CN202012047U - 塔架钢绞线斜拉扣挂系统 - Google Patents

塔架钢绞线斜拉扣挂系统 Download PDF

Info

Publication number
CN202012047U
CN202012047U CN2011200538656U CN201120053865U CN202012047U CN 202012047 U CN202012047 U CN 202012047U CN 2011200538656 U CN2011200538656 U CN 2011200538656U CN 201120053865 U CN201120053865 U CN 201120053865U CN 202012047 U CN202012047 U CN 202012047U
Authority
CN
China
Prior art keywords
steel strand
pylon
rib
buckling
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011200538656U
Other languages
English (en)
Inventor
袁长春
沙权贤
王学哲
王成双
刘宏宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway 13th Bureau Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway 13th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway 13th Bureau Group Co Ltd filed Critical First Engineering Co Ltd of China Railway 13th Bureau Group Co Ltd
Priority to CN2011200538656U priority Critical patent/CN202012047U/zh
Application granted granted Critical
Publication of CN202012047U publication Critical patent/CN202012047U/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型公开一种塔架钢绞线斜拉扣挂系统,包括塔架(1),拱肋节段(2)和锚碇(3),其特征在于:所述的塔架(1)上设置有转向架(4),一端固定连接在锚碇(3)上的钢绞线(5)通过转向架(4)与拱肋节段(2)上的扣点(6)连接,钢绞线(5)与锚碇(3)的连接处设置有张拉千斤顶(7)。它是一种结构简单,设计巧妙,安装方便,定位准确,调整方便的塔架钢绞线斜拉扣挂系统。

Description

塔架钢绞线斜拉扣挂系统
技术领域
本实用新型涉及一种造桥辅助装置,尤其是一种结构简单,安装方便,定位准确的塔架钢绞线斜拉扣挂系统。
背景技术
在进行各种拱桥的拱肋安装时,需要辅助以塔架钢丝绳系统,利用塔架上设置的钢丝绳将组成拱肋的拱肋节段固定在预定位置,然后对拱肋节段进行安装,待拱肋节段固定到位后,将其逐节安装、连接为一体结构,拱肋全部安装完成后,撤去钢丝绳系统,拱肋自身的结构便足以支撑其自身重量,安装工作结束。这种传统的钢丝绳系统存在着施工周期较长,定位及定位后的调整较为麻烦,且不准确,同时还存在着一定的安全隐患。
发明内容
本实用新型是为了解决现有技术所存在的上述不足,提出一种结构简单,设计巧妙,安装方便,定位准确,调整方便的塔架钢绞线斜拉扣挂系统。
本实用新型的具体解决方案是:一种塔架钢绞线斜拉扣挂系统,包括塔架1、拱肋节段2和锚碇3,其特征在于:所述的塔架1上设置有转向架4,一端固定连接在锚碇3上的钢绞线5通过转向架4与拱肋节段2上的扣点6连接,钢绞线5与锚碇3的连接处设置有张拉千斤顶7。
所述的塔架1的顶端设置有平衡梁8,平衡梁8处设置有张拉千斤顶7,与拱肋节段2连接的钢绞线5与此处的张拉千斤顶7连接,在平衡梁8和锚碇3之间还设置有钢绞线平衡索9。
所述的钢绞线5为多根。
本实用新型同现有技术相比,具有如下优点:
本种结构形式的塔架钢绞线斜拉扣挂系统,用性能较好的钢绞线替代了传统的钢丝绳,并在塔架结构上作出了一定的改进,使斜拉扣挂系统的结构更加简单、合理,提高了系统的整体安全性,尤其是它设置有可对远端的扣点位置调整的张拉千斤顶,这样就可以使操作人员在地面上(或较为方便操作的地方)进行操作和调整,可以加快调整的过程;因此可以说这种塔架钢绞线斜拉扣挂系统具备了多种优点,特别适合于在造桥领域中推广应用,其市场前景较为广阔。
附图说明
图1是本实用新型实施例的结构示意图。
具体实施方式
下面将结合附图说明本实用新型的具体实施方式。如图1所示:一种塔架钢绞线斜拉扣挂系统,包括塔架1、拱肋节段2和锚碇3,多个拱肋节段2最终组成桥梁的拱肋;在塔架1的塔身上设置有多个转向架4,每一个转向架4上都连接有钢绞线5,钢绞线5的一端固定连接在拱肋节段2的扣点6上,另一端连接在锚碇3处,且连接在张拉千斤顶7上;在塔架1的顶端设置有平衡梁8,在平衡梁8处设置有张拉千斤顶7,此处的张拉千斤顶7上同样连接有另一端与拱肋节段2连接的钢绞线5,在平衡梁8处,还设置有钢绞线平衡索9,钢绞线平衡索9的另一端与锚碇3处的张拉千斤顶7连接。
利用本实用新型实施例的塔架钢绞线斜拉扣挂系统安装桥梁的拱肋时,首先将塔架1固定在地面上,然后利用卷扬机将钢绞线5和钢绞线平衡索9连接在塔架1上,通过张拉千斤顶7的张拉动作,使钢绞线和钢绞线平衡索9动作,最终实现调整拱肋节段2的空间位置的目的,使拱肋节段2到达设计位置;领用上述方法将所有的拱肋节段2安装到位后,进行拱肋合龙,整体桥梁拱肋安装完成后,将本实施例的塔架钢绞线斜拉扣挂系统拆除即可。

