CN202245865U - Sintering machine head wheel hoisting device - Google Patents
Sintering machine head wheel hoisting device Download PDFInfo
- Publication number
- CN202245865U CN202245865U CN2011203793100U CN201120379310U CN202245865U CN 202245865 U CN202245865 U CN 202245865U CN 2011203793100 U CN2011203793100 U CN 2011203793100U CN 201120379310 U CN201120379310 U CN 201120379310U CN 202245865 U CN202245865 U CN 202245865U
- Authority
- CN
- China
- Prior art keywords
- sintering machine
- hoist
- wheel
- platform
- lifting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)
Abstract
Description
技术领域 technical field
本实用新型涉及一种起吊安装结构,尤其是一种烧结机头轮吊装装置。The utility model relates to a hoisting installation structure, in particular to a sintering machine head wheel hoisting device.
背景技术 Background technique
通常矿山原料烧结机机头星轮吊装是烧结机设备安装中的重要工序。烧结机机头星轮,简称烧结机头轮,其重量在15吨以上。因烧结生产工艺需要,烧结机本体设备安装在厂房结构框架平台上,该平台称为烧结机安装平台,平台是由在成排成列设置的框架立柱上铺搭平板组成,该平台相对于厂房地面的标高一般有十余米,烧结机头轮安装位置就是在十多米高的高空。由于烧结机的铺底料仓、混合料仓上口散料漏斗操作平台的限制,厂房桁车不能直接用于安装烧结机头轮。因此,吊装烧结机头轮的通常做法是:在超出其安装位置上部10米以上标高的散料漏斗操作平台上设承重钢梁,承重钢梁上预留有一个吊孔,从该吊孔悬挂起吊滑轮组,起吊滑轮组通过钢丝绳与卷扬机连接;在框架立柱上安装临时支撑钢柱、钢梁,铺设钢轨,钢轨上安放临时组合台车,利用厂房桁车将烧结机头轮从地面吊装到所述临时组合台车上,将台车推动至吊孔下方,然后,以钢丝绳连接烧结机头轮和起吊滑轮组,卷扬机动作,以手拉葫芦辅助控制烧结机头轮在空中的位置,共同将烧结机头轮起吊就位。Usually, the hoisting of the head star wheel of the mine raw material sintering machine is an important process in the installation of the sintering machine. Sintering machine head star wheel, referred to as sintering machine head wheel, weighs more than 15 tons. Due to the requirements of the sintering production process, the main body equipment of the sintering machine is installed on the structural frame platform of the workshop. This platform is called the installation platform of the sintering machine. The elevation of the ground is generally more than ten meters, and the installation position of the head wheel of the sintering machine is more than ten meters high. Due to the limitation of the operating platform of the sintering machine's bottom bunker and the upper bulk material hopper of the mixing silo, the factory truss truck cannot be directly used to install the sintering machine head wheel. Therefore, the usual method for hoisting the head wheel of the sintering machine is to set a load-bearing steel beam on the bulk material funnel operating platform at a height of more than 10 meters above the installation position, and a lifting hole is reserved on the load-bearing steel beam. Lifting the pulley block, the lifting pulley block is connected with the hoist through a wire rope; installing temporary supporting steel columns and steel beams on the frame columns, laying steel rails, placing temporary combined trolleys on the rails, and using the factory truss truck to lift the head wheel of the sintering machine from the ground to the Put the trolley on the temporary combination trolley, push the trolley to the bottom of the hoisting hole, then connect the sintering machine head wheel and the lifting pulley block with a wire rope, the hoist moves, use the hand chain hoist to assist in controlling the position of the sintering machine head wheel in the air, and jointly lift the sintering machine The head wheel is hoisted in place.
现有方法存在的缺陷是:用于制作支撑钢柱、钢梁及承重钢梁的材料较多;承重钢梁吊点中心稍有偏移就会导致吊绳受力不均,因此在选择滑轮组、吊绳及卡具时,为确保安全,考虑通常的安全系数后还必须进一步加大规格,施工措施费用增加;卷扬机牵引钢丝绳起吊时,必须有人工辅助,操作不安全。The disadvantages of the existing method are: there are many materials used to make supporting steel columns, steel beams and load-bearing steel beams; a slight deviation in the center of the lifting point of the load-bearing steel beams will cause uneven stress on the suspension ropes, so when selecting pulley blocks , slings and jigs, in order to ensure safety, the specifications must be further increased after considering the usual safety factor, and the cost of construction measures will increase; when the hoist pulls the wire rope for lifting, manual assistance must be provided, and the operation is unsafe.
