CN202831102U CN 201220396155 CN201220396155U CN202831102U CN 202831102 U CN202831102 U CN 202831102U CN 201220396155 CN201220396155 CN 201220396155 CN 201220396155 U CN201220396155 U CN 201220396155U CN 202831102 U CN202831102 U CN 202831102U
Authority
CN
China
Prior art keywords
caisson
toilet
blow
casing
captation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN 201220396155
Other languages
Chinese (zh)
Inventor
卫青富
Original Assignee
卫青富
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 卫青富 filed Critical 卫青富
Priority to CN 201220396155 priority Critical patent/CN202831102U/en
Application granted granted Critical
Publication of CN202831102U publication Critical patent/CN202831102U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to the technology field of the building architectural engineering, and definitely relates to a frame used for a toilet caisson and a toilet caisson. The frame used for a toilet caisson consists of a support frame, a catchment device, a ground leakage device and a blow-off pipe connector. The frame is in a superterranean structure. The catchment device is arranged inside the superterranean structure. The pollution discharged pipe connector and the ground leakage device are arranged on the catchment device. The ground leakage device is communicated with the pollution discharged pipe connector to discharge the water collected by the catchment device. The toilet caisson comprises a box body and the frame used for a toilet caisson. A pollution discharged reserved opening is arranged on the inner wall of the box body. The frame used for a toilet caisson is arranged inside the box body. The pollution discharged pipe connector is communicated with the pollution discharged reserved opening. The catchment device is connected with the inner wall of the box body. The frame used for a toilet caisson and a toilet caisson can solve the problem of leaking water of the toilet caisson.

