CN202830788U - Supporting structure with beam fulcrum below bridge cantilever - Google Patents

Supporting structure with beam fulcrum below bridge cantilever Download PDF

Info

Publication number
CN202830788U
CN202830788U CN201220527977.5U CN201220527977U CN202830788U CN 202830788 U CN202830788 U CN 202830788U CN 201220527977 U CN201220527977 U CN 201220527977U CN 202830788 U CN202830788 U CN 202830788U
Authority
CN
China
Prior art keywords
channel steel
plate
steel main
steel
cantilever
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201220527977.5U
Other languages
Chinese (zh)
Inventor
杨基好
踪高峰
吴强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 10 Engineering Group Co Ltd
Original Assignee
China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 10 Engineering Group Co Ltd filed Critical China Railway No 10 Engineering Group Co Ltd
Priority to CN201220527977.5U priority Critical patent/CN202830788U/en
Application granted granted Critical
Publication of CN202830788U publication Critical patent/CN202830788U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型公开了一种既有桥悬臂板下便梁支点支撑结构,属于便梁支点加固技术领域。其包括设在悬臂板下并与悬臂板接触的钢支墩和设在所述钢支墩下部的钢筋混凝土底座(10),所述钢支墩包括两根竖直设置的槽钢主撑(7)、连接在槽钢主撑(7)顶面的顶板(2)、连接在槽钢主撑(7)底部的底板(3),在两根槽钢主撑(7)之间连接有若干块肋带钢板,在所述顶板(2)与槽钢主撑(7)之间及所述底板(3)与槽钢主撑(7)之间均设有若干个牛腿(8),所述钢筋混凝土底座(10)通过其上预埋的调节螺栓(4)与所述钢支墩的底板(3)连接。本实用新型整体稳定性高,在使用中能随时检查其位移和沉降变化,及时进行调整,并且施工难度低,可节省大量人工。

Figure 201220527977

The utility model discloses a fulcrum supporting structure of a convenience beam under a cantilever slab of an existing bridge, which belongs to the technical field of reinforcement of a convenience beam fulcrum. It includes a steel pier arranged under the cantilever plate and in contact with the cantilever plate and a reinforced concrete base (10) provided under the steel pier. The steel pier includes two vertically arranged channel steel main supports ( 7), the top plate (2) connected to the top surface of the channel steel main brace (7), the bottom plate (3) connected to the bottom of the channel steel main brace (7), and the two channel steel main braces (7) are connected with Several ribbed steel plates, between the top plate (2) and the channel steel main support (7) and between the bottom plate (3) and the channel steel main support (7) are provided with several corbels (8) , the reinforced concrete base (10) is connected to the bottom plate (3) of the steel pier through pre-embedded adjusting bolts (4) thereon. The utility model has high overall stability, can check its displacement and settlement changes at any time during use, and adjust in time, and has low construction difficulty, which can save a lot of labor.

Figure 201220527977

Description

一种既有桥悬臂板下便梁支点支撑结构A fulcrum support structure of the cantilever slab under the existing bridge

技术领域 technical field

本实用新型涉及一种当便梁支点位于既有桥悬臂板上时,在悬臂板下加固便梁支点的支撑结构,属于便梁支点加固技术领域。The utility model relates to a support structure for reinforcing the fulcrum of the convenience beam under the cantilever plate when the fulcrum of the convenience beam is located on the cantilever plate of the existing bridge, and belongs to the technical field of reinforcement of the fulcrum of the convenience beam.

背景技术 Background technique

在铁路、公路施工中,常采用顶进法施工,并采用施工便梁作为临时结构加固既有线路。在顶进施工中,有时施工便梁的支点位于既有框架顶部悬臂板上,悬臂板为框架最薄弱部位,无法承受如此大的荷载。以往是对框架薄弱部位采取搭设大面积的扣件式脚手架作支撑,脚手架的纵向、横向杆间距均为25cm,脚手架顶部使用可调顶撑。这种支撑结构搭设时需耗费大量的人工,施工难度大、速度慢,对原地面承载力要求高,脚手架搭设时必须一次性调整到位,在使用中有列车通过时产生动荷载及振动,扣件及可调顶撑会有松动现象,但人工无法进入支撑结构中进行检修,有很大的安全隐患,施工安全系数很低。In the construction of railways and highways, the jacking method is often used, and the construction beams are used as temporary structures to reinforce the existing lines. In jacking construction, sometimes the fulcrum of the construction beam is located on the cantilever plate at the top of the existing frame, and the cantilever plate is the weakest part of the frame, which cannot bear such a large load. In the past, a large area of fastener-type scaffolding was used to support the weak parts of the frame. The vertical and horizontal rod spacing of the scaffolding was 25cm, and the top of the scaffolding used adjustable support. The erection of this kind of supporting structure requires a lot of labor, the construction is difficult and slow, and requires high bearing capacity of the original ground. When erecting the scaffolding, it must be adjusted in place at one time. When a train passes by during use, dynamic loads and vibrations are generated. There will be loosening of parts and adjustable top support, but manual maintenance cannot enter the support structure, which has great potential safety hazards, and the construction safety factor is very low.

