CN202779757U - Integrated-casting duck bill on edge of hot metal ladle - Google Patents

Integrated-casting duck bill on edge of hot metal ladle Download PDF

Info

Publication number
CN202779757U
CN202779757U CN 201220531863 CN201220531863U CN202779757U CN 202779757 U CN202779757 U CN 202779757U CN 201220531863 CN201220531863 CN 201220531863 CN 201220531863 U CN201220531863 U CN 201220531863U CN 202779757 U CN202779757 U CN 202779757U
Authority
CN
China
Prior art keywords
layer
duck bill
duckbilled
edge
ladle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220531863
Other languages
Chinese (zh)
Inventor
米源
韩树良
张晟
陶晓林
唐树平
畅广民
余刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Iron and Steel Group Corp
Original Assignee
Wuhan Iron and Steel Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Iron and Steel Group Corp filed Critical Wuhan Iron and Steel Group Corp
Priority to CN 201220531863 priority Critical patent/CN202779757U/en
Application granted granted Critical
Publication of CN202779757U publication Critical patent/CN202779757U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The utility model discloses an integrated-casting duck bill on the edge of a hot metal ladle. The duck bill comprises a duck bill body, wherein a steel structure layer serves as the outer layer of the duck bill body; and the upper section of the duck bill body is provided with a castable layer on the inner side of the steel structure layer; and the lower section of the duck bill body is provided with an agalmatolite brick layer, a permanent high-alumina brick layer and a high-alumina brick layer on a working layer on the inner side of the steel structure layer from exterior to interior. The duck bill is improved from a masonry refractory brick mode into an integrated casting mode, so that the duck bill is high in integrity and long in service life, and bricks do not drop. After the hot metal ladle edge is integrally cast, circular seams of high-alumina bricks on the working layer are eliminated, the problem that iron penetrates through the duck bill is solved, and thus the safety operation of the hot metal ladle is guaranteed. In a process of treating iron and slag adhered to the edge of the ladle, the damage to duck bill castable on the ladle edge is basically small, and the time for processing the ladle opening is shortened. After the duck bill is burnt and eroded, an iron plate can be additionally welded on the steel structure, back pouring is performed, and the repair is fast, easy and convenient.