Description

Caisson of toilet is with framework and caisson of toilet
Technical field
The utility model relates to the building engineering technical field, is specifically related to a kind of caisson of toilet with framework and caisson of toilet.
Background technology
Caisson of toilet of the prior art as shown in Figure 1, comprise casing 4, and the base plane of casing 4 is lower than the flooring.Comprise successively leveling layer 3, waterproofing course 6 and cement mortar protective course 2 on the inwall of casing 4; the inside of casing 4 is provided with other pipe-line equipments such as drainage pipeline networks, waterline network in addition; wherein other pipe-line equipments such as drainage pipeline networks, waterline network do not draw in Fig. 1; be filled with slag backfill layer 5 in the inside of casing 4, concreting bed course 1 on slag backfill layer 5.
What caisson of toilet of the prior art adopted is concrete self-waterproof and the dual waterproof scheme that adds waterproofing course, the water of the flushing valve place seepage of ground water or closet can leak into the casing 4 of caisson of toilet, again because do not design dewatering installation in the casing, therefore the water that leaks into casing can only accumulate in the inside of casing 4, in order to prevent that the seepage that accumulates in box house from going out, can waterproof construction be set at casing.Main waterproof construction in the prior art in the casing is the waterproofing course 6 on the inwall of casing 4.
Yet waterproofing course of the prior art is the membranaceous structure in the two-layer water-repellent paint formation of inwall brushing of casing.Its Thickness Ratio of waterproofing course of the prior art is thinner, destroyed easily, and the inside of casing especially the pipelines that arrange of four jiaos of casing places can form four jiaos of brushings, not only increased the difficulty of waterproofing course brushing but also so that the brushing of waterproofing course is inhomogeneous, draw thus waterproof construction in the existing caisson and be not and very stablely the crack may occur, caisson of toilet may along crack-leakage to downstairs, occur and the seepage water problem occur in the water that accumulates in the casing.
The utility model content
The caisson of toilet that the utility model provides can solve caisson of toilet seepage water problem with framework and caisson of toilet.
In order to solve this technical problem, the utility model is achieved in that
The caisson of toilet framework comprises: bracing frame, captation, floor drain apparatus and blow-off pipe interface;
Support frame as described above is aerial construction, and described captation is arranged on the inside of described aerial construction;
Support frame as described above is used for supporting described captation, and described captation is used for collecting the water of seepage;
Be provided with blow-off pipe interface and floor drain apparatus on the described captation, described floor drain apparatus is communicated with described blow-off pipe interface, the water of collecting to discharge described captation.
Caisson of toilet comprises casing and described caisson of toilet framework;
Be provided with the blowdown reserved opening on the inwall of described casing;
Described caisson of toilet is arranged on the inside of described casing with framework;
Described blow-off pipe interface is communicated with described blowdown reserved opening;
Described captation is connected with the inwall of described casing.
The caisson of toilet that provides by the utility model can reach following beneficial effect with framework and caisson of toilet:
1. the caisson of toilet framework that provides of the utility model comprises: bracing frame, captation, floor drain apparatus and blow-off pipe interface; Support frame as described above is aerial construction, and described captation is arranged on the inside of described aerial construction; When seepage had been located in flushing valve of ground and closet etc. to caisson of toilet, the water of seepage was collected by captation; Simultaneously because the floor drain apparatus that arranges on the captation is communicated with the blow-off pipe interface, the blow-off pipe interface is communicated with the blowdown reserved opening of setting in the casing, and the blowdown reserved opening be with the house in blow-off line be communicated with, therefore the collected water of captation can be drained into blow-off pipe in the house by floor drain apparatus and blow-off pipe interface, thereby the water that will leak into caisson of toilet is discharged the casing of caisson of toilet, the water of avoiding leaking into caisson of toilet accumulates in the inside of casing, do not have the phenomenon that caisson of toilet percolating water just can not occur yet of accumulating of water in the casing, therefore caisson of toilet of the present utility model can solve caisson of toilet seepage water problem with framework and caisson of toilet.
Blow-off pipe in running into the house stop up situation the time, the water that leaks into caisson of toilet is collected by captation, and captation is connected with the inwall of casing, the water that captation is collected can not drop on the bottom of casing, although the water that therefore leaks into caisson of toilet still still can not drop on the bottom of casing in the inside of casing, thereby prevented that the seepage in the casing from arriving downstairs, thereby caisson of toilet of the present utility model has played the effect of waterproof with framework and caisson of toilet.
3. caisson of toilet of the present utility model, that caisson of toilet is installed in the casing as a finished product with framework, the on-site construction processes such as plaster in the scene, joints cement have been avoided in the caisson of toilet of the prior art construction, therefore caisson of toilet difficulty of construction of the present utility model is low, and the construction period is short.
