CN201659634U - Curbstone production line - Google Patents

Curbstone production line Download PDF

Info

Publication number
CN201659634U
CN201659634U CN2010201221297U CN201020122129U CN201659634U CN 201659634 U CN201659634 U CN 201659634U CN 2010201221297 U CN2010201221297 U CN 2010201221297U CN 201020122129 U CN201020122129 U CN 201020122129U CN 201659634 U CN201659634 U CN 201659634U
Authority
CN
China
Prior art keywords
track
operation track
production line
kerb
cutting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010201221297U
Other languages
Chinese (zh)
Inventor
马贞新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LAIZHOU DAFENG MACHINERY EQUIPMENT CO Ltd
Original Assignee
LAIZHOU DAFENG MACHINERY EQUIPMENT CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LAIZHOU DAFENG MACHINERY EQUIPMENT CO Ltd filed Critical LAIZHOU DAFENG MACHINERY EQUIPMENT CO Ltd
Priority to CN2010201221297U priority Critical patent/CN201659634U/en
Application granted granted Critical
Publication of CN201659634U publication Critical patent/CN201659634U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a curbstone production line. After being placed on a workbench of the curbstone production line, stones can be cut into a plurality of curbstones at one time, and secondary stone arrangement can be omitted during cutting process, thereby solving the difficult problem of secondary clamping of blanks and increasing working efficiency while reducing labor intensity. The curbstone production line comprises a first operating track, at least two cutting units and at least one workbench, wherein the two cutting units are arranged along the first operating track and include a first cutting unit cutting stones along a first direction and a second cutting unit cutting stones along a second direction which is intersected with the first direction, the workbenches can be movably supported on the first track, and the stones to be cut are supported on the workbenches. By aid of the curbstone production line, moving time of the workbenches is reduced, and perpendicularity of flush cutting and split cutting.

