CN202247872U - Pile shoe of wind power installation vessel - Google Patents
Pile shoe of wind power installation vessel Download PDFInfo
- Publication number
- CN202247872U CN202247872U CN2011203715582U CN201120371558U CN202247872U CN 202247872 U CN202247872 U CN 202247872U CN 2011203715582 U CN2011203715582 U CN 2011203715582U CN 201120371558 U CN201120371558 U CN 201120371558U CN 202247872 U CN202247872 U CN 202247872U
- Authority
- CN
- China
- Prior art keywords
- plate
- spud leg
- board
- cylindrical shell
- wind
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000009434 installation Methods 0.000 title abstract description 8
- 230000005611 electricity Effects 0.000 claims description 20
- 238000003466 welding Methods 0.000 claims description 3
- 238000005192 partition Methods 0.000 abstract 4
- 230000002093 peripheral Effects 0.000 abstract 1
- 239000000463 material Substances 0.000 description 4
- 238000004519 manufacturing process Methods 0.000 description 2
- 240000007594 Oryza sativa Species 0.000 description 1
- 235000007164 Oryza sativa Nutrition 0.000 description 1
- 208000008425 Protein Deficiency Diseases 0.000 description 1
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000003028 elevating Effects 0.000 description 1
- 235000009566 rice Nutrition 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances data:image/svg+xml;base64,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 data:image/svg+xml;base64,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 O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Abstract
The utility model relates to a pile shoe of a wind power installation vessel. The pile shoe comprises a bottom plate, wherein multiple partition plates are arranged on the bottom plate; vertical side plates are assembled on the peripheral edge of the bottom plate; each side plate is provided with a top plate; each top plate is trapezoidal and is obliquely arranged; a longer bottom side of each top plate is connected with the top side of the side plate; the inner surface of each top plate is welded with the partition plates on the bottom plate; the top sides of four top plates define a square; a square cover plate is arranged at the square; a round hole is arranged at the center of the square cover plate; a pile leg cylinder is arranged in the round hole; multiple partition plates are also arranged in the pile leg cylinder; the diameter of the round hole is the same as the outer diameter of the pile leg cylinder; a round cover plate is welded at the upper part in the pile leg cylinder and arranged on the partition plate in the pile leg cylinder; and a manhole is arranged on the round cover plate. The pile shoe provided by the utility model has the advantages of simple structure and high working efficiency, and is safe and stable.
Description
Technical field
The utility model relates to a kind of wind-powered electricity generation the ship shoe is installed.
Background technology
Nowadays, external wind-powered electricity generation development is conceived to the deep-sea wind-powered electricity generation, the about 20-30 rice of operating water depth, and wind-powered electricity generation mounting platform size is big, and platform weight is big, mostly adopts six leg tooth bars, gear pump elevating mechanism.Basically there is not a wind-powered electricity generation coastal.Domestic do not have a job platform that is applicable to that coastal mudflat wind electric is installed at present, and the motor-driven difficulty of wind-powered electricity generation mounting platform of only bottom-sitting type is influenced greatly by stormy waves, relies on tidewater, and installation accuracy has satisfied not the demand of wind-powered electricity generation installation.
Coastal wind-powered electricity generation is installed required 4 the spud leg hydraulic lifting systems of ship, can solve coastal wind-powered electricity generation installation and influenced by stormy waves, and platform arrives the assigned address that wind-powered electricity generation is installed, and uses hydraulic lifting system that platform is risen, locatees and carry out the wind-powered electricity generation installation exercise.Wind-powered electricity generation is installed and is divided into piling work and two steps of wind tower installation exercise.The work pattern that floating wind-powered electricity generation mounting platform is installed wind power equipment is: platform is motor-driven to utilize mooring system that platform is carried out coarse positioning to assigned address, beginning wind-powered electricity generation installation exercise.Because it is marine that platform only is fixed on by 4 spud legs, so receive wave and tidewater to go up and down to influence, the step of driving piles location is difficult to control, needs good sea situation ability operation, and is dangerous high, inefficiency.
Summary of the invention
The purpose of the utility model is in order to overcome above deficiency, provides the wind-powered electricity generation of a kind of simple in structure, safety and stability, high efficiency that the ship shoe is installed.
The purpose of
the utility model realizes through following technical scheme: a kind of wind-powered electricity generation is installed the ship shoe, comprises base plate, and base plate is provided with a plurality of dividing plates; The side plate that assembling vertically is provided with on the edge of base plate, each side plate is provided with top board, and each top board is trapezoidal; Each top board all is obliquely installed; The longer base of each top board is connected with the top margin of side plate, the inner surface of each top board and the welding of the dividing plate on the base plate, and the top margin of four top boards is enclosed square; The side of being provided with, square place cover plate; Cover plate center, side is provided with circular hole, is provided with the spud leg cylindrical shell in the circular hole, also is provided with a plurality of dividing plates in the spud leg cylindrical shell; The diameter of circular hole is the same with the external diameter of spud leg cylindrical shell; Spud leg cylindrical shell internal upper part is welded with closing disk, and closing disk places on the dividing plate of spud leg barrel, has manhole on the closing disk.
