CN202324666U - Steel structure segmentation positioning device - Google Patents

Steel structure segmentation positioning device Download PDF

Info

Publication number
CN202324666U
CN202324666U CN2011204385575U CN201120438557U CN202324666U CN 202324666 U CN202324666 U CN 202324666U CN 2011204385575 U CN2011204385575 U CN 2011204385575U CN 201120438557 U CN201120438557 U CN 201120438557U CN 202324666 U CN202324666 U CN 202324666U
Authority
CN
China
Prior art keywords
pier
slide bar
oil pump
location
putting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011204385575U
Other languages
Chinese (zh)
Inventor
刘红梅
刘伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANTONG HUAKAI HEAVY INDUSTRY CO LTD
Original Assignee
NANTONG HUAKAI HEAVY INDUSTRY CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANTONG HUAKAI HEAVY INDUSTRY CO LTD filed Critical NANTONG HUAKAI HEAVY INDUSTRY CO LTD
Priority to CN2011204385575U priority Critical patent/CN202324666U/en
Application granted granted Critical
Publication of CN202324666U publication Critical patent/CN202324666U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a steel structure segmentation positioning device, which comprises a block, a tray and a cross beam. The block is placed on the tray, four angels of the tray are provided with fixing bases, a detachable horizontal adjustment oil pump is arranged between the block and each of the fixing bases, positioning plates whose number corresponds to number of the fixing bases are fixed and connected to the fixing bases through bolts penetrating through positioning holes, the cross beam is arranged above the block, a perpendicular adjustment oil pump is arranged between the block and the cross beam, a side wall of the block is provided with an oil charging hole, and the oil charging hole is communicated with an oil hole of the lower end face of the block. Segmentations are hung to the cross beam of the positioning device, so that primary positioning is achieved. After each of segmentations is processed, when segmentation locations need to be readjusted, the positioning plates are detached, the horizontal adjustment oil pump is placed, and segmentations on the cross beam are adjusted through the horizontal adjustment oil pump and the perpendicular adjustment oil pump. And then, after complement, the horizontal adjustment oil pump is detached and the positioning places are arranged, so that secondary accurate positioning is achieved.