发明内容 Contents of the invention

针对现有技术中存在的上述缺陷,本实用新型提供了一种结构稳定、施工难度小、耗费人工少、维修方便的既有桥悬臂板下便梁支点支撑结构。Aiming at the above-mentioned defects in the prior art, the utility model provides a fulcrum support structure of the cantilever slab under the existing bridge with stable structure, less construction difficulty, less labor cost and convenient maintenance.

本实用新型是通过如下技术方案来实现的:一种既有桥悬臂板下便梁支点支撑结构,其特殊之处是,其包括设在悬臂板下并与悬臂板接触的钢支墩和设在所述钢支墩下部的钢筋混凝土底座,所述钢支墩包括两根竖直设置的槽钢主撑、连接在槽钢主撑顶面的顶板、连接在槽钢主撑底部的底板,在两根槽钢主撑之间连接有若干块肋带钢板,在所述顶板与槽钢主撑之间及所述底板与槽钢主撑之间均设有若干个牛腿,所述钢筋混凝土底座通过其上预埋的调节螺栓与所述钢支墩的底板连接。The utility model is realized through the following technical solutions: an existing bridge cantilever slab fulcrum support structure, which is special in that it includes a steel pier and a design under the cantilever slab and in contact with the cantilever slab. The reinforced concrete base at the bottom of the steel pier, the steel pier includes two vertically arranged channel steel main braces, a top plate connected to the top surface of the channel steel main brace, and a bottom plate connected to the bottom of the channel steel main brace, Several ribbed steel plates are connected between the two channel steel main supports, and several corbels are arranged between the top plate and the channel steel main support and between the bottom plate and the channel steel main support. The concrete base is connected with the bottom plate of the steel pier through pre-embedded adjusting bolts thereon.

本实用新型可以把便梁的静荷载和列车通过时的动荷载由钢支墩传递到地基,使悬臂板受力转移由支撑结构受力,保证了便梁支点的安全性。The utility model can transfer the static load of the convenience beam and the dynamic load when the train passes through the steel pier to the foundation, so that the force transfer of the cantilever plate is carried by the support structure, thereby ensuring the safety of the fulcrum of the convenience beam.

为了保证钢支墩与悬臂板可靠接触,以保证悬臂板所受到的荷载可靠转移,所述顶板的上表面为与所述悬臂板的底面相匹配的倾斜面。In order to ensure reliable contact between the steel pier and the cantilever plate, and to ensure reliable transfer of loads on the cantilever plate, the upper surface of the top plate is an inclined surface matching the bottom surface of the cantilever plate.

为了保证支撑结构的整体稳定性,所述钢筋混凝土底座的面层配置有纵横间距均为15cm的钢筋。In order to ensure the overall stability of the supporting structure, the surface layer of the reinforced concrete base is equipped with steel bars with vertical and horizontal spacings of 15 cm.

本实用新型的有益效果是:本实用新型结构简单,整体稳定性高,在使用中能随时检查其位移和沉降变化,及时进行调整,有效保证了行车安全和人身安全,大大提高了施工安全系数。采用本实用新型进行便梁支点加固,可以节省大量人工,能大大降低施工成本。The beneficial effects of the utility model are: the utility model has simple structure, high overall stability, can check its displacement and settlement changes at any time during use, and adjust in time, effectively ensuring driving safety and personal safety, and greatly improving the construction safety factor . Adopting the utility model to reinforce the fulcrum of the convenient beam can save a lot of labor and greatly reduce the construction cost.

