CN201971784U - Primary dust remover - Google Patents

Primary dust remover Download PDF

Info

Publication number
CN201971784U
CN201971784U CN2010206652453U CN201020665245U CN201971784U CN 201971784 U CN201971784 U CN 201971784U CN 2010206652453 U CN2010206652453 U CN 2010206652453U CN 201020665245 U CN201020665245 U CN 201020665245U CN 201971784 U CN201971784 U CN 201971784U
Authority
CN
China
Prior art keywords
barricade
dedusting
resistance
dust remover
shell
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010206652453U
Other languages
Chinese (zh)
Inventor
王福
何刚
吴云川
张少春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pangang Group Steel Vanadium and Titanium Co Ltd
Pangang Group Panzhihua Steel and Vanadium Co Ltd
Original Assignee
Pangang Group Steel Vanadium and Titanium Co Ltd
Pangang Group Panzhihua Steel and Vanadium Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pangang Group Steel Vanadium and Titanium Co Ltd, Pangang Group Panzhihua Steel and Vanadium Co Ltd filed Critical Pangang Group Steel Vanadium and Titanium Co Ltd
Priority to CN2010206652453U priority Critical patent/CN201971784U/en
Application granted granted Critical
Publication of CN201971784U publication Critical patent/CN201971784U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

本实用新型涉及焦化领域,提供了一种一次除尘器,包括外壳、除尘挡墙,所述壳体包括顶面、两侧侧面、两端端面,所述除尘挡墙是钢结构。钢结构具有耐高温、耐腐蚀、耐磨损、抗氧化、抗高流、抗冲击、可焊接的特性,在高温环境下能连续使用,具有良好的抗热疲劳和耐高温性能,反复使用不易产生热列现象,不可能存在跨塌问题,对企业连续生产创造更加有利条件。不再对砖与砌筑有要求,简化操作步骤,降低劳动强度。适用于干熄焦工艺的一次除尘。

The utility model relates to the field of coking, and provides a primary dust remover, which includes a shell and a dust-removing retaining wall. The shell includes a top surface, side surfaces on both sides, and end faces at both ends. The dust-removing retaining wall is a steel structure. The steel structure has the characteristics of high temperature resistance, corrosion resistance, wear resistance, oxidation resistance, high flow resistance, impact resistance, and weldability. It can be used continuously in high temperature environments, has good thermal fatigue resistance and high temperature resistance, and is not easy to use repeatedly. There is no possibility of cross-collapse problem in case of thermal column phenomenon, which will create more favorable conditions for continuous production of enterprises. There is no longer any requirement for bricks and masonry, the operation steps are simplified, and the labor intensity is reduced. It is suitable for primary dust removal in dry coke quenching process.

