少水化热,减少裂缝。但这些措施的效果仍然有限,而且会严重影响工程结构的耐久性。因此有必要开发一种新型的厚墙及其施工方法。In the prior art, cement with a smaller heat of hydration is used, the amount of cement is reduced, the amount of admixtures such as ash and coal ash is increased, and water reducers are added to reduce the heat of hydration and cracks. But the effect of these measures is still limited, and will seriously affect the durability of engineering structures. Therefore it is necessary to develop a novel thick wall and its construction method.
发明内容 Contents of the invention
本申请提供一种新型的厚墙来达到解决水化热产生的一系列问题,加快了施工进度,省去了支模等工序。This application provides a new type of thick wall to solve a series of problems caused by heat of hydration, speed up the construction progress, and save steps such as formwork.
本申请的目的是通过以下技术方案实现的:The purpose of this application is achieved through the following technical solutions:
一种厚墙由灌芯配筋混凝土砌块砌体墙、底板和现浇混凝土部分组成,沿厚墙长度方向和厚度方向的灌芯配筋混凝土砌块砌体墙将厚墙呈棋盘状分割成若干个长方形的小格子,每个小格子由灌芯配筋混凝土砌块砌体墙、底板和现浇混凝土部分组成,混凝土砌块砌体墙与现浇混凝土之间通过混凝土粘结力形成一个整体,灌芯配筋混凝土砌块砌体墙和现浇混凝土与底板之间通过与底板配置的竖筋拉结形成一个整体。A thick wall is composed of a core-reinforced concrete block masonry wall, a base plate and cast-in-place concrete parts, and the core-reinforced concrete block masonry wall along the length direction and thickness direction of the thick wall divides the thick wall into a checkerboard shape It is formed into several small rectangular grids, and each small grid is composed of core-filled reinforced concrete block masonry walls, bottom slabs and cast-in-place concrete parts. As a whole, the core-filled reinforced concrete block masonry wall, the cast-in-place concrete and the bottom slab form a whole through the vertical bars arranged with the bottom slab.
上述厚墙的灌芯配筋混凝土砌块砌体墙由普通混凝土砌块采用通缝或错缝的方式砌筑,从而保证孔洞对齐,每砌1-3皮砌块,铺放沿墙布置的水平拉结钢筋,每砌筑1-2米高,在对齐的孔洞中插入竖向钢筋,竖向钢筋与底板上预留的钢筋搭接或焊接,然后浇注芯柱,并振捣密实,当采用搭接方式时,所插入的竖向钢筋长度为两倍搭接长度加上砌墙高度采用焊接方式时,插入的钢筋长度为所砌墙的高度,沿厚墙长度方向的灌芯配筋混凝土砌块砌体墙之间的间距为0.6-1.2米,沿厚墙厚度方向的灌芯配筋混凝土砌块砌体墙之间的距离3-4米,这样既能方便工人的施工又能解决水化热积聚的问题。灌芯配筋混凝土砌块砌体墙可以是直线也可以采用弧形砌块砌成曲线形,可以适应各种建筑物和构筑物。The concrete block masonry wall with cored reinforcement for the above thick wall is built by ordinary concrete blocks with through joints or staggered joints to ensure the alignment of holes. Horizontally tie steel bars, each masonry is 1-2 meters high, insert vertical steel bars in the aligned holes, the vertical steel bars are lapped or welded with the steel bars reserved on the bottom plate, and then the core column is poured and vibrated compactly. When the lap joint method is used, the length of the inserted vertical steel bar is twice the length of the lap joint plus the height of the wall. When the welding method is used, the length of the inserted steel bar is the height of the wall. The distance between the concrete block masonry walls is 0.6-1.2 meters, and the distance between the concrete block masonry walls with core filling and reinforcement along the thickness direction of the thick wall is 3-4 meters, which can not only facilitate the construction of workers but also Solve the problem of heat of hydration build-up. The concrete block masonry wall with core filling and reinforcement can be straight or curved with curved blocks, and can be adapted to various buildings and structures.
