CN201390951Y - Stepped formwork of roller compacted concrete dam overflow surface - Google Patents

Stepped formwork of roller compacted concrete dam overflow surface Download PDF

Info

Publication number
CN201390951Y
CN201390951Y CN200920107841U CN200920107841U CN201390951Y CN 201390951 Y CN201390951 Y CN 201390951Y CN 200920107841 U CN200920107841 U CN 200920107841U CN 200920107841 U CN200920107841 U CN 200920107841U CN 201390951 Y CN201390951 Y CN 201390951Y
Authority
CN
China
Prior art keywords
girder
template
formwork
panel
brace
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN200920107841U
Other languages
Chinese (zh)
Inventor
韩可林
黄巍
涂怀健
戴瑜
陈恕祥
曾凡杜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 8 Co Ltd
Sinohydro Bureau 1 Co Ltd
Original Assignee
Sinohydro Bureau 8 Co Ltd
Sinohydro Bureau 1 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 8 Co Ltd, Sinohydro Bureau 1 Co Ltd filed Critical Sinohydro Bureau 8 Co Ltd
Priority to CN200920107841U priority Critical patent/CN201390951Y/en
Application granted granted Critical
Publication of CN201390951Y publication Critical patent/CN201390951Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model belongs to the field of building engineering, in particular to a stepped formwork of a roller compacted concrete dam overflow surface, which is formed by combining formworks in step shape, wherein each formwork comprises a panel, a supporting system and a formwork pulling rod part. The supporting system comprises a girder and trusses and has functions of supporting and fixing the panel and assembling adjacent formworks, and the formwork pulling rod part has functions of anchoring and supporting the formworks. During engineering construction, a second-layered formwork is hoisted after a first-layered formwork is poured with concrete full, and the first-layered formwork and the second-layered formwork are connected to form an integral plate. A third-layered formwork is mounted according to the same method after the second-layered formwork is poured with concrete full, and the first-layered formwork is detached after the third-layered formwork is poured with concrete full. The formwork can be mounted circularly according to the above method and can also be turned and raised along with engineering progress rate, thereby meeting requirements of continuous paving and rising of concrete.