Description

Kerb production line
Technical field
The utility model relates to a kind of kerb production line.
Background technology
It is rectangular-shaped that kerb is usually, by materials processings such as marble, granite and concrete and make, is widely used in occasions such as park, square and road, has broad application prospects.
In the existing kerb cutting flow process, used the multiple devices that adopt the separate unit mounting means, these equipment cut into the polylith kerb with a bulk of stone material, and stone material shifts between these equipment, need expend a large amount of time and efforts, and kerb production efficiency is low.
Publication number is that the Chinese patent application prospectus of CN101508148A has disclosed a kind of multi-cutter swivel stone material multi-machine cutoff production line, comprise many cutting units that in-line is arranged, each saw blade diameter that cuts in the unit strengthens successively, is used for the processing continuously on whole production line of stone material super-long and super-wide plate.This production line is fit to a bulk of stone material is cut into the stone material of number of plate-shaped, yet can not once obtain the polylith kerb that length and width satisfy the kerb specification requirement.
Therefore, demand urgently the process equipment of existing kerb is improved.
The utility model content
The purpose of this utility model is to provide a kind of kerb production line.
For this reason, according to an aspect of the present utility model, provide a kind of kerb production line, it comprises: the first operation track; At least two cutting units are arranged along the first operation track, and it comprises along the first cutting unit of first direction cutting building stones with along the second cutting unit of the second direction cutting building stones that intersect with first direction; At least one workbench is supported on the first operation track movably, and wherein, building stones to be cut are supported on the workbench.
In kerb production line of the present utility model, also comprise: the first loading and unloading material track, be provided with the first operation track parallel interval, and its bearing height is identical with the bearing height of the first operation track; And first carry track and second to carry track, lays respectively at the both end sides of the first operation track and the first loading and unloading material track, and wherein, each carries track to be provided with the transportation mine car, and the transportation mine car is provided with for workbench and supports thereon byroad rail or guide groove.
In kerb production line of the present utility model, also comprise the second loading and unloading material track, wherein, the first loading and unloading material track and the second loading and unloading material track lay respectively at the both sides of the first operation track, and first carries track and second to carry track to extend in the both end sides of the first loading and unloading material track and the second loading and unloading material track.
Kerb production line of the present utility model can also comprise: the second operation track be arranged in parallel with the first operation track.
Preferably, the above-mentioned first cutting unit selectively cuts the building stones on the workbench of the first operation track or the second operation track across the first operation track and the second operation track.
In kerb production line of the present utility model, can also be included in the 3rd operation track that extends on the first operation track bearing of trend and the 4th operation track that on the second operation track bearing of trend, extends.
Preferably, the above-mentioned first cutting unit is a butting saw, and the bearing of trend of the first direction and the first operation track is perpendicular; The second cutting unit is the burst multiple blade saw, and second direction is parallel to the bearing of trend of the first operation track.
Preferably, above-mentioned butting saw comprises: crossbeam, extend along second direction, and by two-dimentional drive mechanism, making lifting moving on the short transverse and on first direction, moving horizontally; And organize the sawing unit more, and the position is arranged on the crossbeam adjustablely, and each sawing unit can be used for separately building stones are carried out sawing.
Preferably, above-mentioned two-dimentional driving mechanism comprises: left rail and right guide rail are supported on across the first operation track or while on two bearings across the first operation track and the second operation track; Left side supporting base and right supporting base move on left rail and right guide rail controllably, and constitute upright guide rail; And perpendicular slide plate in a left side and right perpendicular slide plate, on left supporting base and right supporting base, make lifting moving controllably, wherein, crossbeam is fixed between perpendicular slide plate in a left side and the right perpendicular slide plate.
Preferably, above-mentioned burst multiple blade saw has the saw blade that multi-disc is provided with at interval and rotate synchronously, drives its relative building stones by elevating mechanism and moves up and down, and correspondingly, workbench is self-driven workbench.
In addition, the utility model also provides a kind of kerb production line, it comprises: the circulation track, comprise at least two transportation tracks, at least one operation track, and at least one loading and unloading material track that forms material loading station and unloading station, wherein, the transportation track is provided with the transportation mine car, the transportation mine car has for workbench support byroad rail or guide groove thereon, at least two processing stations, be arranged on the operation track of circulation track, at least two processing stations comprise along first cutting work station of first direction cutting building stones with along second cutting work station of the second direction cutting building stones that intersect with first direction; And at least one workbench, each workbench is capable of circulation to be supported on the circulation track movably, and wherein, building stones to be cut are supported on each workbench.