上述厚墙的底板按照设计要求采用双层双向的配筋方式进行配筋,底板中的钢筋与基础承台中的钢筋焊接,从而底板与地基和基础形成一个整体,底板上预留有砌块定位槽,定位槽呈棋盘状分布,沿厚墙的长度方向,每隔0.6-1.2米预留定位槽,沿厚墙厚度方向每隔3-4米预留定位槽,定位槽的深度为0.2-0.3米,宽度由所采用的砌块尺寸决定,定位槽将底板分割成若干个小格子,在定位槽中部和小格子中部预留竖向拉结钢筋,拉结钢筋的间距与将采用的砌块的尺寸相匹配。The bottom slab of the above-mentioned thick wall is reinforced by double-layer two-way reinforcement according to the design requirements. The steel bars in the bottom slab are welded with the steel bars in the foundation cap, so that the bottom slab, the foundation and the foundation form an integral body, and blocks are reserved for positioning on the bottom slab. Slots, the positioning slots are distributed in a checkerboard shape. Along the length direction of the thick wall, positioning slots are reserved every 0.6-1.2 meters, and positioning slots are reserved every 3-4 meters along the thickness direction of the thick wall. The depth of the positioning slots is 0.2- 0.3 meters, the width is determined by the size of the block used, the positioning groove divides the bottom plate into several small grids, and the vertical tie bars are reserved in the middle of the positioning groove and the middle of the small grids. The dimensions of the blocks match.
上述厚墙的现浇部分,模板为灌芯配筋混凝土砌块砌体墙,钢筋为预先扎好的钢筋笼,通过塔吊或吊车将钢筋笼吊装到每一个小格中,采用隔一浇一或连续浇筑的方式进行浇筑,混凝土采用水化热小的配合比,混凝土强度等级和钢筋强度等级按设计要求选用,浇筑后振捣密实,并进行养护,必要时采用一些常规降温措施。For the cast-in-place part of the above-mentioned thick wall, the formwork is concrete block masonry wall with core filling and reinforcement, and the steel bars are pre-tied steel cages. The steel cages are hoisted into each small cell by a tower crane or a crane. Or continuous pouring. Concrete adopts a mix ratio with a small heat of hydration. The strength grade of concrete and the strength grade of steel bars are selected according to the design requirements.
如上所述的厚墙施工步骤如下:The steps of thick wall construction as described above are as follows:
1、准备工作,包括场地平整,砌块的预制,钢筋笼绑扎,机械设备的进场等;1. Preparatory work, including site leveling, prefabrication of blocks, binding of steel cages, entry of mechanical equipment, etc.;
2、开挖基坑,浇筑承台,承台预留钢骨预埋件,在地基上面按照设计的混凝土强度等级和厚度要求浇筑素混凝土垫层;2. Excavate the foundation pit, pour the cap, reserve the steel frame embedded parts for the cap, and pour plain concrete cushion on the foundation according to the designed concrete strength grade and thickness;
3、在垫层上放线,按如下方法定位出预留定位槽的位置:沿厚墙的长度方向,每隔0.6-1.2米预留定位槽,沿厚墙厚度方向每隔3-4米预留定位槽,定位槽的宽度由所采用的砌块尺寸决定。然后铺设双层双向钢筋网,将预埋的竖向钢筋和浇筑承台时钢骨预埋件焊接或绑扎在钢筋网上,竖向预埋钢筋的位置位于定位槽中部和被定位槽所分割成的小格子的中部,定位槽支上侧模,浇筑混凝土,振捣密实;3. Lay out the line on the cushion, and locate the position of the reserved positioning slot according to the following method: along the length direction of the thick wall, reserve positioning slots every 0.6-1.2 meters, and every 3-4 meters along the thickness direction of the thick wall Reserve a positioning slot, the width of which is determined by the size of the blocks used. Then lay double-layer two-way reinforcement mesh, weld or bind the pre-embedded vertical reinforcement and steel frame embedded parts on the reinforcement mesh when pouring the cap. In the middle of the small grid, the side formwork is supported by the positioning groove, and the concrete is poured and compacted by vibrating;
