CN202578781U - Layered load-bearing filling structure beside hard roof gob-side entry retaining - Google Patents

Layered load-bearing filling structure beside hard roof gob-side entry retaining Download PDF

Info

Publication number
CN202578781U
CN202578781U CN 201220232332 CN201220232332U CN202578781U CN 202578781 U CN202578781 U CN 202578781U CN 201220232332 CN201220232332 CN 201220232332 CN 201220232332 U CN201220232332 U CN 201220232332U CN 202578781 U CN202578781 U CN 202578781U
Authority
CN
China
Prior art keywords
filling
gob
side entry
hard roof
filling body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220232332
Other languages
Chinese (zh)
Inventor
宁建国
于斌
吴笛
马鹏飞
杨智文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University of Science and Technology
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN 201220232332 priority Critical patent/CN202578781U/en
Application granted granted Critical
Publication of CN202578781U publication Critical patent/CN202578781U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model discloses a layered load-bearing filling structure beside a hard roof gob-side entry retaining. The layered load-bearing filling structure is characterized by comprising an upper layer of filling bodies and a lower layer of filling bodies, and the upper layer of the filling bodies and the lower layer of the filling bodies are different in strength. The upper layer of the filling bodies is formed by stacking of yielding gangue bags with the width of 0.4-0.6 meter and the length of 1.2-1.5 meters. The lower layer of the filling bodies is a high-strength paste filling wall. The layered load-bearing filling structure can well adapt to movement rules of hard roof rock strata, and stability of the gob-side entry retaining is guaranteed.

Description

坚硬顶板沿空留巷巷旁分层承载充填结构Layered load-bearing filling structure next to gob-side entry retention with hard roof

技术领域 technical field

本实用新型涉及应用在煤矿井下的一种充填技术,具体涉及坚硬顶板条件下沿空留巷巷旁充填结构及施工方法。The utility model relates to a filling technology applied in underground coal mines, in particular to a filling structure and a construction method beside a gob-side roadway under the condition of a hard roof.

背景技术 Background technique

沿空留巷巷旁充填是煤矿开采技术的一项重大改革,此项技术不仅可提高煤炭资源采出率、延长矿井服务年限、减少巷道掘进量、缓解采掘接替矛盾、取消孤岛工作面,而且它也是矿山进行采煤方法改革最有效的途径。Backfilling along the gob-side roadway is a major reform of coal mining technology. This technology can not only improve the recovery rate of coal resources, extend the service life of the mine, reduce the amount of roadway excavation, alleviate the contradiction of mining replacement, and cancel the island working face. It is also the most effective way for mines to reform their coal mining methods.

目前,国内外常用的沿空留巷巷旁充填方式主要有水泥基膏体充填、矸石带充填、高水速凝材料充填等等。由于坚硬顶板条件下沿空留巷,工作面侧向基本顶悬顶时间长,悬顶距大,上述三个充填方式存在的缺陷是:巷旁充填体将承受很大的顶板压力,对于水泥基膏体充填体,其初期强度低、可缩性较差,不能较好地适应坚硬岩层运动规律;矸石带充填工作量大,矸石带提供的支护阻力较小,支护效果较差;高水速凝材料成本较高,支护强度低,不适应沿空巷道的高压突变性,工作面二次采动期间,充填体很容易变形破坏,造成采空区漏风严重,给矿井的通风和巷道的维护工作带来了很大的困难。At present, the commonly used filling methods for gob-side entry retention at home and abroad mainly include cement-based paste filling, gangue belt filling, high-water quick-setting material filling and so on. Due to the gob-side entry retention under the condition of a hard roof, the working face basically has a long time to hang from the top and a large distance from the top, the defects of the above three filling methods are: the filling body next to the road will bear a large roof pressure, and for cement The base paste filling body has low initial strength and poor shrinkability, and cannot well adapt to the movement of hard rock formations; the filling workload of the gangue belt is large, and the support resistance provided by the gangue belt is small, and the support effect is poor; The cost of high-water quick-setting materials is high, the support strength is low, and it is not suitable for the high-pressure mutation of the gob-side roadway. During the secondary mining of the working face, the filling body is easily deformed and damaged, resulting in serious air leakage in the gob. And the maintenance of the roadway has brought great difficulties.