Preferably, the above-mentioned first cutting unit is a butting saw, and the second cutting unit is the burst multiple blade saw.
Preferably, above-mentioned at least two processing units are arranged on the same operation track.
According to kerb production line of the present utility model, the workbench of carrying building stones is moved on track, successively, shortened the time of movable workbench, and can guarantee the perpendicularity of flush cutting and burst cutting via flush and burst twice cutting technique.When stone after putting on the workbench, can disposablely cut into the polylith kerb, pilot process need not to put once more stone, has solved the difficulty of twice clamping of blank, has improved work efficiency and has reduced labour intensity.
Except purpose described above, feature and advantage, the utility model also has other purpose, feature and advantage.Below with reference to accompanying drawings, other purpose, feature and effect of the present utility model is described in further detail.
Description of drawings
Constitute this specification a part, be used for further understanding accompanying drawing of the present utility model and show preferred embodiment of the present utility model, and be used for illustrating principle of the present utility model with specification.Among the figure:
Fig. 1 shows the 3-D view according to the kerb production line of the utility model first embodiment;
Fig. 2 shows the front view of kerb production line shown in Figure 1;
Fig. 3 shows the vertical view of kerb production line shown in Figure 1;
Fig. 4 shows the pinion and rack according to the butting saw cutter unit of kerb production line of the present utility model;
Fig. 5 shows the track and the basis of kerb production line shown in Figure 1;
Fig. 6 shows the schematic layout pattern according to the kerb production line of the utility model second embodiment;
Fig. 7 shows the schematic layout pattern according to the kerb production line of the utility model the 3rd embodiment;
Fig. 8 shows the schematic layout pattern according to the kerb production line of the utility model the 4th embodiment;
Fig. 9 shows the schematic layout pattern according to the kerb production line of the utility model the 5th embodiment; And
Figure 10 shows the work flow according to the kerb of the utility model preferred embodiment.
The specific embodiment
Below in conjunction with accompanying drawing embodiment of the present utility model is elaborated, but the multitude of different ways that the utility model can be defined by the claims and cover is implemented.
Fig. 1 to Fig. 3 shows the structural representation according to the kerb production line of the utility model first embodiment.As shown in Figure 1 to Figure 3, in this preferred embodiment, kerb production line 100 comprises: the first loading and unloading material track 111, first carries track 113, the first operation track 115 and second to carry track 117, butting saw 170 that on the first operation track 115, is arranged in order and burst multiple blade saw 190, carry the material loading transportation mine car 131 that is provided with on the track 113 first, carry the discharging transportation mine car 133 that is provided with on the track 117 second, and the workbench 151,153,157 that is respectively applied for carrying stone 200a, 200b, 200c.
Wherein, the first loading and unloading material track 111 is identical with the bearing of trend of the first operation track 115, promptly be parallel to each other and extend at interval, and bearing height is identical.First carries track 113 and second to carry track 117 to lay respectively at the material loading end and the discharge end of the first operation track 115, and the workbench that the material loading end promptly carries unprocessed stone enters an end of the first operation track, and correspondingly the other end is a discharge end.First, second carries the bearing height of the bearing height of track 113,117 less than the first loading and unloading material track 111 or the first operation track 115, and this highly realizes by the lifting first loading and unloading material track 111 and the first operation track 115.
Transportation mine car 131,133 is respectively arranged with byroad rail 1311 and 1331, the bearing of trend of byroad rail 1311,1331 is identical with the bearing of trend of the first loading and unloading material track or the first operation track, when at transportation mine car 131 when first carries track 113 to move to the first loading and unloading material track end or the first operation track end, this byroad rail 1311 promptly docks with the first loading and unloading material track or the first operation track, and just workbench is carried between the first loading and unloading material track 111 and the first operation track 115.
Butting saw 170 comprises a plurality of sawings unit 171,173,175, and these sawing cell positions are arranged on the crossbeam 172 adjustablely, can distinguish the sawing that realizes separately stone.This crossbeam 172 is being done elevating movement and is being moved horizontally on the direction perpendicular to the first operation track by two-dimentional drive mechanism on the short transverse, to realize the flush cutting to stone.
Each cutter unit 171,173,175 typically comprises motor, main spindle box and saw blade, and its structure is conventionally known to one of skill in the art, does not give unnecessary details at this.
