- CN202467148U CN202467148U CN 201220099848 CN201220099848U CN202467148U CN 202467148 U CN202467148 U CN 202467148U CN 201220099848 CN201220099848 CN 201220099848 CN 201220099848 U CN201220099848 U CN 201220099848U CN 202467148 U CN202467148 U CN 202467148U
- Authority
- CN
- China
- Prior art keywords
- hanging basket
- boom
- frame
- construction
- construction hanging
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 25
- 229910000831 Steel Inorganic materials 0.000 claims description 18
- 239000010959 steel Substances 0.000 claims description 18
- 239000000725 suspension Substances 0.000 claims description 18
- 238000009434 installation Methods 0.000 abstract description 3
- 238000004519 manufacturing process Methods 0.000 abstract description 3
- 238000009415 formwork Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Images
Landscapes
- Movable Scaffolding (AREA)
Abstract
Description
技术领域 technical field
本实用新型涉及一种施工用吊篮,具体地涉及一种用于安装钢结构屋面内板的施工用吊篮。The utility model relates to a construction hanging basket, in particular to a construction hanging basket used for installing steel structure roof inner panels.
背景技术 Background technique
目前,在一般的钢结构厂房屋面内板施工中,由于厂房内部没有安装设备,因此通常可以在厂房内搭设移动式脚手架,以便安装屋面内板。At present, in the construction of the inner panel of the general steel structure factory building, since there is no installation equipment inside the factory building, it is usually possible to set up a mobile scaffold in the factory building to install the inner roof panel.
然而对一些大型设备来说,它们需要从屋顶上空采用汽车吊吊入到厂房内,其组装也需要将构件从屋顶吊入厂房。屋面外板可以在屋顶上安装,但由于室内有设备,因此无法采用移动式脚手架来安装屋面内板。However, for some large-scale equipment, they need to be hoisted into the factory building from above the roof by trucks, and their assembly also requires the components to be hoisted into the factory building from the roof. The outer roof panel can be installed on the roof, but because of the equipment in the room, it is not possible to use mobile scaffolding to install the inner roof panel.
另外,对于一些钢结构厂房或者钢结构建筑来说,由于单层层高太高,容易使搭设移动脚手架的架体过于单薄,从而导致稳定性不好的缺点。另外,也容易使搭设架体过大,移动起来不方便,而如果搭设满堂脚手架,则成本太高。In addition, for some steel structure workshops or steel structure buildings, because the single-story height is too high, it is easy to make the frame body of the mobile scaffold too thin, resulting in the disadvantage of poor stability. In addition, it is also easy to make the erection frame too large, which is inconvenient to move, and if a full house of scaffolding is erected, the cost will be too high.
因此,需要提供一种新型的装置,其能够在不占用地面空间的情况实现钢结构厂房的屋面内板的施工。Therefore, it is necessary to provide a new type of device, which can realize the construction of the roof inner panel of the steel structure factory building without occupying the ground space.
实用新型内容 Utility model content
针对现有技术中所存在的上述技术问题,本实用新型提出了一种施工用吊篮,其结构简单,制造方便,并且不占用任何地面空间。Aiming at the above-mentioned technical problems in the prior art, the utility model proposes a construction hanging basket, which has a simple structure, is convenient to manufacture, and does not occupy any ground space.
根据本实用新型,提供了一种施工用吊篮,包括:棱柱体框架形式的篮体,其包括通过立柱相连的框架底座和框架护栏;从篮体中竖直向上延伸的吊杆组件,其至少包括第一吊杆件;以及悬挂机构。其中,悬挂机构包括从第一吊杆件的顶端沿侧向水平地伸出的横档件,以及沿横档件的末端垂直向下伸出的立柱件,从而构成了一个用于容纳屋面檩条的空腔。According to the utility model, a hanging basket for construction is provided, comprising: a basket body in the form of a prism frame, which includes a frame base and a frame guardrail connected by columns; a suspension rod assembly extending vertically upward from the basket body, which It includes at least a first boom member; and a suspension mechanism. Wherein, the suspension mechanism includes a cross member protruding horizontally laterally from the top of the first suspender member, and a vertical post protruding vertically downward along the end of the cross member, thereby forming a roof purlin for accommodating cavity.
在一个实施例中,悬挂机构还包括穿过立柱件和第一吊杆件的套管,以及能插入到套管中的插销,用于将悬挂机构紧固在屋面檩条上。In one embodiment, the suspension mechanism further includes a bushing passing through the upright column and the first suspender, and a pin inserted into the bushing for fastening the suspension mechanism to the roof purlin.