附图说明 Description of drawings

图1是本实用新型具体实施方式的结构示意图;Fig. 1 is the structural representation of the specific embodiment of the utility model;

图2是图1中的A-A示意图;Fig. 2 is A-A schematic diagram in Fig. 1;

图中:1、既有桥悬臂板,2、顶板,3、底板,4、调节螺栓,5、肋带钢板,6、肋带钢板,7、槽钢主撑,8、牛腿,9、施工便梁,10、混凝土底座。In the figure: 1. Existing bridge cantilever plate, 2. Top plate, 3. Bottom plate, 4. Adjusting bolt, 5. Ribbed steel plate, 6. Ribbed steel plate, 7. Channel steel main brace, 8. Corbel, 9. Construction beam, 10, concrete base.

具体实施方式 Detailed ways

下面结合附图对本实用新型作进一步的说明:Below in conjunction with accompanying drawing, the utility model is further described:

如附图1-2所示,是一种既有桥悬臂板下便梁支点支撑结构,其包括设在既有桥悬臂板1下并与悬臂板接触的钢支墩和设在所述钢支墩下部的钢筋混凝土底座10。所述钢支墩包括两根竖直设置的槽钢主撑7、连接在槽钢主撑7顶面的顶板2、连接在槽钢主撑7底部的底板3,其中,两根槽钢主撑7面对面设置,在两根槽钢主撑7之间焊接有若干块肋带钢板5和若干块肋带钢板6,肋带钢板5和肋带钢板6将两根槽钢主撑7牢固地连接在一起。顶板2和底板3均为钢板,其通过焊接的方式分别焊接在槽钢主撑7的顶部和底部。在所述顶板2与槽钢主撑7之间及所述底板3与槽钢主撑7之间均焊接有若干个牛腿8。钢筋混凝土底座10为C25钢筋混凝土基础,其面层配置有直径为Φ16、纵横间距均为15cm的钢筋。在钢筋混凝土底座10上还预埋有调节螺栓4,钢支墩的底板3通过调节螺栓4连接在钢筋混凝土底座10上。As shown in the accompanying drawings 1-2, it is an existing bridge cantilever slab fulcrum support structure, which includes a steel pier arranged under the cantilever slab 1 of the existing bridge and in contact with the cantilever slab and a steel pier set on the cantilever slab. The reinforced concrete base 10 of the lower part of the pier. Described steel support pier comprises two vertically arranged channel steel main braces 7, a top plate 2 connected to the top surface of channel steel main braces 7, a base plate 3 connected to the bottom of channel steel main braces 7, wherein the two channel steel main braces The braces 7 are set face to face, and several ribbed steel plates 5 and several ribbed steel plates 6 are welded between the two channel steel main braces 7, and the ribbed steel plates 5 and ribbed steel plates 6 securely connect the two channel steel main braces 7 connected together. Both the top plate 2 and the bottom plate 3 are steel plates, which are respectively welded to the top and bottom of the channel steel main brace 7 by means of welding. Several corbels 8 are welded between the top plate 2 and the channel steel main brace 7 and between the bottom plate 3 and the channel steel main brace 7 . The reinforced concrete base 10 is a C25 reinforced concrete foundation, and its surface layer is equipped with steel bars with a diameter of Φ16 and a vertical and horizontal spacing of 15 cm. Adjusting bolts 4 are pre-embedded on the reinforced concrete base 10 , and the bottom plate 3 of the steel pier is connected to the reinforced concrete base 10 through the adjusting bolts 4 .

为了保证钢支墩与悬臂板可靠接触,所述顶板2的上表面为与所述悬臂板的底面相匹配的倾斜面。In order to ensure reliable contact between the steel pier and the cantilever plate, the upper surface of the top plate 2 is an inclined surface matching the bottom surface of the cantilever plate.