In this preferred embodiment, this two dimension driving mechanism comprises: left track and right track 174 are supported on two bearings across the described first operation track; Left side supporting base and right supporting base 176 move horizontally on described left and right guide rail 174 controllably, and constitute upright guide rail; And the perpendicular slide plate in a left side and right perpendicular slide plate 177, lifting moving on described left supporting base and right supporting base 176 controllably.
Butting saw cutter unit 171,173,175 (cutting head) laterally moves.
As shown in Figure 4, the butting saw cutter unit can move along crossbeam 172 length directions, adopts pinion and rack 178 transmissions.
Wherein, pinion and rack 178 comprises tooth bar that is fixedly mounted on the crossbeam 172 and the gear that is installed on the tooth rest 179, handwheel 1791 on the turning gear wheel carrier 179, tooth rest 179 rotation that cogs, tooth rest 179 drives whole flush cutter unit and moves along the crossbeam length direction, to adjust the distance between the flush cutter unit.
In this preferred embodiment, the flush cutter unit on the crossbeam is three, and in other embodiments, the quantity of flush cutter unit can be adjusted, for example two, four or five.
Burst multiple blade saw 190 comprises that multi-disc is provided with at interval and the saw blade 191 of coaxial rotation, and elevating mechanism is made lifting moving by the elevating mechanism driving, realizes feeding with the thickness direction at described stone.Correspondingly, workbench is self-driven workbench, and tooth bar and reducer gear engagement that the workbench bottom is provided with start reducing motor, realize that workbench moves back and forth, to realize the cutting movement of stone length direction.
Multiple blade saw lifting transmission: two columns all adopt the lifting of mariages thick stick, the bevel gear transmission, and reducing motor drives power transmission shaft, propeller shaft couplings small bevel gear wheel shaft, cone pinion drives large bevel gear, and large bevel gear drives elevating screw.The multiple blade saw main shaft is split type, and it is two fractions with running part that the saw blade part promptly is installed: the centre links into an integrated entity by tie-plate, and the transmission main shaft rotation drives the saw blade main shaft and rotates.
Each saw blade is installed on the main shaft by the saw blade ring, makes the diameter dimension of main shaft to reduce, to solve the problem of saw blade loading and unloading difficulty.
Workbench 151,153,157 returns the material loading station by material loading station (certain at the material loading track forms), flush cutting work station and burst cutting work station in turn or loads and unloads other certain of expecting track and carry out discharging by suspender or forklift.
Each component function and effect to the kerb production line of this preferred embodiment is elaborated below.
The operation track i.e. the first operation track, and horizontal positioned is fixed on the operation track basis, is used for support table, and workbench is moved horizontally on its track, thereby finishes kerb cutting processing operation.
Loading and unloading material track i.e. the first loading and unloading material track: parallel with the operation track, contour isometric, place at interval with the first operation track, be horizontally fixed on the loading and unloading material track basis, be used for support table, and workbench is moved horizontally, thereby finish preceding stock board material loading of kerb processing and processing back kerb finished product discharging operation on its track.
Carrying track is first, second conveying track, perhaps is called material loading and carries track and discharging to carry track: vertical with the operation track, lie in a horizontal plane in the both end sides that track is expected in operation track and loading and unloading.One distolaterally is that material loading carries track, and another is distolateral to be discharging conveying track.Material loading carries track and discharging to carry track parallel contour isometric, carry the track height to be lower than the operation track, and be fixed on the feed track base of the rail plinth or on the ground level, carry track to be used for supporting the transportation mine car, and the transportation mine car is moved horizontally on its track, thereby finish before the processing and the transportation of the workbench after processing operation.
Transportation mine car: lie in a horizontal plane in and carry on the track, and can on the conveying track, do reciprocating linear motion.The transportation mine car that is placed on the material loading conveying track is a material loading transportation mine car.The transportation mine car that is placed on the discharging conveying track is a discharging transportation mine car.Be provided with transportation byroad rail above the transportation mine car, be used for support table, and workbench is moved on its byroad rail.
In sum: the operation track, the loading and unloading track carries track to constitute the track net road of a closed cycle in conjunction with the byroad rail on transportation mine car and the transportation mine car.Workbench circulation again and again on the track net road of this closed cycle is moved, form production-lines.
The cutting unit is flush cutting unit and burst cutting unit.Two cutting units are spaced along operation track length direction, carry track one end near material loading, are flush cutting unit, and carrying track one end near discharging is burst cutting unit.
Flush cutting unit level is installed on the basis of flush cutting unit, and the basis of flush cutting unit is across the operation track.Workbench passes from the below, basis of flush cutting unit, and the direction of flush cutting is vertical with the length direction of work track, is referred to as first cut direction.During flush cutting, table latch is motionless, moves by body, driving crossbeam moves along flush track length direction, realize that cut direction cuts continuously, drive the crossbeam lifting by the upright slide plate of lifting and realize layering feed feeding that cutting finishes workbench is shifted to burst cutting unit.
