CN201430375Y - Transmission line live replacement insulator suspension tool assembly - Google Patents

Transmission line live replacement insulator suspension tool assembly Download PDF

Info

Publication number
CN201430375Y
CN201430375Y CN2009203036813U CN200920303681U CN201430375Y CN 201430375 Y CN201430375 Y CN 201430375Y CN 2009203036813 U CN2009203036813 U CN 2009203036813U CN 200920303681 U CN200920303681 U CN 200920303681U CN 201430375 Y CN201430375 Y CN 201430375Y
Authority
CN
China
Prior art keywords
lead screw
screw rod
pull rod
transmission line
tool assembly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009203036813U
Other languages
Chinese (zh)
Inventor
马骏
任钢毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tonghua Power Supply Co of State Grid Jilin Electric Power Co Ltd
State Grid Corp of China
Original Assignee
Tonghua Power Supply Co of State Grid Jilin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tonghua Power Supply Co of State Grid Jilin Electric Power Co Ltd filed Critical Tonghua Power Supply Co of State Grid Jilin Electric Power Co Ltd
Priority to CN2009203036813U priority Critical patent/CN201430375Y/en
Application granted granted Critical
Publication of CN201430375Y publication Critical patent/CN201430375Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

本实用新型涉及一种电力抢修工具,即输电线路带电更换绝缘子吊线工具组件。尤其适用于第四代500千伏同塔双回线路SZ1、SZ2、SZ3、SZ4直线塔。调整尺寸后也可用于220千伏、330千伏绝缘子挂点横担主塔材为接近水平设置的铁塔更换直线绝缘子。它包括丝杠拉杆、丝杠拉杆下部连接有四钩卡。采用两个丝杠拉杆座,两个丝杠拉杆座之间通过可调式拉杆连接;每个丝杠拉杆竖立插座在丝杠拉杆座上。丝杠拉杆座上有插卡在铁塔横担上两侧角钢立边上的插槽,使用时插接在铁塔横担上两侧角钢立边上。满足新型铁塔上安装使用,具有结构简单、合理,使用安全可靠的特点。

Figure 200920303681

The utility model relates to an electric power emergency repair tool, which is a live replacement insulator hanging wire tool assembly for a power transmission line. It is especially suitable for the fourth-generation 500 kV double-circuit line on the same tower SZ 1 , SZ 2 , SZ 3 , SZ 4 linear towers. It can also be used for 220 kV and 330 kV insulator hanging points after the size is adjusted. The cross-arm main tower material is used to replace the linear insulators for iron towers that are close to the level. It comprises a lead screw rod, and the lower part of the lead screw rod is connected with four hooks. Two lead screw pull rod seats are adopted, and the two lead screw pull rod seats are connected by adjustable pull rods; each lead screw pull rod is vertically socketed on the lead screw pull rod seat. There are slots inserted into the vertical edges of the angle steel on both sides of the cross arm of the iron tower on the lead screw rod seat, and inserted into the vertical edges of the angle steel on both sides of the cross arm of the iron tower when in use. It is suitable for installation and use on a new iron tower, and has the characteristics of simple and reasonable structure, safe and reliable use.

Figure 200920303681

Description

输电线路带电更换绝缘子吊线工具组件 Transmission line live replacement insulator suspension tool assembly

技术领域 technical field

本实用新型涉及一种电力抢修工具,即输电线路带电更换绝缘子吊线工具组件。适用于500千伏直线铁塔单回、同塔双回或同塔多回线路直线铁塔更换直线绝缘子时起吊导线。尤其适用于第四代500千伏同塔双回线路SZ1、SZ2、SZ3、SZ4直线塔。调整尺寸后也可用于220千伏、330千伏绝缘子挂点横担主塔材为接近水平设置的铁塔更换直线绝缘子。The utility model relates to an electric power emergency repair tool, which is a live replacement insulator hanging wire tool assembly for a power transmission line. It is suitable for lifting conductors when replacing linear insulators on 500 kV straight line iron tower single circuit, double circuit on the same tower or multiple circuits on the same tower. It is especially suitable for the fourth-generation 500 kV double-circuit line on the same tower SZ 1 , SZ 2 , SZ 3 , SZ 4 straight towers. It can also be used for 220 kV and 330 kV insulator hanging points after the size is adjusted. The cross-arm main tower material is used to replace the linear insulators for iron towers that are close to the level.