实用新型内容 Utility model content

为了克服现有坚硬顶板条件下沿空留巷充填结构施工复杂、成本高、让压不确定的缺陷,本实用新型提供一种新型的充填技术,这是一种不等强的组合充填结构,这种不等强的组合充填结构具有让压功能,其下层充填体可提供较高的支护强度。In order to overcome the defects of complicated construction, high cost, and uncertain yield pressure of the existing gob-side entry filling structure under the condition of a hard roof, the utility model provides a new type of filling technology, which is a combined filling structure of unequal strength. This unequal-strength combined filling structure has the function of yielding pressure, and its underlying filling body can provide higher support strength.

为了实现上述任务,本实用新型的分层承载充填结构是由上下两层不等强充填体组合而成,上层充填体是用宽为0.4-0.6米、长1.2-1.5米的让压矸石袋堆积起来的;所述的下层充填体是一个高强膏体充填墙。In order to achieve the above tasks, the layered load-bearing filling structure of the present invention is composed of upper and lower layers of unequal-strength filling bodies. piled up; the lower filling body is a high-strength paste filling wall.

和其他用于沿空留巷的充填结构相比,本实用新型有如下优势:Compared with other filling structures for gob-side retaining, the utility model has the following advantages:

1、利用不等强体进行组合充填,兼顾了矸石带充填与膏体充填的优势,针对悬顶时间长,悬顶距大的坚硬顶板,该结构前期能提供较好的让压作用,缓解顶板下沉,使充填体不至于在较高的顶板压力下被压坏,后期整体结构则提供较高的支护阻力,保证了沿空留巷的稳定性。1. Use unequal strength for combined filling, taking into account the advantages of gangue belt filling and paste filling. For the hard roof with long suspension time and large suspension distance, the structure can provide better yielding effect in the early stage and relieve pressure. The roof sinks so that the filling body will not be crushed under the high roof pressure, and the overall structure in the later stage provides high support resistance to ensure the stability of the gob-side entry retention.

2、本实用新型的上层充填体具有让压作用,让压的高度在合理的范围之内完全可以大于顶板下沉的高度,坚硬顶板可能发生小的无预兆冲击完全可以顶住,所以施工时,为了保证留巷的成功,在下层充填体凝结前,只需使用巷旁单体液压支柱作为滞后支护和采空区木支柱进行初期支护,不用成本较高的锚杆支护,稳定性好,降低了施工成本;当留巷使用完之后,留巷内全部的单体液压支柱都可以回收,进一步降低了留巷的成本。2. The upper filling body of the utility model has the function of yielding pressure, and the height of the yielding pressure can be greater than the sinking height of the roof within a reasonable range, and the hard roof can completely withstand a small impact without warning, so during construction , in order to ensure the success of the roadway retention, before the lower filling body condenses, it is only necessary to use the single hydraulic prop beside the roadway as the lagging support and the wooden prop in the goaf for the initial support, without using the costly bolt support, and the stability is stable. It has good performance and reduces the construction cost; when the roadway is used up, all the single hydraulic props in the roadway can be recycled, which further reduces the cost of the roadway.

总之,本实用新型的充填体在降低充填体成本和施工成本的前提下,实现了让压量完全可以顶住顶板下沉量的目的,虽然表面上看结构简单,但是它解决了本领域技术人员想解决而没有解决的技术问题,具有显著的进步。In a word, under the premise of reducing the cost of the filling body and the construction cost, the filling body of the utility model realizes the purpose that the amount of pressure can completely withstand the sinking amount of the roof. Significant advances in technical problems that people want to solve but do not.

附图说明 Description of drawings

图1为本实用新型结构的立体图。Fig. 1 is the perspective view of the utility model structure.

图2为本实用新型结构的具体施工示意图。Fig. 2 is the specific construction schematic diagram of the utility model structure.

图中标号分别表示:1-下层充填体,2-上层充填体,3-喷浆机,4-喷浆管道,5-超前支护,6-工作面单体液压支柱,7-工作面,8-充填模板,9-留巷,10-不等强组合充填体,11-木支柱,12-采空区,13-临时支护,14-滞后支护。The numbers in the figure represent respectively: 1-lower filling body, 2-upper filling body, 3-spraying machine, 4-spraying pipeline, 5-advance support, 6-single hydraulic prop of working face, 7-working face, 8-filling template, 9-retaining roadway, 10-unequal strength combined filling body, 11-wooden pillar, 12-goaf, 13-temporary support, 14-lag support.