Burst cutting unit: level is installed on the basis of burst cutting unit, burst cutting unit cutting main body is across the work track, workbench passes between two foundation columns of cutting main body below, the burst cut direction is identical with work track length direction, vertical with flush cut direction, be referred to as second cut direction.During the burst cutting, body maintains static.The cutting main body realizes layering feed feeding by the lifter slide lifting, and workbench moves back and forth along work track length direction, realizes burst cutting cutting continuously.Cutting finishes workbench is shifted to discharging transportation mine car.
Workbench: workbench is horizontally set on work track or the loading and unloading material track usually, be used to support carrying kerb stock board to be cut and follow circuit rail net road, finish the whole production process operation successively by the transportation of material loading, material loading, flush, burst, discharging transportation, six cargo handling operations of discharging.Workbench, all is artificial promotion, but also can be arranged to full-automatic motion in other moving process except that being the motion automatically in the burst cutting process.
By above description as can be seen, make flush and the operation on same track of burst twice cutting technique, shortened the time of movable workbench, and can guarantee the perpendicularity of flush cutting and burst cutting.When stone after putting on the workbench, can disposablely cut into the polylith kerb, pilot process need not to put once more stone, has solved the difficulty of twice clamping of blank, has improved work efficiency and has reduced labour intensity.
In addition, according to the kerb production line of the utility model preferred embodiment, realized that the closed cycle of workbench is moved, the material loading step of workbench and discharging step can be carried out in same place.
Work flow to above-mentioned kerb production line describes below.
The material loading transportation: workbench is lifted building stones to be processed on the workbench by hanging device after moving to the material loading position on the material loading track (loading and unloading material track), and put well the location.Travelling table is to material loading transportation mine car then.Material loading is transported mine car again and move to operation track material loading position along material loading transportation track, the track above the material loading transportation mine car is overlapped with the first operation track, travelling table is to location, butting saw below, locking workbench.
Flush cutting: start butting saw, carry out flush cutting building stones.Flush saw blade automatic lifting is also walked automatically along the crossbeam track, back and forth cuts building stones to cutting and finishes.
Transportation: flush cutting finishes, and release moves to the burst cutting position with workbench along the first operation track, makes the tooth bar and the transmission speed reducer gears engaged of workbench.
Burst cutting: start burst cutting multiple blade saw work operations platform, bring workbench into the multiple blade saw below automatically by the workbench driving motor by the rack-and-pinion transmission, and move back and forth automatically.The reciprocal cutting stone material of saw blade automatic lifting is to finishing to cutting.
The transportation discharging: the burst cutting finishes.Travelling table is to discharging transportation mine car, and discharging transportation mine car is transported to loading and unloading material track end along discharging transportation track with workbench makes the track on the discharging transportation mine car overlap with loading and unloading material track.The work operations platform is moved to discharge position along the first loading and unloading material track.Start hanging device the finished product building stones are unloaded lower table and prune job work top.Enter the next round operation.
Above-mentioned transportation mine car and corresponding first, second carry track to be replaced by other conveying device, and for example, the transportation mine car is replaced by slide plate, or first, second delivery track is replaced by some conveying rollers that set in a row; Secondary track on the transportation mine car can be replaced by chute, with the effect of same realization support table.
In other embodiments, the cutter sweep of other type can be set to form cutting work station or other processing station on the first operation track.
Fig. 5 shows the track and the basis of kerb production line shown in Figure 1.As shown in Figure 5, the first loading and unloading material track 111 is arranged on the brace table 211 that is formed by the basis, is used to support butting saw across the bearing 213 that is formed by the basis of the first operation track.The post 215 that is formed by the basis is used to support multi-disc and divides blade saw, and track 113 and 117 can directly be provided with on the bottom surface that is formed by the basis.Certainly, said here brace table, bearing and post also can by metallic support the seat or post replace, further, function of regulating height thereof can also be set.
Fig. 6 shows the schematic layout pattern according to the kerb production line of the utility model second embodiment.As shown in Figure 6, in the present embodiment, kerb production line comprises that also the second loading and unloading material track, 119, the second loading and unloading material tracks 119 and the first loading and unloading material track were located at the both sides of the first operation track 115 in 111 minutes.