Claims (3)

1. 一种塔架钢绞线斜拉扣挂系统,包括塔架(1)、拱肋节段(2)和锚碇(3),其特征在于:所述的塔架(1)上设置有转向架(4),一端固定连接在锚碇(3)上的钢绞线(5)通过转向架(4)与拱肋节段(2)上的扣点(6)连接,钢绞线(5)与锚碇(3)的连接处设置有张拉千斤顶(7)。
2.根据权利要求1所述的塔架钢绞线斜拉扣挂系统,其特征在于:所述的塔架(1)的顶端设置有平衡梁(8),平衡梁(8)处设置有张拉千斤顶(7),与拱肋节段(2)连接的钢绞线(5)与此处的张拉千斤顶(7)连接,在平衡梁(8)和锚碇(3)之间还设置有钢绞线平衡索(9)。
3.根据权利要求2所述的塔架钢绞线斜拉扣挂系统,其特征在于:所述的钢绞线(5)为多根。
CN2011200538656U 2011-03-03 2011-03-03 塔架钢绞线斜拉扣挂系统 Expired - Lifetime CN202012047U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200538656U CN202012047U (zh) 2011-03-03 2011-03-03 塔架钢绞线斜拉扣挂系统

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200538656U CN202012047U (zh) 2011-03-03 2011-03-03 塔架钢绞线斜拉扣挂系统

Publications (1)

Publication Number Publication Date
CN202012047U true CN202012047U (zh) 2011-10-19

Family

ID=44782660

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200538656U Expired - Lifetime CN202012047U (zh) 2011-03-03 2011-03-03 塔架钢绞线斜拉扣挂系统

Country Status (1)

Country Link
CN (1) CN202012047U (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704405A (zh) * 2012-06-21 2012-10-03 中铁大桥局集团有限公司 一种利用扣、锚索平衡额外水平力的方法
CN103572703A (zh) * 2013-10-08 2014-02-12 中铁十八局集团有限公司 外包混凝土斜拉扣挂和分环分段组合法施工方法
CN104790296A (zh) * 2015-03-30 2015-07-22 广西路桥工程集团有限公司 一种劲性骨架混凝土拱桥的施工方法
CN105155424A (zh) * 2015-09-16 2015-12-16 中铁九桥工程有限公司 一种拱门形钢斜塔斜拉扣挂施工技术
CN106120573A (zh) * 2016-06-30 2016-11-16 中国化学工程第三建设有限公司 跨海多跨提篮拱桥自平衡扣挂施工方法
CN106436574A (zh) * 2015-12-24 2017-02-22 中铁二局集团有限公司 一种桥梁的扣挂方法
CN107227692A (zh) * 2017-07-18 2017-10-03 广西路桥工程集团有限公司 一种斜拉扣挂安装系统
CN109137745A (zh) * 2018-10-22 2019-01-04 四川路桥华东建设有限责任公司 一种利用边跨压塔索兼作扣挂系统背索的施工方法

