CN202079565U - Auxiliary tool for installing steel arch center - Google Patents
Auxiliary tool for installing steel arch center Download PDFInfo
- Publication number
- CN202079565U CN202079565U CN2011201661592U CN201120166159U CN202079565U CN 202079565 U CN202079565 U CN 202079565U CN 2011201661592 U CN2011201661592 U CN 2011201661592U CN 201120166159 U CN201120166159 U CN 201120166159U CN 202079565 U CN202079565 U CN 202079565U
- Authority
- CN
- China
- Prior art keywords
- screw rod
- steel arch
- nut
- arch center
- auxiliary tool
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model relates to tunnel construction equipment, in particular to an auxiliary tool for installing a steel arch center, which solves the problems of large labor intensity, low efficiency and lower safety coefficient when the steel arch center is manually installed. The auxiliary tool for installing the steel arch center comprises a channel steel type bayonet with an upper opened end, a screw rod is fixed at the lower end of the bayonet, a sleeve is sheathed outside the screw rod, a nut screwed on the screw rod is supported on the sleeve, and a wrench is fixed on the side wall of the nut. The auxiliary tool is simple to manufacture and less in material consumption, and the steel arch center can be elevated to a designed height by supporting of the screw rod through rotating the wrench welded on the nut, therefore, the labor intensity of workers can be greatly lightened, the procedure and operation time can be shortened, and the safety and reliability can be achieved.
Description
Technical field
The utility model relates to constructing tunnel equipment, is specially a kind of steel bow member mounting auxiliary.
Background technology
Along with improving constantly of China's tunnel construction technology, large cross-section tunnel is more and more.Steel bow member junction is adopted welding steel and is connected by high-strength bolt, there are a lot of artificial origins during construction, cause the junction to have too many defective, therefore the junction just becomes the stressed weak spot of domain steel bow member, in order not weaken the ability of preliminary bracing carrying, steel bow member unit merogenesis is few more good more, so just cause some large cross-section tunnels (as Line for Passenger Transportation, when three track highways etc.) constructing, single-unit steel bow member is longer, heavier, mainly adopt when at present installing the steel bow member in the constructing tunnel workman pickaback hand lift, labour intensity is big, inefficiency and dangerous again.
Summary of the invention
There is the problem that labour intensity is big, efficient is low and safety coefficient is lower in the utility model when manually installing the steel bow member in order to solve, and a kind of steel bow member mounting auxiliary is provided.
The utility model is to adopt following technical scheme to realize: steel bow member mounting auxiliary, comprise the channel-section steel shape bayonet socket of upper end open, the bayonet socket lower end is fixed with screw rod, and screw jacket has sleeve pipe, the sleeve pipe upper support has the nut that is screwed on the screw rod, and the nut sidewall is fixed with spanner.When installing the steel bow member, steel bow member unit is lifted certain altitude, bayonet socket is blocked steel bow member unit, sleeve is supported on ground, by the rotating spanner nut screw rod is risen steel bow member jack-up, be welded to connect, overcome and have the problem that labour intensity is big, efficient is low and safety coefficient is lower when manually installing the steel bow member.
That the utility model is made is simple, consumptive material is few, is welded on spanner on the nut by rotation, makes screw rod support the steel bow member and is elevated to design height, has alleviated working strength of workers in a large number, has shortened operation and activity duration, and safe and reliable.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Among the figure: 1-bayonet socket, 2-screw rod, 3-sleeve pipe, 4-nut, 5-spanner.
The specific embodiment
Steel bow member mounting auxiliary comprises the channel-section steel shape bayonet socket 1 of upper end open, and bayonet socket 1 lower end is fixed with screw rod 2, and screw rod 2 is outer to be with sleeve pipe 3, and sleeve pipe 3 upper supports have the nut 4 that is screwed on the screw rod 2, and nut 4 sidewalls are fixed with spanner 5.In the specific implementation process, bayonet socket 1 A/F is slightly larger than steel bow member width, and screw rod 2 thicknesses guarantee that this device rigidity and steel bow member weight are complementary, and welds spanner on the nut that is complementary with screw rod, nut is installed in rear lower is provided with sleeve pipe on the screw rod, casing diameter is identical with nut.This device length is adjusted flexibly according to the scene.