在一个实施例中,框架底座和框架护栏均为三角形。In one embodiment, both the frame base and the frame rails are triangular.
优选地,第一吊杆件从所述三角形的顶点区域处向上延伸。Preferably, the first boom member extends upwardly from the apex region of said triangle.
在一个实施例中,吊杆组件还包括第二吊杆件,其从设置在框架底座中的平行于三角形底边的连接件处向上延伸。优选地,在高于框架护栏但低于第一吊杆件的顶端的高度处,在第一吊杆件和第二吊杆件之间设有至少一个连杆。In one embodiment, the boom assembly further includes a second boom member extending upwardly from a connecting member disposed in the frame base parallel to the base of the triangle. Preferably, at least one link is provided between the first boom part and the second boom part at a height above the frame rail but below the top end of the first boom part.
另外,根据本实用新型还设置有连接第一吊杆件的顶端和第二吊杆件的顶端的另一连杆。此外,在所述框架护栏中设有平行于所述连接件的另一连接件,所述连接件和所述另一连接件分别在所述第二吊杆件的两侧与所述第二吊杆件固定连接。In addition, according to the utility model, another connecting rod connecting the top end of the first boom part and the top end of the second boom part is also provided. In addition, another connecting piece parallel to the connecting piece is provided in the frame guardrail, and the connecting piece and the other connecting piece are connected to the second hanging rod on both sides Boom pieces are fixedly connected.
根据本实用新型,篮体由角钢制成,所述吊杆由方钢制成。According to the utility model, the basket body is made of angle steel, and the suspension rod is made of square steel.
根据本实用新型的吊篮优选地是用于安装钢结构屋面内板的施工用吊篮。The hanging basket according to the utility model is preferably a construction hanging basket used for installing steel structure roof inner panels.
根据本实用新型的吊篮在使用中能够方便且牢固地悬挂在屋面檩条上,作业人员站在篮体框架内进行施工,因此不会占用任何地面空间。这样,即便在厂房内安装有大型设备时也能够方便地使用。同时,通过拔出插销便可沿屋面檩条移动该吊篮,因而可以方便地改变吊篮的位置,以适应于不同屋面内板的安装。另外,根据本实用新型的吊篮的结构简单,制造容易,便于推广使用。The hanging basket according to the utility model can be conveniently and firmly hung on the purlins of the roof during use, and the workers stand in the frame of the basket body to carry out construction, so no ground space will be occupied. In this way, it can be used conveniently even when large-scale equipment is installed in the factory building. At the same time, the hanging basket can be moved along the roof purlins by pulling out the bolt, so the position of the hanging basket can be changed conveniently to adapt to the installation of different roof inner panels. In addition, the hanging basket according to the utility model has a simple structure, is easy to manufacture, and is convenient for popularization and use.
附图说明 Description of drawings
在下文中将基于实施例并参考附图来对本实用新型进行更详细的描述。其中:Hereinafter, the present utility model will be described in more detail based on the embodiments and with reference to the accompanying drawings. in:
图1是根据本实用新型的施工用吊篮的正视图;Fig. 1 is the front view of the construction hanging basket according to the utility model;
图2是图1所示施工用吊篮的侧视图;和Fig. 2 is a side view of the hanging basket for construction shown in Fig. 1; and
图3到5分别显示了沿图1中线I-I、线II-II和线III-III的剖视图。3 to 5 show cross-sectional views along line I-I, line II-II and line III-III in FIG. 1, respectively.
在附图中,相同的部件使用相同的附图标记来表示。附图并未按照实际的比例绘制。In the drawings, the same components are denoted by the same reference numerals. The figures are not drawn to scale.
具体实施方式 Detailed ways
下面将结合附图对本实用新型作进一步说明。The utility model will be further described below in conjunction with accompanying drawing.