The first loading and unloading material track 111 and the second loading and unloading material track 119 can provide the workbench that carries the building stones that need processing to the first operation track 115 respectively, also can carry out discharging for the workbench that carries kerb respectively simultaneously.Make that so continuous productive process is more smooth and easy.For making things convenient for the transhipment of workbench, first, second is carried two transportation mine cars 133,135 preferably is set on the track 113,117.
Fig. 7 shows the schematic layout pattern according to the kerb production line of the utility model the 3rd embodiment.Compare with second embodiment, comprise also that in the present embodiment the 3rd loading and unloading material track the 121, the 3rd is carried track 123, the 4th loading and unloading material track 125, the 3rd operation track 127 and the multi-disc that is arranged on the 3rd operation track 127 is divided blade saw 191.
The 3rd operation track 127 and the first operation track 115 be arranged in parallel, and be contour concordant, divides the perpendicular cuts between the blade saw to guarantee butting saw and multi-disc.
Wherein, multi-disc divides blade saw 191 and the multi-disc on the operation track 115 to divide the saw blade spacing of blade saw 190 can be different, so that by the kerb that multi-disc divides blade saw 190,191 to cut into the required size specification respectively, reach and reduce the operating procedure of adjusting distance between the saw blade.
The 3rd carries track 123 to be provided with transportation mine car 137,139, so that workbench is changed between each track 121,125,121.
Fig. 8 shows the schematic layout pattern according to the kerb production line of the utility model the 4th embodiment.Compare with second embodiment, in the present embodiment, one side of the first operation track 115 also comprises the second operation track 116, this second operation track 116 is provided with multi-disc and divides blade saw 193, wherein second operation track 116 and the 115 parallel interval settings of operation track, butting saw 170 is movable to the flush cutting that realizes on the first operation track 115 stone across on operation track 115 and the 3rd operation track 116, also is movable to the flush cutting that realizes on the second operation track 116 stone.So, the shared butting saw of two operation tracks.
Fig. 9 shows the schematic layout pattern according to the kerb production line of the utility model the 5th embodiment.Compare with the 4th embodiment, in the present embodiment, first carries a side of track 113 also to comprise the 3rd loading and unloading material track 121, the 3rd conveying track 123 and the 4th loading and unloading material track 125, and the 3rd operation track 127 and the 4th operation track 129, wherein, three, be respectively arranged with burst multiple blade saw 191,195 on the 4th operation track 127,129, so that cutting is the kerb of a plurality of dimensions or makes multi-disc divide the productivity ratio of blade saw and the productivity ratio of butting saw to be complementary.
Figure 10 shows the kerb work flow according to the utility model preferred embodiment.As shown in Figure 5, this work flow may further comprise the steps: the material loading step: make the material loading station of movable workbench to loading and unloading material track, on stone positioning table to be cut; The first transhipment step: workbench is transported to the operation track from loading and unloading material track; Cutting step: workbench is moved at least one operation track, and successively through at least two cutting work station stone is cut, forms the polylith kerb at two different directions; The second transhipment step: workbench is transported on the loading and unloading material track from the operation track; Discharging step: make movable workbench to unloading station carry out discharging and cleaning work platform, for the material loading step is prepared.
The above-mentioned first transhipment step realizes like this: workbench is moved on the transportation mine car by the end of loading and unloading material track; Make the transportation mine car carry track to move to the end of the same side of operation track along first from the end of loading and unloading material track; And make workbench move to the operation track from the transportation mine car.The similar material loading step of the second transhipment step.
Wherein, discharging and material loading are all finished on loading and unloading material track, and workbench can carry out discharging and material loading at same station.
For realizing streamline production, the workbench more than three or three is used in suggestion at least, make a workbench on first track, carry out the material loading step, other two workbench are used for carrying out flush cutting and burst cutting step respectively on the operation track, and it are transported to loading and unloading material track after cutting step and carry out the discharging material loading.The quantity of above-mentioned workbench can be determined according to what, the ability of material loading discharging of cutting work station, to guarantee the continuous high-efficient running of production line.
In cutting step, the stone on the workbench carries out the burst cutting through the burst cutting work station more earlier through the flush cutting work station at least two cutting work station.
Be preferred embodiment of the present utility model only below, be not limited to the utility model, for a person skilled in the art, the utility model can have various changes and variation.All within spirit of the present utility model and principle, any modification of being done, be equal to replacement, improvement etc., all should be included within the protection domain of the present utility model.

