CN201554236U CN2009202119058U CN200920211905U CN201554236U CN 201554236 U CN201554236 U CN 201554236U CN 2009202119058 U CN2009202119058 U CN 2009202119058U CN 200920211905 U CN200920211905 U CN 200920211905U CN 201554236 U CN201554236 U CN 201554236U
Authority
CN
China
Prior art keywords
exterior wall
construction
scaffold
exterior
reservation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009202119058U
Other languages
Chinese (zh)
Inventor
刘江
张向阳
顾雯琦
方圳海
徐杨斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai First Construction Co Ltd
Original Assignee
Shanghai First Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai First Construction Co Ltd filed Critical Shanghai First Construction Co Ltd
Priority to CN2009202119058U priority Critical patent/CN201554236U/en
Application granted granted Critical
Publication of CN201554236U publication Critical patent/CN201554236U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a retained exterior wall strengthening device. The device is characterized by comprising a ground scaffold, a construction bent, an outer framework and an inner framework, wherein the ground scaffold is built outside the retained exterior wall; the full framing construction bent is built inside the retained exterior wall; the outer framework is arranged over the outside of the retained exterior wall; the inner framework is arranged over the inside of a strengthening wall body in the retained exterior wall; and the ground scaffold, the outer framework, the inner framework and the construction bent are mutually communicated in door and window holes of the retained exterior wall to be a whole. Used in the utility model, a method of matching the construction scaffold with the framework to hoop the exterior wall is simple and easy for operation, thus saving construction period and cost and simultaneously being beneficial to the stability of an old wall. The method is simple and convenient in operation and low in cost.

