CN201541071U - Isolation switch maintenance platform - Google Patents

Isolation switch maintenance platform Download PDF

Info

Publication number
CN201541071U
CN201541071U CN2009202582406U CN200920258240U CN201541071U CN 201541071 U CN201541071 U CN 201541071U CN 2009202582406 U CN2009202582406 U CN 2009202582406U CN 200920258240 U CN200920258240 U CN 200920258240U CN 201541071 U CN201541071 U CN 201541071U
Authority
CN
China
Prior art keywords
isolating switch
workbench
platform
operating platform
maintenance platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009202582406U
Other languages
Chinese (zh)
Inventor
李宏伟
陈志刚
暴鹏
武炜
王刚
周鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHENGZHOU XIANGYU SCIENCE AND TECHNOLOGY DEVELOPMENT Co Ltd
Zhengzhou Power Supply Co of State Grid Henan Electric Power Co Ltd
Original Assignee
ZHENGZHOU XIANGYU SCIENCE AND TECHNOLOGY DEVELOPMENT Co Ltd
Zhengzhou Power Supply Co of Henan Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHENGZHOU XIANGYU SCIENCE AND TECHNOLOGY DEVELOPMENT Co Ltd, Zhengzhou Power Supply Co of Henan Electric Power Co filed Critical ZHENGZHOU XIANGYU SCIENCE AND TECHNOLOGY DEVELOPMENT Co Ltd
Priority to CN2009202582406U priority Critical patent/CN201541071U/en
Application granted granted Critical
Publication of CN201541071U publication Critical patent/CN201541071U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Trip Switchboards (AREA)

Abstract

The utility model discloses a repair platform of an isolating switch, comprising an upper operating platform arranged on an upper bracket and a lower operating platform arranged on a lower bracket. A static contact dismantling frame is arranged at one end of the upper operating platform; an adjustment stable platform and a corresponding spring pressing device are arranged at the other end of the upper operating platform; an upper contact fixed block base is arranged in the middle of the upper operating platform; and the lower operating platform is provided with opening holes enabling rotation at the lower part of the isolating switch. The repair platform greatly improves the working efficiency and solves the problem that the isolating switch is difficult to be fixed, disassembled, assembled and debugged in the construction site.

Description

隔离开关检修平台 Isolation switch maintenance platform

技术领域:Technical field:

本实用新型涉及一种检修装置,特别涉及电力行业变电站中GW16/17系列隔离开关的检修。The utility model relates to a maintenance device, in particular to the maintenance of GW16/17 series isolating switches in substations in the electric power industry.

背景技术:Background technique:

随着电力系统的不断发展,在变电站中大量应用的GW16/17隔离开关已陆续达到检修期限,但由于该系列隔离开关体积较大,形状十分不规则,固定十分困难,结构比较复杂,解体拆装非常麻烦,造成了检修费时费力,据统计检修1组该类型隔离开关需要6位工人2~3天才能完成,这不但大大延长了设备停电时间,降低了工作效率,还增加了供电量的损失,降低了输变电设备可靠性、安全性。With the continuous development of the power system, the GW16/17 isolating switches widely used in substations have successively reached the maintenance deadline. The installation is very troublesome, resulting in time-consuming and laborious maintenance. According to statistics, it takes 6 workers 2 to 3 days to complete the maintenance of a group of this type of isolating switch. This not only greatly prolongs the power outage time of the equipment, reduces work efficiency, but also increases the power supply. Loss, reducing the reliability and safety of power transmission and transformation equipment.

实用新型内容:Utility model content:

本实用新型素要解决的技术问题就是针对以上不足而提供一种隔离开关检修平台,该平台设计为上下两层,合理利用隔离开关的外形结构的不规则性,充分考虑到隔离开关的固定、拆卸、组装、调试等各个环节,利用压缩弹簧、压紧固定等方式,通过对各个拆卸、固定组件的合理配置,从而达到快速检修隔离开关的目的。The technical problem to be solved by the utility model is to provide an isolating switch maintenance platform for the above deficiencies. Disassembly, assembly, commissioning and other links, using compression springs, pressing and fixing, etc., through the reasonable configuration of each disassembly and fixing components, so as to achieve the purpose of quick maintenance of the isolation switch.

本实用新型所采取的技术方案是:The technical scheme that the utility model takes is:

一种隔离开关检修平台,包括有上支架上所设上工作台和下支架上所设下工作台,上工作台的一端设有静触头拆卸架,上工作台的另一端设有调整稳固平台和对应的弹簧压紧装置,上工作台的中部设有上触头固定卡座,下工作台上具有可以使隔离开关下部旋转的开孔。An isolating switch maintenance platform, including an upper workbench set on an upper support and a lower workbench set on a lower support, one end of the upper workbench is provided with a static contact dismantling frame, and the other end of the upper workbench is provided with an adjustment and stabilization The platform and the corresponding spring pressing device, the middle part of the upper worktable is provided with an upper contact fixing holder, and the lower workbench has an opening that can rotate the lower part of the disconnector.