Claims (13)

1. a kerb production line is characterized in that, comprising:
The first operation track;
At least two cutting units are arranged along the described first operation track, and it comprises along the first cutting unit of first direction cutting building stones and cuts the second cutting unit of described building stones along the second direction that intersects with described first direction; And
At least one workbench is supported on the described first operation track movably, and wherein, building stones to be cut are supported on the described workbench.
2. kerb production line according to claim 1 is characterized in that, also comprises:
The first loading and unloading material track be provided with the described first operation track parallel interval, and its bearing height is identical with the bearing height of the described first operation track; And
First carries track and second to carry track, lay respectively at the both end sides of the described first operation track and the first loading and unloading material track, wherein, each described conveying track is provided with the transportation mine car, and described transportation mine car is provided with for described workbench support byroad rail or guide groove thereon.
3. kerb production line according to claim 2, it is characterized in that, also comprise the second loading and unloading material track, wherein, the described first loading and unloading material track and the second loading and unloading material track lay respectively at the both sides of the first operation track, and described first carries track and second to carry track to extend in the both end sides of the described first loading and unloading material track and the second loading and unloading material track.
4. kerb production line according to claim 2 is characterized in that, also comprises the second operation track, be arranged in parallel with the described first operation track.
5. kerb production line according to claim 4, it is characterized in that, the described first cutting unit selectively cuts the building stones on the workbench of the described first operation track or the second operation track across the described first operation track and the second operation track.
6. kerb production line according to claim 5 is characterized in that, also is included in the 3rd operation track that extends on the described first operation track bearing of trend and the 4th operation track that extends on the described second operation track bearing of trend.
7. according to each described kerb production line in the claim 1 to 6, it is characterized in that the described first cutting unit is a butting saw, the bearing of trend of described first direction and the described first operation track is perpendicular; The described second cutting unit is the burst multiple blade saw, and described second direction is parallel to the bearing of trend of the described first operation track.
8. kerb production line according to claim 7 is characterized in that, described butting saw comprises:
Crossbeam extends along described second direction, by two-dimentional drive mechanism, is making lifting moving on the short transverse and is moving horizontally on described first direction; And
Many group sawings unit, the position is arranged on the described crossbeam adjustablely, and each described sawing unit is used for separately building stones are carried out sawing.
9. kerb production line according to claim 8 is characterized in that, described two-dimentional driving mechanism comprises:
Left rail and right guide rail are supported on across described first operation track or while on two bearings across the described first operation track and the second operation track;
Left side supporting base and right supporting base move on described left rail and right guide rail controllably, and constitute upright guide rail; And
Perpendicular slide plate in a left side and right perpendicular slide plate are made lifting moving controllably on described left supporting base and right supporting base, wherein, described crossbeam is fixed between perpendicular slide plate in a described left side and the right perpendicular slide plate.
10. kerb production line according to claim 7, it is characterized in that described burst multiple blade saw has the saw blade that multi-disc is provided with at interval and rotate synchronously, drives its described relatively building stones by elevating mechanism and moves up and down, correspondingly, described workbench is self-driven workbench.
11. a kerb production line is characterized in that, comprising:
The circulation track, comprise at least two transportation tracks, at least one operation track and at least one loading and unloading material track that forms material loading station and unloading station, wherein, described transportation track is provided with the transportation mine car, described transportation mine car has for described workbench support byroad rail or guide groove thereon
At least two processing stations are arranged on the operation track of described circulation track, and described at least two processing stations comprise along first cutting work station of first direction cutting building stones with along second cutting work station of the second direction cutting building stones that intersect with first direction; And
At least one workbench, each described workbench is capable of circulation to be supported on the described circulation track movably, and wherein, building stones to be cut are supported on each described workbench.
12. kerb production line according to claim 11 is characterized in that, the described first cutting unit is a butting saw, and the described second cutting unit is the burst multiple blade saw.
13. kerb production line according to claim 11 is characterized in that, described at least two processing units are arranged on the same operation track.
CN2010201221297U 2010-03-03 2010-03-03 Curbstone production line Expired - Fee Related CN201659634U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010201221297U CN201659634U (en) 2010-03-03 2010-03-03 Curbstone production line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010201221297U CN201659634U (en) 2010-03-03 2010-03-03 Curbstone production line