4. the caisson of toilet that provides of the utility model, do not need the site operations such as plaster in the scene, joints cement, just can not produce the useless slurry of cement yet and wait building waste, and need to waterproofing course be set at the inwall of caisson, can not produce the harmful chemicals such as methyl alcohol, benzene, so the environment pollution that caisson of toilet of the present utility model brings is little.
Description of drawings
In order to be illustrated more clearly in the utility model specific embodiment or technical scheme of the prior art, the below will do to introduce simply to the accompanying drawing of required use in the specific embodiment or the description of the Prior Art, apparently, accompanying drawing in the following describes is embodiments more of the present utility model, for those of ordinary skills, under the prerequisite of not paying creative work, can also obtain according to these accompanying drawings other accompanying drawing.
Fig. 1 is the structure chart of caisson of toilet in the prior art;
Fig. 2 is the structure chart that the utility model embodiment caisson of toilet cooperates with framework and casing;
Fig. 3 is the top view of the utility model embodiment curved slab;
Fig. 4 is the top view that the utility model embodiment curved slab cooperates with connector.
Description of drawings: 1-concrete cushion, 2-cement mortar protective course, 3-leveling layer, 4-casing; 5-slag backfill layer, 6-waterproofing course, 7-master's blow-off pipe interface, 8-connector; 9-washroom body of wall, 10-floor drain apparatus, 11-curved slab, 12-the first girder system; 13-the second girder system, 14-column, 15-bracing frame; 16-floor drain installing hole, 17-leghole, 18-gutter installing hole; 19-master's blow-off pipe installing hole, 20-blow-off pipe installing hole, 21-curved slab edge.
The specific embodiment
Below with reference to accompanying drawing the technical scheme of each embodiment of the utility model is carried out clear, complete description, obviously, described embodiment only is a part of embodiment of the present utility model, rather than whole embodiment.Based on the embodiment in the utility model, those of ordinary skills are resulting all other embodiment under the prerequisite of not making creative work, all belong to the scope that the utility model is protected.
Embodiment 1
The utility model embodiment 1 provides a kind of caisson of toilet framework, comprising: bracing frame, captation, floor drain apparatus and blow-off pipe interface;
Support frame as described above is aerial construction, and described captation is arranged on the inside of described aerial construction;
Support frame as described above is used for supporting described captation, and described captation is used for collecting the water that leaks into caisson of toilet;
Be provided with blow-off pipe interface and floor drain apparatus on the described captation, described floor drain apparatus is communicated with described blow-off pipe interface, the water of collecting to discharge described captation.
The caisson of toilet that present embodiment provides is arranged on the inside of casing with framework as a finished product device, and when seepage had been located in flushing valve of ground and closet etc. to caisson of toilet, the water of seepage was collected by captation; Simultaneously because the floor drain apparatus that arranges on the captation is communicated with the blow-off pipe interface, the blow-off pipe interface is communicated with the blowdown reserved opening of setting in the casing, and the blowdown reserved opening be with the house in blow-off line be communicated with, therefore the collected water of captation can be drained into blow-off pipe in the house by floor drain apparatus and blow-off pipe interface, thereby the water that will leak into caisson of toilet is discharged the casing of caisson of toilet, the water of avoiding leaking into caisson of toilet accumulates in the inside of casing, the phenomenon that caisson of toilet percolating water just can not occur yet of accumulating that does not have water in the casing, so the caisson of toilet of present embodiment can solve caisson of toilet seepage water problem with framework.
In real life, the special circumstances that blow-off pipe in the house can occur stopping up, at this moment, when having seepage in the casing of caisson of toilet, the water of seepage is collected by captation equally, and the water that captation is collected can not drop on the bottom of casing, although therefore leak into the water of caisson of toilet still can not drop on casing in the inside of casing bottom, thereby prevented that the seepage in the casing from arriving downstairs, thereby the caisson of toilet of present embodiment has played the effect of waterproof with framework.
A kind of caisson of toilet that the utility model embodiment 2 provides describes by accompanying drawing 2 to 4 with the caisson of toilet that framework and embodiment 3 provide.
Embodiment 2
The utility model embodiment 2 provides a kind of caisson of toilet framework, comprising: bracing frame 15, captation, floor drain apparatus 10 and blow-off pipe interface;
Support frame as described above 15 is aerial construction; And support frame as described above is divided into two-layer, described captation be arranged on described two-layer between.
Concrete, support frame as described above 15 comprises two-layer, is designated as respectively the first girder system 12 and the second girder system 13;
The first girder system 12 and the second girder system 13 couple together by column system;
Preferably, the first girder system 12 and the second girder system 13 include transverse beam group and longitudinal beam group;
Described transverse beam group comprises a plurality of transverse beams, and the spacing between a plurality of described transverse beam equates;
Described longitudinal beam group comprises a plurality of longitudinal beams, and the spacing between a plurality of described longitudinal beam equates;
Described transverse beam group and described longitudinal beam component are two-layer and link together;
Preferably, the first girder system 12 is identical with the structure of the second girder system 13.
Described column is to comprise a plurality of columns 14, and the spacing between a plurality of columns 14 equates;