为方便移动和固定,上支架的底部设有四个可锁定的万向轮。For the convenience of moving and fixing, four lockable universal wheels are provided at the bottom of the upper bracket.

为便于固定、拆卸、组装、调试的各个环节,下支架设置在滑道上,使得下工作台在上工作台的下方可以抽拉。In order to facilitate the various links of fixation, disassembly, assembly and debugging, the lower bracket is arranged on the slideway, so that the lower workbench can be pulled under the upper workbench.

下支架上还具有可上下调整高度的调整件。The lower bracket also has an adjustment piece that can adjust the height up and down.

开孔的四周设有固定孔,用于螺栓固定。Fixing holes are arranged around the opening for bolt fixing.

本实用新型大大提高了工作效率,解决了施工现场隔离开关固定、拆卸、组装、调试困难的问题。The utility model greatly improves the working efficiency, and solves the problems of difficulty in fixing, disassembling, assembling and debugging the isolating switch at the construction site.

附图说明:Description of drawings:

图1为本实用新型的结构示意图。Fig. 1 is the structural representation of the utility model.

图2为图1的俯视结构示意图。FIG. 2 is a schematic top view of the structure of FIG. 1 .

具体实施方式:Detailed ways:

下面结合附图对本实用新型作进一步的描述:Below in conjunction with accompanying drawing, the utility model is further described:

如图1、图2所示,该隔离开关检修平台,包括有上支架2上所设上工作台6和下支架3上所设下工作台5,上工作台6和下工作台5结构均为长方形钢板,上工作台6设计安装了四个部分,分别为静触头拆卸架7、上触头固定卡座10、调整稳固平台8和弹簧压紧装置9;下工作台5上四个固定孔12孔用于螺栓固定,中部开孔11用于隔离开关下部的旋转,下支架3设置在滑道上,使用时下工作台5通过滑道展开,并通过调整件4的调整使其高度适当且稳固,上支架2安装有四个可锁定的万向轮1,使用时将其锁死,防止其移动。检修过程中,上工作台6主要用于检修、组装GW16/17系列隔离开关的上、下导电杆、接地隔离开关静触头、动触头等,下工作台5主要用于放置检修后的组件及各种耗材、工具、备品等。调试时,可将组装后的隔离开关固定在下工作台5上,通过站立在平台上手动分合隔离开关来调整隔离开关的状态。调试完成后,可将检修完成的隔离开关通过检修平台运至指定位置进行吊装。As shown in Figures 1 and 2, the isolating switch maintenance platform includes an upper workbench 6 set on the upper support 2 and a lower workbench 5 set on the lower support 3. The upper workbench 6 and the lower workbench 5 have the same structure. It is a rectangular steel plate, and the upper workbench 6 is designed and installed with four parts, which are respectively the static contact removal frame 7, the upper contact fixing card seat 10, the adjustment and stability platform 8 and the spring pressing device 9; the lower workbench 5 has four parts The 12 fixing holes are used for bolt fixing, the central opening 11 is used for the rotation of the lower part of the isolating switch, the lower bracket 3 is set on the slideway, and the lower workbench 5 is unfolded through the slideway during use, and the height is adjusted by the adjustment part 4 to make it appropriate And stable, the upper support 2 is equipped with four lockable universal wheels 1, which are locked during use to prevent it from moving. During the inspection and maintenance process, the upper workbench 6 is mainly used for inspection and assembly of the upper and lower conductive rods of the GW16/17 series isolating switch, the static contact and the moving contact of the grounding isolating switch, etc., and the lower workbench 5 is mainly used for placing the overhauled Components and various consumables, tools, spare parts, etc. During debugging, the assembled isolating switch can be fixed on the lower workbench 5, and the state of the isolating switch can be adjusted by standing on the platform and manually opening and closing the isolating switch. After the commissioning is completed, the isolating switch that has been overhauled can be transported to the designated location through the overhaul platform for hoisting.

Claims (5)