图1和2分别显示了根据本实用新型的施工用吊篮100的正视图和侧视图。如图所示,该吊篮100主要包括篮体20、吊杆组件30和悬挂机构40。1 and 2 respectively show a front view and a side view of a construction basket 100 according to the present invention. As shown in the figure, the hanging basket 100 mainly includes a basket body 20 , a
如图1、2和3所示,篮体20为由若干根框架杆组装在一起的大致三棱柱形的框架结构。如作为底部截面图的图3所示,篮体20包括形成三角形斜边的两根斜向放置的框架杆1,以及形成底边的第一连接框架杆1-1,它们一起构成了篮体20的框架底座。在第一连接角钢1-1处设有直立框架杆3,其与类似于框架底座的三角形的框架护栏(如下所详述)相连接,从而构成了三棱柱形的篮体框架。As shown in FIGS. 1 , 2 and 3 , the basket body 20 is a roughly triangular prism-shaped frame structure assembled by several frame rods. As shown in FIG. 3 as a bottom sectional view, the basket 20 includes two obliquely placed
为增强结构的整体强度,在框架底座中在两根斜框架杆1的中间位置还设有连接两根斜框架杆1的第二连接框架杆1-2,而在靠近三角形顶点的位置处还设有第三连接框架杆1-3。在三角形的框架底座上可放置模板,以作为工人的作业平台。容易理解,第一连接框架杆1-1、第二连接框架杆1-2和第三连接框架杆1-3优选地设置为相互间彼此平行。In order to enhance the overall strength of the structure, a second connecting frame bar 1-2 connecting the two
图4显示了三角形框架护栏的截面图,其类似地包括两根斜框架杆2,以及第一连接框架杆2-1、第二连接框架杆2-2和第三连接框架杆3-2。Fig. 4 shows a cross-sectional view of a triangular frame guardrail, which similarly includes two
根据本实用新型,吊篮100还包括吊杆组件30,其具有第一吊杆件5A和第二吊杆件5B。如图1和3所示,第一吊杆件5A从吊篮100的篮体20的三角形框架底座的顶点处直立地向上延伸。第二吊杆件5B从第二连接角钢1-2处直立地向上延伸,优选从其中心处向上延伸。为提高稳定性,第二连接角钢1-2和2-2设置成将第二吊杆件5B夹在中间,即分别从第二吊杆件5B的两侧与第二吊杆件5B固定连接。According to the present invention, the hanging basket 100 further includes a
如图2所示,根据本实用新型的吊篮100还包括悬挂机构40,其包括从第一吊杆件5A的自由端即顶端中沿侧向水平地伸出的横档件9,以及沿横档件9的末端垂直向下伸出的立柱件10。这样,在第一吊杆件5A的顶端形成了一个大致倒U形的空腔。该空腔的尺寸选择为能在其中容纳屋面檩条12(其为C型钢材)。该悬挂机构40还包括穿过立柱件10和第一吊杆件5A的套管8,以及可从套管8中穿过的插销7,用于将悬挂机构40锁定在屋面檩条12上。As shown in Fig. 2, the hanging basket 100 according to the utility model also includes a suspension mechanism 40, which includes a
在使用时,作业人员站在屋面大梁上,系好安全带,将吊篮100用绳子吊至屋顶,将吊篮的悬挂机构40挂在屋面檩条12上,之后将插销7插入到套管8中。这样,吊篮100就紧紧地扣在檩条上了。作业人员可以进入到吊篮篮体20的底座上,进行作业。由于吊篮100悬挂在屋面檩条12上,因此其不会占用任何地面空间,使得即便在厂房内安装有大型设备时也能够方便地使用。When in use, the operator stands on the roof girder, fastens the safety belt, hangs the hanging basket 100 to the roof with a rope, hangs the suspension mechanism 40 of the hanging basket on the
当需要移动吊篮时,作业人员通过吊篮篮体上的护栏爬上檩条12,并将插销7从套管8中拔出。此时。即可沿着檩条12移动吊篮100。当吊篮100移动到所需位置时,作业人员再次插上插销7,之后回到吊篮底座上,即可进行下一块屋面内板的安装。When the hanging basket needs to be moved, the operator climbs up the
在一个优选的实施例中,在高于护栏的位置处在第一吊杆件5A和第二吊杆件5B之间连接有至少一个连杆4。该连杆4一方面进一步增强了吊篮的整体强度,另一方面也可用作踏杆,以方便作业人员往来于篮体底座和屋面檩条之间。可根据护栏及吊杆件顶端之间的高度差而设置适当数量的连杆4。类似地,还可设置连接第一吊杆件5A和第二吊杆件5B的顶端的额外的连杆6。In a preferred embodiment, at least one connecting rod 4 is connected between the
在一个实施例中,这些框架杆和连杆均可由角钢制成,优选为25×25×3的角钢。类似地,吊杆件、横档件和立柱件均可由方钢制成,优选为25×25×3的方钢。在一个实施例中,套管8为25的钢管,插销为T字形的16的圆钢。容易理解,这些尺寸可以根据实际情况的需要而修改。In one embodiment, these frame rods and connecting rods can be made of steel angles, preferably 25×25×3 steel angles. Similarly, the suspenders, crosspieces and uprights can all be made of square steel, preferably 25×25×3 square steel. In one embodiment, the
虽然已经参考优选实施例对本实用新型进行了描述,但在不脱离本实用新型的范围的情况下,可以对其进行各种改进并且可以用等效物替换其中的部件。尤其是,只要不存在结构冲突,各个实施例中所提到的各项技术特征均可以任意方式组合起来。本实用新型并不局限于文中公开的特定实施例,而是包括落入权利要求的范围内的所有技术方案。While the invention has been described with reference to a preferred embodiment, various modifications may be made and equivalents may be substituted for parts thereof without departing from the scope of the invention. In particular, as long as there is no structural conflict, the technical features mentioned in the various embodiments can be combined in any manner. The utility model is not limited to the specific embodiments disclosed herein, but includes all technical solutions falling within the scope of the claims.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN 201220099848 CN202467148U (en) | 2012-03-16 | 2012-03-16 | Hanging basket for construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN 201220099848 CN202467148U (en) | 2012-03-16 | 2012-03-16 | Hanging basket for construction |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN202467148U true CN202467148U (en) | 2012-10-03 |