The two ends of each column 14 connect respectively transverse beam group in the first girder system 12 and the second girder system 13 and the tie point of longitudinal beam group, and each column 14 is all vertical with the second girder system 13 with the first girder system 12.
In the present embodiment, transverse beam and longitudinal beam all can be the square-section square tube, and its inside is hollow-core construction; Column 14 can be hollow pipe;
The material of in the present embodiment, transverse beam, longitudinal beam and column 14 all can be engineering plastic alloy PC+ABS.
Acrylonitrile-butadiene-styrene copolymer (Acrylonitrile-Butadiene-Styrene is called for short ABS) is a kind of universal thermoplastic polymer.Merlon (being called for short PC) is the high molecular polymer that contains carbonate group in the strand.PC+ABS (engineering plastic alloy), plastic alloy, why called after PC+ABS is because this material had both had good heat-resisting weatherability, dimensional stability and the impact resistance of PC resin at the Chinese name of chemical industry.
In the present embodiment, described transverse beam group and described longitudinal beam component are two-layer and link together, and adopt ABS glue to paste between its tie point.
In the present embodiment, the spacing between the column 14 is determined according to the size of washroom, is typically 300mm-500mm;
According to the size of washroom, usually, the length of transverse beam and/or longitudinal beam is that the clear span of washroom deducts 50mm, and for example the clear span of washroom is 1800mm, and then the length of transverse beam and/or longitudinal beam is 1750mm.
In the present embodiment, the spacing between the transverse beam and the spacing between the longitudinal beam are determined according to the spacing between the column 14.
Described captation is arranged on the inside of described aerial construction; Bracing frame 15 is used for supporting described captation, and described captation is used for collecting the water of seepage;
Concrete, described captation is curved slab 11, curved slab 11 protrudes to the bottom of bracing frame 15;
Preferably, the material of curved slab 11 is engineering plastic alloy PC+ABS, and wherein the shape and size of curved slab 11 can be adjusted according to the size and dimension of washroom;
Described captation is that a plurality of legholes 17 are set on the curved slab 11; The column 14 of bracing frame 15 passes leghole 17, and described captation is connected with column 14, so that described captation is arranged on the inside of bracing frame 15.
Concrete, a plurality of legholes 17 are set on the curved slab 11, pass a column 14 in each leghole 17;
The size of each leghole 17 is coincide with the size of the column 14 that passes in leghole 17, and leghole 17 and 14 seamless connections of column of passing in leghole 17.
In the present embodiment, can pass from leghole 17 seamless connection that guarantees simultaneously 17 of column 14 and legholes in order to guarantee column 14, usually the size of leghole 17 is than the large 1-2mm of maximum length of the cross section of column 14; After all columns 14 being inserted respectively the leghole 17 of its design and adjusting to design attitude, it is fixing to adopt ABS glue to paste, and guarantees leghole 17 and 14 seamless connections of column of passing in leghole 17.
In the present embodiment, the number of column 14 is consistent with the number of leghole 17.
Be provided with blow-off pipe interface and floor drain apparatus 10 on the described captation, floor drain apparatus 10 is communicated with described blow-off pipe interface, the water of collecting to discharge described captation.
In the present embodiment, described blow-off pipe installing hole has a plurality of;
Described blow-off pipe interface has a plurality of;
A plurality of described blow-off pipe interfaces are separately positioned on a plurality of described blow-off pipe installing holes place.
Concrete, described blow-off pipe interface comprises drain interface, sub-blow-off pipe interface and main blow-off pipe interface 7;
Floor drain apparatus 10, drain interface, sub-blow-off pipe interface all are communicated with main blow-off pipe interface 7.
Preferably, be respectively arranged with floor drain installing hole 16, gutter installing hole 18, sub-blow-off pipe installing hole 20 and main blow-off pipe installing hole 19 on the curved slab 11; In the present embodiment, the position of floor drain apparatus 10, drain interface, sub-blow-off pipe interface and main blow-off pipe interface 7 is corresponding one by one with the position of floor drain installing hole 16, gutter installing hole 18, sub-blow-off pipe installing hole 20 and main blow-off pipe installing hole 19.
Floor drain apparatus 10 is arranged in the floor drain installing hole 16, and floor drain apparatus 10 and 16 seamless connections of floor drain installing hole; Floor drain apparatus 10 is communicated with main blow-off pipe interface 7 by pipeline, and curved slab 11 collected water flow in the main blow-off pipe interface 7 and by main blow-off pipe interface 7 by floor drain apparatus 10 and discharge caisson of toilet, and guaranteeing does not have ponding in the caisson of toilet;
One end of one end of described drain interface, an end of sub-blow-off pipe interface and main blow-off pipe interface 7 passes respectively described gutter installing hole 18, sub-blow-off pipe installing hole 20 and main blow-off pipe installing hole 19, and the sidewall of the sidewall of described drain interface, sub-blow-off pipe interface and the sidewall of being connected blow-off pipe interface 7 are respectively with gutter installing hole 18, sub-blow-off pipe installing hole 20 be connected 19 seamless connections of blow-off pipe installing hole;
The other end of the other end of described drain interface, sub-blow-off pipe interface is communicated with main blow-off pipe interface 7.
In the present embodiment, an end of drain interface passes described gutter installing hole 18, and is connected with the pipeline of washstand; An end relative with passing a end that described gutter installing hole is connected with the pipeline of washstand of drain interface is communicated with main blow-off pipe interface 7.