具体实施方式 Detailed ways

图1是本实用新型的结构示意图,从图中可以看出,它是由上层充填体2和下层充填体1两种不等强充填体组合而成的,上层充填体是用宽为0.4-0.6米、长1.2-1.5米的让压矸石袋堆积起来的;所述的下层充填体是一个高强膏体充填墙。Fig. 1 is a schematic structural view of the utility model, as can be seen from the figure, it is composed of two kinds of unequal-strength filling bodies, the upper filling body 2 and the lower filling body 1, and the upper filling body is made with a width of 0.4- 0.6 meters and 1.2-1.5 meters long are piled up by pressing gangue bags; the lower filling body is a high-strength paste filling wall.

下面列举一个实施例详细说明能够实施本实用新型结构的方式。List an embodiment below in detail and can implement the mode of the utility model structure.

取上层充填体充填高度为h1,上层充填体中的让压矸石袋的充填材料由质量比为1∶1.7∶5的水、水泥和碎矸石混合物组成,要求该混合物初凝时间为30-40min,终凝时间1.5-2.5h,终凝后矸石袋抗压强度达到2-3MPa;28天后矸石袋抗压强度达到10-20MPa;Taking the filling height of the upper filling body as h 1 , the filling material of the pressure gangue bag in the upper filling body is composed of a mixture of water, cement and crushed gangue with a mass ratio of 1:1.7:5, and the initial setting time of the mixture is required to be 30- 40min, final setting time 1.5-2.5h, after final setting, the compressive strength of the gangue bag reaches 2-3MPa; after 28 days, the compressive strength of the gangue bag reaches 10-20MPa;

取下层充填体的膏体充填墙充填高度为h2,膏体充填墙由质量比为1∶0.3∶0.2∶0.5∶0.2∶0.3∶0.6的水、水泥、废石膏、高炉矿渣、废石灰、粉煤灰和矸石粉混合物形成;要求膏体充填墙材料的抗压强度1天达到5-10MPa,3天达到10-20MPa,7天达到20-28MPa,28天达到30-35Mpa;The filling height of the paste filling wall from the lower filling body is h2 , and the paste filling wall is composed of water, cement, waste gypsum, blast furnace slag, waste lime, A mixture of fly ash and gangue powder is formed; the compressive strength of the paste filling wall material is required to reach 5-10MPa in 1 day, 10-20MPa in 3 days, 20-28MPa in 7 days, and 30-35Mpa in 28 days;

上述充填高度h1和h2由以下方法确定:The above filling heights h1 and h2 are determined by the following method:

第一步:根据采高值和直接顶厚度计算岩梁实际沉降值SA Step 1: Calculate the actual settlement value S A of the rock beam according to the mining height value and the thickness of the direct roof

SA=h-mz(KA-1)S A = hm z (K A -1)

式中:In the formula:

h-采高;h-mining height;

mz-直接顶厚度;m z - immediate roof thickness;

KA-岩梁触矸处下部已冒岩层的碎胀系数,取1.25-1.35;K A - the disintegration coefficient of the rock formation at the lower part of the rock beam touching gangue, which is taken as 1.25-1.35;

第二步:根据岩梁实际沉降值SA计算上层充填体充填高度h1 Step 2: Calculate the filling height h 1 of the upper filling body according to the actual settlement value S A of the rock beam

h1=α0SAh 10 S A

式中:In the formula:

α-上层充填体让压系数,取0.2;α- yield coefficient of upper filling body, take 0.2;

α0-让压安全系数,取1.5;α 0 - yield safety factor, take 1.5;

第三步:根据采高h和上层充填体高度h1计算下层充填体充填高度h2 Step 3: Calculate the filling height h 2 of the lower filling body according to the mining height h and the height h 1 of the upper filling body

h2=h-h1h 2 =hh 1 .

下面参照附图2详细说明本实用新型结构的施工方法。The construction method of structure of the present utility model is described in detail below with reference to accompanying drawing 2.