4、在预留的定位槽中砌筑砌体墙,砌墙的方式采用通缝对齐砌筑或错缝搭接砌筑,从而保证孔洞对齐,每砌1-3皮砖,放一层拉结钢筋,每砌筑1-2米高,在对齐的孔洞中插入竖向钢筋,竖向钢筋与底板上预留的钢筋搭接或焊接,然后浇注芯柱,并振捣密实,所插入的竖向钢筋长度为两倍搭接长度加上砌墙高度,钢筋搭接或焊接应满足规范要求;4. Build a masonry wall in the reserved positioning groove. The way of building the wall is to align the joints or overlap the joints to ensure that the holes are aligned. For each 1-3 skin bricks, put a layer of pulley Construct steel bars, each masonry is 1-2 meters high, insert vertical steel bars in the aligned holes, the vertical steel bars are lapped or welded with the reserved steel bars on the bottom plate, and then the core column is poured and vibrated compactly. The length of the vertical reinforcement is twice the length of the overlap plus the height of the wall, and the overlap or welding of the reinforcement should meet the requirements of the specification;
5、吊装钢筋笼,利用塔吊或者吊车将钢筋笼吊装就位,钢筋笼之间用通过焊接短钢筋的方式形成有效连结;5. Hoisting the steel cage, using a tower crane or a crane to hoist the steel cage in place, and form an effective connection between the steel cages by welding short steel bars;
6、往砌块砌体墙之间部分浇筑混凝土,采用隔一浇一或连续浇筑的顺序浇筑,每次浇筑1-2米高;6. Concrete is poured between the block masonry walls in the order of pouring every other or continuous pouring, each pouring is 1-2 meters high;
7、养护2-3天后,浇筑剩下的需浇筑现浇混凝土的部分;7. After curing for 2-3 days, pour the rest of the cast-in-place concrete;
8、重复流程4-7,循环施工。8. Repeat process 4-7, cycle construction.
本申请与现有技术相比有如下优点:Compared with the prior art, the present application has the following advantages:
1、省去了支设模板的工序,所砌筑的薄墙既是模板又是厚墙的一部分;1. The process of supporting formwork is omitted, and the thin wall built by masonry is both a formwork and a part of a thick wall;
2、减少水化热的积聚,减小混凝土内部与表面的温差,从而减少裂缝的产生,使厚墙的耐久性和安全性能得到有效的提高;2. Reduce the accumulation of heat of hydration, reduce the temperature difference between the interior and the surface of the concrete, thereby reducing the generation of cracks, and effectively improving the durability and safety of thick walls;
3、经济效应好,节省钢筋和工程用水。3. Good economic effect, saving steel bars and engineering water.
4、施工方便,简化了工序,加快施工进度。4. The construction is convenient, the process is simplified, and the construction progress is accelerated.
附图说明 Description of drawings
图1为本申请的底板结构示意图;Fig. 1 is the schematic diagram of the base plate structure of the present application;
图2为砌筑一皮砌块示意图;Fig. 2 is a schematic diagram of building a skin block;
图3为灌芯前示意图;Figure 3 is a schematic diagram before filling the core;
图4为灌芯后吊装钢筋笼示意图;Figure 4 is a schematic diagram of hoisting the reinforcement cage after filling the core;
图5为浇筑混凝土后示意图。Figure 5 is a schematic diagram after pouring concrete.