In the present embodiment, an end of sub-blow-off pipe interface passes sub-blow-off pipe installing hole 20, and is connected with the pipeline of closet; An end relative with an end that passes sub-blow-off pipe installing hole 20 and be connected with the pipeline of closet of sub-blow-off pipe interface is communicated with main blow-off pipe interface 7;
In the present embodiment, the flushing valve of closet is a main water-leaking structure, and the water that flushing valve leaks out collects by curved slab 11 and discharges by floor drain 10, can not accumulate in the casing 4 of caisson of toilet.
In the present embodiment, main blow-off pipe interface 7 is except with floor drain apparatus 10, gutter, sub-blow-off pipe are communicated with, and two port is connected with the reserved opening that arranges in the caisson respectively.
In the present embodiment, the caisson of toilet framework further comprises: overlay;
Described overlay covers the top of bracing frame 15.
The caisson of toilet chassis body of present embodiment is frame construction, at the casing that is installed in caisson of toilet and after setting the various structures such as pipeline in the casing, closet, need to lay at the top of bracing frame 15 and form a plane structure, what present embodiment adopted is to be coated with overlay at the top of bracing frame 15, and the material of wherein said overlay is the light concrete precast plate.
Present embodiment has provided a kind of specific embodiment situation of caisson of toilet with framework, can access the finished product that a kind of caisson of toilet is used framework according to present embodiment.In caisson of toilet, adopt the principle of water-proof drainage combination, use the caisson of toilet framework of finished product formula, can avoid the phenomenon of caisson of toilet generation percolating water, and the finished product formula is produced so that this effect can lasting stability.
Embodiment 3
The utility model embodiment 3 provides a kind of caisson of toilet, comprises casing 4 and described caisson of toilet framework;
Be provided with the blowdown reserved opening on the inwall of casing 4;
Described caisson of toilet is arranged on the inside of casing 4 with framework;
Described blow-off pipe interface is communicated with described blowdown reserved opening;
Described captation is connected with the inwall of casing 4.
In the present embodiment, the outer ledge of captation is connected with the inwall of casing 4 is seamless, and preferably, described captation is connected with the inwall of casing 4 by connector 8;
Concrete, connector 8 is three-back-shaped or annular laminated structure;
Preferably, the material of connector 8 is flexiplast.
Preferably, in the present embodiment, be provided with leveling layer on the inwall of casing 4.
Be uneven or the gradient because the inner wall surface of casing 4 may exist, therefore can carry out the laying of leveling layer in the inner wall surface of casing 4, so that the inner wall surface of casing 4 is smooth.
Preferably, in the present embodiment, described captation is curved slab 11, and curved slab edge 21 is 50mm apart from the spacing between the inwall of casing.
In order to realize that curved slab 11 is connected with the seamless of inwall of casing 4, preferably, described captation is that curved slab 11 is connected with the inwall of casing 4 by connector 8.
Concrete, connector 8 can be three-back-shaped or annular laminated structure, connector 8 is that rectangular central portion is the laminated structure of hollow out for outer shape in the present embodiment, and it is that curved slab 11 arranges around described captation.
In the present embodiment, connector 8 is the laminated structure of middle part hollow out, and the circulus that centers on openwork part has certain width; The side at the hollow out position, contiguous middle part of connector 8 sticks on the curved slab 11, and is connected seamless connection with curved slab, and the shape at hollow out position, middle part is definite according to the shape of curved slab 11.
The side away from the hollow out position, middle part of curved slab 11 of connector 8 sticks on the inwall of casing 4;
Preferably, the material of connector 8 is flexiplast, is beneficial to the inwall of being connected with casing with curved slab 11 and is connected.
When the caisson of toilet that uses the utility model to provide is constructed with framework and caisson of toilet:
According to the size of washroom and be lower than the casing that the flooring construction arranges caisson of toilet;
Use frame installation in described casing the caisson of toilet that is provided with captation;
Described caisson of toilet is communicated with the described blowdown reserved opening that arranges in the described blow-off pipe interface of framework and the casing;
Described captation is connected with the inwall of described casing;
Preferably, described captation is connected with the inwall of described casing by connector; Connector is arranged on the periphery of captation, and the outer side edges of described captation is connected with the sidewall of described casing is seamless; And at interface brush waterproof agent; Before being set, connector also needs caisson of toilet is fixed in described casing with framework;
After being installed, bedpan lays overlay at support frame as described above; Preferably, the asphalt mortar, bituminous mortar joint filling of the seam crossing between described overlay.Preferably, according to the size of washroom and be lower than after the flooring construction arranges the casing of caisson of toilet, before the caisson of toilet usefulness frame installation that will be provided with captation is in described casing, further comprise: brushing leveling layer on the inwall of described casing, so that the inner wall surface of casing is smooth.
The work progress of caisson of toilet construction of the prior art is:
According to the size of washroom and be lower than the casing that the flooring construction arranges caisson of toilet;