背景技术 Background technique

在现有技术中,输电线路带电更换绝缘子吊线工具包括丝杠拉杆,每个丝杠拉杆下部连接有四钩卡,丝杠拉杆座插在铁塔上两个间隔的横角铁之间。第四代500千伏同塔双回线路SZ1、SZ2、SZ3、SZ4直线塔采用了新型结构,前述间隔的横角铁之间取消了缝隙,使原有的丝杠拉杆无处可插。In the prior art, the insulator suspension tool for live replacement of power transmission lines includes screw rods, each screw rod bottom is connected with four hooks, and the screw rod seat is inserted between two spaced horizontal angle irons on the iron tower. The fourth-generation 500 kV double-circuit line on the same tower SZ 1 , SZ 2 , SZ 3 , and SZ 4 linear towers adopt a new structure, and the gaps between the aforementioned horizontal angle irons are eliminated, so that the original screw rods have nowhere to go can be plugged.

实用新型内容 Utility model content

本实用新型的目的是针对上述情况而提供一种适应新型铁塔使用的输电线路带电更换绝缘子吊线工具组件。The purpose of the utility model is to provide a live replacement insulator suspension tool assembly for a new type of iron tower in view of the above situation.

本实用新型的技术解决方案是:输电线路带电更换绝缘子吊线工具组件包括丝杠拉杆、丝杠拉杆下部连接有四钩卡。采用两个丝杠拉杆座,两个丝杠拉杆座之间通过可调式拉杆连接;每个丝杠拉杆竖立插座在丝杠拉杆座上。丝杠拉杆座上有插卡在铁塔横担上两侧角钢立边上的插槽,使用时插接在铁塔横担上两侧角钢立边上。The technical solution of the utility model is: the live replacement insulator suspension wire tool assembly of the transmission line includes a lead screw pull rod, and four hooks are connected to the lower part of the lead screw pull rod. Two lead screw pull rod seats are adopted, and the two lead screw pull rod seats are connected by adjustable pull rods; each lead screw pull rod is vertically socketed on the lead screw pull rod seat. There are slots inserted into the vertical edges of the angle steel on both sides of the cross arm of the iron tower on the lead screw rod seat, and inserted into the vertical edges of the angle steel on both sides of the cross arm of the iron tower when in use.

本实用新型的优点是:1、满足新型铁塔上安装使用。2、结构简单、合理,使用安全可靠。3、摆脱了铁塔横担头处绝缘子挂点形式的限制。The utility model has the advantages of: 1. It can be installed and used on the new iron tower. 2. The structure is simple and reasonable, and the use is safe and reliable. 3. Get rid of the limitation of the hanging point form of the insulator at the cross-arm head of the iron tower.

下面将结合附图对本实用新型的实施方式作进一步详细描述。Embodiments of the utility model will be further described in detail below in conjunction with the accompanying drawings.

附图说明 Description of drawings

图1是本实用新型使用状态结构简图。Fig. 1 is a schematic diagram of the structure of the utility model in use.

图2是丝杠拉杆座单件俯视放大结构简图。Fig. 2 is a schematic enlarged structural diagram of a single-piece top view of the lead screw rod seat.

图3是本实用新型在铁塔上安装示意图。Fig. 3 is a schematic diagram of installing the utility model on an iron tower.