Claims (1)
1. steel bow member mounting auxiliary, it is characterized in that: the channel-section steel shape bayonet socket (1) that comprises upper end open, bayonet socket (1) lower end is fixed with screw rod (2), the outer sleeve pipe (3) that is with of screw rod (2), sleeve pipe (3) upper support has the nut (4) that is screwed on the screw rod (2), and nut (4) sidewall is fixed with spanner (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011201661592U CN202079565U (en) | 2011-05-24 | 2011-05-24 | Auxiliary tool for installing steel arch center |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011201661592U CN202079565U (en) | 2011-05-24 | 2011-05-24 | Auxiliary tool for installing steel arch center |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202079565U true CN202079565U (en) | 2011-12-21 |
Family
ID=45340219
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011201661592U Expired - Fee Related CN202079565U (en) | 2011-05-24 | 2011-05-24 | Auxiliary tool for installing steel arch center |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202079565U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106089267A (en) * | 2016-06-30 | 2016-11-09 | 中交航局第四工程有限公司 | Excavator auxiliary steel arch-shelf mounting process |
CN106166724A (en) * | 2016-09-23 | 2016-11-30 | 江西洪都航空工业集团有限责任公司 | A kind of packing ring clamping tool |
CN107511812A (en) * | 2017-09-25 | 2017-12-26 | 北京首钢股份有限公司 | A kind of robot device for being dismounted to hydraulic cylinder |
CN108608363A (en) * | 2018-04-26 | 2018-10-02 | 上海宝冶集团有限公司 | The flat uniaxial photovoltaic bracket mounting tool of one kind and installation method |
CN109590941A (en) * | 2018-12-06 | 2019-04-09 | 中国航发贵州黎阳航空动力有限公司 | Aero-engine Complex Panels assemble device and preparation method thereof |
-
2011
- 2011-05-24 CN CN2011201661592U patent/CN202079565U/en not_active Expired - Fee Related
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106089267A (en) * | 2016-06-30 | 2016-11-09 | 中交航局第四工程有限公司 | Excavator auxiliary steel arch-shelf mounting process |
CN106166724A (en) * | 2016-09-23 | 2016-11-30 | 江西洪都航空工业集团有限责任公司 | A kind of packing ring clamping tool |
CN107511812A (en) * | 2017-09-25 | 2017-12-26 | 北京首钢股份有限公司 | A kind of robot device for being dismounted to hydraulic cylinder |
CN107511812B (en) * | 2017-09-25 | 2021-03-09 | 北京首钢股份有限公司 | Manipulator device for disassembling and assembling hydraulic cylinder |
CN108608363A (en) * | 2018-04-26 | 2018-10-02 | 上海宝冶集团有限公司 | The flat uniaxial photovoltaic bracket mounting tool of one kind and installation method |
CN109590941A (en) * | 2018-12-06 | 2019-04-09 | 中国航发贵州黎阳航空动力有限公司 | Aero-engine Complex Panels assemble device and preparation method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202079565U (en) | Auxiliary tool for installing steel arch center | |
CN204355957U (en) | A kind of novel pipeline anchor ear lifting connection structure | |
CN202063631U (en) | Double-crane lifting freely-unhooking device | |
CN201940933U (en) | Tool special for detaching expansion sleeve of trimmed roller way | |
CN204237516U (en) | A kind of fork truck otic placode bearing pin | |
CN209363921U (en) | In small-bore steel short tube assembly weld accessory cart | |
CN204024443U (en) | Adopt the bamboo ladder stand of connector overlapping | |
CN206984028U (en) | A kind of trolley for improving precast concrete production efficiency | |
CN202911754U (en) | Round bucket transportation vehicle | |
CN201071684Y (en) | Sheave wheel platform connected by L shaped bolt | |
CN204265249U (en) | A kind of transfer crane and portal frame thereof | |
CN203113885U (en) | Hydraulic type rod straightening device | |
CN204152192U (en) | A kind of scaffold fastenings | |
CN203159149U (en) | Large-span prestress double-arching-frame hoisting structure | |
CN204470864U (en) | A kind of slewing tower rotary tooling | |
CN203082363U (en) | Vertical shaft cable bridge integral installation structure | |
CN204024432U (en) | Adopt the bamboo ladder stand of link overlapping | |
CN203486437U (en) | Refractory brick raw material transport vehicle | |
CN202544406U (en) | Spiral thimble type large building template dismantling instrument | |
CN203655532U (en) | Wheel hub structure of wind driven generator | |
CN202561404U (en) | Hoisting device | |
CN204470892U (en) | A kind of slewing tower chip frock | |
CN203486742U (en) | Steel girder for equipment for hoisting slipping tail | |
CN204024453U (en) | The bamboo ladder stand plug-in connection of power communication repairing overlapping | |
CN204024458U (en) | The bamboo ladder stand plug-in connection of power communication repairing overlapping |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20111221 Termination date: 20190524 |
|
CF01 | Termination of patent right due to non-payment of annual fee |