CN202323958U CN 201120477846 CN201120477846U CN202323958U CN 202323958 U CN202323958 U CN 202323958U CN 201120477846 CN201120477846 CN 201120477846 CN 201120477846 U CN201120477846 U CN 201120477846U CN 202323958 U CN202323958 U CN 202323958U
Authority
CN
China
Prior art keywords
concrete pile
water
reinforced concrete
piles
locking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201120477846
Other languages
Chinese (zh)
Inventor
王秉勇
杨文辉
张振龙
李科
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northwest Research Institute Co Ltd of CREC
Original Assignee
Northwest Research Institute Co Ltd of CREC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northwest Research Institute Co Ltd of CREC filed Critical Northwest Research Institute Co Ltd of CREC
Priority to CN 201120477846 priority Critical patent/CN202323958U/en
Application granted granted Critical
Publication of CN202323958U publication Critical patent/CN202323958U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model provides a deep-water foundation pit support and water-stop self-locking supporting pile structure, which comprises plain concrete piles, reinforced concrete piles and a locking ring beam. The plain concrete piles and the reinforced concrete piles are all bored cast-in-place piles, the reinforced concrete piles are vertical support beams, the plain concrete piles and the reinforced concrete piles are alternately nested on the periphery of a foundation pit, bottom ends of the piles are driven into foundation base bedrock, the locking ring beam is disposed at the top ends of the piles, horizontal restraint of the upon the pile bottom ends and the locking ring beam at the pile top ends enables the piles and the locking ring beam form a stable self-locking support and water-stop system. By means of the self-locking support pile structure, the problem of gradual construction of supports in foundation pit excavation is solved, a nested mass of the plain concrete piles and the reinforced concrete piles forms an airtight water-stop curtain, and the problem of water stop insufficiency of existing bored secant piles is solved thoroughly.