Description

Integrated casting type hot-metal bottle tank is along duckbilled
Technical field
The utility model relates to the steel-refining water pot and builds by laying the field, refers to that particularly a kind of integrated casting type hot-metal bottle tank is along duckbilled.
Background technology
Iron wraps in the use procedure, because the Desulphuring Process of Molten Iron requirement is converted iron and must be skimmed before behind the hot-metal bottle desulfurizing iron.Hot-metal bottle often causes hot-metal bottle duckbilled place dry slag serious in the desulphurization and slag skimming process, causes hot-metal bottle overweight, and duckbilled place tank mouth is high, and then makes the difficulty of skimming.
As shown in Figure 1, existing hot-metal bottle tank comprises duckbilled body 1 along duckbilled, and duckbilled body 1 is comprised of the high aluminium brick layer 5 of steel construction layer 2, agalmatolite brick layer 4, permanent layer, the high aluminium brick layer 6 of working lining from outside to inside.Between building by laying, process duckbilled place tank mouth dry slag, burn clearly through flame, the mechanical removal two procedures.In this process, very large to the brick damage at hot-metal bottle duckbilled place, destroy hot-metal bottle working lining globality, and then caused hot-metal bottle working lining circumferential weld large, cause tank skin to ooze the iron accident, seriously affected the safe operation of hot-metal bottle.
In addition, build the refractory brick mode by laying bricks or stones because the hot-metal bottle tank adopts along duckbilled, have following problem:
1, during molten iron drossing, the top high-alumina brick often falls brick easily;
2, loosening easily behind the multiple slagging; Brickwork joint oozes iron easily simultaneously, has accelerated the duckbilled erosion;
3, after duckbilled scaling loss, the erosion, repair, repair comparatively difficulty;
In sum, the existing duckbilled life-span is low, iron bag overhaul life 650 ~ 700 times, and the duckbilled life-span can not be synchronous, needs to carry out repeatedly the duckbilled construction midway, affects the production direct motion.
Summary of the invention
The purpose of this utility model be exactly to provide a kind of can reduce the hot-metal bottle injury of mouth and then reduce the tank skin circumferential weld cause greatly oozing integrated casting type hot-metal bottle tank that the iron accident occurs along duckbilled.
For solving the problems of the technologies described above, the designed integrated casting type hot-metal bottle tank of the utility model is along duckbilled, comprise the duckbilled body, the skin of described duckbilled body is the steel construction layer, the epimere of described duckbilled body is provided with the cast bed of material in the inboard of steel construction layer, and the hypomere of described duckbilled body is provided with the high aluminium brick layer of agalmatolite brick layer, permanent layer and the high aluminium brick layer of working lining from outside to inside in the inboard of steel construction layer.
Further, the described cast bed of material is cast in the top of the high aluminium brick layer of the high aluminium brick layer of agalmatolite brick layer, permanent layer and working lining, and the described cast bed of material and steel construction layer are cast for one.
Further, the thickness of the described cast bed of material equals the thickness sum of the high aluminium brick layer of the high aluminium brick layer of agalmatolite brick layer, permanent layer and working lining.
The beneficial effects of the utility model are:
1, with the hot-metal bottle tank along the duckbilled position by build by laying bricks or stones the refractory brick mode be improved to integrated poured, the duckbilled good integrity, the structure one can not fallen the brick problem, intensity is high; Duckbilled is integrated poured, easy construction, and the life-span is high, more can satisfy Production requirement.
2, can ensure the use of a tank labour after integrated poured through the hot-metal bottle tank, and tank eliminates working lining high-alumina brick circumferential weld along having pushed down the hot-metal bottle operational layer brick, do not existed duckbilled to ooze the iron problem, guaranteed the hot-metal bottle safe operation.
3, since tank along the characteristics high temperature of castable and be not easy slag, basically less along the damage of duckbilled castable to tank in the sticking iron dry slag process of process tank mouth, and shortened the process tank mouth time.After duckbilled scaling loss, the erosion, can add the soldering iron plate at steel construction, carry out back pouring, repair, repair fast and simple.
Description of drawings
Fig. 1 is the structural representation of existing hot-metal bottle tank along duckbilled.
Fig. 2 is that the utility model integrated casting type hot-metal bottle tank is along the structural representation of duckbilled.
The specific embodiment
Below in conjunction with the drawings and specific embodiments the utility model is described in further detail.
Existing hot-metal bottle tank shown in Figure 1 has been done detailed introduction along duckbilled in background technology, repeat no more in this.
Integrated casting type hot-metal bottle tank shown in Figure 2 is along duckbilled, comprise duckbilled body 1, the skin of duckbilled body 1 is steel construction layer 2, the epimere of duckbilled body 1 is provided with the cast bed of material 3 in the inboard of steel construction layer 2, the hypomere of duckbilled body 1 is provided with the high aluminium brick layer 5 of agalmatolite brick layer 4, permanent layer and the high aluminium brick layer 6 of working lining from outside to inside in the inboard of steel construction layer 2.
The cast bed of material 3 is cast in the top of the high aluminium brick layer 6 of the high aluminium brick layer 5 of agalmatolite brick layer 4, permanent layer and working lining, and the cast bed of material 3 is cast for one with steel construction layer 2.The thickness of the cast bed of material 3 equals the thickness sum of the high aluminium brick layer 6 of the high aluminium brick layer 5 of agalmatolite brick layer 4, permanent layer and working lining.
Selecting of the castable of the above-mentioned cast bed of material 3: iron wraps in the use procedure, and iron bag tank directly contacts the molten iron slag along the duckbilled position.So require the anti-material of the cast bed of material 3 to have good medium and high temperature strength, and tool is resisted the ability of molten iron, desulfurization slag corrosion.
Cast of the present utility model: at the bottom of overhaul iron bag is finished tank, tank skin brick and slag line brick masonry, the wall working lining is built to go up most 3 ring places to hot-metal bottle and is ended, and hot-metal bottle duckbilled cast structure chart welds anchoring piece at steel construction layer 2 inner surface as shown in Figure 2, longitudinal pitch 180mm, horizontal spacing 200mm; Then casting tyre mould is installed.Use afterwards again forced stirrer that castable is mixed, be dry mixed first 2-3 minute, add again water and stirred 5-6 minute, fully go out machine behind the mixing, carry out tank and pour into a mould along duckbilled, the vibration while feeding in raw material during cast, after material adds, vibrate again 3-4 minute, to be advisable without a large amount of removal of bubbles.Be poured natural curing and remove loose tool after 8 hours.Can toast after the demoulding, by overhaul baking 24 hours.Press normal procedure after the baking of iron bag is complete and drop into the turnover long journey.
Attended operation of the present utility model:
Iron wraps in the circular flow, particularly in the middle and later periods that the iron bag uses, has the phenomenon of the residual iron residue that tank adheres to along the duckbilled castable, and during along the residual iron residue that adheres to, tank has the damaged phenomenon that comes off along the local idol of castable because of process tank.Can add the soldering iron plate at steel construction layer 2, carry out back pouring, repair, repair fast and simple, guarantee the safe handling of iron bag.
During the iron of middle and later periods is guaranteed the repair free of charge reason, surperficial defective material is cleaned out, add on the steel construction layer 2 method that the soldering iron plate adopts teeming to tank along the serious position of duckbilled castable melting loss or the position that comes off carry out teeming.Adopt at present this maintaining method, effect is more satisfactory, and tank can reach synchronous with the tank skin life-span along castable.