Description

A kind of step template of roller compacted concrete Dam spillwag chute
Technical field
The utility model belongs to building engineering field, relates in particular to a kind of step template of roller compacted concrete Dam spillwag chute.
Background technology
Roller compacted concrete Dam spillwag chute step template specialized application is in the construction of Hydraulic and Hydro-Power Engineering roller compacted concrete Dam spillwag chute downstream step surface concrete blinding, the construction characteristic that overflow monolith roller compacted concrete rises rapidly, continuously can be satisfied, the requirement that the continuous making of roller compacted concrete rises can be adapted to.
In work progress, not high usually as the roller compacted concrete aspect planeness of basal plane, and template is fixed on the concrete that just rolls not final set, certain displacement takes place under the vibration effect easily rolling.Simultaneously owing to worry the template displacement, vibrate and the work of rolling is subjected to certain restriction, concrete quality also is subjected to certain influence.In addition the set-up time of template longer, be difficult for satisfying the construction requirement that roller compacted concrete rises rapidly, continuously.
The utility model content
The utility model is to provide a kind of step template of roller compacted concrete Dam spillwag chute, can design the template corresponding size according to different spillwag chute structures, further optimize formwork structure and installed and fixed scheme, can effectively prevent the displacement phenomenon of template in work progress.Template can constantly rise along with programming in work progress, satisfies the requirement that the concrete continuous making rises.
The technical solution of the utility model is: a kind of step template of roller compacted concrete Dam spillwag chute is characterized in that: described step template by template by regulating system with joint cover is stepped combines.After the first floor template was watered full concrete, lifting second layer template made first and second layer template be linked to be integral slab.After second layer template is watered full concrete, the 3rd layer of template is installed in the same way again, treat that the 3rd layer is watered and remove the first floor template behind the full concrete, method is carried out cycle installation as described above, template also can along with programming constantly circulation turn over liter.
Template comprises panel, is installed on support system and drawing-die rod member on the panel.Support system is the truss-like back of the body frame that offers connection holes, comprises girder and truss two parts of being connected with panel, a common panel configuration two cover support systems.
The truss of support system comprises perpendicular to the cross tube of girder and sheer pole, be parallel to vertical rod that girder and two ends are connected cross tube and sheer pole respectively, be last brace, middle brace and following brace that N shape is connected successively; Sheer pole is installed on the girder bottom, and cross tube is installed on the position that flushes with panel; Last brace one end is connected in the girder upper end, and the other end is connected with cross tube; Middle brace and following V-shaped connection of brace, its end that intersects is connected in girder jointly, and the other end connects cross tube and sheer pole separately respectively.
Connecting pore on the support system comprises last connecting pore and the middle connecting pore that lays respectively at girder upper end and middle part, is arranged in the right connecting pore and the following connecting pore that is positioned at sheer pole and vertical rod junction of brace and brace connection.
Regulating system adopts jackscrew, by the connecting pore adjustment on the template and fixing two adjacent templates.During installation, the last connecting pore of first floor template is connected to the right connecting pore of second layer template by regulating system, and the middle connecting pore of first floor template connects the following connecting pore of second layer template by gusset piece.Make first and second layer template be linked to be integral body by the adjustable screw jack, become new cantilever form.
The drawing-die rod member passes the drawing-die muscle hole that is opened on girder and the panel, and an end of drawing-die rod member is fixed in girder, and the other end is embedded in the concrete.The part that the drawing-die rod member is positioned at panel is cone-shaped, and weaving done in fine silks and gold thread by the tapestry method in the conehead is inserted in the weaving done in fine silks and gold thread by the tapestry method of drawing-die muscle in the cone when template is installed, and plays the effect of anchoring and support shuttering.Each template disposes quadruplet drawing-die rod member at least.
Panel is a rectangular steel plates, for increasing its intensity, secondary beam and strength plate is installed on steel plate.Cat ladder is housed on panel, is convenient to Installation and Debugging template in construction.In the girder upper end hanger is housed, is used for lifting by crane template in assembling.
Advantage of the present utility model is: in the downstream step surface concrete construction of Hydraulic and Hydro-Power Engineering roller compacted concrete Dam spillwag chute, the simple installation of step template is quick, adopt the job practices of the stepped progressively fluid concrete of template, need not to worry when roller compacted concrete, to cause template to issue the position of changing rolling the vibration effect, make and to vibrate and roll that everything goes well with your work carries out, quality of concrete also is protected, and satisfies the construction characteristic that roller compacted concrete rises rapidly, continuously.
Description of drawings
Fig. 1 is the assembling schematic diagram of the step template of roller compacted concrete Dam spillwag chute described in the utility model;
Fig. 2 is the rear elevation of the step template of roller compacted concrete Dam spillwag chute described in the utility model;
Fig. 3 is the formwork structure schematic diagram of the step template of roller compacted concrete Dam spillwag chute described in the utility model;
Fig. 4 is the drawing-die rod schematic representation of the step template of roller compacted concrete Dam spillwag chute described in the utility model;
Fig. 5 is the regulating system schematic diagram of the step template of roller compacted concrete Dam spillwag chute described in the utility model.
The specific embodiment
Below in conjunction with the drawings and specific embodiments the utility model is described in further detail.
As shown in Figure 1 to Figure 3, the step template combines by template is stepped, and template comprises panel 1, is installed on support system and drawing-die rod member on the panel 1.Support system is a truss-like back of the body frame, comprise girder 4 and truss two parts of being connected with panel 1, truss comprises perpendicular to the cross tube 9 of girder 4 and sheer pole 10, be parallel to vertical rod 11 that girder 4 and two ends are connected cross tube 9 and sheer pole 10 respectively, be last brace 12, middle brace 13 and following brace 14 that N shape is connected successively; Sheer pole 10 is installed on girder 4 bottoms, and cross tube 9 is installed on the position that flushes with panel 1; Last brace 12 1 ends are connected in girder 4 upper ends, and the other end is connected with cross tube 9; Middle brace 13 and following 14 V-shaped connections of brace, its end that intersects is connected in girder 4 jointly, and the other end connects cross tube 9 and sheer pole 10 separately respectively.Hanger 21 is equipped with in the girder upper end, is used to lift by crane template.Connecting pore on the support system comprises last connecting pore 15 and the middle connecting pore 16 that lays respectively at girder 4 upper ends and middle part, is arranged in the right connecting pore 18 and the following connecting pore 17 that is positioned at sheer pole 14 and vertical rod 11 junctions of brace 12 and brace 13 connections.Panel 1 disposes two cover support systems.
Panel 1 is a rectangular steel plates, for increasing its intensity, secondary beam 7 and strength plate 8 is installed on steel plate.Cat ladder 19 is housed on panel, is convenient to Installation and Debugging template in construction.
The drawing-die rod member passes the drawing-die muscle hole 5 that is opened on girder 4 and the panel 1, and an end of drawing-die rod member is fixed in girder 4, and the other end is embedded in the concrete.The part that the drawing-die rod member is positioned at panel 1 is cone-shaped, and weaving done in fine silks and gold thread by the tapestry method in the conehead 25 is inserted in 24 weaving done in fine silks and gold thread by the tapestry methods of drawing-die muscle in the cone when template is installed, and plays the effect of anchoring and support shuttering.A template configuration has quadruplet drawing-die rod member.
Regulating system is a jackscrew 6, by the connecting pore adjustment on the template and fixing two adjacent templates.During installation, the last connecting pore 15 of first floor template is connected to the right connecting pore 18 of second layer template by regulating system, the middle connecting pore 16 of first floor template connects the following connecting pore 17 of second layer template by gusset piece 20, make first and second layer template be linked to be integral body by adjustment, become new cantilever form.After second layer template is watered full concrete, the 3rd layer of template is installed in the same way again, treat to remove the first floor template after the 3rd layer of template watered full concrete, method is carried out cycle installation as described above, and template also can be turned over liter along with programming constantly circulates.
As shown in Figure 4, weaving done in fine silks and gold thread by the tapestry method in the conehead 25 of drawing-die rod member, 24 weaving done in fine silks and gold thread by the tapestry methods of drawing-die muscle were inserted in the conehead 25 when template was installed, and played the effect of anchoring and support shuttering.
As shown in Figure 5, regulating system is a jackscrew 6, comprises screw rod 27 and sleeve 26, and the two ends of jackscrew 6 are provided with the last connecting pore 15 that is connected to adjacent two templates and the through hole 28 of right connecting pore 18.