Retaining is 24 hours in the casing of washroom, checks phenomenon that percolating water whether occurs, if there is seepage, need to process and needs to repeat the experiment of retaining until leakproof leak source;
Brushing leveling layer on the inwall of casing;
Behind the leveling layer dry through, the brushing waterproofing course, and generally brush waterproofing course twice;
After the waterproofing course film forming, (this process generally needs 24 hours) smears cement mortar protective course on the waterproofing course surface;
At cement mortar protective course after sclerosis two days later, the devices such as the net that fixes a drainpipe, waterline network, closet;
The light material such as backfill slag is as backfill layer in the casing of washroom, and compaction in layers;
At the surperficial concreting bed course of backfill layer, the thickness of general concrete cushion is 60mm.
What caisson of toilet of the prior art adopted is to rely mainly on prevention, the seepage that is the seepage of locating seepage on ground and flushing valve etc. behind the caisson by the anti-sealing of each layer structures such as waterproofing course; And caisson of toilet of the present utility model is take row as main, the water that seepage is located in the flushing valve of ground and closet etc. is captured in together by harvester and discharges caisson of toilet by the draining blowdown apparatus, do not have stockpiling of water in the casing of assurance caisson, caisson of toilet of the present utility model can solve caisson of toilet seepage water problem with framework and caisson of toilet.
Caisson of toilet job practices of the prior art, working procedure is many, and for field operation relates to coordinating operation between the various work posts, has increased the difficulty of organizing of site operation.
And caisson of toilet of the present utility model is in work progress; after designing the casing of caisson; after the inwall of casing has been smeared leveling layer; the caisson of toilet framework directly is installed; do not need to carry out again the operation of waterproofing course, cement mortar protective course and slag backfill layer, greatly reduce the difficulty of engineering.
The engineering time of caisson of toilet of the prior art is long, all needs certain curing time after every procedure is finished, and usually, the construction of finishing whole caisson of toilet needs 15-20 days; And the engineering time of caisson of toilet of the present utility model is short, and the site operation duration is 3-5 days.
The caisson of toilet degree of depth of the prior art is large, and the washroom clear height is lower, and the main body construction difficulty is large.Take crouching formula lavatory as example, the degree of depth of the casing of the caisson in crouching formula lavatory is approximately 500mm, adds the concrete cushion of 50-100mm, whole height is approximately 600mm, and the house height be generally about 3 meters, so the clear height of washroom only has 2.4m, make the people feel very oppressive.And the deck-molding in house generally is to be lower than indoor plane 450mm, cause the end of caisson of toilet to be lower than the end of the beam in house, for the bottom that makes caisson of toilet is connected with the bottom of the beam in house, need to do hanging beam in the bottom of beam, so not only increase the cost of construction but also increased the difficulty of constructing.
Caisson of toilet in the utility model, the degree of depth that has reduced the casing of caisson of toilet increased the washroom clear height, make things convenient for main structure construction.Caisson of toilet framework of the present utility model, take crouching formula lavatory as example, the height of bracing frame is 200mm, the height of the casing of caisson of toilet is 350mm, the thickness of overlay that adds the top of upper frame, so that the bottom of caisson of toilet flushes with the bottom of the beam in house, greatly reduce the difficulty of main body construction.
In the caisson of toilet work progress of the prior art, the concreting etc. of need to plastering, need the situ wet operation, environment pollution is large, generally adopt in addition polyurethane water-proof paint in the waterproofing course, the chemical solvent of the inside contains the chemical substances such as methyl alcohol, benzene, and is volatile, and it is larger that the operator sucks behind the human body hazard ratio to health.Caisson of toilet of the present utility model, need to not smear waterproofing course at the sidewall of the caisson of washroom, can not produce the chemical substance larger to the hazard ratio of health, and in the work progress, working procedure is few, and the situ wet operations such as concreting that do not need to plaster also can reduce the pollution of environment.
To sum up, in the utility model, caisson of toilet is installed in the casing of caisson of toilet as a finished product device with framework, has changed the many present situations of caisson of toilet on-site construction processes in the prior art, reduced the difficulty of construction; And caisson of toilet of the present utility model adopts in design principle is the principle that draining is combined with waterproof, no matter whether the blow-off pipe in the house stops up and unimpededly can both play the effect that well prevents percolating water, adopts simultaneously low in the pollution of the environment that caisson of toilet of the present utility model brings.
The various embodiment that the utility model provides can be as required in any way mutually combination, the technical scheme that obtains by this combination is also in scope of the present utility model.Obviously, those skilled in the art can carry out various changes and modification to the utility model and not break away from spirit and scope of the present utility model.Like this, if of the present utility model these are revised and modification belongs within the scope of the utility model claim and equivalent technologies thereof, then the utility model also comprises these changes and modification interior.