Description

A kind of steel work split fix device
Technical field
The present invention relates to a kind of steel work split fix device, particularly a kind of steel work split fix device easy to adjust.
Background technology
When large-scale steel structure closes up in general assembly, at first each segmentation is moved to putting on the pier of precalculated position, realize location just, after segmentation puts in place, need adjust and realize second positioning accurately by crane gear.When accurately locating, still move segmentation through crane or other crane gear, the adjustment of this method is very inconvenient, adjust not only consuming timely, and the increase energy source raises the cost.
Summary of the invention
The technical problem that the present invention will solve provides a kind of steel work split fix device easy to adjust.
For solving the problems of the technologies described above, technical scheme of the present invention is: a kind of steel work split fix device comprises and puts pier; Its innovative point is also to comprise: a pallet; Be placed with on the said pallet and put pier, the said pier sidewall of putting has oil filler point, and this oil filler point is communicated with the oil outlet of putting the pier lower surface; Four jiaos of said pallet are provided with holder; The end is installed on the said holder props up the location-plate of putting pier; Have some locating holes that distribute along the location-plate long axis direction on the said location-plate, said location-plate can be connected fixing through the bolt that passes locating hole with holder; Said holder and putting can be placed with level and regulate oil pump between the pier; One crossbeam, said crossbeam is arranged on the top of putting pier, puts the vertical adjusting oil pump is installed between pier and the crossbeam, said crossbeam and put and be provided with vertically-guided mechanism between the pier;
Further, said pallet around be provided with one the circle spacing preiection.
Further, said vertically-guided mechanism comprises vertical slide bar and slide bar guide ring, and the two ends, lower surface of said crossbeam are welded with vertical slide bar, the said fixing slide bar guide ring corresponding in pier both sides of putting with vertical slide bar, and said vertical slide bar passes the slide bar guide ring.
Further, the lower end of said vertical slide bar is welded with limiting plate.
Further, said location-plate cross section is a T shape.
The invention has the advantages that: when adopting the steel work split fix device of technical scheme structure of the present invention to carry out split fix; In oil filler point, inject lubricant grease, reduce and put the frictional force between pier and the pallet, utilize level adjusting oil pump will put pier and be adjusted to dismounting level adjusting oil pump behind the pallet center; Location-plate is connected fixing with holder through bolt or bearing pin; Make the end of location-plate prop up and put pier, avoid putting pier and move, can segmentation be winched on the crossbeam of this positioner and realize location just.
In the time of after each segmentation is handled, need readjusting the segmentation position, remove location-plate, put into level adjusting oil pump between the pier with putting at holder; That utilizes that level regulates that oil pump and vertical adjusting oil pump realize segmentation on the crossbeam reaches the left-right and front-back adjustment up and down, accomplish adjustment and end-of-job to be assembled after, the adjusting of dismounting level again oil pump; Install location-plate; Can realize that secondary accurately locatees, after erection work finished, the vertical adjusting oil pump descended and falls after rise.
Be provided with a circle spacing preiection around the pallet, be used for mobilely carrying out spacingly, avoid putting pier and break away from pallet, in addition, also play the effect that the restriction lubricant grease leaks outside what put pier.
Vertically-guided mechanism utilizes the up-down adjustment oil pump vertically to carry out up-down adjustment exactly on the crossbeam, and cleverly with top rail with put pier and link into an integrated entity, improve steadiness.
Description of drawings
Fig. 1 is a steel work split fix device vertical view of the present invention.
Fig. 2 is along A-A line sectional view among Fig. 1.
Fig. 3 is along B-B line sectional view among Fig. 1.
Fig. 4 is steel work segmentation adjustment state diagram of the present invention.
The specific embodiment
Like Fig. 1,2, shown in 3, comprise pallet 1, put pier 2, oil filler point 3, holder 4, location-plate 5, level regulate oil pump 6, crossbeam 7, vertical adjusting oil pump 8, vertical slide bar 9 and slide bar guide ring 10, spacing preiection 11.
Be placed with on the above-mentioned pallet 1 and movably put pier 2, this sidewall of putting pier 2 is opened an oil filler point 3, and this oil filler point 3 is communicated with the oil outlet of putting pier 2 lower surfaces.Can inject in the oil filler point 3 and improve the lubricant grease of putting pier 2 and pallet 1 frictional force.Be provided with a circle around the pallet 1 and be used to limit the spacing preiection 11 of putting pier and lubricant grease.
Be welded with holder 4 respectively on four jiaos of pallet 1 or four limits; This holder 4 is welded on the pallet 1 by the riser of two perforates and constitutes; Connect a location-plate 5 on each holder 4 respectively, these location-plate 5 cross sections are T shape, have some locating holes 51 that distribute along the location-plate long axis direction on the riser of location-plate 5; Location-plate 5 is connected fixing with holder 4 through the bolt that passes locating hole 51, can make location-plate 5 ends prop up through the position of adjustment location-plate 5 and put pier 2.
After removing location-plate 5, can and put placement level adjusting oil pump 6 between the pier 2 at holder 4.
Crossbeam 7 is arranged on the top of putting pier 2; Put between pier 2 and the crossbeam 7 vertical adjusting oil pump 8 is installed; Crossbeam 7 and put and be provided with vertically-guided mechanism between the pier 2, this vertically-guided mechanism comprises vertical slide bar 9 and slide bar guide ring 10, the two ends, lower surface of crossbeam 7 are welded with vertical slide bar 9; Put the corresponding slide bar guide ring 10 of the fixing and vertical slide bar in pier 2 both sides 9, vertically slide bar 9 passes slide bar guide ring 10.The lower end of vertical slide bar 9 is welded with limiting plate.
Before the use, earlier, as shown in Figure 4 to the adjustment that resets of steel work split fix device; Remove location-plate 5, level is regulated oil pump 6 be positioned over holder 4 and put between the pier 2, after utilizing four levels adjusting oil pumps 6 will put pier 2 to be adjusted to pallet 1 center; The dismounting level is regulated oil pump 6; Install location-plate 5 again, make the end of location-plate 5 prop up and put pier, avoid putting pier 2 and move.
First location, steel work split fix device is placed into the relevant position after, can the steel work segmentation be winched on the crossbeam 7 of this steel work split fix device and realize location just.
Second positioning in the time of after each segmentation is handled, need readjusting the segmentation position, is removed location-plate 5; At holder 4 and put the level of putting between the pier 2 and regulate oil pump 6; Utilize level to regulate the adjustment of segmentation on oil pump 6 and the vertical adjusting oil pump 8 realization crossbeams 7, after the completion adjustment, dismounting level is again regulated oil pump 6; Install location-plate 5, can accomplish secondary and accurately locate.