Description

The self-locking fender post structure of deep water bracing of foundation pit and sealing
Technical field
The utility model relates to the deep excavation project technical field, is specifically related to the self-locking fender post structure of a kind of deep water bracing of foundation pit and sealing.
Background technology
The two large problems that the excavation of special foundation ditch is mainly faced is: the stable and partition underground water of hole wall.And on great rivers, build all kinds of bridges, and for the foundation construction of building the island in some water, just be similar to the excavation of deep foundation ditch in the deep water, also be quite difficult construction link.
Although similar engineering uses fender post as pattern foundation pit supporting structure like the excavation of subway station usually.But for the excavation of foundation pit of building the island in the water is under the condition of deep water and circulating water, to carry out; If simply apply mechanically the space enclosing structure of subway station; Owing to receive the influence of support system not only can reduce work efficiency, and do not make full use of actual geological conditions, can cause certain waste.
When the subway station foundation ditch adopts rotary churning pile, boring interlock stake etc. to solve the excavation problem; The self-supporting effect of fender post is not generally considered in design; But in Excavation Process, fender post is provided with horizontal support layer by layer; These support the continuation operation that has a strong impact on the bottom again, and stagnant water effect is bad simultaneously.Some specially bad to bracing of foundation pit stake waterproof and compound water stop structure of design is in use executed and is done complicatedly, still can not reach desirable stagnant water effect fully.And owing to receive the influence of foundation depth and the restriction of foundation ditch base rock to be difficult to implement, also there is stable defect of bad in steel sheet pile supporting and protection structure commonly used even execute reluctantly.In addition, the job site of above prior art needs the special equipment support, and limitation is bigger.
The utility model content
The purpose of the utility model is to provide a kind of both safety economies, stagnant water effect good, and the job site is simple, the deep water bracing of foundation pit that need not special equipment and the self-locking fender post structure of sealing.
For realizing above-mentioned purpose, the technical scheme that the utility model is taked is:
The self-locking fender post structure of a kind of deep water bracing of foundation pit and sealing; It comprises plain concrete pile, reinforced concrete pile and fore shaft collar tie beam; Plain concrete pile and reinforced concrete pile all adopt bored pile; The reinforced concrete pile conduct is brace summer vertically, and replaces along the nested arrangement of foundation ditch periphery with plain concrete pile, the stake bottom entering substrate basement rock of plain concrete pile and reinforced concrete pile; Its top is provided with the fore shaft collar tie beam, and basement rock makes it to form a stable self-locking to the horizontal restraint of the horizontal restraint of stake bottom and stake top fore shaft collar tie beam and goes along with sb. to guard him and the sealing system.
The nested 5cm that is no less than between described reinforced concrete pile and plain concrete pile stake.
Described reinforced concrete pile and plain concrete pile are set the stake bottom must get into 1~1.5m below the substrate basement rock.
The self-locking fender post structure of above-mentioned deep water bracing of foundation pit that the utility model provides and sealing has taken into full account the concrete characteristics of job site, adopts reinforced concrete pile as vertical brace summer; And with plain concrete pile alternately along the nested arrangement of foundation ditch periphery, the stake bottom gets into the substrate basement rock, utilizes basement rock to the horizontal restraint of stake bottom and the horizontal restraint of stake top fore shaft collar tie beam; Making it to form a stable self-locking goes along with sb. to guard him and the sealing system; Not only guaranteed the stable of supporting, and reached the purpose of complete shutoff water, brought great convenience to construction; And when guaranteeing the subsequent job quality, reached the purpose of saving cost.Its beneficial effect is embodied in: 1. structural calculation is simple, distinct.2. economical and practical: construction equipment and construction manipulation process are simple, can many scope of operations construct simultaneously, and what need only is the precision that improves construction control.Through measuring and calculating, reduce approximately 15~20% than the subway station bracing of foundation pit cost of similar structures, speed improves 23%.Foundation depth during greater than 10 meters economic effect more obvious.3. safe and reliable: utilize basement rock to stake bottom and near coal-mine fore shaft collar tie beam to the horizontal restraint on stake top, formed a complete support system, guaranteed operating personnel's safety in the hole greatly, below the water surface, built the construction environment of a safety.4. the stake between the effective nested purpose that reaches abundant water shutoff.Even nested fall flat between the construction king-pile, cement also can produce improved effect to slit filler (mud skin) in the process of setting of pile concrete, also can reach the water blockoff purpose to improve its intensity.
Description of drawings
Fig. 1 is the nested arrangement sketch map with plain concrete pile of reinforced concrete pile
Fig. 2 is a stake top floor map
Fig. 3 is the profile of self-locking fender post structure.
The specific embodiment
Extremely shown in Figure 3 like Fig. 1; The self-locking fender post structure of deep water bracing of foundation pit that the utility model provides and sealing, it comprises plain concrete pile 1, reinforced concrete pile 2 and fore shaft collar tie beam 3, plain concrete pile 1 all adopts bored pile with reinforced concrete pile 2; Reinforced concrete pile 2 is as vertical brace summer; And with plain concrete pile 1 alternately along the nested arrangement of foundation ditch periphery, accurate setting-out all will be carried out in all piles position, the center off normal on plane is no more than 2cm.The stake bottom of plain concrete pile 1 and reinforced concrete pile 2 gets into substrate basement rock 4; Its top is provided with fore shaft collar tie beam 3, and the horizontal restraint of the horizontal restraint of 4 pairs of stake bottoms of basement rock and stake top fore shaft collar tie beam 3 makes it to form a stable self-locking and goes along with sb. to guard him and the sealing system.
According to the diameter of foundation ditch design size and reinforced concrete pile 2, the nested 5cm that is no less than between the depth of nesting between the stake footpath of the nested stake of rationally arranging and stake, 1 of reinforced concrete pile 2 and plain concrete pile.
According to geological section; Reinforced concrete pile 2 is set the stake bottom with plain concrete pile 1 must get into substrate basement rock 1~1.5m below 4 (the basement rock weathering slight person get the small value); Thereby make its fore shaft collar tie beam 3 form a complete self-locking support system, need not increase other support system with the stake top.
During construction, must carry out various design inspections and calculate, the result must satisfy the related specifications requirement.First construction plain concrete pile 1, and guarantee that its gradient surpasses 0.5%, the intensity of treating plain concrete pile 1 reach the design label 75% after, the construction reinforced bar concrete pile 2 again.Reinforced concrete pile 2 must guarantee during concrete perfusion that as vertical girder structure reinforcing cage does not float.The construction of reinforced concrete pile 2 makes 1 nested arrangement of reinforced concrete pile 2 and plain concrete pile by means of the guide effect of plain concrete pile 1.The concrete strength of fore shaft collar tie beam 3 reach design strength 70% after can begin the full-face tunneling of foundation ditch, execute again and make cushion cap 5.
This self-locking fender post structure has avoided executing step by step in the Excavation Process problem of doing support; The airtight water-stop curtain of the common formation of the nested body of plain concrete pile 1 and reinforced concrete pile 2; Thoroughly solved the problem that existing boring interlock stake does not reach abundant sealing, be about to bored pile and not only fully utilize as supporting and protection structure but also as water-stop curtain.

Claims (3)

1. the self-locking fender post structure of deep water bracing of foundation pit and sealing; It is characterized in that: it comprises plain concrete pile (1), reinforced concrete pile (2) and fore shaft collar tie beam (3); Plain concrete pile (1) and reinforced concrete pile (2) all adopt bored pile; Reinforced concrete pile (2) is as vertical brace summer; And with plain concrete pile (1) alternately along the nested arrangement of foundation ditch periphery; The stake bottom of plain concrete pile (1) and reinforced concrete pile (2) gets into substrate basement rock (4), and its top is provided with fore shaft collar tie beam (3), and basement rock (4) makes it to form a stable self-locking to the horizontal restraint of the horizontal restraint of stake bottom and stake top fore shaft collar tie beam (3) and goes along with sb. to guard him and the sealing system.
2. the self-locking fender post structure of deep water bracing of foundation pit according to claim 1 and sealing is characterized in that: the nested 5cm of being no less than between the stake of described reinforced concrete pile (2) and plain concrete pile (1).
3. the self-locking fender post structure of deep water bracing of foundation pit according to claim 1 and 2 and sealing is characterized in that: described plain concrete pile (1) and reinforced concrete pile (2) are set the stake bottom must get into 1~1.5m below the substrate basement rock (3).
CN 201120477846 2011-11-27 2011-11-27 Deep-water foundation pit support and water-stop self-locking supporting pile structure Expired - Fee Related CN202323958U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120477846 CN202323958U (en) 2011-11-27 2011-11-27 Deep-water foundation pit support and water-stop self-locking supporting pile structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120477846 CN202323958U (en) 2011-11-27 2011-11-27 Deep-water foundation pit support and water-stop self-locking supporting pile structure

