CN201857606U CN 201020598116 CN201020598116U CN201857606U CN 201857606 U CN201857606 U CN 201857606U CN 201020598116 CN201020598116 CN 201020598116 CN 201020598116 U CN201020598116 U CN 201020598116U CN 201857606 U CN201857606 U CN 201857606U
Authority
CN
China
Prior art keywords
shaped steel
pile
cement mixing
novel combination
mixing method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201020598116
Other languages
Chinese (zh)
Inventor
宋伟民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Qiangjin Foundation Engineering Co Ltd
Original Assignee
Shanghai Qiangjin Foundation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Qiangjin Foundation Engineering Co Ltd filed Critical Shanghai Qiangjin Foundation Engineering Co Ltd
Priority to CN 201020598116 priority Critical patent/CN201857606U/en
Application granted granted Critical
Publication of CN201857606U publication Critical patent/CN201857606U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a novel combined uplift pile, which comprises a soil cement mixing pile body, wherein a profiled bar is inserted into the center of the pile body. During the construction, the soil cement mixing pile is firstly constructed, whole-process mixing or partial mixing is carried out according to the soil texture distribution and the soil compression situation, then the profiled bar with the calculated cross section data is inserted by a pile press machine, and the soil cement mixing pile and the inserted profiled bar collectively form a large-diameter combined uplift pile. The novel combined uplift pile has a large diameter which is formed through the soil cement with low price, and then the profiled bar is added as a supporting skeleton, so the carrying capacity of the pile body is greatly improved, the soil compression and the noise are simultaneously reduced, the influence of the construction on the environment is reduced, and the construction is rapid, safe and reliable. The novel combined uplift pile is safe and reliable, and the manufacturing cost is reduced.

