CN201457716U - Connection structure of box girder and tubular pile - Google Patents

Connection structure of box girder and tubular pile Download PDF

Info

Publication number
CN201457716U
CN201457716U CN 200920075933 CN200920075933U CN201457716U CN 201457716 U CN201457716 U CN 201457716U CN 200920075933 CN200920075933 CN 200920075933 CN 200920075933 U CN200920075933 U CN 200920075933U CN 201457716 U CN201457716 U CN 201457716U
Authority
CN
China
Prior art keywords
crossbeam
box girder
box
connection structure
tubular pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 200920075933
Other languages
Chinese (zh)
Inventor
费康一
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shipbuilding NDRI Engineering Co Ltd
Original Assignee
China Shipbuilding NDRI Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shipbuilding NDRI Engineering Co Ltd filed Critical China Shipbuilding NDRI Engineering Co Ltd
Priority to CN 200920075933 priority Critical patent/CN201457716U/en
Application granted granted Critical
Publication of CN201457716U publication Critical patent/CN201457716U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model discloses a connection structure of a box girder and a tubular pile, which comprises the box girder, a cross beam, a hollow tubular pile, and is characterized in that the cross section of the box girder is n-shaped; two ends of the cross beam are provided with bearing platforms which are transversely provided with through grooves; the through grooves are internally provided with through holes; two ends of the box girder are respectively embedded into the through grooves of the cross beam; and the cross beam is supported on the hollow tubular pile so as to connect the box girder, the cross beam and the hollow tubular pile into a whole by cast-in-situ reinforced concrete in the through holes. Compared with the prior art, the connection structure has the advantages of having more reasonable structure stress, little using amount of reinforced concrete material, simple and convenient construction and short construction period, reducing pile-sinking dangers, and lowering engineering construction cost.

Description

The connection structure of box crossbeam and pile tube
Technical field
The utility model relates to the hydro-structure technical field, the specifically a kind of box crossbeam of arine railway and connection structure of pile tube of being used for.
Background technology
At present, the slideway crossbeam structural shape that the engineering of slideway under water of conventional ultra-large type building berth is used all adopts solid prefabricated cross beam, it is by longitudinal slipway crossbeam and two slideway structures that transverse strut is formed of two two ends cantilevers, it is installed on the precast reinforced concrete square pile of band major part by behind the cast-in-place point of attachment under water.The hoisting capacity waterborne of single Pin slideway crossbeam of this structural shape is (to comprise that the land and water boundary place is also identical) more than 140 tons, its planar dimension be 9 meters * more than 10 meters, every Pin slideway crossbeam must be installed in aslope 4 under water on the precast reinforced concrete square pile with major part, therefore, the slideway crossbeam structural shape difficulty of construction of prior art is big, setting accuracy is high.Load-carrying ability must reach more than 150 tons and will satisfy certain width of cloth requirement of hanging on the water, preferably there is big part harbour to use for lifting, and the requirement that major part stake under water is prefabricated and pile sinking is located is than higher, its pile sinking positioning requirements will be higher than the regulation of 10 centimeters deviations of permission of national regulation, also has high absolute altitude control requirement, otherwise cross beam will be difficult to guarantee to install stablize, and the major part precast pile can not be repaired if any damage in the pile sinking, the construction costs height.
Summary of the invention
The purpose of this utility model is a kind of box crossbeam that provides at the deficiencies in the prior art and the connection structure of pile tube, it adopts cast-in-situ steel concrete to connect the structure of box crossbeam and hollow shell pill, stressed more reasonable, making under water, pile foundation effectively reduces difficulty of construction, thereby saved material of construction effectively, further reduce construction costs, made easy construction, duration shorten.
The concrete technical scheme that realizes the utility model purpose is: the connection structure of a kind of box crossbeam and hollow shell pill, comprise box crossbeam, crossbeam, hollow shell pill, and characteristics are that the cross section of box crossbeam is " door " font; The crossbeam two ends are provided with cushion cap, laterally are provided with groove on the cushion cap, are provided with through hole in the groove; Box crossbeam two ends are embedded in respectively in the groove of crossbeam mutually, and beam supporting is an one by cast-in-situ steel concrete captive joint box crossbeam, crossbeam and hollow shell pill in the through hole on hollow shell pill.
Described through hole is a truncated cone-shaped.
Described groove and box crossbeam are with wide.
The utility model compared with prior art has the following advantages.
1., crossbeam is connected reliably with pile tube, overall construction intensity improves greatly.
2., help strengthening the stake quantity that pilespacing reduces whole slideway, and can suitably reduce the control requirement of pile sinking, reduced the pile sinking risk, reduce construction costs.
3., construction install convenience, workable, can adapt to various construction situations, the single prefabricated components biggest lifting capacity alleviates, and only must control the planimetric position and the absolute altitude of 2 piles during assembling, but and secondary regulation and control on absolute altitude.
Description of drawings
Fig. 1 is the utility model structural representation
Fig. 2 is the A-A schematic cross-section of Fig. 1
Fig. 3 is the utility model scheme of installation
The specific embodiment
Consult accompanying drawing 1~accompanying drawing 2, the utility model is made up of box crossbeam 1, crossbeam 2, hollow shell pill 3, and the cross section of box crossbeam 1 is the long beam of empty stomach of " door " font; Crossbeam 2 two ends are provided with the cushion cap 4 of supporting box crossbeam 1, laterally are provided with groove 5 on the cushion cap 4, groove 5 and crossbeam 2 vertical and with box crossbeam 1 with wide, be provided with through hole 6 in the groove 5, through hole 6 is last young, the truncated cone-shaped hole that end opening is big; The two ends of box crossbeam 1 are embedded in respectively in the groove 5 of crossbeam 2 mutually, crossbeam 2 is bearing on the hollow shell pill 3 by the 7 captive joint hollow shell pills 3 of cast-in-situ steel concrete in the through hole 6 and is bearing in box crossbeam 1 on the crossbeam 2, cast-in-situ steel concrete 7 will adjacent two box crossbeams 1 and crossbeam 2, hollow shell pill 3 be fixedly connected into steel concrete integral structure.
Consult accompanying drawing 3, the utility model is to install like this: the cushion cap 4 at crossbeam 2 two ends is placed on the hollow shell pill 3, the two ends of box crossbeam 1 are embedded in the groove 5 of cushion cap 4 mutually, an end of the adjacent two box crossbeams 1 of phase embedding in the groove 5, behind the installation in position in the through hole 6 of crossbeam 2 cast-in-situ steel concrete 7, cast-in-situ steel concrete 7 is fixedly connected into steel concrete integral structure with adjacent two box crossbeams 1 and crossbeam 2, hollow shell pill 3.