第一步:井下巷道开挖后进行锚、索、网、带支护和工作面单体液压支柱6支护,同时布置工作面,井下工作面7布置之后开始正常割煤、回柱,割煤后形成采空区12。Step 1: After the excavation of the underground roadway, carry out anchor, cable, net, belt support and 6 supports of single hydraulic props on the working face, and arrange the working face at the same time. The goaf 12 is formed after the coal is coaled.

第二步:在留巷9内使用单体液压支柱作为超前支护5加铰接顶梁支护,在留巷侧充填宽度内再用木支柱11进行支护加固,随着工作面的推进,在超前支护5处增加单体液压支柱,加强为滞后支护14,滞后支护14和木支柱11共同承担了下层充填体凝结前顶板的初期来压。Step 2: Use a single hydraulic prop in the retaining entry 9 as the advance support 5 plus a hinged top beam support, and then use wooden pillars 11 for support and reinforcement within the filling width of the retaining entry side. With the advancement of the working face, the advance A single hydraulic prop is added to the support 5, and it is strengthened into a lag support 14. The lag support 14 and the wooden pillar 11 jointly bear the initial pressure of the roof before the lower filling body condenses.

第三步:同时地面开始备料,准备水、水泥、矸石、粉煤灰等充填材料运至留巷内,充填材料注入喷浆机3内加水搅拌均匀。Step 3: At the same time, the ground starts to prepare materials, prepare filling materials such as water, cement, gangue, and fly ash, and transport them to the retention lane.

第四步:在工作面后方支设临时支护13和充填模板8,充填高度为h2,由喷浆机3通过喷浆管道4将下层充填体的充填材料注入到充填模板8上进行膏体充填,作为图1结构中的下层充填体1。Step 4: Set up temporary support 13 and filling formwork 8 behind the working face, the filling height is h 2 , and the filling material of the lower filling body is injected into the filling formwork 8 by the shotcrete machine 3 through the spraying pipe 4 for paste Body filling, as the lower filling body 1 in the structure shown in Fig. 1 .

第五步:待下层充填体1的膏体充填体凝固后,在膏体充填体上充填让压矸石袋并紧密排列,堆砌到顶板,形成图1中充填结构的上层充填体2。本实施例图1中让压矸石袋只画有一层,在实际工程中,矸石袋需要堆积的层数需根据矸石袋中材料终凝后的压实厚度和矸石袋的充填高度而定。Step 5: After the paste filling body of the lower filling body 1 is solidified, fill the pasty filling body with gangue bags and arrange them closely, and stack them on the top plate to form the upper filling body 2 of the filling structure in Figure 1. In Fig. 1 of this embodiment, only one layer of gangue bags is drawn. In actual engineering, the number of layers of gangue bags to be piled up depends on the compacted thickness of the materials in the gangue bag after final setting and the filling height of the gangue bag.

第六步:待上层充填体2的矸石袋凝固2-3天之后,撤去临时支护13,同时回收工作面后方200米范围之外的除巷旁两侧的滞后支护14,上层充填体2和下层充填体1形成图2中所示的不等强组合充填体10。Step 6: After the gangue bag of the upper filling body 2 is solidified for 2-3 days, remove the temporary support 13, and at the same time recover the lag support 14 on both sides of the roadside and the upper filling body outside the range of 200 meters behind the working face. 2 and the lower filling body 1 form a combined filling body 10 of different strengths shown in FIG. 2 .

第七步:同时,随着工作面推进重复上述步骤二至步骤六。Step 7: At the same time, repeat the above steps 2 to 6 as the working face advances.

Claims (1)

1.一种坚硬顶板沿空留巷巷旁分层承载充填结构,其特征在于,它是由上下两层不等强充填体组合而成,上层充填体是用宽为0.4-0.6米、长1.2-1.5米的让压矸石袋堆积起来的;所述的下层充填体是一个高强膏体充填墙。1. A layered load-bearing filling structure next to a gob-side retaining entry with a hard roof, which is characterized in that it is composed of two layers of unequal-strength filling bodies, and the upper filling body is 0.4-0.6 meters wide and long. 1.2-1.5 meters of gangue bags are piled up; the lower filling body is a high-strength paste filling wall.
CN 201220232332 2012-05-12 2012-05-12 Layered load-bearing filling structure beside hard roof gob-side entry retaining Expired - Fee Related CN202578781U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220232332 CN202578781U (en) 2012-05-12 2012-05-12 Layered load-bearing filling structure beside hard roof gob-side entry retaining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220232332 CN202578781U (en) 2012-05-12 2012-05-12 Layered load-bearing filling structure beside hard roof gob-side entry retaining