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704405B (zh) * 2012-06-21 2014-11-05 中铁大桥局集团有限公司 一种利用扣、锚索平衡额外水平力的方法
CN102704405A (zh) * 2012-06-21 2012-10-03 中铁大桥局集团有限公司 一种利用扣、锚索平衡额外水平力的方法
CN103572703A (zh) * 2013-10-08 2014-02-12 中铁十八局集团有限公司 外包混凝土斜拉扣挂和分环分段组合法施工方法
CN104790296A (zh) * 2015-03-30 2015-07-22 广西路桥工程集团有限公司 一种劲性骨架混凝土拱桥的施工方法
CN104790296B (zh) * 2015-03-30 2016-08-24 广西路桥工程集团有限公司 一种劲性骨架混凝土拱桥的施工方法
CN105155424A (zh) * 2015-09-16 2015-12-16 中铁九桥工程有限公司 一种拱门形钢斜塔斜拉扣挂施工技术
CN106436574B (zh) * 2015-12-24 2018-12-21 中铁二局集团有限公司 一种桥梁的扣挂方法
CN106436574A (zh) * 2015-12-24 2017-02-22 中铁二局集团有限公司 一种桥梁的扣挂方法
CN106120573A (zh) * 2016-06-30 2016-11-16 中国化学工程第三建设有限公司 跨海多跨提篮拱桥自平衡扣挂施工方法
CN106120573B (zh) * 2016-06-30 2018-03-16 中国化学工程第三建设有限公司 跨海多跨提篮拱桥自平衡扣挂施工方法
CN107227692A (zh) * 2017-07-18 2017-10-03 广西路桥工程集团有限公司 一种斜拉扣挂安装系统
CN107227692B (zh) * 2017-07-18 2023-01-24 广西路桥工程集团有限公司 一种斜拉扣挂安装系统
CN109137745A (zh) * 2018-10-22 2019-01-04 四川路桥华东建设有限责任公司 一种利用边跨压塔索兼作扣挂系统背索的施工方法
CN109137745B (zh) * 2018-10-22 2020-06-23 四川路桥华东建设有限责任公司 一种利用边跨压塔索兼作扣挂系统背索的施工方法

Similar Documents

Publication Publication Date Title
CN202012047U (zh) 塔架钢绞线斜拉扣挂系统
CN202881852U (zh) 悬索桥缆索安装系统
CN101967796A (zh) 一种平行钢丝斜拉索的安装方法
CN103001146B (zh) 钢管杆作业平台的使用方法
CN103288002B (zh) 简易组合门架高空重物吊装装置
CN109853393A (zh) 一种主塔竖转斜拉桥的挂索施工系统及其施工方法
CN203284126U (zh) 简易组合门架高空重物吊装装置
CN201118145Y (zh) 输电线路空中跨越器
CN101966823A (zh) 一种承力索跨越架及其架设方法
CN204992417U (zh) 一种机械化自升降门型跨越架
CN204185775U (zh) 一种双线往复门架式大循环牵引系统
CN201598842U (zh) 大直径预应力钢索高空穿越装置
CN105162033A (zh) 一种机械化自升降门型跨越架
CN201722937U (zh) 网架安装滑移平台
CN204662383U (zh) 一种水电站尾水管检修平台
CN203701878U (zh) 屏蔽门立柱分体式承载连接机构
CN203546600U (zh) 钢绞线导向装置
CN203514918U (zh) 带有爬梯装置的混凝土杆塔
CN203655140U (zh) 一种龙门吊上下直梯安全防坠装置
CN102733612B (zh) 电动葫芦轨道安装方法
CN105480873A (zh) 不停运高铁跨越设备的跨梁变幅旋转机构
CN202936115U (zh) 施工索道对接平台及货运平移装置
CN203333122U (zh) 新型重锤钢丝绳头架
CN203755166U (zh) 一种用于施工人员上下的简易升降装置
CN205632168U (zh) 适用于地铁线路的接触网放线车

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20111019

CX01 Expiry of patent term