1.一种隔离开关检修平台,包括有上支架上所设上工作台和下支架上所设下工作台,其特征在于:上工作台的一端设有静触头拆卸架,上工作台的另一端设有调整稳固平台和对应的弹簧压紧装置,上工作台的中部设有上触头固定卡座,下工作台上具有开孔。1. An isolating switch maintenance platform, including an upper workbench set on the upper support and a lower workbench set on the lower support, is characterized in that: one end of the upper workbench is provided with a static contact removal frame, and the upper workbench The other end is provided with an adjusting and stabilizing platform and a corresponding spring pressing device, the middle part of the upper workbench is provided with an upper contact fixing holder, and the lower workbench has an opening. 2.如权利要求1所述的隔离开关检修平台,其特征在于:上支架的底部设有万向轮。2. The isolating switch maintenance platform according to claim 1, characterized in that: the bottom of the upper bracket is provided with universal wheels. 3.如权利要求1所述的隔离开关检修平台,其特征在于:下支架设置在滑道上。3. The isolating switch maintenance platform according to claim 1, characterized in that: the lower bracket is arranged on the slideway. 4.如权利要求1所述的隔离开关检修平台,其特征在于:下支架上还具有调整件。4. The maintenance platform of the isolating switch according to claim 1, characterized in that: the lower bracket also has an adjustment piece. 5.如权利要求1所述的隔离开关检修平台,其特征在于:开孔的四周设有固定孔。5. The isolating switch maintenance platform according to claim 1, characterized in that: there are fixing holes around the opening.
CN2009202582406U 2009-11-19 2009-11-19 Isolation switch maintenance platform Expired - Fee Related CN201541071U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009202582406U CN201541071U (en) 2009-11-19 2009-11-19 Isolation switch maintenance platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009202582406U CN201541071U (en) 2009-11-19 2009-11-19 Isolation switch maintenance platform

Publications (1)

Publication Number Publication Date
CN201541071U true CN201541071U (en) 2010-08-04

Family

ID=42592527

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009202582406U Expired - Fee Related CN201541071U (en) 2009-11-19 2009-11-19 Isolation switch maintenance platform

Country Status (1)

Country Link
CN (1) CN201541071U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102251655A (en) * 2011-04-22 2011-11-23 江苏省电力公司靖江市供电公司 Multifunctional high-voltage insulated overhauling platform
CN103441435A (en) * 2013-08-26 2013-12-11 国家电网公司 Disconnecting switch overhauling trolley
CN103928857A (en) * 2014-05-05 2014-07-16 国家电网公司 Integrated portable disconnecting switch fast overhaul platform
CN105552761A (en) * 2016-02-29 2016-05-04 国网福建省电力有限公司泉州供电公司 Multipurpose portable high-voltage isolating switch overhaul worktable and using method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102251655A (en) * 2011-04-22 2011-11-23 江苏省电力公司靖江市供电公司 Multifunctional high-voltage insulated overhauling platform
CN103441435A (en) * 2013-08-26 2013-12-11 国家电网公司 Disconnecting switch overhauling trolley
CN103441435B (en) * 2013-08-26 2016-09-07 国网河南省电力公司郑州供电公司 Disconnecting switch overhaul chassis
CN103928857A (en) * 2014-05-05 2014-07-16 国家电网公司 Integrated portable disconnecting switch fast overhaul platform
CN105552761A (en) * 2016-02-29 2016-05-04 国网福建省电力有限公司泉州供电公司 Multipurpose portable high-voltage isolating switch overhaul worktable and using method thereof

Similar Documents

Publication Publication Date Title
CN203871715U (en) Mobile overhaul platform for mechanism case of high-voltage circuit-breaker
CN201541071U (en) Isolation switch maintenance platform
CN204414035U (en) Breaker closing spring assembling/disassembling tool
CN205610068U (en) A auxiliary device for high tension switchgear current transformer dismouting
CN103928857A (en) Integrated portable disconnecting switch fast overhaul platform
CN105552761B (en) A kind of multipurpose portable maintaining high-voltage isolation switch workbench and its application method
CN202957492U (en) Special-purpose tool for overhauling circuit breaker spring mechanism
CN205407062U (en) Multi -purpose portable high voltage isolator examines and repair work platform
CN202772496U (en) Tool adapted to mount and dismount bird repeller in electrified state
CN201260040Y (en) High-voltage oil circuit breaker examining and operating platform
CN203014220U (en) An overhauling platform of a GW5 isolating switch
CN103281886A (en) Auxiliary assembling and disassembling structure for heavy components in equipment cabinet and application method of auxiliary assembling and disassembling structure
CN209184057U (en) It is a kind of for replacing the device of flip-over type current transformer in 10kV switchgear
CN202906257U (en) Mobile workbench for mounting transformer station isolation switch
CN203813273U (en) 500kV GW16/17 Type Isolating Switch Comprehensive Maintenance Platform
CN203850683U (en) Integrated portable disconnecting switch quick maintenance platform
CN206820326U (en) A kind of self-contained whole dismounting platform torn open of breaker
CN201270383Y (en) Auxiliary installation apparatus for outdoor switch cabinet electromagnetic operating mechanism
CN209699006U (en) A kind of provision for disengagement for nut
CN202240406U (en) Automobile shock absorber disassembly table
CN205141486U (en) Auxiliary device of electric power secondary equipment debugging usefulness
CN204615228U (en) A kind of multi-functional onsite maintenance workbench
CN201937204U (en) Portable power maintenance bracket
CN204835323U (en) Portable isolator touches and indicates change instrument
CN104134944A (en) Fast CT replacing device for 10kV switch cabinet

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100804