具体实施方式 Detailed ways

参见图1,输电线路带电更换绝缘子吊线工具组件包括两个丝杠拉杆1和每个丝杠拉杆1下部连接有四钩卡2(都是电力部门常用工具)。在此基础上增加了两个丝杠拉杆座3,以适应新型铁塔结构要求。两个丝杠拉杆座3之间通过可调式拉杆4连接,用于增加连接强度和稳定性。每个丝杠拉杆1竖立插座在丝杠拉杆座3上。丝杠拉杆座3上有插卡在铁塔横担角钢6的立边7上的插槽5。安装使用时(图1状态),进行组装,丝杠拉杆座3插接在铁塔横担边缘上的角钢6的立边7上(见图3),将拉杆4与丝杠拉杆座3连接并调整,插上丝杠拉杆1,四钩卡2钩上四股导线。搬动手柄13,丝杠拉杆1上移,带动四钩卡2上提及与其连接的四股导线上提,释放绝缘瓷瓶承重,可以方便取下与导线连接的整串绝缘瓷瓶。Referring to Fig. 1, the power transmission line replacement insulator suspension tool assembly includes two screw rods 1 and each screw rod 1 bottom is connected with four hooks 2 (all are common tools in the power sector). On this basis, two lead screw tie rod seats 3 are added to meet the structural requirements of the new iron tower. An adjustable tie rod 4 is used to connect the two lead screw rod seats 3 to increase connection strength and stability. Each leading screw rod 1 is vertically socketed on the leading screw rod seat 3 . The slot 5 inserted on the vertical edge 7 of the iron tower cross arm angle steel 6 is arranged on the leading screw rod seat 3 . During installation and use (Fig. 1 state), assemble, lead screw tie rod seat 3 is plugged on the vertical edge 7 of angle steel 6 on the iron tower cross-arm edge (seeing Fig. 3), pull bar 4 is connected with lead screw tie bar seat 3 and Adjust, insert the lead screw pull rod 1, and hook the four-strand wire on the four-hook card 2. Move the handle 13, the leading screw pull bar 1 moves up, and the four-strand wires connected with it are mentioned on the four-hook card 2 on the drive to carry, release the load-bearing of the insulating porcelain bottle, and can conveniently take off the whole string of insulating porcelain bottles connected with the wire.

参见图2,丝杠拉杆1穿过孔8,搭在槽9、10上。Referring to Fig. 2, the lead screw pull rod 1 passes through the hole 8 and rides on the grooves 9,10.

参见图3,现在新型铁塔11上的两个角钢12是靠在一起的。在已有技术中,两个角钢12是间隔的,丝杠拉杆1插立在两个角钢12之间,所以原有结构不适用了。现在的丝杠拉杆1通过两个丝杠拉杆座3插立于铁塔11上。Referring to Fig. 3, the two angle steels 12 on the new iron tower 11 are leaning together now. In the prior art, the two angle steels 12 are spaced apart, and the lead screw rod 1 is inserted between the two angle steels 12, so the original structure is not applicable. Present leading screw rod 1 is inserted on the iron tower 11 by two leading screw rod seats 3 .

Claims (2)

1.一种输电线路带电更换绝缘子吊线工具组件,包括丝杠拉杆(1)、丝杠拉杆(1)下部连接有四钩卡(2),其特征在于还包括两个丝杠拉杆座(3),两个丝杠拉杆座(3)之间通过可调式拉杆连接(4);每个丝杠拉杆(1)竖立插座在丝杠拉杆座(3)上。1. A transmission line live replacement insulator suspension tool assembly, comprising a screw rod (1), the lower part of the screw rod (1) is connected with four hooks (2), is characterized in that it also includes two screw rod seats (3 ), the two screw rod seats (3) are connected by an adjustable pull rod (4); each screw rod (1) is vertically socketed on the screw rod seat (3). 2.按照权利要求1所述的输电线路带电更换绝缘子吊线工具组件,其特征在于丝杠拉杆座(3)上有插卡在铁塔横担角钢(6)的立边(7)上的插槽(5)。2. According to the power transmission line live replacement insulator suspension tool assembly according to claim 1, it is characterized in that there is a slot inserted on the vertical edge (7) of the iron tower cross arm angle steel (6) on the lead screw rod seat (3) (5).
CN2009203036813U 2009-05-27 2009-05-27 Transmission line live replacement insulator suspension tool assembly Expired - Fee Related CN201430375Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009203036813U CN201430375Y (en) 2009-05-27 2009-05-27 Transmission line live replacement insulator suspension tool assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009203036813U CN201430375Y (en) 2009-05-27 2009-05-27 Transmission line live replacement insulator suspension tool assembly