Description

Keep the exterior wall bracing means
Technical field
The utility model relates to a kind of building top structure construction reinforcing technique, specifically discloses a kind of reservation exterior wall bracing means.
Background technology
In outstanding historical protective buildings improvement project, when needs keep exterior wall, again structure replacing is carried out in its inside simultaneously, in the internal construction displacement with during to the exterior wall seismic hardening, the monolithic stability of guaranteeing to keep exterior wall is most important.
Carry out the inside reconstruction at building; under the situation that exterior wall need keep; current way commonly used is to adopt the one side formwork construction technology or adopt split bolt perforation construction on exterior wall, can't effectively protect the stable while of exterior wall self to carry out certain destruction to keeping exterior wall again like this when exterior wall self is reinforced.
Summary of the invention
Technical problem to be solved in the utility model provides a kind ofly promptly can protect exterior wall, can satisfy again and reinforce the reservation exterior wall bracing means that requires, thereby overcome the above-mentioned defective that prior art exists.
The technical scheme of the utility model technical solution problem is as follows:
A kind of reservation exterior wall bracing means, it is characterized in that, comprise land scaffold, the construction framed bent, exterior sheathing and inner formword, the described scaffold building that lands is keeping the exterior wall outside, described full hall construction framed bent is set up and is being kept inner side of outer wall, described exterior sheathing is covered in and keeps the exterior wall outside, and described inner formword is covered in and keeps the outer inboard of reinforcing wall within the walls, and described scaffold, exterior sheathing, inner formword and the construction framed bent of landing is interconnected and is one keeping exterior wall door and window hole.
By above disclosed technical scheme as can be known; the utility model lands scaffold by erection construction outside reconstruction Lao Lou; set up full hall construction framed bent in inside; utilize a determining deviation door and window hole to be communicated with interior out-mould scaffold; use inner and outer template to wale exterior wall simultaneously in protection exterior wall inside and outside simultaneously; and utilize a determining deviation door and window hole to be communicated with inner and outer template and reinforce steel pipe and be linked to be integral body with inside full hall construction framed bent simultaneously; thereby play when exterior wall is reinforced as construction formwork, when internal construction is replaced, play and reinforce and the effect of protection exterior wall.
It is simple to operation to use construction scaffolding to cooperate template to wale the method for exterior wall, has saved duration and expense, simultaneously also favourable old wall stable.This method is easy and simple to handle and expense is low.
Description of drawings
Fig. 1 keeps exterior wall bracing means structural representation for the utility model.
Fig. 2 is an A-A sectional view among Fig. 1.
Reference numeral is as follows:
1, keep exterior wall 2, land scaffold 3, construction framed bent
4, nine clamping plate 5, flitch 6, reinforcing wall
7, floor face 8, structural column 9, steel tube fastener
10, windowsill
The specific embodiment
Below in conjunction with drawings and Examples the utility model is described further.
As shown in Figure 1 and Figure 2, the utility model keeps the exterior wall bracing means, comprise and land scaffold 2, a full hall construction framed bent 3, exterior sheathing and inner formword, the described scaffold 2 that lands is set up in reservation exterior wall 1 outside, described full hall construction framed bent 3 is set up and is being kept exterior wall 1 inboard, described exterior sheathing is covered in and keeps exterior wall 1 outside, described inner formword is covered in and keeps the outer inboard of reinforcing wall 6 within the walls, and described scaffold 2, exterior sheathing, inner formword and the full hall construction framed bent 3 of landing is interconnected and is one keeping exterior wall door and window hole.
Described exterior sheathing comprises nine clamping plate 4 and flitch 5, and described exterior sheathing is waled the reservation exterior wall by steel tube fastener 9.Described inner formword comprises nine clamping plate 4 and flitch 5, and described inner formword is waled the reservation exterior wall by steel tube fastener 9.
Keep exterior wall protection strengthening construction flow process:
A, the outside is covered with the flitch of the thick nine clamping plate templates of 20mm and 50 * 100mm in keeping exterior wall, and the steel pipe of employing Φ 48 * 3.5mm fixes, and the steel pipe spacing is selected according to wall thickness;
B, set up full hall construction framed bent keeping exterior wall 1 inside, set up routine and land scaffold (internal force bar with keep exterior wall keep effective spacing 300mm at least) keeping exterior wall 1 outside, and crus mediale hand framed bent steel pipe, the inner side template steel pipe door and window hole by former Lao Lou one determining deviation is connected with exterior wall scaffold with the outboard template steel pipe, wale the template and the flitch (accompanying drawing 1) that overlay on the exterior wall in this way;
The out-mould scaffold steel pipe is communicated with the back and is communicated with the both sides exterior wall with re-using long steel pipe in c, the exterior wall, makes an outside circle construction scaffolding, exterior wall hardened system and internal construction framed bent be linked to be integral body;
D, carry out exterior wall seismic hardening and inner displacement construction.

Claims (4)

1. reservation exterior wall bracing means, it is characterized in that, comprise land scaffold (2), the construction framed bent (3), exterior sheathing and inner formword, the described scaffold (2) that lands is set up in reservation exterior wall (1) outside, described construction framed bent (3) is set up and is being kept exterior wall (1) inboard, described exterior sheathing is covered in and keeps exterior wall (1) outside, described inner formword is covered in and keeps the outer inboard of reinforcing wall (6) within the walls, and described scaffold (2), exterior sheathing, inner formword and the construction framed bent (3) of landing is interconnected and is one keeping exterior wall door and window hole.
2. reservation exterior wall bracing means according to claim 1 is characterized in that, described exterior sheathing comprises nine clamping plate (4) and flitch (5), and described exterior sheathing is waled the reservation exterior wall by steel tube fastener (9).
3. reservation exterior wall bracing means according to claim 1 is characterized in that, described inner formword comprises nine clamping plate (4) and flitch (5), and described inner formword is waled the reservation exterior wall by steel tube fastener (9).
4. reservation exterior wall bracing means according to claim 1 is characterized in that, construction framed bent (3) is full hall construction framed bent.
CN2009202119058U 2009-11-05 2009-11-05 Retained exterior wall strengthening device Expired - Fee Related CN201554236U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009202119058U CN201554236U (en) 2009-11-05 2009-11-05 Retained exterior wall strengthening device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009202119058U CN201554236U (en) 2009-11-05 2009-11-05 Retained exterior wall strengthening device

Publications (1)

Publication Number Publication Date
CN201554236U true CN201554236U (en) 2010-08-18