本实用新型在现场施工时,应先在现场进过反复的测量、校核定位,精确测定钢支墩的位置及钢支墩的高度,必须保证悬臂板上便梁支点中心与悬臂板下钢支墩受力中心重合。然后浇筑钢筋混凝土底座10并预埋调节螺栓4,同时切割好两根槽钢主撑1、顶板2,底板3,牛腿8,肋带钢板5及肋带钢板6。待底座强度达到100%,在底座面上精确定出钢支墩位置,放置底板3,将两根槽钢主撑1竖起在底板3上并定位,先焊接肋带钢板5将两根槽钢固定,再焊接顶板2,焊接肋带钢板6、牛腿钢板8,通过调整调节螺栓4的螺帽使顶板2与悬臂板底面紧贴密实,在底板与钢筋混凝土底座缝隙内用1~5mm厚度的薄钢板塞填密实,使荷载可由钢支墩直接传递到底座至地基。When the utility model is being constructed on the spot, it should be repeatedly measured and checked on the spot to accurately measure the position of the steel pier and the height of the steel pier. The stress centers of the buttresses coincide. Then pour the reinforced concrete base 10 and pre-embed the adjusting bolt 4, and cut two channel steel main braces 1, top plate 2, base plate 3, corbel 8, ribbed steel plate 5 and ribbed steel plate 6 simultaneously. When the strength of the base reaches 100%, the position of the steel pier is accurately determined on the base surface, the base plate 3 is placed, and the two channel steel main supports 1 are erected on the base plate 3 and positioned. The steel is fixed, and then the top plate 2 is welded, the ribbed steel plate 6, and the corbel steel plate 8 are welded. By adjusting the nut of the adjusting bolt 4, the top plate 2 and the bottom surface of the cantilever plate are tightly connected. The thick thin steel plate is packed tightly so that the load can be directly transmitted from the steel pier to the base to the foundation.

本实用新型在使用时,便梁的静荷载和列车通过时的动荷载由本实用新型传递到地基,使悬臂板受力转移由支撑结构受力,保证了便梁支点的安全性。When the utility model is in use, the static load of the convenience beam and the dynamic load when the train passes are transmitted to the foundation by the utility model, so that the force transfer of the cantilever plate is carried by the support structure, which ensures the safety of the fulcrum of the convenience beam.

本实用新型在使用中,可定期检查列车通过产生的动荷载及振动对钢支墩位移和沉降的变化情况,发现变化超限及时修整。When the utility model is in use, the dynamic load and vibration generated by the passage of the train can be regularly checked for changes in the displacement and settlement of the steel pier, and the change can be repaired in time if the change exceeds the limit.

本实用新型结构简单、取材方便、制作简单、成本低廉,具有较高的实用性,其解决了现有的便梁支点加固技术中存在的施工难度大、耗费大量人工、结构不稳定、无法进行检修及安全隐患大的问题,可完全代替现有的采用扣件式脚手架作便梁支点加固的技术方案。The utility model has the advantages of simple structure, convenient material acquisition, simple manufacture, low cost and high practicability. The problems of maintenance and safety hazards can completely replace the existing technical scheme of using fastener-type scaffolding as the fulcrum of the beam.

本实用新型中的其他部分采用现有技术,在此不再赘述。Other parts in the utility model adopt prior art, do not repeat them here.

Claims (3)

1.一种既有桥悬臂板下便梁支点支撑结构,其特征是:包括设在悬臂板下并与悬臂板接触的钢支墩和设在所述钢支墩下部的钢筋混凝土底座(10),所述钢支墩包括两根竖直设置的槽钢主撑(7)、连接在槽钢主撑(7)顶面的顶板(2)、连接在槽钢主撑(7)底部的底板(3),在两根槽钢主撑(7)之间连接有若干块肋带钢板,在所述顶板(2)与槽钢主撑(7)之间及所述底板(3)与槽钢主撑(7)之间均设有若干个牛腿(8),所述钢筋混凝土底座(10)通过其上预埋的调节螺栓(4)与所述钢支墩的底板(3)连接。1. a kind of existing bridge cantilever slab lower convenient beam fulcrum support structure, it is characterized in that: comprise the steel buttress that is located at under the cantilever slab and contact with cantilever slab and be located at the reinforced concrete base (10 ), the steel pier includes two vertically arranged channel steel main supports (7), a top plate (2) connected to the top surface of the channel steel main support (7), a bottom plate connected to the channel steel main support (7) Bottom plate (3), several ribbed steel plates are connected between two channel steel main braces (7), between said top plate (2) and channel steel main braces (7) and between said bottom plate (3) and There are several corbels (8) between the channel steel main supports (7), and the reinforced concrete base (10) connects with the bottom plate (3) of the steel pier through the pre-embedded adjusting bolts (4) on it. connect. 2.根据权利要求1所述的既有桥悬臂板下便梁支点支撑结构,其特征是:所述顶板(2)的上表面为与所述悬臂板的底面相匹配的倾斜面。2. The fulcrum support structure of the cantilever slab under the existing bridge according to claim 1, characterized in that: the upper surface of the top slab (2) is an inclined surface matching the bottom surface of the cantilever slab. 3.根据权利要求1或2所述的既有桥悬臂板下便梁支点支撑结构,其特征是:所述钢筋混凝土底座(10)的面层配置有纵横间距均为15cm的钢筋。3. According to claim 1 or 2, the existing bridge cantilever slab fulcrum support structure, characterized in that: the surface layer of the reinforced concrete base (10) is equipped with steel bars with a vertical and horizontal spacing of 15cm.
CN201220527977.5U 2012-10-16 2012-10-16 Supporting structure with beam fulcrum below bridge cantilever Expired - Fee Related CN202830788U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201220527977.5U CN202830788U (en) 2012-10-16 2012-10-16 Supporting structure with beam fulcrum below bridge cantilever