Publications (1)

Publication Number Publication Date
CN201659634U true CN201659634U (en) 2010-12-01

Family

ID=43230046

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010201221297U Expired - Fee Related CN201659634U (en) 2010-03-03 2010-03-03 Curbstone production line

Country Status (1)

Country Link
CN (1) CN201659634U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101786297A (en) * 2010-03-03 2010-07-28 莱州大丰机械设备有限公司 Kerb production line and kerb processing method
CN102975293A (en) * 2012-12-12 2013-03-20 晋江市连盛液压机械有限公司 Stone cutting machine for double door shape beams
CN103009073A (en) * 2012-12-19 2013-04-03 林雄 Automatic intermittent cycle worktable
CN103028952A (en) * 2012-12-19 2013-04-10 林雄 Work sliding table movement limiting device of automatic intermittent circulation work table
CN105108909A (en) * 2015-08-14 2015-12-02 福建省华隆机械有限公司 Multi-disc frame saw assembly
CN105216128A (en) * 2015-09-30 2016-01-06 上海日进机床有限公司 Be applied to the multi-wire saw equipment of silicon ingot evolution

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101786297A (en) * 2010-03-03 2010-07-28 莱州大丰机械设备有限公司 Kerb production line and kerb processing method
CN101786297B (en) * 2010-03-03 2013-09-11 莱州大丰机械设备有限公司 Kerb production line and kerb processing method
CN102975293A (en) * 2012-12-12 2013-03-20 晋江市连盛液压机械有限公司 Stone cutting machine for double door shape beams
CN103009073A (en) * 2012-12-19 2013-04-03 林雄 Automatic intermittent cycle worktable
CN103028952A (en) * 2012-12-19 2013-04-10 林雄 Work sliding table movement limiting device of automatic intermittent circulation work table
CN103028952B (en) * 2012-12-19 2016-01-27 林雄 The working slider of automatic intermittent circulating work platform moves stopping means
CN103009073B (en) * 2012-12-19 2016-03-16 福鼎市金雄机车部件有限公司 Automatic intermittent circulating work platform
CN105108909A (en) * 2015-08-14 2015-12-02 福建省华隆机械有限公司 Multi-disc frame saw assembly
CN105216128A (en) * 2015-09-30 2016-01-06 上海日进机床有限公司 Be applied to the multi-wire saw equipment of silicon ingot evolution
CN105216128B (en) * 2015-09-30 2017-07-28 上海日进机床有限公司 Multi-wire saw equipment applied to silicon ingot evolution

Similar Documents

Publication Publication Date Title
CN101786297B (en) Kerb production line and kerb processing method
CN201659634U (en) Curbstone production line
CN205614431U (en) Automatic descaling machine of polishing of bent axle
CN108582266B (en) Wood floor stacker crane
CN103056532A (en) Laser cutter standalone automatic feeding and discharging device and laser cutter standalone automatic feeding and discharging method
CN105216128B (en) Multi-wire saw equipment applied to silicon ingot evolution
KR20120046875A (en) Multi-blades type cutting machine for stone
CN106671673B (en) One machine of one kind drives formula double-station engraving machine more
CN210365854U (en) A turn to conveying equipment for casting mould transports
CN203110160U (en) Bridge type stone cutting machine with polishing function
CN207808101U (en) A kind of five axis slab cutting machines
CN114043615B (en) Full-automatic cushion block production line
CN212639130U (en) Unloader on slabstone
CN201291521Y (en) Automatic grinding machine for stone surface
CN108501222B (en) Strip stone cutting production line
CN207943585U (en) Novel material is dialled from formula unstacker
CN207027749U (en) The facing cut of timber four
CN105108909A (en) Multi-disc frame saw assembly
CN105196424B (en) Chipped ashlar cutting production line
CN111573267A (en) Unloader on slabstone
CN211466608U (en) A guillootine for smart card production
CN114619569A (en) Neat dissection device of curbstone
CN204819609U (en) Circulation dry plate cutting equipment
CN104441262A (en) Feedstock slab bottom horizontal cutting machine
CN219465671U (en) Billiard table surface grinder

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101201

Termination date: 20160303

CF01 Termination of patent right due to non-payment of annual fee