实用新型内容 Utility model content
为了克服现有烧结机头轮吊装装置过于简易、安全性不高的不足,本实用新型所要解决的技术问题是提供一种安全性高的烧结机头轮吊装装置。In order to overcome the shortcomings of the existing sintering machine head wheel hoisting device which is too simple and not high in safety, the technical problem to be solved by the utility model is to provide a sintering machine head wheel hoisting device with high safety.
本实用新型解决其技术问题所采用的技术方案是:烧结机头轮吊装装置,包括设置在烧结机头轮安装位置上方的散料漏斗操作平台,在烧结机安装平台上安装有一对延伸至烧结机头轮安装位置的滑轨梁,滑轨梁上配备有与之轮轨配合的台车,在散料漏斗操作平台上设置有两个吊孔,在每一个吊孔下方均设置有起吊滑轮组,起吊滑轮组通过钢丝绳各与一台卷扬机连接,所述起吊滑轮组与卷扬机之间的钢丝绳由分力导向轮导向,分力导向轮和卷扬机固定设置在烧结机安装平台上。The technical scheme adopted by the utility model to solve the technical problem is: the hoisting device of the head wheel of the sintering machine includes a bulk material funnel operating platform arranged above the installation position of the head wheel of the sintering machine, and a pair of hoppers extending to the sintering machine are installed on the installation platform The slide rail beam at the installation position of the nose wheel, the slide rail beam is equipped with a trolley matched with the wheel rail, two lifting holes are set on the operating platform of the bulk material hopper, and a lifting pulley block is set under each lifting hole , the hoisting pulley blocks are connected to a winch through steel wire ropes, the wire ropes between the lifting pulley blocks and the hoisting machines are guided by component force guide wheels, and the force component guide wheels and hoisting machines are fixedly arranged on the sintering machine installation platform.
所述起吊滑轮组、分力导向轮和卷扬机相对于台车走行轨中心线对称布置。The lifting pulley block, force component guide wheel and hoist are arranged symmetrically with respect to the centerline of the trolley's running rail.
所述两台卷扬机采用匀速卷扬机,并由控制器控制同时启、停。The two winches adopt uniform speed winches, and are controlled by a controller to start and stop simultaneously.
本实用新型的有益效果是:提高了烧结机头轮吊装的安全性,实用高效,节省成本。The beneficial effects of the utility model are: the safety of hoisting the head wheel of the sintering machine is improved, the utility model is practical and efficient, and the cost is saved.
附图说明Description of drawings
图1是本实用新型烧结机头轮吊装装置的示意图。Fig. 1 is a schematic diagram of the lifting device for the head wheel of the sintering machine of the present invention.
图中标记为,1-烧结机头轮,2-起吊滑轮组,3-吊孔,4-分力导向轮,5-卷扬机,6-烧结机安装平台,7-散料漏斗安装平台,8-滑轨梁,9-台车,10-控制器,11-钢丝绳。Marked in the figure, 1-sintering machine head wheel, 2-lifting pulley block, 3-lifting hole, 4-force guide wheel, 5-hoist, 6-sintering machine installation platform, 7-bulk material hopper installation platform, 8- Slide rail beam, 9-Trolley, 10-Controller, 11-Wire rope.
具体实施方式 Detailed ways
下面结合附图对本实用新型进一步说明。Below in conjunction with accompanying drawing, the utility model is further described.