Family
ID=46915315
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN 201220099848 Expired - Fee Related CN202467148U (en) | 2012-03-16 | 2012-03-16 | Hanging basket for construction |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN202467148U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104746864A (en) * | 2015-03-27 | 2015-07-01 | 河北工业大学 | Operating platform system used for high-rise building robot |
| CN105523329A (en) * | 2015-12-09 | 2016-04-27 | 国网上海市电力公司 | Hanging scattered cable storage cage |
| CN108468433A (en) * | 2018-04-12 | 2018-08-31 | 陈年康 | A kind of construction tool of workshop metal Roof inner panel |
-
2012
- 2012-03-16 CN CN 201220099848 patent/CN202467148U/en not_active Expired - Fee Related
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104746864A (en) * | 2015-03-27 | 2015-07-01 | 河北工业大学 | Operating platform system used for high-rise building robot |
| CN105523329A (en) * | 2015-12-09 | 2016-04-27 | 国网上海市电力公司 | Hanging scattered cable storage cage |
| CN108468433A (en) * | 2018-04-12 | 2018-08-31 | 陈年康 | A kind of construction tool of workshop metal Roof inner panel |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN100590277C (en) | Overhead bridge type suspension scaffold | |
| CN103276886B (en) | Overhanging frame at position of high-rise building sloping roof outer eave window and construction method thereof | |
| CN112049405A (en) | Hanging basket wall-penetrating type overhanging structure and method for erecting hanging basket on inclined roof | |
| CN202467148U (en) | Hanging basket for construction | |
| CN213626572U (en) | Tool type external cantilever operation platform | |
| CN111945561B (en) | Special-shaped cable tower decorative plate installation device and construction method | |
| CN104153586A (en) | Construction method for installing purline through suspension cable cranes | |
| CN212295608U (en) | System for stabilizing climbing scaffold | |
| JP2012188826A (en) | Roof structure for temporary scaffold and assembly method of structure using the same | |
| CN201714051U (en) | High altitude operation hanging frame | |
| CN104278830A (en) | Integral combined scaffold | |
| CN219585686U (en) | Safe telescopic channel for suspended tower crane driver | |
| CN205259928U (en) | Perpendicular cat ladder of suspension type | |
| CN105926915B (en) | Grow the construction method for workbench of encorbelmenting in Bailey beam high-altitude | |
| CN211229470U (en) | Multi-point suspension scaffold | |
| CN204435824U (en) | Elevator frock lift platform | |
| CN217782775U (en) | Scaffold for civil engineering construction | |
| CN219753919U (en) | Hanging plate type hanging basket support column | |
| CN218375102U (en) | Metal roofing furred ceiling bottom plate installation device | |
| CN208604911U (en) | A kind of novel suspention beam bracket | |
| CN207686266U (en) | A kind of means for fastening scaffolding of fast demountable | |
| CN219118718U (en) | Climbing frame horizontal protection | |
| CN115288406B (en) | Operating platform for cornice of metal roof | |
| CN222478106U (en) | Hanging basket | |
| CN112554532A (en) | Protective frame system free of pulling connection with wall surface and construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20121003 Termination date: 20190316 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |