CN201826315U - Grouting sleeve valve pipe - Google Patents

Grouting sleeve valve pipe Download PDF

Info

Publication number
CN201826315U
CN201826315U CN201020562705XU CN201020562705U CN201826315U CN 201826315 U CN201826315 U CN 201826315U CN 201020562705X U CN201020562705X U CN 201020562705XU CN 201020562705 U CN201020562705 U CN 201020562705U CN 201826315 U CN201826315 U CN 201826315U
Authority
CN
China
Prior art keywords
pipe
slip casting
grouting
sleeve valve
grouting pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201020562705XU
Other languages
Chinese (zh)
Inventor
许兆交
周英有
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 5 Engineering Group Co Ltd
Third Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
China Railway No 5 Engineering Group Co Ltd
Third Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 5 Engineering Group Co Ltd, Third Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical China Railway No 5 Engineering Group Co Ltd
Priority to CN201020562705XU priority Critical patent/CN201826315U/en
Application granted granted Critical
Publication of CN201826315U publication Critical patent/CN201826315U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The utility model discloses a grouting sleeve valve pipe comprising a grouting pipe A and a grouting pipe B; a grouting pipe A (4) is arranged inside the grouting pipe B (2), a grouting perforated pipe section (7) with two stop-grouting plugs (6) and a joint (8) are arranged on the grouting pipe A (4), grout-discharging holes (5) are arranged on the grouting pipe B (2), and a cone-shape plug (1) is arranged at the end of the grouting pipe B. A rubber sleeve valve jacket (3) is arranged at the periphery of the grout-discharging hole (5) on the grouting pipe B. 6-12 grout-discharging holes (5) with phi6-phi8mm of diameter are uniformly distributed at the circumference of the grouting pipe B (2) along the length direction with 0.6-1m of spacing, and 3-4 stop-grouting rubber cups are arranged at the contact section of the joint (8) of the grouting pipe A (4) and the stop-grouting plugs (6). In the utility model, the structure is simple, the manufacturing cost is low, the construction is convenient, the reinforcing effect is good and the economic benefit is high.

Description

Slip casting sleeve valve pipe
Technical field
The utility model relates to a kind of slip casting sleeve valve pipe that is used for the correcting and then reinforcing of ground stabilization processing and treatment of soft foundation and building.
Background technology
At present, aspect the reinforcing of construction work, as the correcting and then reinforcing of ground stabilization processing and treatment of soft foundation and building, the bracing means complex structure of its use, the construction technology complexity, inconvenient operation, and cost and cost height use very uneconomical.
Summary of the invention
The technical problems to be solved in the utility model is, a kind of slip casting sleeve valve pipe is provided, and this sleeve valve tubular structure is simple, and easy construction, occupied ground is few, consolidation effect good, to overcome the complex structure that prior art exists, deficiencies such as inconvenient operation.
The technical scheme that the utility model adopted is: it comprises slip casting A pipe and slip casting B pipe, slip casting A pipe is inner at slip casting B pipe, slip casting A pipe is provided with grouting tube section and the joint with two stop grouting plugs, and slip casting B pipe is provided with slurry discharging hole, and its termination is provided with the taper plug.
Be with rubber sleeve valve pocket outside the slurry discharging hole on slip casting B pipe.
Slurry discharging hole is spaced apart 0.6~1m on slip casting B length of tube, evenly lay on the circumference, and quantity is 6~12, and diameter is φ 6~φ 8mm.
Be provided with 3~4 in the contact-segment of the plunger of slip casting A pipe and stop grouting plug and only starch rubber cup.
Construction is divided into boring, inserts slip casting B pipe, inserts grouting valve A pipe, sealing of hole, 5 steps of slip casting, can depthkeeping in the construction, quantitatively, carry out branch preface, segmentation, gap and repetition slip casting, combine fracture grouting method, close slip casting method of pressure (squeezing) and the advantage of infiltrating slip casting method.Do not offer the slurry hole of overflowing on the slip casting A pipe, have the slurry discharging hole of φ 6~φ 8mm on the B kind Grouting Pipe.Manage outside, porose position at slip casting B and overlapping the rubber sleeve that anti-burst pressure is 4.5MPa tightly, rubber sleeve is covered with slurry discharging hole, like this, during slip casting, slurries can enter the stratum by slurry discharging hole, and water in the stratum and particle are difficult to enter in the Grouting Pipe, thereby reach the one way valve effect of Grouting Pipe.The floral tube section of slip casting B pipe can adopt steel pipe or pvc pipe, lays the slurry discharging hole of 6~12 φ 6~8mm around generally long 0.6~1m equably.Only starch rubber cup for 3~4 about having in the floral tube section bottom scope of slip casting A pipe,, play only slurry effect to form the plasma resistance plug.Slip casting A pipe adopts steel pipe processing, and the long 2~4m of every joint takes screwed connection between tube coupling.
The utlity model has up and down two stop grouting plugs, slurries can be limited in arbitrary segment limit in slip casting zone and carry out slip casting, reach the purpose of segmenting slip casting.
Stop grouting plug can move freely in smooth sleeve valve pipe, as required a certain section repeatedly slip-casting in the slip casting zone.
Needn't establish thicker concrete before the slip casting and end the magmatic rock wall, emit the possibility of slurry, string slurry little when taking bigger grouting pressure.
Can in a Grouting Pipe, adopt different slip casting according to stratum characteristic, select for use different grouting parameters to carry out mortar depositing construction.
Boring, slip casting can take the parallel operations mode, and boring and injected hole spacing distance be generally suitable>6 m, increase work efficiency.
The utility model is simple in structure, and cost of manufacture is low, easy construction, and consolidation effect is good, the economic benefit height.
Description of drawings
Fig. 1 is slip casting sleeve valve tubular structure schematic diagram; 1---the taper plug, 2---slip casting B pipe, 3---rubber sleeve valve, 4---slip casting A pipe, 5---slurry discharging hole, 6---stop grouting plug, 7---band double-piston grouting tube, 8---joint, 9---connect grouting pump.
Fig. 2 is slip casting sleeve valve pipe grouting and reinforcing schematic diagram; 2---slip casting B pipe, 4---slip casting A pipe, 6---stop grouting plug, 9-connect grouting pump, 10---the sealing of hole filler, 11---positive stabilization zone, 12---stabilization zone.
The specific embodiment
Embodiment of the present utility model: it comprises slip casting A pipe and slip casting B pipe, slip casting A pipe 4 is in the inside of slip casting B pipe 2, left side section among slip casting A pipe 4(such as Fig. 1) is provided with grouting tube section 7 and joint (8) with two stop grouting plugs 6, slip casting B pipe 2 is provided with slurry discharging hole 5, and its termination is provided with taper plug 1.
Be with rubber sleeve valve pocket 3 outside the slurry discharging hole 5 on slip casting B pipe 2.
Slurry discharging hole 5 is managed the 0.6~1m that is spaced apart on 2 length at slip casting B, evenly lays on the slip casting B pipe circumference, and quantity is 6~12, and diameter is φ 6~φ 8mm.
Be provided with 3~4 in the contact-segment of the joint 8 of slip casting A pipe 4 and stop grouting plug 6 and only starch rubber cup.
Stop grouting plug 6 is the step stop grouting plug.
During construction, boring can be adopted geology brill, hidden hole drilling or water jetting pore-forming.Sleeve pipe retaining wall water jetting drilling and forming hole, drilling depth should reach grouting reinforcement section height.According to the slip casting requirement, in the B of slip casting position mounting strap injected hole pipe floral tube section, non-slip casting position is installed not short with the real pipe of B pipe of injected hole.Grouting Pipe B is inserted in the inlet well, guarantee under the Grouting Pipe that at the bottom of the hole, the top is above ground level.Add stifle down in the slip casting A that connects pipe bottom, slowly, insert in the slip casting B pipe by joint.Slip casting A pipe injects the space that the sealing of hole slurries are filled expires between the slip casting B pipe and the soil body after being inserted into slip casting B pipe bottom, and the sealing of hole slurries adopt low intensive slurries, generally adopt the match ratio of cement: swell soil=1:2, in mass ratio (being weight ratio).After the sealing of hole slurries injected, topped up with water in slip casting B pipe was utilized action of gravity, and slip casting B pipe can not floated, and afterwards slip casting A pipe was proposed lentamente, at last stifle on slip casting B pipe upper cap.After slip casting A pipe is extracted, sentence employing accelerated cement mortar shutoff down at ground 1m.The sealing of hole slurries inject and could to inject the reinforcing slurries after 48 hours, and the segmentation injection mode is taked in slip casting, and every section slip casting length is called the slip casting step pitch, and the slip casting step pitch is identical with slurry discharging hole step pitch on the slip casting B pipe.Grouting pressure, grouting amount are determined according to different geology and groundwater table, generally calculate grouting amount control slip casting effect with the void ratio of geology in the construction.The slip casting step pitch is 0.6~1m, can reduce the influence of stratum inequality to slip casting effect effectively like this.In the slip casting process, after every section slip casting is finished, move up or down core barrel (A pipe) length of a step pitch.The employing lifting means moves, or manually adopts 2 pipe wrench symmetries to clamp core barrel, and evenly firmly, move core barrel (A pipe) simultaneously both sides.Whenever finish 2~4m slip casting length, the joint slip casting core barrel of dismantling.After slip casting finishes, go out the slurries of B pipe, on the B pipe, cover stifle, so that annotate construction again with clear water.

Claims (4)

1. slip casting sleeve valve pipe, it is characterized in that: it comprises slip casting A pipe and slip casting B pipe, slip casting A pipe (4) is in the inside of slip casting B pipe (2), slip casting A pipe (4) is provided with grouting tube section (7) and the joint (8) with two stop grouting plugs (6), slip casting B pipe (2) is provided with slurry discharging hole (5), and its termination is provided with taper plug (1).
2. slip casting sleeve valve pipe according to claim 1 is characterized in that: be with rubber sleeve valve pocket (3) outside the slurry discharging hole (5) on slip casting B pipe (2).
3. slip casting according to claim 1 sleeve valve pipe is characterized in that: slurry discharging hole (5) is spaced apart 0.6~1m on slip casting B pipe (2) length, evenly lay on the circumference, and quantity is 6~12, and diameter is φ 6~φ 8mm.
4. slip casting according to claim 1 sleeve valve pipe is characterized in that: be provided with 3~4 in the contact-segment of the joint (8) of slip casting A pipe (4) and stop grouting plug (6) and only starch rubber cup.
CN201020562705XU 2010-10-15 2010-10-15 Grouting sleeve valve pipe Expired - Fee Related CN201826315U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201020562705XU CN201826315U (en) 2010-10-15 2010-10-15 Grouting sleeve valve pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201020562705XU CN201826315U (en) 2010-10-15 2010-10-15 Grouting sleeve valve pipe

Publications (1)

Publication Number Publication Date
CN201826315U true CN201826315U (en) 2011-05-11

Family

ID=43964862

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201020562705XU Expired - Fee Related CN201826315U (en) 2010-10-15 2010-10-15 Grouting sleeve valve pipe

Country Status (1)

Country Link
CN (1) CN201826315U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561365A (en) * 2011-12-01 2012-07-11 成都理工大学 Sliding sand slope reinforcing device
CN103573274A (en) * 2013-11-11 2014-02-12 浙江大学 Steel sleeve grouting reinforcement device for settlement control over shield tunnel of soft foundation
CN104805842A (en) * 2015-04-20 2015-07-29 中铁建设集团有限公司 Steel flower pipe segmented grouting system and construction method thereof
CN104975594A (en) * 2015-06-17 2015-10-14 中国矿业大学 Grouting pipe for miscellaneous fill stratum and construction method
CN107724378A (en) * 2016-08-11 2018-02-23 中国二十冶集团有限公司 The preparation method of sleeve valve barrel grouting sheath body
CN109339053A (en) * 2018-11-12 2019-02-15 檀煜 A kind of bridge Grouting Pipe
CN112459072A (en) * 2020-12-15 2021-03-09 安徽省城建基础工程有限公司 Layered grouting device and application thereof

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561365A (en) * 2011-12-01 2012-07-11 成都理工大学 Sliding sand slope reinforcing device
CN103573274A (en) * 2013-11-11 2014-02-12 浙江大学 Steel sleeve grouting reinforcement device for settlement control over shield tunnel of soft foundation
CN103573274B (en) * 2013-11-11 2016-01-20 浙江大学 Soft foundation shield tunnel subsidence controls steel sleeve grouting and reinforcing device
CN104805842A (en) * 2015-04-20 2015-07-29 中铁建设集团有限公司 Steel flower pipe segmented grouting system and construction method thereof
CN104805842B (en) * 2015-04-20 2017-05-17 中铁建设集团有限公司 Steel flower pipe segmented grouting system and construction method thereof
CN104975594A (en) * 2015-06-17 2015-10-14 中国矿业大学 Grouting pipe for miscellaneous fill stratum and construction method
CN107724378A (en) * 2016-08-11 2018-02-23 中国二十冶集团有限公司 The preparation method of sleeve valve barrel grouting sheath body
CN109339053A (en) * 2018-11-12 2019-02-15 檀煜 A kind of bridge Grouting Pipe
CN112459072A (en) * 2020-12-15 2021-03-09 安徽省城建基础工程有限公司 Layered grouting device and application thereof

Similar Documents

Publication Publication Date Title
CN201908308U (en) Grouting sleeve valve pipe
CN102444118A (en) Sleeve valve pipe grouting reinforcement construction method
CN201826315U (en) Grouting sleeve valve pipe
CN204112308U (en) A kind of simple and easy sleeve valve grouting device based on bowlder stone, Thief zone coefficient stratum
CN103410182B (en) Unilateral pile foundation unloading horizontal top-level pull deviation rectifying and broken pile reinforcement construction method
CN101644049B (en) Slurry injection technique of double-valve sleeve valve tube of cloth bag
CN101230573B (en) Construction equipment for quadruple-pipe formation decompression double-fluid horizontal rotary spraying
CN101215833A (en) Air Injection Vacuum Dewatering Method
CN100570128C (en) Construction method of all-round high-pressure jet grouting with orifice stopper
CN104963351A (en) Reinforced structure for reinforcing treatment of artificial filled soil slopes and construction method thereof
CN105178285B (en) A kind of method for expanding ground grouting and reinforcing and antiseepage extent of congestion
CN104141305A (en) Multi-layer spiral blade self-drilling-type soil anchor rod and constructing method thereof
CN101644048B (en) Slurry injection technique of sleeve valve tube of cloth bag
CN203271766U (en) Grouting pipe and grouting device of pipe shed advanced support
CN105386435A (en) Double-liquid grouting system used for cement and water glass solution and construction process of double-liquid grouting system
CN202644538U (en) A grouting device used for a water-rich quicksand stratum
CN101492917B (en) Hollow Bolt Cyclic Pressure Grouting Method and Its Special Grouting System
CN107859028B (en) Double-hole double-liquid grouting method
CN110453682A (en) A kind of tubular pole reinforcement system construction method
CN203161250U (en) Deep hole grouting reinforcing system for tunnel
CN111622217A (en) A kind of grouting prefabricated pipe pile after rotary spray construction and its construction technology
WO2021103210A1 (en) Construction method and device for full-casing composite expanded disk pile
CN204491617U (en) A kind of static pressure or hammering concrete precast pipe pile pile bottom post-grouting device
CN109750668A (en) A sleeve valve pipe and construction technology for the bottom reinforcement of a deep foundation pit in a water-rich pebble layer
CN101358529A (en) Consolidation construction technology of short pipe and short pipe sand-consolidating agent

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110511

Termination date: 20181015