如图1所示,本实用新型的烧结机头轮吊装装置包括设置在烧结机头轮安装位置上方的散料漏斗操作平台7,在烧结机安装平台6上安装有一对延伸至烧结机头轮安装位置的滑轨梁8,滑轨梁8上配备有与之轮轨配合的台车9,与现有结构不同的是,在散料漏斗操作平台7上设置有两个吊孔3,在每一个吊孔3下方均设置有起吊滑轮组2,起吊滑轮组2通过钢丝绳11各与一台卷扬机5连接,所述起吊滑轮组2与卷扬机5之间的钢丝绳11由分力导向轮4导向,分力导向轮4和卷扬机5固定设置在烧结机安装平台6上,因为有两个吊点,烧结机头轮1是以抬吊的方式起升,因此,起吊更平稳,即使吊点略有偏移,也能保证稳定起升,起升过程不需要以手拉葫芦等作为牵引,安全性更好,单组起升设备如滑轮组、分力导向轮4和卷扬机6、钢丝绳11的最大受力减小,在考虑通常的安全系数后时不需要再进一步加大规格。As shown in Figure 1, the hoisting device of the sintering machine head wheel of the present invention includes a bulk material funnel operating platform 7 arranged above the installation position of the sintering machine head wheel, and a pair of The slide rail beam 8 at the installation position is equipped with a
如图1所示,所述起吊滑轮组2、分力导向轮4和卷扬机5相对于台车9走行轨中心线对称布置,从而保证由两组起升设备均匀受力。As shown in Fig. 1, the lifting pulley block 2, force component guide wheel 4 and hoist 5 are arranged symmetrically with respect to the center line of the traveling rail of the
两台卷扬机5可以由两个操作人员依起升过程中目测的起升速度来控制启停。如图1所示,为保证同步性,所述两台卷扬机5采用匀速卷扬机,并由控制器10控制同时启、停。Two winches 5 can be controlled to start and stop according to the lifting speed of visual inspection in the lifting process by two operators. As shown in FIG. 1 , in order to ensure synchronization, the two hoisting machines 5 adopt uniform speed hoisting machines, and are controlled by the
应用本实用新型的安装作业过程:在烧结机头部上台车轨道梁位置,沿机头方向各安装一根滑轨梁8;在滑轨梁8上安钢轨(钢轨顶面标高、型号同台车车轮适配);在滑轨梁8下安支撑钢架;在铺底料仓、混合料仓上口钢筋混凝土平台梁两侧,预留2个200×200mm孔,在2个预留孔位置设吊点悬挂起吊滑轮组2;在烧结机安装平台6的框架柱位置固定卷扬机5,用穿绕过分力导向轮4的钢丝绳11将起吊滑轮组2同卷扬机5连接牢靠。利用厂房桁车将烧结机头轮1吊装到烧结机中部骨架台车9上(三台台车并排),推动台车9将烧结机头轮1送到其支承座横向中心位置;再用卷扬机5牵引钢丝绳11使起吊滑轮组2起升,在烧结机头轮1起升约300mm左右时,移开台车9,拆除钢轨、滑轨梁8及支撑钢架,操作卷扬机5控制起吊滑轮组2缓慢下降,将烧结机头轮1安放到支承座上就位。Apply the installation process of the utility model: install a slide rail beam 8 on the trolley track beam position on the head of the sintering machine along the head direction; install rails on the slide rail beam 8 (rail top surface elevation, model same platform Vehicle wheel adaptation); install a supporting steel frame under the slide rail beam 8; reserve two 200×200mm holes on both sides of the reinforced concrete platform beam at the top of the bottom silo and the mixing silo, and reserve two holes at the positions of the two reserved holes Set the lifting point to hang the hoisting pulley block 2; fix the hoisting machine 5 at the frame column position of the sintering machine installation platform 6, and connect the hoisting pulley block 2 with the hoisting machine 5 firmly with the
应用本实用新型进行单台烧结机机头星轮安装与传统方法相比较,工期可提前2天,节约施工措施耗材约18t,降低了施工成本,且安全可靠。Compared with the traditional method, the application of the utility model to install the star wheel of the head of a single sintering machine can shorten the construction period by 2 days, save about 18 tons of consumables for construction measures, reduce the construction cost, and is safe and reliable.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2011203793100U CN202245865U (en) | 2011-10-08 | 2011-10-08 | Sintering machine head wheel hoisting device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2011203793100U CN202245865U (en) | 2011-10-08 | 2011-10-08 | Sintering machine head wheel hoisting device |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN202245865U true CN202245865U (en) | 2012-05-30 |
Family
ID=46107138
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2011203793100U Expired - Lifetime CN202245865U (en) | 2011-10-08 | 2011-10-08 | Sintering machine head wheel hoisting device |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN202245865U (en) |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104973517A (en) * | 2015-06-26 | 2015-10-14 | 天津二十冶建设有限公司 | Electric gantry platform for installing sintering machine head equipment and application method thereof |
| CN106015729A (en) * | 2016-06-08 | 2016-10-12 | 中国十七冶集团有限公司 | Reverse in-position method for vaporization flue in closed plant |
| CN106855356A (en) * | 2015-12-08 | 2017-06-16 | 中国二冶集团有限公司 | The construction method of quick integral translation sintering machine head upper skeleton and feeding device |
| CN106946163A (en) * | 2017-05-03 | 2017-07-14 | 武汉科技大学 | Drum type filter screen A shapes frame installs special tooling |
| CN112284131A (en) * | 2020-09-22 | 2021-01-29 | 广东韶钢松山股份有限公司 | Sintering machine trolley guiding device and guiding method thereof |