附图标注说明:Notes on drawings:
1-底板 2-定位槽 3-竖向拉结钢筋 4-竖向钢筋 5-灌芯配筋砌块砌体墙 6-沿墙布置的水平钢筋 7-灌芯配筋砌块砌体墙8-钢筋笼 9-现浇混凝土。1-Bottom plate 2-Location groove 3-Vertical tie reinforcement 4-Vertical reinforcement 5-Core reinforcement block masonry wall 6-Horizontal reinforcement arranged along the wall 7-Core reinforcement block masonry wall 8 - Reinforcement cage 9 - Cast-in-place concrete.
具体实施方式 Detailed ways
结合附图对本申请作更一进步说明:In conjunction with the accompanying drawings, the application is described further:
实施例1:Example 1:
准备工作,包括场地平整,砌块的预制,钢筋笼绑扎,机械设备的进场等;开挖基坑,浇筑承台,承台预留钢骨预埋件,在地基上面按照设计要求采用C10混凝土浇筑素混凝土垫层,垫层厚300mm;然后在垫层上放线,按如下方法定位出预留定位槽的位置:沿厚墙的长度方向,每隔0.6米预留定位槽,沿厚墙厚度方向每隔4米预留定位槽,定位槽的宽度由所采用的砌块尺寸决定,本实施例选用390x240x190mm砌块,因此定位槽宽度为250mm。然后铺设双层双向钢筋网,将承台中钢骨预埋件和竖向预留钢筋焊接或绑扎在钢筋网上,竖向预埋钢筋的位置位于定位槽中部和被定位槽所分割成的小格子的中部,定位槽中每两根预埋钢筋的间距为195mm,然后支上侧模,浇筑混凝土,振捣密实;然后在预留的定位槽中砌筑砌体墙,砌墙的方式采用通缝砌筑方式砌筑,保证孔洞对齐,每砌1皮砖,放一层拉结钢筋,每砌筑2米高,在对齐的孔洞中插入竖向钢筋,竖向钢筋与底板上预留的钢筋搭接,然后浇注芯柱,并振捣密实,所插入的竖向钢筋长度为2.4m,钢筋搭接或焊接应满足规范要求;吊装钢筋笼,利用塔吊或者吊车将钢筋笼吊装就位,钢筋笼之间用通过焊接短钢筋的方式形成有效连结;往砌块砌体墙之间部分浇筑混凝土,采用隔一浇一或连续浇筑的顺序浇筑,每次浇筑2米高;养护2-3天后,浇筑剩下的需浇筑现浇混凝土的部分;然后再砌砌体墙,如此循环施工。Preparatory work, including site leveling, prefabrication of blocks, tying of steel cages, entry of mechanical equipment, etc.; excavation of foundation pits, pouring of caps, pre-embedded steel parts for caps, and C10 on the foundation according to the design requirements Concrete pouring plain concrete cushion, the cushion is 300mm thick; then put the line on the cushion, and locate the position of the reserved positioning groove according to the following method: along the length direction of the thick wall, reserve positioning grooves every 0.6 meters, along the thick wall Positioning grooves are reserved every 4 meters in the thickness direction of the wall. The width of the positioning grooves is determined by the size of the blocks used. In this embodiment, 390x240x190mm blocks are selected, so the width of the positioning grooves is 250mm. Then lay double-layer two-way reinforcement mesh, weld or bind the embedded parts of the steel frame in the cap and the vertical reserved steel bars on the reinforcement mesh, and the position of the vertical embedded steel bars is located in the middle of the positioning groove and the small grid divided by the positioning groove In the middle of the center, the distance between every two pre-embedded steel bars in the positioning groove is 195mm, and then the side formwork is supported, concrete is poured, and the concrete is vibrated and compacted; Seam masonry is used to ensure that the holes are aligned. For each brick, a layer of tie reinforcement is placed. Each masonry is 2 meters high. Vertical reinforcement is inserted into the aligned holes. Lap the reinforcement, then cast the core column, and vibrate it compactly. The length of the inserted vertical reinforcement is 2.4m. The overlap or welding of the reinforcement should meet the requirements of the specification; hoist the reinforcement cage by using a tower crane or a crane to hoist the reinforcement cage in place. The effective connection between the steel cages is formed by welding short steel bars; the concrete is poured between the block masonry walls, and the concrete is poured every other time or continuously, and the height of each pour is 2 meters; maintenance 2-3 Days later, pour the remaining part that needs to be poured with cast-in-place concrete; then build masonry walls, and so on.