Description

A kind of novel combination uplift pile
Technical field
The utility model relates to a kind of NEW TYPE OF COMPOSITE uplift pile, particularly a kind of compound uplift pile at the middle implanted metal stake of cement mixing method core.
Background technology
Stake commonly used at present is divided into preformed pile and castinplace pile two big classes.Bored pile generally adopts the mud off pore-forming, and the placing of concrete technology exists speed of application slow under water, defectives such as cost height.Speed of application is fast, low cost and other advantages and tube-sinking cast-in-situ pile has, but is easy to produce quality problems such as constriction, broken pile, local folder soil, concrete disintegration and strength deficiency.
Precast reinforced concrete piles is an a kind of maximum type of domestic use, adopts shapes such as the cross section is square, circle.The pile sinking mode of preformed pile has hammering method, vibratory drilling method and static pressure method, has advantages such as reliable in quality, speed of application is fast, cost is low.But it belongs to the soil compaction stake, in pile driving process the soil body is produced extruding, influences neighboring buildings, road, underground utilities etc., cause dispute easily, for fear of the influence of piling to surrounding environment, needing increases extra protection expense, so its use is subjected to many condition restriction.
The utility model content
Technical problem to be solved in the utility model is, overcomes problems of the prior art, and a kind of novel combination uplift pile is provided.This stake is a cement mixing method, and the centre is provided with shaped steel class steel.
In order to address the above problem the technical solution of the utility model is such:
A kind of novel combination uplift pile comprises a cement mixing method pile body, and described pile body center is inserted with shaped steel.
Described shaped steel is one, and a shaped steel vertically inserts cement mixing method pile body center.
Described shaped steel is two, and two shaped steel is at interval both sides, vertical insertion cement mixing method pile body center side by side.
Described shaped steel is three and above quantity, and shaped steel is evenly distributed in the cement mixing method pile body.
Interconnected stirrup between the shaped steel.
Described shaped steel is the wherein a kind of or mutual combination of H shaped steel, channel-section steel, angle steel, steel pipe, square steel.
Described shaped steel outer wall is provided with the joint that increases frictional resistance, and the longitudinal cross-section of described joint is rectangle or triangle.
The diameter of described cement mixing method is 250mm-2000mm, and stake is long to be 3-60 rice.
Described shaped steel is concordant with the cement mixing method end face.
Described shaped steel exceeds at least 0.01 meter of cement mixing method end face.
Described shaped steel is lower than at least 0.01 meter of cement mixing method end face.
During construction, carry out cement-soil stirring pile construction earlier, look soil property and distribute and the soil compaction situation, the omnidistance stirring or the part stirring, then with the shaped steel that inserts through the cross-section data that calculates, the common compound uplift pile that forms of the shaped steel of cement mixing method and insertion.
Beneficial effect:
Novel combination uplift pile described in the utility model forms major diameter by cheap cement-soil, and adding shaped steel then is support frame, strengthen the uplift resistance of pile body greatly, reduced soil compaction and noise simultaneously, the Construction on Environment influence is reduced, and construction rapidly, the safety reliability height., significantly reduce construction costs.
Description of drawings
Describe the utility model in detail below in conjunction with the drawings and specific embodiments;
Fig. 1 is the cross-sectional structure schematic diagram of novel combination uplift pile described in the utility model;
Fig. 2 is the longitudinal cross-section structural representation of novel combination uplift pile embodiment 1 described in the utility model;
The structural representation of Fig. 3 for saving on the shaped steel of novel combination uplift pile described in the utility model;
Fig. 4 is the longitudinal cross-section structural representation of novel combination uplift pile embodiment 2 described in the utility model;
Fig. 5 is the longitudinal cross-section structural representation of novel combination uplift pile embodiment 3 described in the utility model;
The specific embodiment
For technological means, creation characteristic that the utility model is realized, reach purpose and effect is easy to understand, below in conjunction with concrete diagram, further set forth the utility model.
Embodiment 1
Referring to Fig. 1
A kind of novel combination uplift pile comprises a cement mixing method pile body 1, and described pile body center is inserted with shaped steel 2.Inserting shaped steel 2 can carry out the structure reinforcement to pile body, increases the extraction-resistant behavior of pile body.Shaped steel is the wherein a kind of or mutual combination of H shaped steel, channel-section steel, angle steel, steel pipe, square steel.
Inserting shaped steel 2 is one, two or several.When being one of shaped steel, a shaped steel vertically inserts cement mixing method pile body center.When being two for shaped steel, two shaped steel is at interval both sides, vertical insertion cement mixing method pile body center side by side.When being many for shaped steel, shaped steel is evenly distributed in the cement mixing method pile body, and forms polygonized structure.Under the situation of needs, also interconnected stirrup 3 between the shaped steel, with the bearing capacity of further reinforcement pile body.Certainly between each shaped steel stirrup can also be set.
Referring to Fig. 2
The diameter of described cement mixing method 1 is 250mm-2000mm, and stake is long to be 3-60 rice.
Described shaped steel 2 is concordant with the cement mixing method end face.Make the even pressure-bearing of whole pile body like this.
Referring to Fig. 3
Shaped steel 2 outer walls are provided with the joint 21 that increases frictional resistance in addition, and the longitudinal cross-section of described joint 21 is the shape of rectangle or triangle or other increase friction.
During construction, carry out cement-soil stirring pile construction earlier, look soil property and distribute and the soil compaction situation, the omnidistance stirring or the part stirring, with the shaped steel that inserts through the cross-section data that calculates, the shaped steel of cement mixing method and insertion forms large diameter compound uplift pile jointly then.
Embodiment 2
Referring to Fig. 4
Described shaped steel 2 exceeds cement mixing method 1 end face.Exceed at least 0.01 meter of end face, the part that exceeds is used to connect the building on the pile body.All the other are with embodiment 1
Embodiment 3
Referring to Fig. 5
Described shaped steel 2 is lower than cement mixing method 1 end face.Because in constructions such as basement, foundation ditch, after cement mixing method 1 construction finishes, also to excavate, excavate for convenience, shaped steel 2 is squeezed into below the excavation face, so just made shaped steel 2 be lower than cement mixing method 1 end face certain distance, stay the soil layer space to excavation.Shaped steel 2 is lower than at least 0.01 meter of cement mixing method end face.Be generally the basement floor rise from.
All the other are with embodiment 1
More than show and described basic principle of the present utility model, principal character and advantage of the present utility model.The technician of the industry should understand; the utility model is not restricted to the described embodiments; that describes in the foregoing description and the manual just illustrates principle of the present utility model; the utility model also has various changes and modifications under the prerequisite that does not break away from the utility model spirit and scope, and these changes and improvements all fall in claimed the utility model scope.The claimed scope of the utility model is defined by appending claims and equivalent thereof.