Claims (3)

1. an integrated casting type hot-metal bottle tank is along duckbilled, comprise duckbilled body (1), it is characterized in that: the skin of described duckbilled body (1) is steel construction layer (2), the epimere of described duckbilled body (1) is provided with the cast bed of material (3) in the inboard of steel construction layer (2), the hypomere of described duckbilled body (1) is provided with the high aluminium brick layer (5) of agalmatolite brick layer (4), permanent layer and the high aluminium brick layer (6) of working lining from outside to inside in the inboard of steel construction layer (2).
2. integrated casting type hot-metal bottle tank according to claim 1 is along duckbilled, it is characterized in that: the described cast bed of material (3) is cast in the top of the high aluminium brick layer (6) of the high aluminium brick layer (5) of agalmatolite brick layer (4), permanent layer and working lining, and the described cast bed of material (3) is cast for one with steel construction layer (2).
3. integrated casting type hot-metal bottle tank according to claim 1 is characterized in that along duckbilled: the thickness of the described cast bed of material (3) equals the thickness sum of the high aluminium brick layer (6) of the high aluminium brick layer (5) of agalmatolite brick layer (4), permanent layer and working lining.
CN 201220531863 2012-10-17 2012-10-17 Integrated-casting duck bill on edge of hot metal ladle Expired - Fee Related CN202779757U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220531863 CN202779757U (en) 2012-10-17 2012-10-17 Integrated-casting duck bill on edge of hot metal ladle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220531863 CN202779757U (en) 2012-10-17 2012-10-17 Integrated-casting duck bill on edge of hot metal ladle

Publications (1)

Publication Number Publication Date
CN202779757U true CN202779757U (en) 2013-03-13

Family

ID=47807099

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220531863 Expired - Fee Related CN202779757U (en) 2012-10-17 2012-10-17 Integrated-casting duck bill on edge of hot metal ladle

Country Status (1)

Country Link
CN (1) CN202779757U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106392048A (en) * 2016-11-09 2017-02-15 南京钢铁股份有限公司 Operation method of double-layer wet construction of high-alumina bricks on permanent layer of steel ladle
CN108543940A (en) * 2018-05-04 2018-09-18 武汉精鼎科技股份有限公司 A kind of molten steel pot of non-bonnet (NB) plate is along masonry construction and construction method
CN113333726A (en) * 2021-06-09 2021-09-03 攀钢集团研究院有限公司 Hot metal ladle building structure and maintenance method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106392048A (en) * 2016-11-09 2017-02-15 南京钢铁股份有限公司 Operation method of double-layer wet construction of high-alumina bricks on permanent layer of steel ladle
CN108543940A (en) * 2018-05-04 2018-09-18 武汉精鼎科技股份有限公司 A kind of molten steel pot of non-bonnet (NB) plate is along masonry construction and construction method
CN113333726A (en) * 2021-06-09 2021-09-03 攀钢集团研究院有限公司 Hot metal ladle building structure and maintenance method

Similar Documents

Publication Publication Date Title
CN101767197B (en) Method for pouring steel ladle working lining
CN102554201A (en) Large steel ladle and manufacturing method for same
CN111659870A (en) Centrifugal roller die casting tool and casting process thereof
CN205165859U (en) Prevent novel molten iron of slag backward flow and take off slag plate
CN104529485B (en) Two-layer compound refractory material and two-layer compound refractory material ditch cover and its manufacture method and application
CN214814757U (en) High-stability composite steel ladle edge structure
CN105195723A (en) Repairing method for steel ladle wall permanent layer
CN106111970A (en) A kind of device and method being reduced ladle top slag oxidisability by excessive slag method
CN107282917B (en) A kind of novel ladle and its packet are along building by laying method
CN106270471B (en) The steel ladle opening one-piece casting of resistance to material technique
CN205237051U (en) Sediment device is arranged to package developments in middle of continuous casting
CN204545407U (en) The steel ladle opening dross extractor of the convenient cleaning accumulated slag of a kind of energy
CN110355356A (en) A kind of pouring structure of molten steel tank
CN211135508U (en) Molten steel tank edge pouring structure
CN101637941B (en) Process for integrally pouring hot metal ladle and forming die device
CN101623662A (en) Method for padding gap of lining plate of cone crusher
CN109628704B (en) RH vacuum refining furnace and building method thereof
CN205165860U (en) Prevent molten iron of slag backward flow and take off slag plate
CN201971846U (en) Integrally-assembled iron tap channel for blast furnace
CN203061852U (en) Mold for casting
CN203695934U (en) Molten iron jar slag stopper with molten iron flowing opening
CN209792594U (en) Novel ladle opening brick
CN209006665U (en) A kind of continuously casting ladle structure
CN204495051U (en) The efficient feed arrangement of mineral hot furnace in high-carbon chrome iron for smelting
CN204975304U (en) KR stirs hot metal bottle

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130313

Termination date: 20171017

CF01 Termination of patent right due to non-payment of annual fee