实施例2:Example 2:
准备工作,包括场地平整,砌块的预制,钢筋笼绑扎,机械设备的进场等;开挖基坑,浇筑承台,承台预留钢骨预埋件,在地基上面按照设计要求采用C15混凝土浇筑素混凝土垫层,垫层厚100mm;然后在垫层上放线,按如下方法定位出预留定位槽的位置:沿厚墙的长度方向,每隔1.2米预留定位槽,沿厚墙厚度方向每隔3米预留定位槽,定位槽的宽度由所采用的砌块尺寸决定,本实施例选用390x240x190mm砌块,因此定位槽宽度为250mm。然后铺设双层双向钢筋网,将承台中钢骨预埋件和竖向预留钢筋焊接或绑扎在钢筋网上,竖向预埋钢筋的位置位于定位槽中部和被定位槽所分割成的小格子的中部,定位槽中每两根预埋钢筋的间距为195mm,然后支上侧模,浇筑混凝土,振捣密实;然后在预留的定位槽中砌筑砌体墙,砌墙的方式采用错缝搭接砌筑方式砌筑,保证孔洞对齐,每砌3皮砖,放一层拉结钢筋,每砌筑1米高,在对齐的孔洞中插入竖向钢筋,竖向钢筋与底板上预留的钢筋焊接,然后浇注芯柱,并振捣密实,所插入的竖向钢筋长度为1.2m,钢筋搭接或焊接应满足规范要求;吊装钢筋笼,利用塔吊或者吊车将钢筋笼吊装就位,钢筋笼之间用通过焊接短钢筋的方式形成有效连结;往砌块砌体墙之间部分浇筑混凝土,采用隔一浇一或连续浇筑的顺序浇筑,每次浇筑1米高;养护2-3天后,浇筑剩下的需浇筑现浇混凝土的部分;然后再砌砌体墙,如此循环施工。Preparatory work, including site leveling, prefabrication of blocks, tying of steel cages, entry of mechanical equipment, etc.; excavation of foundation pits, pouring of caps, pre-embedded steel parts for caps, and C15 on the foundation according to the design requirements Concrete pouring plain concrete cushion, the cushion is 100mm thick; then put the line on the cushion, and locate the position of the reserved positioning groove according to the following method: along the length direction of the thick wall, reserve positioning grooves every 1.2 meters, along the thick wall Positioning slots are reserved every 3 meters in the thickness direction of the wall. The width of the positioning slots is determined by the size of the blocks used. In this embodiment, 390x240x190mm blocks are selected, so the width of the positioning slots is 250mm. Then lay double-layer two-way reinforcement mesh, weld or bind the embedded parts of the steel frame in the cap and the vertical reserved steel bars on the reinforcement mesh, and the position of the vertical embedded steel bars is located in the middle of the positioning groove and the small grid divided by the positioning groove In the middle of the center, the distance between every two pre-embedded steel bars in the positioning groove is 195mm, then the side formwork is supported, concrete is poured, and the concrete is vibrated and compacted; Seam lap joint masonry is used to ensure the alignment of the holes. For every 3 skin bricks, a layer of tie reinforcement is placed. Each masonry is 1 meter high, and vertical reinforcement is inserted in the aligned holes. Weld the remaining steel bars, then cast the core column, and vibrate it compactly. The length of the inserted vertical steel bar is 1.2m. The overlapping or welding of the steel bar should meet the requirements of the specification; hoist the steel bar cage by using a tower crane or a crane to hoist the bar cage in place The steel cages are effectively connected by welding short steel bars; the concrete is poured between the block masonry walls, and the concrete is poured every other time or continuously, and the height of each pour is 1 meter; maintenance 2- After 3 days, pour the remaining parts that need to be poured with cast-in-place concrete; then build masonry walls, and so on.