Publications (1)

Publication Number Publication Date
CN201430375Y true CN201430375Y (en) 2010-03-24

Family

ID=42034114

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009203036813U Expired - Fee Related CN201430375Y (en) 2009-05-27 2009-05-27 Transmission line live replacement insulator suspension tool assembly

Country Status (1)

Country Link
CN (1) CN201430375Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101820144A (en) * 2010-03-26 2010-09-01 福建省电力有限公司莆田电业局 Special tool of live line work for replacing rectilinear insulator string of large-section double multiple wire
CN102074909A (en) * 2010-10-28 2011-05-25 福建省电力有限公司漳州电业局 Adjustable cross arm straight fixture
CN103276941A (en) * 2013-04-27 2013-09-04 国家电网公司 Principal material replacing support assembly of electric transmission line tower

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101820144A (en) * 2010-03-26 2010-09-01 福建省电力有限公司莆田电业局 Special tool of live line work for replacing rectilinear insulator string of large-section double multiple wire
CN101820144B (en) * 2010-03-26 2012-06-27 福建省电力有限公司莆田电业局 Special tool of live line work for replacing rectilinear insulator string of large-section double multiple wire
CN102074909A (en) * 2010-10-28 2011-05-25 福建省电力有限公司漳州电业局 Adjustable cross arm straight fixture
CN103276941A (en) * 2013-04-27 2013-09-04 国家电网公司 Principal material replacing support assembly of electric transmission line tower
CN103276941B (en) * 2013-04-27 2015-12-23 国家电网公司 Electric power line pole tower main material replacing bracket component

Similar Documents

Publication Publication Date Title
CN101174761B (en) Up-spinning Live Replacement Method for Tension Insulator Strings of High-Voltage Transmission Lines
CN204645808U (en) Bar stepped on by cement pole cable
CN202586171U (en) Supporting plate device of special hook card for live line replacement linear horizontal double-division insulator
CN203871745U (en) Double-hoisting-point rod head fixture for live changing of linear insulator on steel pipe pole of 220kV line
CN203787855U (en) Power transmission line linear charged wire lifting device
CN201332249Y (en) Tangent tower in shape of goblet of same-tower and three-circuit transmission line
CN203014270U (en) A triangular connecting plate connector used for a double bundled conductor in a power transmission line
CN203288943U (en) Intelligent switch installing accessory
CN205355675U (en) Suspension insulator changes device
CN105178677A (en) Linear tower for ultrahigh-voltage direct-current lines and with two poles arranged vertically
CN201556716U (en) Grounding clamp for high-voltage electrical inspection in the distribution transformer station area
CN203891557U (en) Compact insulation support
CN202882514U (en) 220-kilovolt all-angle single-circuit drilling cross tower
CN202405714U (en) Anti-swirl lifting support
CN204657344U (en) Be applied to the bending machine of step down side insulated conductor
CN203631193U (en) Pin-type insulator
CN202850574U (en) Wire rod
CN116260095A (en) Jumper wire up-winding type composite cross arm drilling structure suitable for 750kV line
CN202797820U (en) Electric lead wall support
CN201674161U (en) SZ type double-circuit straight line tower live replacement suspension insulator suspension wire fixture assembly
CN203071493U (en) Adjustable line tackle
CN201549854U (en) Insulation support device between conductors
CN204876745U (en) A tangent tower that is used for two poles of earth vertical arrangement of special high voltage direct current circuit
CN204311819U (en) A kind of 500kV double back broken line type cross-arm tangent tower
CN204703578U (en) Bar stepped on by gate framework type cable

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Effective date: 20121011

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20121011

Address after: Tonghua City, Jilin Province, Xinhua Street 134001 Dongchang District No. 770

Patentee after: Jilin Electric Power Company Limited, Tonghua Power Supply Company

Patentee after: State Grid Corporation of China

Address before: Tonghua City, Jilin Province, Xinhua Street 134001 Dongchang District No. 770

Patentee before: Jilin Electric Power Company Limited, Tonghua Power Supply Company

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100324

Termination date: 20180527

CF01 Termination of patent right due to non-payment of annual fee