Claims (3)

1. the connection structure of box crossbeam and hollow shell pill comprises box crossbeam (1), crossbeam (2), hollow shell pill (3), it is characterized in that the cross section of box crossbeam (1) is " door " font; Crossbeam (2) two ends are provided with cushion cap (4), laterally are provided with groove (5) on the cushion cap (4), are provided with through hole (6) in the groove (5); Box crossbeam (1) two ends are embedded in respectively in the groove (5) of crossbeam (2) mutually, and crossbeam (2) is bearing in hollow shell pill (3) and upward is one by the interior cast-in-situ steel concrete of through hole (6) (7) captive joint box crossbeam (1), crossbeam (2) and hollow shell pill (3).
2. according to the connection structure of described box crossbeam of claim 1 and pile tube, it is characterized in that described through hole (6) is truncated cone-shaped.
3. according to the connection structure of described box crossbeam of claim 1 and pile tube, it is characterized in that described groove (5) and box crossbeam (1) are with wide.
CN 200920075933 2009-08-06 2009-08-06 Connection structure of box girder and tubular pile Expired - Lifetime CN201457716U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200920075933 CN201457716U (en) 2009-08-06 2009-08-06 Connection structure of box girder and tubular pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200920075933 CN201457716U (en) 2009-08-06 2009-08-06 Connection structure of box girder and tubular pile

Publications (1)

Publication Number Publication Date
CN201457716U true CN201457716U (en) 2010-05-12

Family

ID=42385070

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200920075933 Expired - Lifetime CN201457716U (en) 2009-08-06 2009-08-06 Connection structure of box girder and tubular pile

Country Status (1)

Country Link
CN (1) CN201457716U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102134854A (en) * 2011-02-16 2011-07-27 中交二航局第四工程有限公司 Slipway underwater pile foundation and construction method thereof
CN103628504A (en) * 2013-11-28 2014-03-12 广州市恒盛建设工程有限公司 Connecting method of splicing type prefabricated reinforced concrete platform structure underground joints

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102134854A (en) * 2011-02-16 2011-07-27 中交二航局第四工程有限公司 Slipway underwater pile foundation and construction method thereof
CN102134854B (en) * 2011-02-16 2012-08-22 中交二航局第四工程有限公司 Slipway underwater pile foundation and construction method thereof
CN103628504A (en) * 2013-11-28 2014-03-12 广州市恒盛建设工程有限公司 Connecting method of splicing type prefabricated reinforced concrete platform structure underground joints

Similar Documents

Publication Publication Date Title
CN110528405B (en) Bridge high-altitude lifting and shifting device based on vehicle set and construction method thereof
CN204919588U (en) A board -like assembly of cavity round platform basis for frozen soil area transmission line iron tower
CN101649604A (en) Construction bracket of 1# block of inclined pull bridge and constructing method thereof
CN201581409U (en) Combined tower crane foundation of cross beam supported by steel latticework columns in deep foundation pit
CN104005569A (en) Construction method for supporting beam and removing columns
CN201610546U (en) Prestress anchoring frame plat
CN201457716U (en) Connection structure of box girder and tubular pile
CN209779634U (en) Assembled reinforced concrete bearing structure suitable for subway station foundation ditch
CN201080597Y (en) Multifunctional cast-in-situ cantilever plate construction bracket
CN201457715U (en) Underwater box type slipway
CN111139747A (en) Long-distance pushing construction system for large-span steel-concrete composite beam
CN202530364U (en) Inverted triangle pier simply supported or continuous bridge structure
CN215925647U (en) Arch rib buckle cable anchoring beam for tower buckle integration
CN102535344A (en) Concrete transportation method for bridge body of high-pier bridge in gully region
CN109397522A (en) A kind of universal precast beam pedestal being applicable in Soft Clay and its construction method
CN201943006U (en) Main tower zone movable bracket for assisting non-variable amplitude girder erecting crane to erect steel box girders
CN210369025U (en) Floor-free tower crane foundation construction structure with steel structure
CN210712562U (en) Tower crane system for construction of cast-in-situ tower column of cable-stayed bridge
CN201713807U (en) Steel node of prefabricated concrete pipe pile capable of translating and expanding outwards
CN201972148U (en) Pretensioned prestressed concrete dynamic load pile
CN107338734B (en) Prefabricated jacking construction method for prefabricated temporary girder buttress
CN111188264A (en) Double-limb thin-wall T-shaped pier
CN218090941U (en) Whip type precast concrete equipment foundation
CN205369301U (en) Supporting structure of subway transfer section lid digs and props against making interval board
CN220414302U (en) Prefabricated assembled shell-shaped bearing platform structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20100512

CX01 Expiry of patent term