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201220527977.5U CN202830788U (en) 2012-10-16 2012-10-16 Supporting structure with beam fulcrum below bridge cantilever

Publications (1)

Publication Number Publication Date
CN202830788U true CN202830788U (en) 2013-03-27

Family

ID=47942534

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201220527977.5U Expired - Fee Related CN202830788U (en) 2012-10-16 2012-10-16 Supporting structure with beam fulcrum below bridge cantilever

Country Status (1)

Country Link
CN (1) CN202830788U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102912739A (en) * 2012-10-16 2013-02-06 中铁十局集团有限公司 Supporting structure for temporary beam pivot below existing bridge cantilever plate
CN104328748A (en) * 2014-11-18 2015-02-04 中铁大桥局武汉桥梁特种技术有限公司 Reinforcing structure for corbel end of cantilever girder bridge and mounting method for reinforcing structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102912739A (en) * 2012-10-16 2013-02-06 中铁十局集团有限公司 Supporting structure for temporary beam pivot below existing bridge cantilever plate
CN102912739B (en) * 2012-10-16 2015-08-26 中铁十局集团有限公司 The construction method of just beam fulcrum support structure under a kind of existing bridge outrigger base
CN104328748A (en) * 2014-11-18 2015-02-04 中铁大桥局武汉桥梁特种技术有限公司 Reinforcing structure for corbel end of cantilever girder bridge and mounting method for reinforcing structure

Similar Documents

Publication Publication Date Title
CN110722318B (en) Accurate adjustable steel truss assembling jig frame and assembling method
CN102808383B (en) Curved bridge counter-slope jacking construction process
CN205636496U (en) A interim strutting arrangement that is used for support frame bridge crane and whole hole case roof beam
CN203222738U (en) Steel pipe latticed column temporary buttress supporting device
CN103469735B (en) The installation method of the formwork of the solid section of the pier top of the hollow column and slab pier with curved superelevation
CN103882808B (en) Construction method for erecting precast beam supporting system between ramp bridge and main line bridge
CN203113226U (en) Formwork support system with towering asymmetric concrete cantilever structure
CN202830788U (en) Supporting structure with beam fulcrum below bridge cantilever
CN102758405B (en) Technology for integrally jacking steel box girder and concrete beam
CN203855879U (en) Novel high-pier turnout continuous beam support
CN204626266U (en) Single column pier bridge exempts to build overturning or slip resistance analysis steel structure reinforcing device
CN209194354U (en) High-altitude long-span binder base-supporting shellfish thunder support construction
CN203866711U (en) Large span cable-stayed bridge tower beam three-way temporary consolidation structure
CN211228923U (en) Fixing device for pre-buried steel plate under shock insulation support
CN212270703U (en) Bridge deck bearing combined support
CN201794280U (en) High-accuracy stone terrace laying support structure
CN205329738U (en) Novel umbelliform ground bearing capacity detecting device
CN203603264U (en) Externally-wrapped pillar base
CN207277211U (en) Large steel pipe truss for bent cap cast-in-place construction
CN217479961U (en) Independent few support of cross-river variable cross-section cast-in-place box girder
CN104532758A (en) A Construction Support for No. 0 Block of Prestressed Concrete Cantilevered Continuous Beam
CN108914777A (en) A kind of superelevation beam-column type bracket
CN203795327U (en) Disassembling bracket for overpass
CN103556577B (en) Elevation adjusting device for steel truss and method for adjusting elevation of steel truss
CN201704698U (en) Detachable tower footing

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130327

Termination date: 20151016

EXPY Termination of patent right or utility model