Claims (10)

1. the caisson of toilet framework is characterized in that, comprising: bracing frame, captation, floor drain apparatus and blow-off pipe interface;
Support frame as described above is aerial construction, and described captation is arranged on the inside of described aerial construction;
Be provided with blow-off pipe interface and floor drain apparatus on the described captation, described floor drain apparatus is communicated with described blow-off pipe interface, the water of collecting to discharge described captation.
2. caisson of toilet framework according to claim 1 is characterized in that, a plurality of legholes are set on the described captation; The column of support frame as described above passes described leghole, and described captation is connected with described column, so that described captation is arranged on the inside of support frame as described above.
3. caisson of toilet framework according to claim 1 is characterized in that, is provided with floor drain installing hole and blow-off pipe installing hole on the described captation;
Described floor drain apparatus is arranged on described floor drain installing hole place, and described floor drain apparatus and described seamless connection of floor drain installing hole;
Described blow-off pipe interface is arranged on described blow-off pipe installing hole place.
4. caisson of toilet framework according to claim 3 is characterized in that, described blow-off pipe installing hole has a plurality of;
Described blow-off pipe interface has a plurality of;
A plurality of described blow-off pipe interfaces are separately positioned on a plurality of described blow-off pipe installing holes place.
5. caisson of toilet framework according to claim 1 is characterized in that support frame as described above is divided into two-layer, described captation be arranged on described two-layer between.
6. according to claim 1 to 5 each described caisson of toilet frameworks, it is characterized in that described captation is curved slab, described curved slab protrudes to the bottom of support frame as described above.
7. caisson of toilet framework according to claim 1 is characterized in that, further comprises: overlay;
Described overlay covers the top of support frame as described above.
8. caisson of toilet is characterized in that, comprises casing and such as each described caisson of toilet framework of claim 1 to 7;
Be provided with the blowdown reserved opening on the inwall of described casing;
Described caisson of toilet is arranged on the inside of described casing with framework;
Described blow-off pipe interface is communicated with described blowdown reserved opening;
Described captation is connected with the inwall of described casing.
9. caisson of toilet according to claim 8 is characterized in that, described captation is connected with the inwall of described casing by connector;
Described connector is three-back-shaped or annular laminated structure.
10. caisson of toilet according to claim 8 is characterized in that, is provided with leveling layer on the inwall of described casing.
CN 201220396155 2012-08-10 2012-08-10 Frame used for toilet caisson and toilet caisson Withdrawn - After Issue CN202831102U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220396155 CN202831102U (en) 2012-08-10 2012-08-10 Frame used for toilet caisson and toilet caisson