The utility model compared with prior art has the following advantages:
Simple in structure and the spud leg of the utility model is used together, and the contact area of shoe is bigger than spud leg, can increase platform in stability in the sea, and security performance has also strengthened, and need not to receive the up-down of wave and tidewater to influence, and has improved operating efficiency.
Description of drawings:
Fig. 1 is the structural representation of the utility model;
Label among the figure: 1-side plate, 2-top board, 3-side's cover plate, 4-spud leg cylindrical shell, 5-closing disk, 6-manhole.
The specific embodiment:
In order to deepen understanding to the utility model, will combine embodiment and accompanying drawing that the utility model is done further to detail below, this embodiment only is used to explain the utility model, does not constitute the qualification to the utility model protection domain.
Show a kind of embodiment that the utility model wind-powered electricity generation is installed the ship shoe like Fig. 1, comprise base plate, base plate is provided with a plurality of dividing plates; The side plate 1 that assembling vertically is provided with on the edge of base plate, each side plate 1 is provided with top board 2, and each top board 2 is trapezoidal; Each top board 2 all is obliquely installed, and the longer base of each top board 2 is connected with the top margin of side plate 1, the inner surface of each top board 2 and the welding of the dividing plate on the base plate; The top margin of four top boards 2 is enclosed square, the side of being provided with, square place cover plate 3, and square cover plate 3 centers are provided with circular hole; Be provided with spud leg cylindrical shell 4 in the circular hole, also be provided with a plurality of dividing plates in the spud leg cylindrical shell 4, the diameter of circular hole is the same with the external diameter of spud leg cylindrical shell 4; Spud leg cylindrical shell 4 internal upper parts are welded with closing disk 5, and closing disk 5 places on the dividing plate of spud leg cylindrical shell 4 inside, has manhole 6 on the closing disk 5.
Wind-powered electricity generation is installed crane ship has 4 shoes, is shaped as the body structure of disc-like shape, 9.2 meters of each shoe length, and 8.7 meters of width, 1.6 meters of height, each shoe weight is about 104 tons, totally 416 tons of 4 shoes.The shoe panel all adopts the 32mmCCSDH36 deck of boat, and central dividing plate thickness is respectively 16mm, 20mm, 26mm, and material is respectively CCSAH36, CCSAH36, CCSDH36; Top board, base plate are strengthened angle steel and have been adopted L160*100*14, and material is CCSAH36; Spud leg embeds the spud leg cylindrical shell of shoe part, and high spud leg cylindrical shell degree is H=1868mm, and material is CCSEH36 for the 48mm material.Shoe top panel and central dividing plate all need be opened manhole, divide two kinds of the oval manholes of Φ 450 and 400*600.The utility model adopts sectional making, and the technical matters that final integral is closed up through the accuracy of manufacture of control sectional making, guarantees the whole accuracy of manufacture of closing up, the planeness of base plate≤2mm/ ㎡, free tolerance size 1/1000.Simple in structure and the spud leg of the utility model is used together, and the contact area of shoe is bigger than spud leg, can increase platform in stability in the sea, and security performance has also strengthened, and need not to receive the up-down of wave and tidewater to influence, and operating efficiency has also improved.
Claims (1)
1. a wind-powered electricity generation is installed the ship shoe, comprises base plate, and it is characterized in that: said base plate is provided with a plurality of dividing plates; The side plate (1) that assembling vertically is provided with on the edge of said base plate, each said side plate (1) is provided with top board (2), and each said top board (2) is trapezoidal; Each said top board (2) all is obliquely installed; The longer base of each said top board (2) is connected with the top margin of said side plate (1), the said dividing plate welding on the inner surface of each said top board (2) and the said base plate, and the top margin of four said top boards (2) is enclosed square; The side of being provided with, said square place cover plate (3); Said side's cover plate (3) center is provided with circular hole, is provided with spud leg cylindrical shell (4) in the said circular hole, also is provided with a plurality of dividing plates in the said spud leg cylindrical shell (4); The diameter of said circular hole is the same with the external diameter of said spud leg cylindrical shell (4); Said spud leg cylindrical shell (4) internal upper part is welded with closing disk (5), and said closing disk (5) places on the inner dividing plate of said spud leg cylindrical shell (4), has manhole (6) on the said closing disk (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011203715582U CN202247872U (en) | 2011-09-28 | 2011-09-28 | Pile shoe of wind power installation vessel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011203715582U CN202247872U (en) | 2011-09-28 | 2011-09-28 | Pile shoe of wind power installation vessel |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202247872U true CN202247872U (en) | 2012-05-30 |