Claims (11)

1. a novel combination uplift pile comprises a cement mixing method pile body, it is characterized in that, described pile body center is inserted with shaped steel.
2. a kind of novel combination uplift pile according to claim 1 is characterized in that described shaped steel is one, and a shaped steel vertically inserts cement mixing method pile body center.
3. a kind of novel combination uplift pile according to claim 1 is characterized in that described shaped steel is two, and two shaped steel is at interval both sides, vertical insertion cement mixing method pile body center side by side.
4. a kind of novel combination uplift pile according to claim 1 is characterized in that described shaped steel is three above quantity of machine, and shaped steel is evenly distributed in the cement mixing method pile body.
5. according to claim 3 or 4 described a kind of novel combination uplift piles, it is characterized in that, interconnected stirrup between the shaped steel.
6. a kind of novel combination uplift pile according to claim 1 is characterized in that, described shaped steel is the wherein a kind of or mutual combination of H shaped steel, channel-section steel, angle steel, steel pipe, square steel.
7. a kind of novel combination uplift pile according to claim 1 is characterized in that, described shaped steel outer wall is provided with the joint that increases frictional resistance, and the longitudinal cross-section of described joint is rectangle or triangle.
8. a kind of novel combination uplift pile according to claim 1 is characterized in that the diameter of described cement mixing method is 250mm-2000mm, and stake is long to be 3-60 rice.
9. a kind of novel combination uplift pile according to claim 1 is characterized in that described shaped steel is concordant with the cement mixing method end face.
10. a kind of novel combination uplift pile according to claim 1 is characterized in that described shaped steel exceeds at least 0.1 meter of cement mixing method end face.
11. a kind of novel combination uplift pile according to claim 1 is characterized in that described shaped steel is lower than at least 0.1 meter of cement mixing method end face.
CN 201020598116 2010-11-09 2010-11-09 Novel combined uplift pile Expired - Lifetime CN201857606U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201020598116 CN201857606U (en) 2010-11-09 2010-11-09 Novel combined uplift pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201020598116 CN201857606U (en) 2010-11-09 2010-11-09 Novel combined uplift pile

Publications (1)

Publication Number Publication Date
CN201857606U true CN201857606U (en) 2011-06-08

Family

ID=44103416

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201020598116 Expired - Lifetime CN201857606U (en) 2010-11-09 2010-11-09 Novel combined uplift pile

Country Status (1)

Country Link
CN (1) CN201857606U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103603347A (en) * 2013-10-31 2014-02-26 周兆弟 Anti-soil-accumulation cement mixing precast pile foundation and forming method
CN104631440A (en) * 2015-01-29 2015-05-20 南昌市建筑工程集团有限公司 Stiffening core lengthening foundation pit support structure for existing large-diameter bored concrete pile and construction method
CN104863132A (en) * 2014-04-29 2015-08-26 周兆弟 Bougainvillea spectabilis willd-shaped cement-soil mixing pile and shaping method thereof
CN105002906A (en) * 2015-07-28 2015-10-28 济南轨道交通集团有限公司 Binding type anchor cable composite pile structure serving as main body structure stand column and construction method thereof
CN106759266A (en) * 2017-01-09 2017-05-31 王立明 Combination reinforcement diaphragm wall and its construction method
CN107246020A (en) * 2017-08-09 2017-10-13 中交公局第五工程有限公司 A kind of means of defence on landslide
CN111827307A (en) * 2020-08-13 2020-10-27 上海智平基础工程有限公司 A combined construction method pile supporting structure and its construction method
CN111962499A (en) * 2020-07-09 2020-11-20 广州一建建设集团有限公司 Construction method for adding section steel column in manual hole digging pile