Family

ID=42613916

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009202119058U Expired - Fee Related CN201554236U (en) 2009-11-05 2009-11-05 Retained exterior wall strengthening device

Country Status (1)

Country Link
CN (1) CN201554236U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383617A (en) * 2010-09-03 2012-03-21 上海天演建筑物移位工程有限公司 Temporary reinforcement method of ancient building and device
CN107313607A (en) * 2017-07-02 2017-11-03 上海二十冶建设有限公司 Supporting protection device and construction method for preserved building thing in projects
CN107700668A (en) * 2017-10-17 2018-02-16 上海建工二建集团有限公司 Retain the attachment structure and its construction method of exterior wall and newly-built steel reinforced concrete horizontal member
CN110318559A (en) * 2019-07-29 2019-10-11 江苏东南特种技术工程有限公司 A kind of landmark reinforcement for rushing danger device and method
CN114737789A (en) * 2022-04-28 2022-07-12 中建八局第三建设有限公司 Combined structure dismantling and external wall temporary reinforcing construction method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383617A (en) * 2010-09-03 2012-03-21 上海天演建筑物移位工程有限公司 Temporary reinforcement method of ancient building and device
CN107313607A (en) * 2017-07-02 2017-11-03 上海二十冶建设有限公司 Supporting protection device and construction method for preserved building thing in projects
CN107700668A (en) * 2017-10-17 2018-02-16 上海建工二建集团有限公司 Retain the attachment structure and its construction method of exterior wall and newly-built steel reinforced concrete horizontal member
CN110318559A (en) * 2019-07-29 2019-10-11 江苏东南特种技术工程有限公司 A kind of landmark reinforcement for rushing danger device and method
CN110318559B (en) * 2019-07-29 2024-03-19 江苏东南特种技术工程有限公司 Rescue reinforcement device and method for cultural relics and buildings
CN114737789A (en) * 2022-04-28 2022-07-12 中建八局第三建设有限公司 Combined structure dismantling and external wall temporary reinforcing construction method

Similar Documents

Publication Publication Date Title
CN201554236U (en) Retained exterior wall strengthening device
CN203452799U (en) Corrugated steel tunnel supporting structure
CN201554237U (en) Seismic strengthening structure of retained exterior wall
CN104805960B (en) One kind exempts from form removal beams of concrete and its construction method
CN105804283A (en) Full assembly type steel pipe concrete side frame combined shear wall structure
CN101858124A (en) A New Type of Seismic Reinforced Structural Column for Masonry Structures
CN103161309A (en) Narrow deformation joint inner side template installation and construction method
CN109577643B (en) Embedded steel formwork for supporting steel platform and construction method thereof
CN110630011A (en) Template reinforcing system for double shear walls at deformation joint and construction method thereof
CN205776755U (en) A kind of encased steel plate multi-cavity combination type shear wall core wall structure system
CN103615112A (en) Construction process of metal reinforced frame bamboo plywood fabricated formwork
CN206289945U (en) A kind of assembled Portable safety crosshead
CN205637239U (en) Completely assembling formula steel pipe concrete frame compound shear wall structure
CN209040598U (en) Auxiliary unloading device for replacement of shear wall concrete by support-free method
CN208534081U (en) A kind of reconstruction structure of old building constructional column
CN103397721A (en) Steel plate precast concrete double-plate shear wall
CN212927030U (en) Embrace frame post template reinforcing apparatus
CN205314534U (en) Frame post can't harm drawknot steel form structure
CN208310200U (en) A kind of expansion joint two side columns template reinforcing device
CN105442832A (en) Formwork for concrete guide wall
CN216196545U (en) Prefabricated type assembling combined type building engineering template
CN201148734Y (en) Special-shaped cement pillar reinforcement device
CN206289786U (en) The prefabricated overlapping built-in prestressed steel reinforced concrete wall of formwork
CN201103240Y (en) Expansion type drawknot screw
CN208473286U (en) A kind of wall form of car ramp circular arc wall

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100818

Termination date: 20111105