Claims (5)

1. a steel work split fix device comprises and puts pier, it is characterized in that also comprising:
One pallet is placed with on the said pallet and puts pier, and the said pier sidewall of putting has oil filler point, and this oil filler point is communicated with the oil outlet of putting the pier lower surface;
Four jiaos of said pallet are provided with holder; The end is installed on the said holder props up the location-plate of putting pier; Have some locating holes that distribute along the location-plate long axis direction on the said location-plate, said location-plate can be connected fixing through the bolt that passes locating hole with holder; Said holder and putting can be placed with level and regulate oil pump between the pier;
One crossbeam, said crossbeam is arranged on the top of putting pier, puts the vertical adjusting oil pump is installed between pier and the crossbeam, said crossbeam and put and be provided with vertically-guided mechanism between the pier.
2. steel work split fix device according to claim 1 is characterized in that: be provided with a circle spacing preiection around the said pallet.
3. steel work split fix device according to claim 1; It is characterized in that: said vertically-guided mechanism comprises vertical slide bar and slide bar guide ring; The two ends, lower surface of said crossbeam are welded with vertical slide bar; The said fixing slide bar guide ring corresponding with vertical slide bar in pier both sides of putting, said vertical slide bar passes the slide bar guide ring.
4. steel work split fix device according to claim 3, it is characterized in that: the lower end of said vertical slide bar is welded with limiting plate.
5. steel work split fix device according to claim 1 is characterized in that: said location-plate cross section is a T shape.
CN2011204385575U 2011-11-08 2011-11-08 Steel structure segmentation positioning device Expired - Fee Related CN202324666U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011204385575U CN202324666U (en) 2011-11-08 2011-11-08 Steel structure segmentation positioning device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011204385575U CN202324666U (en) 2011-11-08 2011-11-08 Steel structure segmentation positioning device

Publications (1)

Publication Number Publication Date
CN202324666U true CN202324666U (en) 2012-07-11

Family

ID=46436647

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011204385575U Expired - Fee Related CN202324666U (en) 2011-11-08 2011-11-08 Steel structure segmentation positioning device

Country Status (1)

Country Link
CN (1) CN202324666U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103603506A (en) * 2013-09-23 2014-02-26 云南建工基础工程有限责任公司 Inner-support and reverse-construction-technique column perpendicularity controller
CN107344594A (en) * 2017-05-26 2017-11-14 如皋市磨头建设开发有限公司 A kind of superstructure streamline building technology
CN107882340A (en) * 2017-11-14 2018-04-06 中国五冶集团有限公司 Lifting apparatus for high-altitude steel girder erection

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103603506A (en) * 2013-09-23 2014-02-26 云南建工基础工程有限责任公司 Inner-support and reverse-construction-technique column perpendicularity controller
CN103603506B (en) * 2013-09-23 2015-11-25 云南建工基础工程有限责任公司 Inner support, Counter procedure verticality of stand column controller
CN107344594A (en) * 2017-05-26 2017-11-14 如皋市磨头建设开发有限公司 A kind of superstructure streamline building technology
CN107882340A (en) * 2017-11-14 2018-04-06 中国五冶集团有限公司 Lifting apparatus for high-altitude steel girder erection
CN107882340B (en) * 2017-11-14 2019-08-30 中国五冶集团有限公司 Lifting apparatus for high-altitude steel girder erection

Similar Documents

Publication Publication Date Title
CN203604918U (en) Device for correcting horizontal position of large-sized apparatus
CN202324666U (en) Steel structure segmentation positioning device
CN203726056U (en) Auxiliary support device for sidewise-mounting welding of large structures
CN104400566A (en) High intensity profile machining center
CN104880318A (en) Movable support adjusting device of diesel engine
CN105711680A (en) Automatic transmission and engine combination tool
CN203821878U (en) Integral horizontal moving device for building with foundation
CN204263119U (en) A kind of adjustable locating support of bar planting percussion drill
CN205178966U (en) Solar cell panel frame joint structure
CN209740454U (en) Pre-positioning device for installing elevator guide rail
CN102704696A (en) Space locator for high, big and heavy steel upright column
CN202725930U (en) Riveting machine
CN103590389A (en) Gap adjustment device and dynamic compaction machine
CN111216061A (en) Petroleum pipeline installation device
CN202725932U (en) Riveting machine
CN203817656U (en) Elevator guide wheel installing tool
CN106077522A (en) A kind of hot box shoot core machine
CN105089271A (en) Mechanical embedded bolt positioning and installing assembly
CN206592713U (en) A kind of fulcrum bearing
CN105317373B (en) A kind of rig translating device
CN207957653U (en) A kind of die station lifting gear
CN208828741U (en) A kind of water conservancy and hydropower pipe detection transposer
CN210968700U (en) Shaft sleeve mounting device in open type movable guide vane of water turbine
CN202725937U (en) Riveting machine
CN102493689B (en) Easily detachable water turbine maintenance platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120711

Termination date: 20121108