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103603347A (en) * 2013-10-31 2014-02-26 周兆弟 Anti-soil-accumulation cement mixing precast pile foundation and forming method
CN104863132A (en) * 2014-04-29 2015-08-26 周兆弟 Bougainvillea spectabilis willd-shaped cement-soil mixing pile and shaping method thereof
CN104631440A (en) * 2015-01-29 2015-05-20 南昌市建筑工程集团有限公司 Stiffening core lengthening foundation pit support structure for existing large-diameter bored concrete pile and construction method
CN105002906A (en) * 2015-07-28 2015-10-28 济南轨道交通集团有限公司 Binding type anchor cable composite pile structure serving as main body structure stand column and construction method thereof
CN106759266A (en) * 2017-01-09 2017-05-31 王立明 Combination reinforcement diaphragm wall and its construction method
CN106759266B (en) * 2017-01-09 2019-11-05 王立明 Combine reinforcement diaphragm wall and its construction method
CN107246020A (en) * 2017-08-09 2017-10-13 中交公局第五工程有限公司 A kind of means of defence on landslide
CN111962499A (en) * 2020-07-09 2020-11-20 广州一建建设集团有限公司 Construction method for adding section steel column in manual hole digging pile
CN111827307A (en) * 2020-08-13 2020-10-27 上海智平基础工程有限公司 A combined construction method pile supporting structure and its construction method

Similar Documents

Publication Publication Date Title
CN203684230U (en) Prefabricated double-row pile structure
CN102561377A (en) Seismic-resistant-columned rock bolt foundation with enlarged toe and construction method of seismic-resistant-columned rock bolt foundation with enlarged toe
CN206941608U (en) A kind of diaphram wall foundation pit supporting construction
CN202595731U (en) High-bearing-capacity multistage enlarged bore pile convenient to construct
CN113026760A (en) Combined type supporting pile for double-element foundation pit of soil and rock and construction method thereof
CN201245839Y (en) Composite bearing pile of concrete stirring soil implanted prefabricated reinforced concrete core rod
CN206495217U (en) A kind of foundation ditch soil-baffling structure
CN101691760B (en) Composite foundation combining anchor rods with excavation and construction method thereof
CN108677934A (en) The construction method of uplift pile and uplift pile
CN101545255B (en) Method for making PHC pipe piles with reaming and grouting in soft soil areas
CN201874008U (en) Discontinuous concrete grouting pile and wall structure
CN106049413B (en) A kind of composite power drain consolidation system and construction method applied to deep layer foundation in saturated soft soil
CN204401602U (en) A kind of rigid-flexible composite support water stop RCP stake
CN202247910U (en) Soil retaining structure with different inclination angles of anti-skid cement soil pile
CN202148523U (en) Jet grouting soil-cement-pile strengthened pile
CN202124857U (en) Splitting pile
CN108643215B (en) Construction method of anchor pier type foundation after rotary spraying and pressing into variable cross section
CN201857608U (en) Synthetic pile
CN110258526A (en) The method of prefabricated diaphram wall and construct outer wall of basement and floor
CN214614090U (en) Composite pre-stressed precast pile foundation pit supporting structure
CN211898436U (en) Diaphragm wall structure with high vertical bearing capacity
CN212642298U (en) A wall structure to improve the seismic capacity of the water inlet tower group
CN109811786B (en) Offshore wind power composite foundation structure with inner steel pipe pile and outer steel pipe pile combined
CN113737972A (en) External ring beam construction column expansion joint structure and construction method thereof
CN209082469U (en) A kind of construction reinforcement structure of foundation engineering

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20110608