Publications (1)

Publication Number Publication Date
CN202323958U true CN202323958U (en) 2012-07-11

Family

ID=46435941

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120477846 Expired - Fee Related CN202323958U (en) 2011-11-27 2011-11-27 Deep-water foundation pit support and water-stop self-locking supporting pile structure

Country Status (1)

Country Link
CN (1) CN202323958U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103726496A (en) * 2013-12-27 2014-04-16 中铁大桥局集团第一工程有限公司 Circular deep foundation pit bored secant pile wall supporting construction method
CN105089062A (en) * 2015-08-17 2015-11-25 陕西桩鑫建设工程有限公司 Engaged retaining pile and construction method and application thereof
CN105569666A (en) * 2016-01-20 2016-05-11 铁道第三勘察设计院集团有限公司 Stratum reinforcing method matched with shield long-distance tunneling normal-pressure tool changing
CN106567424A (en) * 2016-10-28 2017-04-19 中国市政工程中南设计研究总院有限公司 Design method of big-diameter well
CN108797641A (en) * 2018-07-20 2018-11-13 中铁十八局集团有限公司 A kind of structure and its construction method of Underground Subway Station construction period full station sealing
CN109853556A (en) * 2019-01-22 2019-06-07 华北有色工程勘察院有限公司 The ultra-deep that can bear explosion influence adopts hole supporting and retaining system and its construction method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103726496A (en) * 2013-12-27 2014-04-16 中铁大桥局集团第一工程有限公司 Circular deep foundation pit bored secant pile wall supporting construction method
CN105089062A (en) * 2015-08-17 2015-11-25 陕西桩鑫建设工程有限公司 Engaged retaining pile and construction method and application thereof
CN105089062B (en) * 2015-08-17 2016-08-17 陕西桩鑫建设工程有限公司 It is engaged lagging pile and construction method thereof and application
CN105569666A (en) * 2016-01-20 2016-05-11 铁道第三勘察设计院集团有限公司 Stratum reinforcing method matched with shield long-distance tunneling normal-pressure tool changing
CN106567424A (en) * 2016-10-28 2017-04-19 中国市政工程中南设计研究总院有限公司 Design method of big-diameter well
CN108797641A (en) * 2018-07-20 2018-11-13 中铁十八局集团有限公司 A kind of structure and its construction method of Underground Subway Station construction period full station sealing
CN109853556A (en) * 2019-01-22 2019-06-07 华北有色工程勘察院有限公司 The ultra-deep that can bear explosion influence adopts hole supporting and retaining system and its construction method

Similar Documents

Publication Publication Date Title
CN101864773B (en) Deep foundation pit support process
CN202323958U (en) Deep-water foundation pit support and water-stop self-locking supporting pile structure
CN106638640B (en) Construction method without bottom concrete combined type cofferdam under the conditions of formation geology
CN101215834A (en) Construction Method of Outrigger Type Diaphragm Wall
CN103410156B (en) Support space enclosing structure and application process thereof before a kind of recyclable vertical type steel pipe
CN102953341A (en) Overhead trestle structure built on non-covering steep bare rocks in deep rapids
CN102966108A (en) Construction method of deep foundation pit close to building and adopting underground structure as internal support
CN207063982U (en) Mechanical assistance sealing Station structure in a kind of pilot tunnel
CN105587320B (en) Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN103306289A (en) Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN107012871B (en) A kind of suspension type goes along with sb. to guard him the deep reversed construction method for greatly enhancing foundation pit fabricated construction
CN103321244A (en) Construction method for additionally arranged basement in existing building on sand foundation
CN102561371A (en) Steel caisson enclosure structure at island-tunnel combination part
CN101538833A (en) Vertical subsection double-wall steel cofferdam water stopping construction method
CN109778839A (en) Construction system and construction method for steel pipe pile with deep-water compact pebble covering layer
CN107905817B (en) Pre-reinforcing system for ground working well advance pipe shed penetrating existing objects in shield region
CN110042843A (en) A kind of large deep foundation pit construction method of complex condition
CN201891123U (en) Single-wall steel hanging box with concrete bottom plate
CN115717536A (en) Inclined shaft forward-hole-entering and top-raising construction method for large-section tunnel in weak water-rich stratum
CN107620316A (en) A kind of rocky bed large volume deepwater foundation construction method
CN201826292U (en) Bare rock steel pipe pile platform in steep slopes under deep sea
CN104695446B (en) Basement construction method for supporting
CN103397634A (en) Anchoring construction method for fastener steel tube pile cofferdam
CN202273233U (en) Deep foundation pit of three-dimensional garage

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120711