| CN116986478A (en) * | 2023-08-21 | 2023-11-03 | 中国二十二冶集团有限公司 | Installation method of large flue ash hopper in sintering chamber |
| CN117429890A (en) * | 2023-11-28 | 2024-01-23 | 中国十七冶集团有限公司 | An efficient installation structure and method for long-distance conveyor belt conveyor rollers in steelmaking engineering |
-
2011
- 2011-10-08 CN CN2011203793100U patent/CN202245865U/en not_active Expired - Lifetime
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104973517A (en) * | 2015-06-26 | 2015-10-14 | 天津二十冶建设有限公司 | Electric gantry platform for installing sintering machine head equipment and application method thereof |
| CN106855356A (en) * | 2015-12-08 | 2017-06-16 | 中国二冶集团有限公司 | The construction method of quick integral translation sintering machine head upper skeleton and feeding device |
| CN106855356B (en) * | 2015-12-08 | 2019-04-16 | 中国二冶集团有限公司 | The construction method of the skeleton and the feeding equipment on the head of the fast integral translation sintering machine |
| CN106015729A (en) * | 2016-06-08 | 2016-10-12 | 中国十七冶集团有限公司 | Reverse in-position method for vaporization flue in closed plant |
| CN106015729B (en) * | 2016-06-08 | 2018-03-06 | 中国十七冶集团有限公司 | A kind of reverse method in place of evaporated flue under sealing power house |
| CN106946163A (en) * | 2017-05-03 | 2017-07-14 | 武汉科技大学 | Drum type filter screen A shapes frame installs special tooling |
| CN112284131A (en) * | 2020-09-22 | 2021-01-29 | 广东韶钢松山股份有限公司 | Sintering machine trolley guiding device and guiding method thereof |
| CN116986478A (en) * | 2023-08-21 | 2023-11-03 | 中国二十二冶集团有限公司 | Installation method of large flue ash hopper in sintering chamber |
| CN117429890A (en) * | 2023-11-28 | 2024-01-23 | 中国十七冶集团有限公司 | An efficient installation structure and method for long-distance conveyor belt conveyor rollers in steelmaking engineering |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102556854B (en) | Mine hydraulic hoisting traveling crane | |
| CN104973517B (en) | A kind of electronic gantry platform that installs for sintering machine head device and its using method | |
| CN107201721A (en) | Stay cable installation construction method | |
| CN104477736A (en) | Shaft elevator installation method | |
| CN104060835B (en) | Lifting-sliding construction method for single plane truss | |
| CN105003082A (en) | Glass curtain wall mounting equipment and glass curtain mounting method | |
| CN104140037A (en) | Wallboard lifting system | |
| CN201376848Y (en) | Large-scale double-tower automatic-elevation hoisting equipment | |
| CN105645275B (en) | Cable hoist and its construction method | |
| CN103899093A (en) | Step-by-step hoisting construction method of mega-frame steel truss beam | |
| CN112647413A (en) | Deep buried tunnel type anchorage cable saddle installation construction method | |
| CN105781210B (en) | A kind of conical tower and its tool section assist punching construction method for lifting whole | |
| US20070090074A1 (en) | Mobile crane with ballasting | |
| CN109704215A (en) | Steel platform Lift-on/Lift-off System and method in a kind of chimney | |
| CN111851314B (en) | A steel cushion beam lifting device and use method thereof | |
| CN103821084B (en) | Operational method at the bottom of implement at the bottom of beam and beam | |
| CN102963817A (en) | Tailing force-free large equipment hoisting vertical tail removal method | |
| CN108625270A (en) | Nose girder gantry crane installs bridge prefabrication box girder construction method | |
| CN102062538B (en) | Method for mounting head sprocket wheel of belt sintering machine | |
| CN107720652A (en) | A kind of construction method for hanging of frame structure large scale equipment | |
| CN104528506B (en) | Mine hoist and unhooking test method thereof | |
| CN207061690U (en) | Bridge crane with suspender maintenance rig | |
| CN109694010B (en) | Counterweight lifting method | |
| CN201857225U (en) | Hoisting device for bridge crane frame | |
| CN206667058U (en) | A kind of across cable walking cord clip handling erecting device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CX01 | Expiry of patent term | ||
| CX01 | Expiry of patent term |
Granted publication date: 20120530 |