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220396155 CN202831102U (en) 2012-08-10 2012-08-10 Frame used for toilet caisson and toilet caisson

Publications (1)

Publication Number Publication Date
CN202831102U true CN202831102U (en) 2013-03-27

Family

ID=47942846

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220396155 Withdrawn - After Issue CN202831102U (en) 2012-08-10 2012-08-10 Frame used for toilet caisson and toilet caisson

Country Status (1)

Country Link
CN (1) CN202831102U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102767218A (en) * 2012-08-10 2012-11-07 卫青富 Frame for bathroom caisson, bathroom caisson and construction method
CN104514196A (en) * 2013-09-27 2015-04-15 潘连山 Rigid alloy plastic bridge drain pipe

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102767218A (en) * 2012-08-10 2012-11-07 卫青富 Frame for bathroom caisson, bathroom caisson and construction method
CN104514196A (en) * 2013-09-27 2015-04-15 潘连山 Rigid alloy plastic bridge drain pipe
CN104514196B (en) * 2013-09-27 2017-01-25 潘连山 Rigid alloy plastic bridge drain pipe

Similar Documents

Publication Publication Date Title
CN102767218B (en) Frame for bathroom caisson, bathroom caisson and construction method
CN103821181A (en) Basement bottom plate water drainage layer construction method
CN202745335U (en) Sunken type toilet water-resistant deodorization settling basin structure
CN111305566B (en) High-rise residential full-professional alternate construction floor water interception method
CN102587416A (en) Basement attached lane structure and construction method thereof
CN104234089B (en) The construction method that a kind of basement guarded drainage combines
CN202831102U (en) Frame used for toilet caisson and toilet caisson
CN110878700B (en) Tunnel waterproof structure and construction method thereof
CN110541431A (en) waterproof structure of pipe gallery and construction method thereof
CN202466623U (en) Basement attached lane structure
CN207331931U (en) A kind of water seepage prevention floor drain
CN112081254B (en) Toilet waterproof structure and construction method thereof
CN205804419U (en) The tenon formula joint waterproofing structure of concrete waist rail embedded structure side wall
CN102912945B (en) Roof compound seepage-proofing steam exhausting hole detail treatment technology
CN107989287A (en) Inverted roof light and shade drainage system construction method
CN211599772U (en) Floor waterproof construction is worn to pipeline
CN103410318A (en) Construction method for preventing leakage of restroom tubular well
CN209585309U (en) Subsided rest room waterproof construction
CN103882918B (en) The water discharge method of floor hydrops and device during construction of super highrise building
CN111075228A (en) Sink built on stilts water absorption formula prefabricated plate lavatory in pond
CN206554180U (en) A kind of integrated water-proof chassis of toilet pipeline
CN206477382U (en) Rainwater recycle comprehensively utilizes structure
TW451019B (en) Water-proof and damp-proof method for basement side wall
CN207296028U (en) Applied to the waterproof system in the interior space
CN206800534U (en) Gravity flow ensures waterproof system

Legal Events

Date Code Title Description
GR01 Patent grant
C14 Grant of patent or utility model
AV01 Patent right actively abandoned

Granted publication date: 20130327

Effective date of abandoning: 20140129

RGAV Abandon patent right to avoid regrant