Publications (1)

Publication Number Publication Date
CN202578781U true CN202578781U (en) 2012-12-05

Family

ID=47248202

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220232332 Expired - Fee Related CN202578781U (en) 2012-05-12 2012-05-12 Layered load-bearing filling structure beside hard roof gob-side entry retaining

Country Status (1)

Country Link
CN (1) CN202578781U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103291319A (en) * 2013-05-20 2013-09-11 山东科技大学 Rigid-flexible combination gob-side entry retaining method and rigid-flexible combination gob-side entry retaining device by aid of roadside supports
CN103573287A (en) * 2013-11-14 2014-02-12 山东科技大学 Method for determining thickness of flexible material of roadside flexible-strength double-layer composite support in gob-side entry retaining
CN108223006A (en) * 2018-03-16 2018-06-29 北京瑞诺安科新能源技术有限公司 A kind of filling bag body, supporting packed column and construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103291319A (en) * 2013-05-20 2013-09-11 山东科技大学 Rigid-flexible combination gob-side entry retaining method and rigid-flexible combination gob-side entry retaining device by aid of roadside supports
CN103573287A (en) * 2013-11-14 2014-02-12 山东科技大学 Method for determining thickness of flexible material of roadside flexible-strength double-layer composite support in gob-side entry retaining
CN103573287B (en) * 2013-11-14 2015-09-02 山东科技大学 The other soft strong two-layer compound supporting flexible material thickness defining method in gob side entry retaining lane
CN108223006A (en) * 2018-03-16 2018-06-29 北京瑞诺安科新能源技术有限公司 A kind of filling bag body, supporting packed column and construction method

Similar Documents

Publication Publication Date Title
CN102705002B (en) Roadside proper yielding unequal combined filling structure of gob-side entry retaining and construction method
CN112360462B (en) Mining process for filling and grouting short-wall fully-mechanized mining gangue
CN106321103B (en) A kind of solid filling collaboration artificial ore pillar recycling room formula coal column method
CN105422146B (en) A kind of underground mining stope manually puts post expansion and connects ejection device and construction method
Steiner Tunnelling in squeezing rocks: case histories
CN101864987B (en) Building method of filled wall body for gob-side entry retaining of large-inclination coal seam
CN109595029B (en) Local filling support structure and its construction method in goaf under hard roof condition
CN102071941B (en) Fully mechanized mining gob-side entry retaining-based concrete block staggered joint longitudinal stacking wall forming method
CN103485820B (en) Ya Hu lane filled wall and construction method thereof is allowed without coal column filling mining flexibility
WO2019085052A1 (en) Method for filling coal mining to recover residual coal pillar and controlling stability of waterproof key layer
CN111335943B (en) A method of point source interval grouting using roof caving and swell filling and directional drilling
CN101864957A (en) A large amount of ore-drawing synchronous filling without top-pillar retention mining method
CN110118089B (en) A kind of mining FRP grid-coal gangue-self-compacting concrete recycled roof and its construction method
CN111608726A (en) A method for grouting loss reduction of spaced overlying rock crushed and filled steel cages
CN108194132A (en) A kind of pier formula multi-arch type Mined-out Area control method
CN114109490B (en) A kind of prefabricated reinforced concrete slab artificial false roof key layer construction technology
CN103061767B (en) Lower to horizontal slice Dry-placed fill mining
CN101892860A (en) Method of building walls and retaining lanes next to steel cylinder pillar lanes
CN102337925B (en) Method for enlarging, filling and supporting coal-pillar-free mining roadway for fully-mechanized top coal caving
CN108278113A (en) A kind of super high seam layering non-integral filling mining method
Xuan et al. Backfill mining practice in China coal mines
CN202578781U (en) Layered load-bearing filling structure beside hard roof gob-side entry retaining
CN202673299U (en) Double-layer mold constructing composite lining supporting structure of weak surrounding rock tunnel
CN108590655A (en) Assemble the method that wall realizes gob side entry retaining
CN101737068A (en) Method for substituting reconstructed gangue bearing body for roadway protection coal post

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121205

Termination date: 20140512