Description

Disposable dust remover
Technical field
The utility model relates to the coking field, especially a kind of disposable dust remover.
Background technology
Dry quenching system mainly partly is made up of dried stove, charging apparatus, coke discharging device, lift, disposable dust remover, secondary filter, coke dry quenching boiler system, recirculation blower, dedusting terrestrial station, water treatment system, automatic control system, the power generation system etc. put out.Wherein disposable dust remover utilizes gravity settling formula dust-cleaning principle that the macrobead coke powder in the recycle gas is separated, and reduces recycle gas to erosive wear, especially two stage superheater pipeline that generator tube produces, reaches the purpose of protection generator tube.
The disposable dust remover shell is welded by the taper ash bucket of end face, side, both sides, two ends end face, bottom, and constitutes airtight cavity by end face, side, both sides, two ends end face, ash bucket encirclement, and enclosure is built heat insulation wall by laying bricks or stones.Disposable dust remover inlet, outlet are arranged at the two ends end face respectively and respectively by high temperature expansion joint and the dried pipe connection that puts out stove, boiler.The dedusting barricade is built by laying bricks or stones with wearing-proof refractory material and is formed, be arranged at inlet the place ahead and vertical with air flow line, top is connected with the end face insulated wall, the side is connected with the both sides insulated wall, the bottom is connected with the insulated wall on ash bucket surface, by the dedusting barricade cavity is divided into two portions, and dedusting barricade bottom is provided with connection cavity two portions, holds the arch opening that gas passes through.
After the recycle gas that contains coke powder enters fly-ash separator, stopped that by the dedusting barricade gas alters course after the opening of dedusting barricade bottom enters opposite side, and finally enters outlet; And coke powder falls after touching the dedusting baffle plate, and is collected by ash bucket, thereby realizes dust separating purpose.The impact of dedusting barricade own wt and high speed recycle gas is being connected by arch opening both sides and ash bucket insulated wall all, carry with the connection of corresponding insulated wall two sides, therefore to the specification of quality of building materials with to build requirement by laying bricks or stones all very high, especially along with the maximization of industrial coke oven and supporting dry coke quenching, the dedusting barricade is also increased thereupon and is widened, thereby to the specification of quality of building materials with to build requirement by laying bricks or stones strict more, when a certain link has problem slightly, being easy to cause barricade to stride in process of production collapses, cause dried put out stove and boiler systems production interruption, have to total system is carried out decrease temperature and pressure, satisfy the requirements afterwards barricade to be striden to collapse and remove and organize manpower, material resources are built by laying bricks or stones again, and enterprise is caused heavy losses.
The utility model content
Technical problem to be solved in the utility model provides a kind of disposable dust remover that can avoid the dedusting barricade to collapse.
The technical scheme that its technical problem that solves the utility model adopts is: disposable dust remover, comprise shell, dedusting barricade, and described shell comprises end face, side, both sides, two ends end face, described dedusting barricade is a steel construction.
Described dedusting barricade comprises framework and is covered in one group of steel plate on framework surface, passes through bolting between described steel plate and the framework.
Described outer casing top surface is provided with the lifting groove of dedusting barricade, the sealing cover of lifting groove; Described lifting groove both sides are respectively arranged with and hang the fixedly fixed beam of dedusting barricade, and described dedusting barricade top is connected by latch or bolt with fixed beam.
Described shell both sides are respectively arranged with guide path on the side.
The beneficial effects of the utility model are: steel construction has high temperature resistant, corrosion-resistant, wear-resistant, anti-oxidant, anti-high stream, shock resistance, welding characteristic, under hot environment, can use continuously, have good thermal fatigue resistance and resistance to elevated temperatures, use repeatedly and be difficult for producing hot row phenomenon, can not exist and stride the problem of collapsing, enterprise's continuous production is created favourable condition more.No longer to brick with built requirement by laying bricks or stones, the step that simplifies the operation reduces labour intensity.
Description of drawings
Fig. 1 is a structure diagram of the present utility model;
Fig. 2 is the front view of the utility model dedusting barricade.
Embodiment
Below in conjunction with drawings and Examples the utility model is further specified.
As shown in Figure 1 and Figure 2, disposable dust remover of the present utility model comprises shell 1, dedusting barricade 2, and described shell 1 comprises end face 3, side, both sides, two ends end face, and described dedusting barricade 2 is steel construction.
That steel construction has is high temperature resistant, corrosion-resistant, wear-resistant, anti-oxidant, anti-high stream, shock resistance, welding characteristic, under hot environment, can use continuously, have good thermal fatigue resistance and resistance to elevated temperatures, use repeatedly and be difficult for producing hot row phenomenon, can not exist and stride the problem of collapsing, enterprise's continuous production is created favourable condition more.No longer to brick with built requirement by laying bricks or stones, the step that simplifies the operation reduces labour intensity.
Steel construction can directly be fixedlyed connected with shell 1 by welding, when the 1 local appearance of dedusting barricade is damaged, repairs by the mode of cutting, welding.But the aforesaid way troublesome poeration, for convenience to the 2 partial maintenances of dedusting barricade, further, described dedusting barricade 2 comprises framework 21 and is covered in one group of steel plate 22 on framework 21 surfaces, passes through bolting between described steel plate 22 and the framework 21.When certain steel plate 22 needs to change, only need this steel plate 22 of dismounting and change to get final product.
Further, for convenience of the integral replacing of dedusting barricade 2, described shell 1 end face 3 is provided with the lifting groove 4 of dedusting barricade 2, the sealing cover 5 of lifting groove 4, and described dedusting barricade 2 is fixing by detachably fixedlying connected with shell 1.In addition, also shell 1 end face 3 all can be set to detachable structure with side, both sides, two ends end face, but operation is loaded down with trivial details when changing.
Dedusting barricade 2 can be fixed by side, both sides or side, both sides and bottom ash bucket etc.But in order further to simplify the operation, described lifting groove 4 both sides are respectively arranged with and hang the fixedly fixed beam 6 of dedusting barricade 2, and described dedusting barricade 2 tops and fixed beam 6 are connected by latch.Except that latch, also can fix by bolt.
Because dedusting barricade 2 adopts to hang and fixes, in order to guarantee the stability of its position under gas shock, guarantee the resistance to air loss of dedusting barricade 2 both sides, described shell 1 both sides are respectively arranged with guide path 7 on the side.Guide path 7 the installation that can also make things convenient for simultaneously dedusting barricade 2 is set.