Family
ID=46109134
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011203715582U Expired - Lifetime CN202247872U (en) | 2011-09-28 | 2011-09-28 | Pile shoe of wind power installation vessel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202247872U (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102704455A (en) * | 2012-07-05 | 2012-10-03 | 南通中远船务工程有限公司 | Method for connecting pile leg and pile shoe of windmill installation vehicle |
CN103406679A (en) * | 2013-08-20 | 2013-11-27 | 南通中新钢构重工有限公司 | Welding technology of stereoscopic section composed of platform board and lateral plates |
CN105442516A (en) * | 2015-12-04 | 2016-03-30 | 大连中远船务工程有限公司 | Underwater installation method for pile shoe extending structure of drilling platform |
CN106120784A (en) * | 2016-07-05 | 2016-11-16 | 武汉船用机械有限责任公司 | A kind of ocean platform shoe |
CN106638589A (en) * | 2017-02-16 | 2017-05-10 | 广东精铟海洋工程股份有限公司 | High-strength offshore platform pile shoe |
CN106759317A (en) * | 2017-02-16 | 2017-05-31 | 广东精铟海洋工程股份有限公司 | A kind of offshore platform shoe |
CN107059859A (en) * | 2016-12-23 | 2017-08-18 | 张英传 | Multifunction fishing upper mounting plate shoe |
CN112252354A (en) * | 2020-10-21 | 2021-01-22 | 浙江大学 | Offshore wind power pile shoe expands large-scale jacket basis |
-
2011
- 2011-09-28 CN CN2011203715582U patent/CN202247872U/en not_active Expired - Lifetime
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102704455A (en) * | 2012-07-05 | 2012-10-03 | 南通中远船务工程有限公司 | Method for connecting pile leg and pile shoe of windmill installation vehicle |
CN102704455B (en) * | 2012-07-05 | 2014-11-26 | 南通中远船务工程有限公司 | Method for connecting pile leg and pile shoe of windmill installation vehicle |
CN103406679A (en) * | 2013-08-20 | 2013-11-27 | 南通中新钢构重工有限公司 | Welding technology of stereoscopic section composed of platform board and lateral plates |
CN105442516A (en) * | 2015-12-04 | 2016-03-30 | 大连中远船务工程有限公司 | Underwater installation method for pile shoe extending structure of drilling platform |
CN106120784A (en) * | 2016-07-05 | 2016-11-16 | 武汉船用机械有限责任公司 | A kind of ocean platform shoe |
CN107059859A (en) * | 2016-12-23 | 2017-08-18 | 张英传 | Multifunction fishing upper mounting plate shoe |
CN106638589A (en) * | 2017-02-16 | 2017-05-10 | 广东精铟海洋工程股份有限公司 | High-strength offshore platform pile shoe |
CN106759317A (en) * | 2017-02-16 | 2017-05-31 | 广东精铟海洋工程股份有限公司 | A kind of offshore platform shoe |
CN106638589B (en) * | 2017-02-16 | 2019-11-05 | 广东精铟海洋工程股份有限公司 | A kind of high intensity offshore platform shoe |
CN112252354A (en) * | 2020-10-21 | 2021-01-22 | 浙江大学 | Offshore wind power pile shoe expands large-scale jacket basis |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202247872U (en) | Pile shoe of wind power installation vessel | |
CN201538971U (en) | Basic structure of high-rise pile cap type offshore wind driven generator | |
JP2004001750A (en) | Special working ship and execution method for offshore structure | |
CN102704452B (en) | Ultra-large self-elevating wind turbine installation vessel with multi-type pile legs and design method thereof | |
CN103225315B (en) | Offshore wind power foundation consisting of single pile, cylindrical foundations and anchor cable | |
CN102060088A (en) | Special technology for offshore combined floating wind power generation | |
CN103228909A (en) | Process for installing an offshore tower | |
CN102296565A (en) | Deep-water ring-shaped floating type artificial harbor | |
CN103452742A (en) | Semi-submersible type multi-floater wave energy conversion device | |
CN108284923A (en) | A kind of hybrid offshore wind farm buoyant foundations partly latent-Spar | |
CN203698619U (en) | Semi-submerged platform | |
CN201941953U (en) | Marine combined floating wind power generation platform | |
EP3276086B1 (en) | Gravity foundation for the installation of offshore wind turbines | |
EP2789847B1 (en) | Floating type wind turbine generation apparatus and installation method thereof | |
CN110949633A (en) | Barge type floating fan system and floating fan platform | |
CN201914862U (en) | Self-rising fan mounting platform | |
CN201971133U (en) | Bottom-supported blower installation platform | |
CN104234069A (en) | Offshore wind turbine foundation with plug-in honeycomb structure chassis | |
CN104960637A (en) | Offshore nuclear power platform for shallow ice sea regions | |
CN202610825U (en) | Prefabricated reinforced concrete-caisson-type offshore wind turbine foundation structure | |
CN203113330U (en) | Pile shoe of wind power installation vessel | |
CN204489133U (en) | For the floating box device of the large-scale single pipe pile foundation construction in shallow sea | |
CN202987472U (en) | Truss type offshore wind turbine mounting barge capable of sitting on bottom | |
CN202414121U (en) | Marine wind-powered installation vessel | |
CN103195080B (en) | Towing method for gravity foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
C14 | Grant of patent or utility model | ||
CX01 | Expiry of patent term |
Granted publication date: 20120530 |
|
CX01 | Expiry of patent term |