上述附图及实施例仅用于说明本申请较优选的一种,对本申请的保护范围不构成任何限制,本领域的技术人员在本实用新型方案范围内进行通常的变化和替换都应包含在本实用新型的保护范围之内。The above-mentioned drawings and embodiments are only used to illustrate the preferred one of the present application, and do not constitute any limitation to the protection scope of the present application. Those skilled in the art carry out common changes and replacements within the scope of the utility model solution and all should be included in the scope of the present invention. Within the protection scope of the present utility model.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220593883 CN202925714U (en) | 2012-01-10 | 2012-11-12 | Thick wall |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201220008042 | 2012-01-10 | ||
CN201220008042.6 | 2012-01-10 | ||
CN 201220593883 CN202925714U (en) | 2012-01-10 | 2012-11-12 | Thick wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202925714U true CN202925714U (en) | 2013-05-08 |
Family
ID=48215689
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220593883 Expired - Fee Related CN202925714U (en) | 2012-01-10 | 2012-11-12 | Thick wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202925714U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102561551A (en) * | 2012-01-10 | 2012-07-11 | 湖南大学 | Thick wall and construction method thereof |
-
2012
- 2012-11-12 CN CN 201220593883 patent/CN202925714U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102561551A (en) * | 2012-01-10 | 2012-07-11 | 湖南大学 | Thick wall and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107882240B (en) | A kind of recycled block concrete prefabricated laminated board and its production process | |
CN104924452A (en) | Tension pile splicing device for prestressed concrete solid square pile | |
CN103306501B (en) | Energy-saving domestic architecture with cast-in-place industrial gypsum bearing wall and manufacturing method thereof | |
CN107905424A (en) | Full prefabricated band splicing groove unidirectional harden structure, making and assembly method | |
CN105002819A (en) | Gradient-structure composite bridge pier | |
CN104947846B (en) | A kind of prefabricated integral frame light filling lining and preparation method thereof | |
CN108104284A (en) | Shear wall steel arm is embedded in the wallboard connecting structure and assembly method of floor | |
CN106437034A (en) | Steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column and preparation method thereof | |
CN102561551A (en) | Thick wall and construction method thereof | |
CN108018972A (en) | Full precast floor slab and laminated floor slab combining structure, making and assembly method | |
CN208023601U (en) | A kind of prefabricated pile foundation support table side form of mutual buckle type | |
CN103821263A (en) | Precast assembly self-heat preservation concrete shear wall system and construction method thereof | |
CN210117716U (en) | Trapezoidal foundation ditch lateral wall concrete typical forms of elevartor shaft | |
CN204001278U (en) | A kind of prefabricated assembled self-insulating concrete shear wall system | |
CN108166681A (en) | A kind of assembled partial precast part external wrapping concrete combination beam and its construction method | |
CN114592688A (en) | Construction Method of Obliquely Reinforced Reinforced Concrete Shear Wall Based on Equivalent Member Model | |
CN113668730A (en) | An assembled mixed recycled aggregate concrete composite wallboard and preparation method thereof | |
CN202925714U (en) | Thick wall | |
CN110820983B (en) | A longitudinal connection method of prefabricated prefabricated wall panels | |
CN205116220U (en) | Pour cable pit after assembly of L type precast concrete spare | |
CN210288465U (en) | Assembled retaining wall post-cast strip plugging member | |
CN111851861A (en) | Partial prefabricated reinforced structure of existing H-shaped steel column and its construction technology | |
CN111549690A (en) | A low-cost, high-performance rainwater tank-culvert combined structure and its construction method | |
CN105839824B (en) | Shed deckhead construction method | |
CN102403662A (en) | Circuit breaker foundation quick replacement method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130508 Termination date: 20151112 |
|
EXPY | Termination of patent right or utility model |