Claims (5)

1. disposable dust remover comprises shell (1), dedusting barricade (2), and described shell (1) comprises end face (3), side, both sides, two ends end face, it is characterized in that; Described dedusting barricade (2) is a steel construction.
2. disposable dust remover as claimed in claim 1 is characterized in that: described dedusting barricade (2) comprises framework (21) and is covered in one group of steel plate (22) on framework (21) surface, passes through bolting between described steel plate (22) and the framework (21).
3. disposable dust remover as claimed in claim 1 or 2, it is characterized in that: described shell (1) end face (3) is provided with the lifting groove of dedusting barricade (2), the sealing cover (5) of lifting groove, and described dedusting barricade (2) is fixing by detachably fixedlying connected with shell (1).
4. disposable dust remover as claimed in claim 3 is characterized in that: described lifting groove both sides are respectively arranged with and hang the fixedly fixed beam (6) of dedusting barricade (2), and described dedusting barricade (2) top is connected by latch or bolt with fixed beam (6).
5. disposable dust remover as claimed in claim 3 is characterized in that: described shell (1) is respectively arranged with guide path (4) on the side, both sides.
CN2010206652453U 2010-12-17 2010-12-17 Primary dust remover Expired - Fee Related CN201971784U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010206652453U CN201971784U (en) 2010-12-17 2010-12-17 Primary dust remover

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010206652453U CN201971784U (en) 2010-12-17 2010-12-17 Primary dust remover

Publications (1)

Publication Number Publication Date
CN201971784U true CN201971784U (en) 2011-09-14

Family

ID=44576891

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010206652453U Expired - Fee Related CN201971784U (en) 2010-12-17 2010-12-17 Primary dust remover

Country Status (1)

Country Link
CN (1) CN201971784U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103361086A (en) * 2012-04-10 2013-10-23 北京信力筑正新能源技术有限公司 Primary dust remover for dry quenching
CN106433698A (en) * 2016-09-26 2017-02-22 北京华泰焦化工程技术有限公司 Dry quenching coke stove primary dedusting system and hanging screen device thereof
CN115895692A (en) * 2022-12-15 2023-04-04 中冶焦耐(大连)工程技术有限公司 A structure of CDQ primary dust collector

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103361086A (en) * 2012-04-10 2013-10-23 北京信力筑正新能源技术有限公司 Primary dust remover for dry quenching
CN106433698A (en) * 2016-09-26 2017-02-22 北京华泰焦化工程技术有限公司 Dry quenching coke stove primary dedusting system and hanging screen device thereof
CN115895692A (en) * 2022-12-15 2023-04-04 中冶焦耐(大连)工程技术有限公司 A structure of CDQ primary dust collector

Similar Documents

Publication Publication Date Title
CN202254893U (en) Flue gas radiation-type waste heat boiler recovery system for electric arc furnace
CN103398375B (en) With the cyclone separator of circulating fluidized bed boiler of wear-resisting target area and guider
CN105062566B (en) A kind of plasma gasification reactor for domestic waste
CN201971784U (en) Primary dust remover
KR101224267B1 (en) Boiler combine incinerator
CN102322746A (en) Electric arc furnace smoke radiation type waste heat boiler recovery system
CN201636834U (en) Calcium carbide afterheat boiler
CN222363869U (en) Flue-type natural circulation waste heat boiler
CN214830151U (en) Novel dust removal cooling device
CN203464307U (en) Internal multi-tube dust removal device of boiler
CN202692089U (en) Light type membrane-wall water-cooling air hopper
CN202501159U (en) Compensator special for waste heat power generation
CN202322723U (en) 125t/h dry quenching barricade-free one-time dust removing device
CN201636832U (en) Steelmaking electric furnace waste heat boiler
CN109341365A (en) A coal coking flue gas waste heat recovery system
CN210826050U (en) Dry quenching dust removal air duct structure
CN202555419U (en) Novel interference type separator
CN202349980U (en) Novel afterheat boiler for pyrite-based acid preparation
CN204873851U (en) Air -breather in unsettled graphitizing furnace of stove bottom
CN207699525U (en) A kind of preparation facilities of carbon-rich solids cleaning products
CN204268465U (en) A kind of gas fired-boiler
CN204787858U (en) Hot stove high temperature flue gas in ore deposit contact tube that stretches out and draws back
CN202675333U (en) Energy-saving biomass dust removal and heat exchange device
CN222670012U (en) Dangerous waste incineration waste heat boiler with internal hanging screen
CN203190799U (en) Energy-saving dual melting furnace with waste heat recycling function

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110914