Claims (5)

1. the step template of a roller compacted concrete Dam spillwag chute, it is characterized in that: described step template combines by template is stepped; Described template is made up of panel (1), the support system and the drawing-die rod member that are loaded on the panel (1); Described support system is made up of truss and the girder (4) that is loaded on panel (1); Girder (4) and panel (1) are provided with the drawing-die muscle hole (5) that the drawing-die rod member is installed; Described drawing-die rod member passes drawing-die muscle hole (5), and an end is fixed in girder (4), and the other end is embedded in the concrete; Described regulating system is the jackscrew (6) that is installed between the template; Hanger (21) is equipped with in described girder (4) upper end.
2. the step template of roller compacted concrete Dam spillwag chute as claimed in claim 1 is characterized in that: described panel (1) is for being equipped with the rectangular steel plates of secondary beam (7) and strength plate (8).
3. the step template of roller compacted concrete Dam spillwag chute as claimed in claim 1 is characterized in that: the truss of described support system comprises perpendicular to the cross tube of girder (4) (9) and sheer pole (10), be parallel to vertical rod (11) that girder (4) and two ends are connected cross tube (9) and sheer pole (10) respectively, be last brace (12), middle brace (13) and following brace (14) that N shape is connected successively; Sheer pole (14) is installed on girder (4) bottom, and cross tube (9) is installed on and the neat high position of panel (1); Last brace (12) one ends are connected in girder (4) upper end, and the other end is connected with cross tube (9); Middle brace (13) and V-shaped connection of following brace (14), its end that intersects is connected in girder (4) jointly, and the other end connects cross tube (9) and sheer pole (10) separately respectively.
4. the step template of roller compacted concrete Dam spillwag chute as claimed in claim 1 is characterized in that: described support system is made up of the middle connecting pore (16) of the last connecting pore that lays respectively at girder (4) upper end and middle part (15), the right connecting pore (18) that is arranged in brace (12) and brace (13) connection, the following connecting pore (17) that is positioned at sheer pole (10) and vertical rod (11) junction.
5. the step template of roller compacted concrete Dam spillwag chute as claimed in claim 1 is characterized in that: described panel (1) is equipped with cat ladder (19).
CN200920107841U 2009-05-05 2009-05-05 Stepped formwork of roller compacted concrete dam overflow surface Expired - Lifetime CN201390951Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200920107841U CN201390951Y (en) 2009-05-05 2009-05-05 Stepped formwork of roller compacted concrete dam overflow surface

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200920107841U CN201390951Y (en) 2009-05-05 2009-05-05 Stepped formwork of roller compacted concrete dam overflow surface

Publications (1)

Publication Number Publication Date
CN201390951Y true CN201390951Y (en) 2010-01-27

Family

ID=41597774

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200920107841U Expired - Lifetime CN201390951Y (en) 2009-05-05 2009-05-05 Stepped formwork of roller compacted concrete dam overflow surface

Country Status (1)

Country Link
CN (1) CN201390951Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104452763A (en) * 2014-11-07 2015-03-25 葛洲坝集团第二工程有限公司 Overflow surface concrete formwork drawing construction method with embedded rails
CN105926625A (en) * 2016-05-06 2016-09-07 中国葛洲坝集团第工程有限公司 Die-jacking-free rapid construction method for overflow surface concrete of gate dam
CN116219967A (en) * 2023-04-24 2023-06-06 中国水利水电第三工程局有限公司 Construction method of downstream dam face step structure of roller compacted concrete dam

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104452763A (en) * 2014-11-07 2015-03-25 葛洲坝集团第二工程有限公司 Overflow surface concrete formwork drawing construction method with embedded rails
CN105926625A (en) * 2016-05-06 2016-09-07 中国葛洲坝集团第工程有限公司 Die-jacking-free rapid construction method for overflow surface concrete of gate dam
CN105926625B (en) * 2016-05-06 2018-01-23 中国葛洲坝集团第一工程有限公司 Gate dam overflow surface concrete exempts from backform rapid constructing method
CN116219967A (en) * 2023-04-24 2023-06-06 中国水利水电第三工程局有限公司 Construction method of downstream dam face step structure of roller compacted concrete dam

Similar Documents

Publication Publication Date Title
CN110700105B (en) Synchronous construction method and formwork used for high pier pier column and tie beam
CN103669655B (en) Deformation joint both walls body concrete pouring construction process
CN206438529U (en) Beam and slab type raft foundation formwork support structure
CN206942131U (en) Cast-in-situ concrete beam plate form bracing system
CN201666157U (en) Inverted arch integral type moving die carrier
CN208668596U (en) A kind of reinforced concrete girder slab system and prefabricated post assembly node
CN107053440A (en) A kind of precast plate girder pedestal preparation method
CN207419711U (en) Steel plate shear force wall and the connection structure of steel bar girder floor plates
CN107905111B (en) A kind of construction technology of rigid frame continuous beam side span
CN116290089A (en) Concrete pouring formwork system used in underground space and construction method thereof
CN201390951Y (en) Stepped formwork of roller compacted concrete dam overflow surface
CN218233146U (en) Supporting device for pouring drainage side ditch
CN102352690B (en) Construction method of anti-floating locating system of cast-in-place concrete hollow floorslab steel tube
CN204081475U (en) A kind of adjustable floor one-piece keel structure
CN205712565U (en) A kind of prefabricated two-sided wall
CN201367730Y (en) A die plate supporting device convenient for dismounting die plates
CN209760872U (en) Diagonal draw bar for supporting-free formwork
CN207392715U (en) A kind of overhanging inclined support structure
CN104164882A (en) Construction method for building support structural beam foundation on slope and structure thereof
CN203361642U (en) Cast-in-place stair steel formwork of assembled structure
CN218862104U (en) Column formwork reinforced structure
CN202227255U (en) Cat anchor device for steel truss girder
CN210947661U (en) Installation device of socket type overhanging scaffold
CN104847111B (en) Construction method for coupling beam between shear wall limbs
CN204510688U (en) A kind of temporary fixing structure of precast wall panel

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20100127

CX01 Expiry of patent term